S.
No Description of Works Status %
Civil Structure Activities
RCC
1 Footings RCC Completed 100%
2 Footing Column upto Basements RCC Completed 100%
3 Backfilling Completed 100%
Yet not Started 0%
4 Grade Slab PCC
5 Grade Slab RCC Yet not Started 0%
6 Basement-2 Floor Columns RCC Completed 100%
Completed 100%
7 Basement-2 Slab RCC
8 Basement-1 Floor Columns RCC Completed 100%
Completed 100%
9 Basement-1 Slab/Podium Slab RCC
10 Basement-1 Slab VDF CC Yet not Started 0%
Completed 100%
11 Stilt Floor Columns RCC
Completed 100%
12 Stilt Roof Slab RCC
13 1st Floor Columns RCC Completed 100%
Completed 100%
14 1st Roof Slab RCC
15 2nd Floor Columns RCC Completed 100%
Completed 100%
16 2nd Roof Slab RCC
17 3rd Floor Columns RCC Completed 100%
Completed 100%
18 3rd Roof Slab RCC
19 4th Floor Columns RCC Completed 100%
Completed 100%
20 4th Roof Slab RCC
21 5th Floor Columns RCC Completed 100%
Completed 100%
22 5th Roof Slab RCC
23 6th Floor Columns RCC Completed 100%
Completed 100%
24 6th Roof Slab RCC
25 7th Floor Columns RCC Completed 100%
Completed 100%
26 7th Roof Slab RCC
27 8th Floor Columns RCC Completed 100%
Completed 100%
28 8th Roof Slab RCC
29 9th Floor Columns RCC Completed 100%
Completed 100%
30 9th Roof Slab RCC
31 10th Floor Columns RCC Completed 100%
Completed 100%
32 10th Roof Slab RCC
33 11th Floor Columns RCC Completed 100%
Completed 100%
34 11th Roof Slab RCC
35 12th Floor Columns RCC Completed 100%
Completed 100%
36 12th Roof Slab RCC
37 13th Floor Columns RCC Completed 100%
Completed 100%
38 13th Roof Slab RCC
39 14th Floor Columns RCC Completed 100%
Completed 100%
40 14th Roof Slab RCC
41 15th Floor Columns RCC Completed 100%
Completed 100%
42 15th Roof Slab RCC
43 16th Floor Columns RCC Completed 100%
Completed 100%
44 16th Roof Slab RCC
45 17th Floor Columns RCC Completed 100%
Completed 100%
46 17th Roof Slab/Terrace RCC
47 18th Floor/ Duplex Columns RCC Completed 100%
48 18th Roof/Duplex Slab RCC Completed 100%
Completed 100%
49 Above Terrace works RCC
50 Stilt Floor Landscaping Works WIP 5%
Description of
Remarks
Works
tivities
T1 expantion joint near by
PCC pending. Exit ramp
Subsoil pipe laying done.
Ramp gutters pending
Basement-2
Basement-1
Stilt Floor
1st Floor
2nd Floor
3rd Floor
4th Floor
5th Floor
6th Floor
7th Floor
8th Floor
9th Floor
10th Floor
11th Floor
12th Floor
13th Floor
14th Floor
15th Floor
16th Floor
17th Floor
18th Floor\Terrace floor
Resources Req Status %
Block Work
Mason-10nos,Helper-10nos Yet not Started 0%
Same as above WIP 85%
Mason-10nos,Helper-10nos WIP 90%
same as above WIP 90%
same as above WIP 90%
same as above WIP 90%
same as above WIP 90%
same as above WIP 90%
same as above WIP 90%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
same as above WIP 85%
Tower-1 Work Status
Remarks
Civ
ck Work
Passenger lifts and MEP Shaft Block work pending
Passenger lift bw pending at B&C wing and Mep shaft block work pending
Passenger lift blockwork pendingat B & C WING and Mep shaft blockwork
pending
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.
Notes:-
Block work mason- 28ma, Helper-28 nos
Plastering mason-50ma, Helper-50nos
Hacking,Buffing- 12nos
Lintel works-8nos
unskilled labours- 50nos
scaffolders-15nos
tatus
Description of
Status
Works
Civil Finishing Activities
Basement-2 N/A
Basement-1 N/A
Stilt Floor WIP
1st Floor WIP
2nd Floor WIP
3rd Floor In Complete
4th Floor In Complete
5th Floor In Complete
6th Floor In Complete
7th Floor In Complete
8th Floor In Complete
9th Floor WIP
10th Floor WIP
11th Floor WIP
12th Floor WIP
13th Floor WIP
14th Floor WIP
15th Floor WIP
16th Floor WIP
17th Floor WIP
18th Floor\Terrace floor WIP
Resources Req %
ng Activities
Plastering Work
Mason-8nos,helper-8nos,Hacking & buffing work- 6nos 50%
same as above 50%
Mason-15nos,helper-15nos,Hacking & buffing work- 6nos 20%
Mason-10nos, helpers-10nos, lintel work lab-8nos 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
same as above 85%
mason-6nos,helper-6nos , unskilled labour-10 nos
Remarks
Plastering Work
Retaining wall buffing pending , Tie Rod hole packing pending and celling buffing pending,Passeng
pending and Mep shaft plastering pending.
Retaining wall buffing pending,columns tie rod packing pending. Passenger lift door side plasterin
plastering pending.
Ceiling and Columns plastering work in progress at A-WING
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing, Flatno C-507 internal plastering pendin
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing, Flatno C-707 internal plastering pendin
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Passenger lifts front door plastering pending at A,B,C wing.
Duplex flat A2,A3,A6,C2,C5,C6 Internal plastering pending.
Terrace floor house-keeping pending to HO waterproofing work, pergola plastering ,parapet wall p
TYPICAL PENDING WORK :-
1- Internal flats handover pending for Tiles work ( 70 nos HO, Balance-253nos pending)-
2- Internal flats touch-up work pending- 4mason
3 All staircases granite skirting finishing work pending-4mason
4- Internal flats skirting finishing pending-4mason
5- Staircase internal touch-ups pending-4mason
6- Mep shafts internal side touch-ups pending -2mason
7- External area rod cutting pending, touch-ups pending,and PHE shafts touch-ups pending-4nos
8- All floor Corridoor house-keeping pending- unskilled labour-30nos
9- All floors PHE shaft house-keeping pending- and OTS-10nos
10-All floor flats upstanding beam concreting pending- mason-4mason
11- screeding work pending from 12th floor to 17th floors- RCC labour-10nos
12- Terrace floor house-keeping pending to HO waterproofing work-10nos
13- Ledge wall block from 7th floor to 17th floor- Mason-8nos,Helper-8nos
14-Ledge wall plastering- mason-8nos ,Helper-8nos