MOVEMENT 4
Right turn from major road
Conflicting Traffic, Vc4 Vc4 = V6 + V5
= 0 + 395
= 395 vph
Critical Gap, Tc4 Tc4 = 5.0
(Table 4-3)
Potential Capacity, Cp4 Cp4=800 pcph
Impendance Factor, P4 Percentage of Cp utilized, % = Vp / Vc4 x 100 %
= 9/800 x 100%
= 1.13 %
Therefore,
P4 = 0.99
Actual Capacity, Cm4 Cm4 = Cp4
=800 pcph
MOVEMENT 1
Right turn from minor road
Conflicting Traffic, Vc1 Vc1 = ½ V6 + V3 + V5 + V4
= ½ (0) + 845 + 395 + 9
= 1249
Critical Gap, Tc1 Tc1 = 6.5 sec
(Table 4-3) Right turn from minor road
Potential Capacity, Cp1 Cp1 = 160 pcph
(Figure 4-2)
Actual Capacity, Cm1 Cm1 = Cp1 x P4
= 160 x 0.99
= 158.4 pcph
Shared Capacity, Csh 𝑉1+ 𝑉2
𝐶𝑠ℎ =
𝑉1 𝑉2
( ) +( )
𝐶𝑚1 𝐶𝑚2
11 + 14
𝐶𝑠ℎ =
11 14
(158.4) + ( 710 )
= 280.39 pcph
TABLE 5 RESULT OF LEVEL OF SERVICE (LOS) ANALYSIS
Movement Volume, Actual Shared Reserve Level of
No. V(pcph) Capacity,Cm Capacity, Csh Capacity, Service,
(pcph) (pcph) Cr = Csh - V LOS
4 9 800 800 791 A
(Little or
no delay)
1 11 158.4 269.39 Average
traffic delay
280.39
2 14 800 266.39
Average
traffic delay