0% found this document useful (0 votes)
56 views15 pages

Tower-1 Work Status

The document outlines the status of various civil structure activities, indicating that most tasks are completed while some, such as grade slab work and landscaping, are yet to start or are in progress. It also details resource requirements for ongoing plastering work and highlights several pending tasks across different floors, including internal touch-ups and housekeeping. Overall, the project shows significant progress with a few areas needing attention to complete the construction.

Uploaded by

srimantasurveyor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views15 pages

Tower-1 Work Status

The document outlines the status of various civil structure activities, indicating that most tasks are completed while some, such as grade slab work and landscaping, are yet to start or are in progress. It also details resource requirements for ongoing plastering work and highlights several pending tasks across different floors, including internal touch-ups and housekeeping. Overall, the project shows significant progress with a few areas needing attention to complete the construction.

Uploaded by

srimantasurveyor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

S.

No Description of Works Status %

Civil Structure Activities


RCC
1 Footings RCC Completed 100%
2 Footing Column upto Basements RCC Completed 100%
3 Backfilling Completed 100%

Yet not Started 0%


4 Grade Slab PCC
5 Grade Slab RCC Yet not Started 0%
6 Basement-2 Floor Columns RCC Completed 100%

Completed 100%
7 Basement-2 Slab RCC
8 Basement-1 Floor Columns RCC Completed 100%

Completed 100%
9 Basement-1 Slab/Podium Slab RCC

10 Basement-1 Slab VDF CC Yet not Started 0%

Completed 100%
11 Stilt Floor Columns RCC

Completed 100%
12 Stilt Roof Slab RCC

13 1st Floor Columns RCC Completed 100%

Completed 100%
14 1st Roof Slab RCC
15 2nd Floor Columns RCC Completed 100%

Completed 100%
16 2nd Roof Slab RCC
17 3rd Floor Columns RCC Completed 100%

Completed 100%
18 3rd Roof Slab RCC
19 4th Floor Columns RCC Completed 100%

Completed 100%
20 4th Roof Slab RCC
21 5th Floor Columns RCC Completed 100%

Completed 100%
22 5th Roof Slab RCC
23 6th Floor Columns RCC Completed 100%

Completed 100%
24 6th Roof Slab RCC
25 7th Floor Columns RCC Completed 100%

Completed 100%
26 7th Roof Slab RCC
27 8th Floor Columns RCC Completed 100%

Completed 100%
28 8th Roof Slab RCC
29 9th Floor Columns RCC Completed 100%

Completed 100%
30 9th Roof Slab RCC
31 10th Floor Columns RCC Completed 100%

Completed 100%
32 10th Roof Slab RCC
33 11th Floor Columns RCC Completed 100%

Completed 100%
34 11th Roof Slab RCC
35 12th Floor Columns RCC Completed 100%

Completed 100%
36 12th Roof Slab RCC
37 13th Floor Columns RCC Completed 100%

Completed 100%
38 13th Roof Slab RCC
39 14th Floor Columns RCC Completed 100%

Completed 100%
40 14th Roof Slab RCC
41 15th Floor Columns RCC Completed 100%

Completed 100%
42 15th Roof Slab RCC
43 16th Floor Columns RCC Completed 100%

Completed 100%
44 16th Roof Slab RCC
45 17th Floor Columns RCC Completed 100%

Completed 100%
46 17th Roof Slab/Terrace RCC
47 18th Floor/ Duplex Columns RCC Completed 100%
48 18th Roof/Duplex Slab RCC Completed 100%
Completed 100%
49 Above Terrace works RCC
50 Stilt Floor Landscaping Works WIP 5%
Description of
Remarks
Works
tivities

