Appeal Merged Pagenumber
Appeal Merged Pagenumber
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
1. The complainants at Sr. 1 to 4 are home buyers and allottees within the meaning of
section 2(d) of the Real Estate (Regulation and Development) Act, 2016 (hereinafter
Page 1 of 8
52
3. The complainants/allotees at Sr. no.1 to 4 are seeking following reliefs: (Sr.no. 2 and
4 are the interim applications filed by the complainant/allottees at Sr. no.1)
Page 2 of 8
53
Page 3 of 8
54
5. The brief submissions of the complainant/allottee at Sr no.1 along with Sr.no. 2 & 4
are as follows:
A. That, the complainant entered into an agreement for sale dated
16.04.2016 with respondent to purchase flat 503, C -wing, 5th Floor,
"Kingston Aura “project for a total consideration amount of 40,53,400/-
Page 4 of 8
55
out of which the complainant has paid Rs. 34,69,896/- till date towards
the flat. The date of possession as per the agreement is 15.04.2018.
B. That, the complainant/allottees had filed a complaint
CC005000000054113 seeking interest for delayed possession which was
allowed, and the reliefs were granted to the allottees by this Hon’ble
authority vide order dated 04.08.2020. The respondent/promoter has
filed an appeal against the order bearing Appeal No.
AT005000000052662 and the same is subjudice.
C. Thus, the complainant is seeking refund along with interest and
compensation as per amendment application at Sr. no. 4.
1
Pune Metropolitan Region Development Authority.
Page 5 of 8
56
9. From the facts and submissions made by both the parties the issue that needs to be
examined at this juncture is as follows:
A. Whether the complainants/allotees are entitled to the reliefs claimed under
Section 18 and 19 of the Act?
10. Before determining the issue at para-9A, the following observations are noteworthy:
A. It is observed with respect to complaint at Sr.1 that, the complainant had earlier
filed a complaint bearing No. CC005000000054113 before this authority which
was adjudicated by Hon’ble Member 2 seeking reliefs of interest which was
granted vide order dated 04.08.2020. The relevant part of the order is
reproduced hereunder for ease of reference:
“A. The respondents shall pay simple interest at the rate of 9% p.a. on the
complainants' amount of consideration Rs. 34,69,896/- from 16.10.2018
till handing over possession of their flat with occupancy certificate or
completion certificate.
B. The respondents shall also pay the complainants Ps.-20,000/- towards the
cost of their complaint.
C. The parties are at liberty to adjust their respective current claims and pay the
Page 6 of 8
57
FINAL ORDER
11. Therefore, after considering the above-mentioned observations and provisions of
the act, the materials placed on record, the facts of the case and submissions made
by the parties, the authority passes the following order:
A. The complaint at Sr. no.1 along with applications at Sr.no.2 & 4 are dismissed.
B. The complaint at Sr. no.3 is allowed.
C. The allottee is entitled to claim interest for delay in handover of possession on
the total amount paid to the respondent (excluding amounts paid towards
taxes and other charges such as stamp duty, registration fees and such other
Page 7 of 8
58
amounts paid to statutory authorities) from the date 01.04.2021 at the rate as
prescribed under Rule 18 of the Maharashtra Real Estate (Regulation and
Development) (Registration of Real Estate Projects, Registration of Real Estate
Agents, Rate of Interest and Disclosures on Website) Rules 2017 till the date of
delivery of possession i.e., .
D. The respondent/promoter is directed to allot a covered car parking space as
per the terms of the agreement or to make any alternative provisions for a
covered car parking space till the actual allotment of parking space.
E. The total arrears of interest accrued, shall be set off /adjusted against any
outstanding dues or interest required to be paid by the allottee towards the
cost of the subject flat and the remaining amount, if any, shall be paid by the
promoter in one instalment to the allottee within sixty days from the date of
this order.
F. All other reliefs claimed by the complainants in complaint stand rejected, save
and except what has been mentioned hereinabove in para 11-A to 11-E.
G. No order as to cost.
Manoj Saunik
Chairperson, MahaRERA
Page 8 of 8
59
0
Index
Sr.No Particulars
1 Complaint Copy- (Form A) Complaint to the Authority
2 Copy of relevant pages of Agreement to Sale dated 16/04/2016
3 Copy of relevant pages of Agreement to Sale dated 16/04/2016 showing the period
of possession
4 Copy of the Order in RERA Complaint no. CC005000000054113 dated 04/08/2020.
5 Copy of the Interest Calculation Sheet.
6 Copy of the Recovery Warrant dated 23/12/2020
7 Copy of the Partial Occupancy Certificate dated 11/12/2020
8 Copy of Index-II showing such discrepancy
9 Copy of the Index-II of adjacent Flat 504 situated on the Fifth Floor of 'C'
Building in the project "Kingston Aura
10 Copy of the Sanction Plan drawing dated 17/6/2014 obtained under RTI Act 2005
11 Copy of Respondents stated submission for delay reason in prior Complaint no.
CC005000000054113 trails and appeals
12 Copy of "Declaration about Commencement Certificate" that the Respondent
disclosed on the MahaRERA website.
13 Copy of "Society Registration Certificate" that the Respondent disclosed on the
MahaRERA website.
14 Copy of a legal notice dated 24/12/2020 and emails sent on 16/07/2021 &
22/09/2021 to the Respondent.
15 Copy of the legal notice dated 13/10/2021 & 15/03/2022 sent to the Respondent.
16 Copy of Respondent’s under calculated compliance report as submitted in the
Appeal matter.