T1 expantion joint near by


PCC pending. Exit ramp
Subsoil pipe laying done.
Ramp gutters pending

Basement-2

Basement-1

Stilt Floor

1st Floor

2nd Floor

3rd Floor

4th Floor

5th Floor

6th Floor
7th Floor

8th Floor

9th Floor

10th Floor

11th Floor

12th Floor

13th Floor

14th Floor

15th Floor

16th Floor

17th Floor

18th Floor\Terrace floor


Resources Req Status %

Block Work

Mason-10nos,Helper-10nos Yet not Started 0%

Same as above WIP 85%

Mason-10nos,Helper-10nos WIP 90%

same as above WIP 90%

same as above WIP 90%

same as above WIP 90%

same as above WIP 90%

same as above WIP 90%

same as above WIP 90%


same as above WIP 85%

same as above WIP 85%

same as above WIP 85%

same as above WIP 85%

same as above WIP 85%

same as above WIP 85%

same as above WIP 85%

same as above WIP 85%

same as above WIP 85%

same as above WIP 85%

same as above WIP 85%


Tower-1 Work Status
Remarks

Civ
ck Work

Passenger lifts and MEP Shaft Block work pending

Passenger lift bw pending at B&C wing and Mep shaft block work pending

Passenger lift blockwork pendingat B & C WING and Mep shaft blockwork
pending

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing.


Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,
Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Passenger lifts B &C Wing, AC ledge blockwork pending at A, B & C wing,


Flush tank ledge wall blockwork pending.

Notes:-
Block work mason- 28ma, Helper-28 nos
Plastering mason-50ma, Helper-50nos
Hacking,Buffing- 12nos
Lintel works-8nos
unskilled labours- 50nos
scaffolders-15nos
tatus
Description of
Status
Works
Civil Finishing Activities

Basement-2 N/A

Basement-1 N/A

Stilt Floor WIP

1st Floor WIP

2nd Floor WIP

3rd Floor In Complete

4th Floor In Complete

5th Floor In Complete

6th Floor In Complete


7th Floor In Complete

8th Floor In Complete

9th Floor WIP

10th Floor WIP

11th Floor WIP

12th Floor WIP

13th Floor WIP

14th Floor WIP

15th Floor WIP

16th Floor WIP

17th Floor WIP

18th Floor\Terrace floor WIP


Resources Req %

ng Activities
Plastering Work

Mason-8nos,helper-8nos,Hacking & buffing work- 6nos 50%

same as above 50%

Mason-15nos,helper-15nos,Hacking & buffing work- 6nos 20%

Mason-10nos, helpers-10nos, lintel work lab-8nos 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%


same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

same as above 85%

mason-6nos,helper-6nos , unskilled labour-10 nos


Remarks

Plastering Work

Retaining wall buffing pending , Tie Rod hole packing pending and celling buffing pending,Passeng
pending and Mep shaft plastering pending.

Retaining wall buffing pending,columns tie rod packing pending. Passenger lift door side plasterin
plastering pending.

Ceiling and Columns plastering work in progress at A-WING

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing, Flatno C-507 internal plastering pendin

Passenger lifts front door plastering pending at A,B,C wing.


Passenger lifts front door plastering pending at A,B,C wing, Flatno C-707 internal plastering pendin

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Passenger lifts front door plastering pending at A,B,C wing.

Duplex flat A2,A3,A6,C2,C5,C6 Internal plastering pending.

Terrace floor house-keeping pending to HO waterproofing work, pergola plastering ,parapet wall p

TYPICAL PENDING WORK :-


1- Internal flats handover pending for Tiles work ( 70 nos HO, Balance-253nos pending)-
2- Internal flats touch-up work pending- 4mason
3 All staircases granite skirting finishing work pending-4mason
4- Internal flats skirting finishing pending-4mason
5- Staircase internal touch-ups pending-4mason
6- Mep shafts internal side touch-ups pending -2mason
7- External area rod cutting pending, touch-ups pending,and PHE shafts touch-ups pending-4nos
8- All floor Corridoor house-keeping pending- unskilled labour-30nos
9- All floors PHE shaft house-keeping pending- and OTS-10nos
10-All floor flats upstanding beam concreting pending- mason-4mason
11- screeding work pending from 12th floor to 17th floors- RCC labour-10nos
12- Terrace floor house-keeping pending to HO waterproofing work-10nos
13- Ledge wall block from 7th floor to 17th floor- Mason-8nos,Helper-8nos
14-Ledge wall plastering- mason-8nos ,Helper-8nos

You might also like