17 Copy of Partial Occupancy Certificate dated 30/12/2022.
18 Form B - Application to Adjudication Officer
60
1
Form 'A'
[see rule 6]
COMPLAINT TO THE AUTHORITY
(Complaint under section 31 of the Act)
Date of filing:…………………………………………………………………………………
Complaint No.:………………………………………………………………………………
Signature:…………………………………………………………………………………….
Authorized Officer:………………………………………………………………………….
Between
1. Miss. Poonam Mewalal Gupta
(Mrs. Poonam Charles Kumar)
2. Mr. Charles Suresh Kumar …Complainant(s)
Versus
M/s. Vedant Estate & Properties
Through its Partners
a) Sandeep Deepak Agarwal
b) Shashikala Deepak Agarwal ….Respondent(s)
Details of claim:
(M): 9923052850
E-mail ID:
[email protected]
citizens of India and had booked a unit in the project being developed
and constructed by the Respondent under the name 'Kingston Aura'
located at Autade Handewadi, Pune - 411028.
3) That Complainants were looking for a suitable flat in Pune for their
dwelling and they came to know about the scheme of the Respondent
via advertisements undertaken by Respondent. The Complainants
had purchased a Flat No. 503, situated on the Fifth Floor in 'C'
Building in the project "Kingston Aura" registered with MahaRERA
vide project Registration No. P52100005126 being constructed by the
Respondent at Autade -Handewadi, Tal. Haveli, Dist. Pune
(hereinafter referred to as "the said Flat") vide Agreement to Sell
dated 16/04/2016, which is duly registered with the Sub-Registrar,
Haveli No.-10 vide Sr. no. 5697/2016 on 18/04/2016, for stated Flat
Carpet area admeasuring 64.68 sq.mtrs (696 sq.ft) and terrace
admeasuring 11.98 sq.mtrs (129 sq.ft), i.e. 103.62 sq.mtrs (1115
sq.ft) saleable Built-up including the proportionate area of passage
along with exclusive right to use one Car Parking Space No. 'C-07' in
the aforementioned project of stated true market valuation of Rs.
42,90,700/- (Rupees Forty-Two Lakh Ninety Thousand Seven
Hundred Only) computed by the Respondent at the prevailing year
2015-16 Annual Schedule of Rates (ASR) / Ready Reckoner Govt.
Rate of Rs. 38,280/- Per Sq. mt, for an agreed consideration amount
of Rs. 40,53,400/- (Rupees Forty Lakh Fifty-Three Thousand Four
Hundred Only). The sale of the said Flat was based on carpet area
only as per MOFA. Attached herewith is the copy of relevant pages
of the Agreement to Sale dated 16/04/2016
64
5
5) The Complainants submit that, as per the agreed terms of the said
agreement, these Complainants were to receive possession within 24
months from the date of the agreement, i.e. on or before
15/04/2018. However, the possession was delayed, and these
Complainants were constrained to file a complaint under RERA
bearing no. CC005000000054113 before the MahaRERA Authority.
Attached herewith is a copy of the relevant pages of the
Agreement dated 16/04/2016 showing the period of possession.
10) The Complainants submit that they have learned that the Respondent
has received a Partial Occupancy Certificate dated 11/12/2020
issued for their project 'Kingston Aura' from the competent authority,
i.e., the Pune Metropolitan Region Development Authority. The
Complainants had to run from pillar to post to obtain a copy of the
same. Since the Respondent has obtained the Partial Occupancy
Certificate, it was his duty and responsibility to intimate the same to
the Complainants and hand over the possession of Flat no. 503 in 'C'
Building to these Complainants. But, to date, the Respondent has
deliberately not handed over possession to these Complainants. Even
after a lapse of over 25 months, particularly when the Respondent
has received the substantial amount towards the flat in the year 2018
itself. Attached herewith is a copy of the Partial Occupancy
Certificate dated 11/12/2020.
66
7
11) It is pertinent to note that after receiving Sanction Plan copies under
RTI by these Complainants, (which has been revised by the
Respondent time to time without the Consent of these Complainants),
it reveals that Flat Carpet Area mentioned in the said Sanction Plan
and in the agreement is mismatched. The Complainants also noticed
the descripancy in the valuation of Government Ready Recknor Price
after perusing the other flat agreement executed with the other
allottee/s by the Respondent. The Respondent had deliberartelty
shown inflated valuation at the time of registration of the flat
Agreement dated 16/04/2016. Attached herewith copy of Index-II
showing discrepancy. If the Hon‟ble Authority peruses the copy of
Index-II then it will conclude that the Respondent had deliberately
stated inflated rate of Government valuation, so that the buyers came
put forward and purchase the said flat below the rate of said
government valuation and on such fraudulent presentation, these
Complainants had purchased the said flat for the said consdeiration
which was as such shown by the Respondent. This itself shows the
malafide intention of the Respondent to bait the Buyer/s who can
come forward to purchase the flat in their project. Attached herewith
is the copy of the Index-II of adjacent Flat 504 situated on the
Fifth Floor of 'C' Building in the project "Kingston Aura".
12) The Respondent had never produced a copy of the sanction plan
drawing dated 17/6/2014 before these Complainants at the time of
booking, they had just provided a bogus floor plan that was attached
to the Agreement. The Complainants are ordinary citizens, therefore,
not aware about the knowledge of the sanction plan, hence, they
trusted Repondent‟s said fact at the time of registration of their
Agreement dated 16/04/2016 but while obtaining and perusing the
Sanction plan drawing dated 17/6/2014 it was noticed that the carpet
area mentioned in the agreement and shown in the actual sanction
plan at the time is mismatched. After appreciating the said fact, these
67
8
Complainants were shocked and realised that they had paid a higher
amount to the Respondent against their Flat on the basis of such
fraudulent disclosures made by the Respondent about the carpet
area. Hence, the Respondent is liable to refund the additional amount
that was received by them through such fraudulent disclosures. The
agreement was executed under the MOFA Act, and the above finding
is in volition of the same. Attached herewith is the copy of the
Sanction Plan drawing dated 17/6/2014 obtained under RTI Act
which was prevailing at the time of Complainants Sale Agreement
dated 16/04/2016.
13) The Complainants have put their hard earned money and savings
towards buying their first house from the Respondent with agreed
delivery / possession of their Flat by 15/04/2018 (24 months from
the date of registered agreement), but then the Complainant have
been waiting for almost 7 years to live in their own house. If the
Hon‟ble Authority peruses prior Complaint no.
CC005000000054113, in the Respondent‟s stated submission for
delay in project completion and possession it shall find conflicting to
what the Respondent have stated as the reason for the said delay and
the subsequent Complainants aggrieving factual findings showing the
malifide intentions of the Respondent. Attached herewith is a copy
of Respondents stated submission for delay reason in prior
Complaint no. CC005000000054113 trails and appeals.
14) The Respondent had revised the project sanction plan time and again,
especially dated 31/12/2016 and 07/06/2021 without obtaining the
express consent of these Complainants, including other allottees of
the said project, and introduced new buildings in the project, i.e.,
Buildings F & G & extending additional floors in the Buildings A, D &
E which were never part of the earlier sanction plan dated 17/6/2014
legitimate at the time of this Complianants Agreement to Sell dated
68
9
15) It is brought to the Hon‟ble Authority notice as is shown per the initial
Sanction Plan drawings dated 17/06/2014 and its NA
Commencement letter dated 05/03/2015 which were approved by the
Town planning development jurisdiction under Rural Gram Panchayat
of Autade Handewadi, under which the Resdondent began marketing
the project and baiting unaware citizens as the Complainants into
purchasing unit in their project by fraudulent disclosures and
misrepresentations. The ulterior motive of the Respondent to without
Complainants express consent first revisions of the sanction plan on
31/12/2016, when the project came under PMDRA jurisdiction with
a revised Commence Certificate dated 31/12/2016 and extending the
project timeline, and second present revision of the sanction plan on
69
10
18) Until the filling of this Complaint, the Repondent has not come
forward or provided Complainants with any written clarification on
their seeked information and grieavances regarding the actual
dimensions, reduced carpet area and impact on the Govt. Ready
Reckoner valuation on their purchased Flat 503 in building „C‟ of the
project „Kignston Aura‟ following the Respondent‟s unilateral multiple
sanction plan modifications. Thus, by pursuing the details of
equivalent adjacent mirror Flat 504 Sale deed dated 21/02/2018
executed at Haveli 10 in Pune Doc No.3093/2018 which was as per
the modified Sanction plan 31/12/2016, the Complainants can
establish, based on the 2016 prevailing Ready Reckoner Rate of Rs.
38280, that the Complainants constructed Flat 503 actual Govt.
Valautaion is approximately Rs. 34,47,882/- (Rupees Thirty Four
Lakh Forty-seven Thousand Eight Hundred and Eighty-two Only).
Further more as the Complainants agreed to purchase the said flat as
Repondents offered the same below Govt. Valuation and after
adjusting a proportionate 5.5% reduction the actual consideration
amount shall be Rs. 32,58,246/- (Rupees Thirty Two Lakh Fifty-
71
12
19) It must also be noted by the Hon‟ble Authority, that the Respondents,
without consulting the Complainants or offering the possession of the
flat or any settlement for the Complainants rights violations and
grievances until the filing of this complaint, have unilaterally adjusted
the disputed balance payment of Rs. 5,83,531/- from the accruing
delay interest amount awarded in Order dated 04/08/2020 of
Complaint no. CC005000000054113 to falsely show compliance
before Hon‟ble High Court and before MahaRERAT in MA for
Restoration in Appeal AT005000000052662, by under calculating the
delay compensation amount due for delay in legal possession of
Complainants Flat. This Act of Respondent reflect their malicious
intent to make Complainants suffer and delay justice for them.
Attached herewith is a copy of Respondent’s under calculated
compliance report as submitted in the Appeal matter.
21) Because of the said illegal acts of the Respondent, these Complainants
have suffered mental agony and financial losses for all of which the
Complainants are entitled for compensation and seeking penal and
criminal action against the Respondent for mispresentation,
misapproproriating Complainants money by means of fraud and
breach of trust.
k) Any other just and equitable order may be passed in favor of the
Complainant.
Place: Pune
Date: 18/02/2023
DECLARATION
I further declare that the matter regarding which this complaint has been
made is not pending before any court of law or any other Authority or any other
Tribunal(s).
Place: Pune
Date: 18/02/2023
Complainant Name: Poonam Mewalal Gupta & another Compliant No: CC005000000054113
34,69,896 13,56,967
t ) /2 23re/2oRo-oR
feis/o/20RR
HERTE TTHT
TIquit HTUTYA
fe5TRE TRT HRCT TTAT TYT ,
H./4,/337/2,6/3/3,/37,/33,t/8,6/4/3.6/4/3,
qpff
34qrty
MM
HET, ATR
(.3T.A.uts)
f i C/o/Ro
( qUT TT (8), TuT
115
116
117
118
119
120
121
122
123
To,
M/s. Vedant Estate and Properties,
4. Additionally, we are also awaiting the actual dimensions and area of the
constructed flat, since in our opinion the constructed flat is of reduced Carpet
Area and True Market Valuation than what was described in Sale
Agreement as stated in Point 1. We seek technical clarification from you in
writing on this matter, as we are uncertain of the impact due to your
subsequent unilateral modification to the project Sanction Plan or maybe due
to utilization of increased land potential or benefitting from Transferable
Development Rights (TDR) and changes to FSI/FAR.
5. Being a first-time home buyer and in hope of a better life we had put our
trust in you and your integrity, when we entered into Sale Agreement for our
Dream Home. Thus, we implore and urge you to fulfill your obligation as
promoter, besides respecting our rights as unit buyer / allotees in project
Kingston Aura, also praying you to comply with the Complaint No.
CC005000000054113 Order passed by Hon’ble The Maharashtra Real
Estate Regulatory Authority.
Regards,
Contact # +91-9923052850
2 attachments
Legal Notice_Mr. Charles Kumar 24-12-2020 (1).pdf
1315K
Copy of MahaRERA Order and Recovery Warrant.pdf
4899K
127
128
129
130
alc
Le.qal Notice
To,
M/s. Vedant Estate and Properties,
Through its Authorized Partner
Mr. Sandeep Deepak Agarrral,
Having its office at: 10 1, Dattaguru Complex,
Lane No. 6, Koregaon Park,
Above Bank of India, Pune - 411001
Sir,
Notice_Page 1 of 7
\
\o 131
Notice_Page 3 of 7
133
Notice_Page 5 of 7
135
Advocate
Notice_Page 7 of 7
137
138
139
140
141
142
143
144
145
146
1
147
2
148
3
149
4
150
5
151
6
152
7
153
8
154
9
155
10
156
157
158
159
160
Reply Notice
Through Email
Subject: - Reply to CRM Vedant Email Notice dated 16th March-2024, for
Inspection & Possession of project Kingston Aura Flat C-503.
After 7 years 11 months wait, we finally received your Notice for Inspection &
Possession of the Kingston Aura flat C-503 on 16th March-2024. Please find our
following noted summarization of events, our interim findings basis permitted
inspection and consulted expert assessment of your constructed project unit.
A. Brief
1|Page
161
4) Since you failed to show justifiable and reasonable cause for non-
compliance with the order, a warrant for recovery of the interest amount
under Section 40(1) of the RERA was issued on 28th Dec-2020.
Accordingly, MahaRERA has forwarded the recovery warrant to the
Collector, Pune, as of till date is pending execution. (MahaRERA
Recovery Warrant Ref. No. MahaRERA/VH/WARRANT/111/12/2020).
5) You, being aggrieved with the order passed by the Hon’ble MahaRERA
Authority, filed an Appeal bearing No. AT005000000052662 before the
Hon’ble Maharashtra Real Estate Appellate Tribunal, Mumbai, on 29th Sep-
2020. In the said appeal along with your various grounds and presented
exhibits, you also submitted Exhibit D on Pagination-126 an Architecture
Completion Certificate by Vilas Tarwadi stating that, the construction
is according to the plans sanctioned vide order No.
PMH/NA/SR/320/2014 dated 5th March-2015 and No provision of
the Act or the building Regulations, no requisitions made, condition
prescribed or orders issued there under have been transgressed in
the course of the work. You’re this Appeal bearing No.
AT005000000052662 as for your knowledge was dismissed for want of
compliance by Hon’ble Maharashtra Real Estate Appellate Tribunal,
Mumbai, vide order dated 18th March-2021 and subsequent restoration
of appeal AT005000000052662 by order of Hon’ble High Court in SA
No.423 of 2021 was again dismissed for want of your appearance and
other grounds by Hon’ble Maharashtra Real Estate Appellate Tribunal,
Mumbai, vide order dated 6th September-2023.
6) It must also be noted by yourselves, as per the Hon’ble MahaRERA
Authority CC005000000054113 Order on the Recovery Application
dated 28th Dec-2020, you were directed to form the Association / Society
of the Allottees and register it in 15 days. In compliance of the order, you
have made available on the Maha RERA website the Society Registration
Certificate dated 8th Jan-2021, it was obligatory and binding on you to
execute and register a conveyance deed in favour of the association of the
allottees of the apartment or the common areas as per both MOFA & RERA
Acts. Which as per our learning you have not yet fulfilled, neither are you
forthcoming with any clarification.
Issuance of Partial Occupancy Certificate reason of suspicions :-
7) As we learned that the Partial Occupancy Certificate dated 11th Dec-2020
issued for the project 'Kingston Aura' from the competent authority, i.e.,
the Pune Metropolitan Region Development Authority. We have reached
out to you multiple time seeking clarification on suspected discrepancies;
however, you willfully kept restraining us from providing any explanation,
restraining of access to the approval documents and restricting admission
to premises of the project to inspect our flat, as in the events of 9th May-
2023 pertaining to your representative using their muscle
power/dominance. Your and your employees’ conduct on numerous
occasions have caused an experience of great pain and suffering for us
having paid an enormous amount for the purchase of a ‘Dream Home’.
8) After running from pillar to post to obtain information through multiple
RTI applications as recent as 24th Jan-2024 and consulting multiple
experts and basis the technical & legal report dated 22-June-2023,
STRUCTURAL REVIEW & OPINION - KINGSTON AURA by YG Consulting
& Engineers LLP-Delhi, Oculus Legal-Delhi, Adv. Nilesh Borate and others.
Also, we acknowledge valuable support of the authorities and honest well-
wishers in enabling factual discoveries and various breach of our rights by
yourselves. Having experienced your non-cooperation, dishonest
disclosures, suppression of truths, refusal and unlawful restraint pushing
2|Page
162
3|Page
163
4|Page
164
granted permission.
2. Now after pursuing Pune Metropolitan Region Development Authority
(PMRDA) through applications under Right to Information Act 2005 and
appraising the obtained N.A. & construction permission by The Collector,
Pune, vide its order No. PMH/NA/SR/320/2014 dated 5th March-2015
and the approved construction drawing plan dated 17th June-2014
therewith detailed in granted permission, we found to our shock and
revelation you baited us with the false and fraudulent disclosure about
Carpet area, Built-up area, dimensions, Govt. True Market valuation,
intentional omissions and other violations regarding project ‘Kingston
Aura’ & sold unit Flat C-503.
5|Page
165
3. On our inspection of the project ‘Kingston Aura’ & Flat C-503 in response
to your ([email protected]) CRM Vedant email notice dated 16th
March-2024, we submit to you being aggrieved and affirming that the
constructed flat is not as per the executed agreement stated N.A. &
construction permission by The Collector, Pune, vide its order No.
PMH/NA/SR/320/2014 dated 5th March-2015 and the approved
construction drawing plan dated 17th June-2014 therewith detailed in
granted permission. In contrast we duly bring to your notice, your attested
own submissions in the proceedings of our delay possession Complaint
CC005000000054113 with Hon'ble MahaRERA Authority and your
appeals against the impugned order is that per the Architecture Certificate
(see above, Section A: Point-5) the building that is indicated ready in Aug-
2019 is not as per the granted permission No. PMH/NA/SR/320/2014
dated 5th March-2015. For such unit buyer / allottee rights violated
construction you applied and obtained Partial OC granted on 11th Dec-
2020, furthermore on 7th June-2021 you got the unconsented unilateral
illegal constructions regularized by sanction plan revision provisions with
about 99 more flats/units (refer. Section B; Point-v). This act of yours is
absolute misuse and exploitative for the end-user consumer the allottees
as us, therefore you have breached our trust, severely caused damages to
our investments both in time & money, compromised the quality and the
amenities. Based on your conduct and violations it is clear you have no
regard for the rights of allottees, nor for the established MOFA & RERA
promoter obligations. Thus, our ‘Dream Home’ has been completely
compromised and the same is non-existent.
4. As of today, after 7 years 11 months 21 days delay during which we
continue to endure significant financial hardship living on rental
accommodation, compromised living to make ends meet in servicing the
Axis Bank Home Loan A/c PHR157601867178, as this is to be our first
and only house we qualified and are recipients of Pradhan Mantri Awas
Yojana launched by Hon'ble Prime Minister Shri Narendra Modi ji. Families
majorly avail home loan top-up for home furnishing, renovation, revamp,
besides other life enriching reasons. Contrariwise we had to rely upon top-
up loan funding to cover the cost of litigations which sadly was blatant
attempts to oppress us, delay & deny justice for our sufferings. The mental
agony and harassment we experienced is beyond words, suffering multiple
anxiety & stress related hospitalizations. Our personal and professional
lives and marriage suffered, because of the lack of our own home we
deferred family planning. Now we just often painfully reminisce and
wonder how different our life could have been and the opportunities we
lost having got entrapped in your scam.
5. Lastly Under Protest with absolute reservation of our unit buyer /
allottees rights and privileges including initiating appropriate legal
remedies for the damages and sufferings caused to us due to your violation
of our trust & rights. We are willing to take Possession of the disputed
Kingston Aura flat C-503 on following conditions.
a. With our rights reserved to seek restoration of original granted N.A.
& construction permission by The Collector, Pune, vide its order No.
PMH/NA/SR/320/2014 dated 5th March-2015 and the approved
construction drawing plan dated 17th June-2014 therewith detailed
in granted permission. Presently pending listing for hearing before
MahaRERA through our Complaint No: CC005000000228339.
6|Page
166
Place :- Pune
Mrs. Poonam Charles Kumar
Mr. Charles Suresh Kumar
Unit Buyer / Allottees
[email protected]
[email protected]
PTL
+91-9923052850
7|Page
4/6/24, 7:15 PM Gmail - Regarding Possession letter for flat C-503
167
Dear Sir/Madam,
I am happy to inform you that your flat no - C-503 in project Kingston Aura is ready for
possession. So Kindly request you to visit the site as earliest as possible and sign on the
possession checklist. After this process is completed you can come and collect a possession
letter from the Head office.
Best Regards,
Crm Team,
VEDANT DEVELOPMENTS.
Dattaguru Complex, Lane No. 6
Above Bank of India Koregaon Park Pune - 411 001
Maharashtra State [INDIA]
Tel: 020-67623118
web : www.vedantdevelopments.com
https://mail.google.com/mail/u/0/?ik=d9f82b0140&view=pt&search=all&permthid=thread-f:1793677042148869684&simpl=msg-f:1793677042148869684 1/1
168
Disclaimer: This Report has been prepared by taking into consideration the expert opinion of lawyers, structural engineers and other
professional(s) by YG Consulting & Engineers LLP on the basis of the documents shared by Mr. Charles Kumar, the allottee of Unit No. 503,
5th Floor, Wing - C, Kingston Aura, Handewadi, Pune, on the basis of the information and documents obtained from the public domain
including the portal of Maharashtra RERA and other documents and information obtained directly from the Competent Authority(s). The
purpose of this Report is to point out the various violations and acts of overstepping the law committed by the Promoter which in turn has
widely prejudiced the project and its allottees. YG Consulting & Engineers LLP bears no responsibility of the opinion formulated on the basis
of any incorrect information, fact and/or document(s) (if any) available online. This review and opinion is simply to help the cause of the
suffering allottees and point out to the concerned Competent Authority(s) the various illegal acts committed by the Promoter in the captioned
project. That this document is nothing but an assessment and opinion of experts the authors do not intend defamation, libel or any such
unwarranted loss to the project or its Promoter. That this present document shall be read and interpreted in absolute conformity of the
documents/plans/information attached herein as Annexures.
1|Page
fi
169
TABLE OF CONTENTS
ANNEXURES
2|Page
170
Brief Background:
M/s Vedantestate and Properties, a partnership firm registered under the Partnership Act,
1932, hereinafter referred to as “Promoter” proposed to develop and sell a real estate
project in the name and style of “Kingston Aura” proposed to be developed at Village
Aubade Handewadi, Taluka Haveli, District Pune, within the limits of Zilla Parishad, Pune,
Taluka Panchayat Samitee Haveli Pune hereinafter referred to as the “Project”. The said
project was marketed and thereafter sold to the public at larges some time around 2014 -
2016. The said property, hereinafter referred to as “Project Land” is admeasuring 88.25
Acres (28,825 Sq. Mts.).
Thereafter, in the year 2016 the parliament of India introduced the Real Estate (Regulation
& Development) Act, 2016 hereinafter referred to as “RERA Act”. The said Act was
notified in the year 2017. In compliance of the Section 3 read with Section 4 of the RERA
Act the Promoter duly registered the said project with the Maharashtra Real Estate
Regulatory Authority, hereinafter referred to as the “Authority” vide registration bearing
No. P52100005126 vide Registration Certificate dated 09.09.2021 for a period commencing
on 09.08.2017 to 30.03.2022.
In the year 2016, one Mr. Charles Suresh Kumar & Ms. Poonam Mewalal Gupta,
hereinafter referred to as the “Allottee” were approached by the marketing representatives
of the Promoter for sale of a flat in the captioned project. Thereafter, an Agreement to Sell
dated 16.04.2016 duly registered with the Sub Registrar, Haveli No. 10, vide Sr. No.
5697/2016 was executed between the Allottees and Promoter for sale and purchase of a flat
bearing no. 503, 5th Floor, C-Wing admeasuring carpet area 76.67 Sq. Mt. (825 Sq. Ft.) for
a total sale consideration of Rs. 40,53,400/- (Rupees Forty Lakhs Fifty-Three Thousand
Four Hundred Only) hereinafter referred to as the “Unit”. It is noteworthy that a floor plan
demarcating and specifying the dimensions of the flat had also been attached with the said
registered Agreement to Sell.
As per the provisions of Section 4 of the RERA Act, 2016 the Promoter was liable to upload
true and complete information as prescribed thereunder on the portal of the Authority. In
compliance, of the said mandate of the law the Promoter has uploaded certain Building
Plans and other information on the web portal of the Authority. On examination of the portal
it has become outrightly clear that the information submitted/uploaded by the Promoter is
incomplete. Furthermore, on inspection of the portal it was revealed to the allottees that the
dimensions, specifications of their unit and that of the project as a whole are in contradiction
to the terms and conditions and promises made by the Promoter at the time of allotment. It
is also evident that there are certain violations that seem to have been committed by the
Promoter in contravention to the provisions of the RERA Act, 2016, Maharashtra Flat
3|Page
171
This case study and the conclusion herein is based out of the various documents at hand
including but not limiting to those submitted by the Promoter to various Competent
Authorities, Agreement To Sell dated 16.04.2016, applicable laws etc. The purpose of this
analysis and the opinion formulated thereunder is to point out the various violations
committed by the Promoter in regards to the captioned project, the safety hazards entailing
such violations and to also point out the various laws that have been bypassed by the
Promoter in the commission of such violations.
Furthermore, for a concise understanding of events herein above elaborated a list of events
has been tabulated herein below:
Timeline
Applicable coming
Date Event Notes
into Force.
4|Page
172
5|Page
173
2nd Partial
As per the applicable Rules and Regulations
Occupancy
thereunder, upon the request of the holder of
Certificate for
the building permission the Authority may
Wing A, Wing D,
issue a part occupancy certificate for a
and Wing E was
building or part thereof, before completion of
obtained for the
the entire work as per building or part
Project
thereof, before completion of the entire work
as per building permission provided sufficient
30.12.2022 The OC was
precautionary measures are taken by the
granted
holder of the building permission to ensure
arbitrarily i.e.
public safety and health safety, The part
without the
occupancy certificate shall be given by
consent of the
Authority subject to the owner indemnifying
Allottees
the authority as per the given Partial
inclusive of extra
Occupancy Certificate Appendix B of the said
units and major
Rules.
changes in the
layout.
As on date the current status of the Project is
such that the construction/completion of the
Project remains to be incomplete. The
Promoter/Developer is yet to obtain
Present Day Completion Certificate and Complete OC in
respect of the project as can also be
understood from the perusal of the
information uploaded on the MahaRERA web
portal.
6|Page
174
The Plans uploaded on the portal of the Authority are dated 2016 or thereafter but on perusal
of the documents, public record of the Town Planning & Valuation Department, Pune
Branch and other Competent Authority(s) it has been revealed that the Promoter has
obtained sanctioned plans as earlier as 2014. As per the said sanction plan dated 21.05.2014
including the relevant building plans, layout plans etc the proposed project had 5(five)
towers/wings namely A,B,C,D & E each of the said towers/wings compromised of G+11
Floors.
More particularly, the unit in question i.e. 503 has been reflected in ‘C’ Wing (5th Floor
Plan).
A copy of the sanctioned Plans obtained in the year 2014 have been attached herein as
Annexure ‘A’.
It is noteworthy, that on perusal of the portal of the Authority it is appropriately clear that
the Promoter has uploaded certain sanctioned plans and requisite documents on the said
portal but there seems to be clear cut concealment of facts and documents including certain
sanctioned plans that are relevant to the said subject project. To point out, the entire set of
Updated/Revised Sanctioned Plans including the Approval Letter for such revision/
alteration has not been uploaded on the portal further, for instance, Section Plan is not
uploaded, the Elevation Plan pertaining to ‘C’ Wing has not been uploaded and so on so
forth. The biggest concealment of it all is this that the Promoter has categorically failed to
upload the Latest Permission/Approval/NOC obtained from the Competent Authority(s) for
additional towers/wings i.e. Wing - F & Wing - G.
As per the plans and information available on the portal it can be seen that the dimensions/
specifications and the layout of the unit in question have been changed more particularly the
balconies have been altered with. It is also important to point that major changes in the floor
plans have also been undertaken such as the location of Passenger & Service Lifts have
been changed in contradiction of the original sanctioned plan.
Further perusal of the plans showcases that the total height of certain towers/wings has been
changed as per the initial sanctioned plans all the towers/wings were G+11 Floors as of now
the same has been changed G+13/14 Floors, basement(s) have also been added.
7|Page
175
It is also relevant to point out that the initial footprint of the Building and the existing
footprint more particularly of the Wing - C has also been changed/altered.
A copy of the sanctioned Plans as uploaded on the portal of the Authority dated 2016 or
thereafter have been attached herein as Annexure ‘B’.
Hereinbelow, portions of the sanctioned plans have been extracted and thereafter points of
relevance have been marked out to point out the changes/alterations/variations:
Figure 1
8|Page
176
Figure 2
9|Page
177
Figure 3
Figure 4
10 | P a g e
178
Figure 5
11 | P a g e
179
Figure 6
NOTE: The latest pictures of the project have been added as Annexure ‘C’. The pictures have
been clicked from various angles to showcase the construction of the project in contradiction to
the approved plans and also to show the current status.
12 | P a g e
180
From perusing through the above mentioned figures/extracts the following comparative
table has been drawn to summarise the changes:
13 | P a g e
181
Analysis of Applicable provisions of the National Building Code, 2005 (as amended
time to time)
The National Building Code, 2005 (as amended from time to time) is the Bible that all
professionals including architects, engineers, contractors, builders, developers including the
Promoter of the subject project are bound by for development of a real estate project across
the country.
As discussed in the paras above the Promoter has advanced various changes in the
Sanctioned Plan so it is imperative to look at the various provisions of the National Building
Code, applicable to the project at hand:
I. At the very outset it is to be pointed out that the Promoter has not uploaded the Fire
Safety Plan on the portal of the Authority and neither uploaded the NOC (No Objection
Certificate) that is to be obtained from the fire safety point of view from the concerned
Fire Department. The Fire Safety Plan approved by the Competent Authority depicts the
fire safety facilities in the project including routes of evacuation, exit etc.
II. As per Rule 12.7 of the Part - II, ‘Administration’ of the National Building Code,
2005 (it has not been reproduced herein for the sake of brevity) it has been prescribed
that for any deviation from the sanctioned plans, revised plans shall be sanctioned by the
Competent Authority in this case Town Planning & Valuation Department, Pune Branch
or any other Competent Authority and due procedure for the previous sanctioned plan
shall be duly followed. In the instant case, the Promoter has never disclosed the
existence of a previous Sanctioned Plan or the fact that there has been any deviation/
revision from the same to an extent that even towers/wings have been further added. As
per the disclosures made at the time of registration of the project with the Authority only
plans dated 2016 or thereafter have been uploaded. There is no material on record to
show whether or not the Promoter has duly disclosed/complied with the directives as
mentioned above.
III. As per Rule 12.10.1 of the Part - II, ‘Administration’ of the National Building Code,
2005 (it has not been reproduced herein for the sake of brevity) it is mandatory that the
approved, sanctioned building plans of the subject project should have been scrutinised
by the concerned Fire Authority/Department. As per the information on public domain it
is not clear whether or not the said approval of the Fire Department has been obtained.
Furthermore, in the sanctioned plans post 2016 the structure of the concerned towers has
been changed and post the said changes it is unclear whether approval of the concerned
Fire Department has been obtained.
14 | P a g e
182
IV. As per Rule 9.6 of the Part - III, ‘Development Control Rules and General Building
Requirements’ of the National Building Code, 2005 (it has not been reproduced herein
for the sake of brevity) in case of a “Group Housing” project it has been provided as to
the permissible density, FAR (Floor Area Ratio), Maximum Ground Coverage etc. As
per the sanctioned plans dated post 2016 it is clear that the FAR has been increased, it
has not been disclosed as to on what basis the FAR has been increased and/or whether
the Promoter has complied with the applicable Structural Safety Norms, Policy Norms
that are applicable for such increase in FAR.
15 | P a g e
183
In consonance with the National Building Code, being the central code for construction
States have codified their own Building Byelaws to be applicable within the subject state.
Likewise, Maharashtra Building Byelaws are applicable to the subject project.
The relevant Rules to be discussed in the facts and circumstances of the subject project are
as such:
Part V of the said By-Laws enlists the conditions and pre-requisites under which
additional FSI may be granted to a Residential Building on various occurrences such as
widening of roads, Buildings of PSUs, amongst others.
In the instant project the Promoter has failed to disclose or adduce any document of
relevance as to on what grounds additional FSI has been obtained neither has he produced
on record any sanction, approval, NOC etc on record to show such grant of additional FSI.
16 | P a g e
184
From a perusal of the Agreement to Sell dated 16.04.2016 it evident that the subject unit
has been defined in Clause 2.1 @Pg. 32-33. The said Clause defines the area of the flat
and that the sale of the said unit shall be only on the basis of Carpet Area, furthermore, it
also mentions that the carpet area is subject of increase of 4-5% and that such increase or
decrease shall render no changes in the Total Sale Consideration agreed upon by the
parties.
Further, in Schedule II (Description of the FLAT) @Pg. 55 of the said Agreement the
unit in question has been defined, the rate at which the total sale consideration has been
fixed has been quoted to be Rs. 38,280/- per Sq. Mt.
The Fifth Floor Plan has been affixed @ Pg. 87 of the said Agreement, at the outset it is
pertinent to mention that the said plan, the readings therein are not legible and the
markings thereunder are unclear. But from the perusal of the same it can be observed that
the common areas, stair case area etc apart from balconies has been pointed out in the
said plan but the same has neither been defined nor explained in the Schedule II and/or
Clause 2.1.
Such lack of disclosures in the said Agreement to Sell contemplate violations of the
provisions of the MOFA Act, 1963, the relevant provisions have been enlisted hereunder:
A. Section 3 r/w Section 4 of the MOFA Act, 1963: That the said provisions of the law
mandate the clear cut disclosure of carpet area of the subject unit, proportionate
percentage undivided interest in the common areas & facilities, the balcony/verandah
areas etc. and that the said disclosure shall duly underlined and explicitly mentioned the
Agreement to Sell to be entered under section 4 of the said Act. In the instant case the
existence of the initial sanctioned plant i.e. those dated as early as 2014 were never
disclosed to the allottees, neither uploaded on the portal of Authority. That the said plans
also do not form matter and content of the Agreement to Sell dated 16.04.2016 contrary
to the directive of the law. As has been elaborated in the paragraphs of previous sections
on perusal of the various plans it is outrightly clear that the dimensions and
specifications of the unit in the plan attached to the Agreement to Sell and those
disclosed before the Authority are different, therefore, it is unclear as to on the basis of
which plan the Promoter has computed Total Sale Consideration and thereafter charged
the same from the Allottees.
17 | P a g e
185
B. Section 7 of the MOFA Act, 1963: In the instant project the sanctioned plans dated
2014 have been changed/altered compared to those of the year 2016 (disclosed on
public domain). The provisions of Section 7 clearly stipulate the obtaining of explicit
consent from the allottees of the subject project before any such alteration, addition or
change as such is effectuated in the building contrary to the already disclosed
sanctioned plans. The Promoter has failed to disclose on the portal of the Authority the
obtaining of any such consent from the respective allottees and therefore without
complying with the mandate of the Law as per section 7 of the MOFA Act, 1963 the
said changes/alterations/variations are blatantly arbitrary.
A copy of the Agreement to Sell dated 16.04.2016 has been attached herein as Annexure
‘D’.
18 | P a g e
186
A. Section 4 of the RERA Act, 2016: As per Section 4 of the said Act the Promoter is duty
bound to disclose all the crucial details of the subject project including but not limiting
to the Sanctioned Plans, the consent of the allottees as per MOFA obtained before the
change/alteration in sanctioned plans, the agreement to sell executed with the Allottees,
the complete set of approved building plans, the approval letter for revision/change in
sanctioned plans, the NOC from Fire Department, Fire Fighting Plans, the approval
from concerned competent authority along with policy documents for the additional FSI
etc. All these valuable disclosures have not been provided by the Promoter in its
application for registration of the Project.
A copy of the Project Details as available on the portal of the Authority have been
attached herein as Annexure ‘E’.
B. Section 11 of the RERA Act, 2016: As per Section 11 of the said Act the various
obligations have been casted upon the Promoter. Under sub class (3) the promoter is
liable to provide the approved layout, sanctioned plans etc to the prospective allottees
along with allotment letter at the time of booking. The said disclosures have not been
provided by the Promoter.
C. Section 12 of the RERA Act, 2016: The allottees booked a unit in the subject project as
per the limited information/documents provided by the Promoter including the floor
Plan of the Fifth Floor, C-Wing wherein the dimensions of the unit in question, the
limited common areas etc have been pointed out and also the layout plan of the subject
project. Compared to the said information as available in the Agreement to Sell the
sanctioned plans as uploaded on the portal of the Authority there are specific changes in
the area of the unit in question, eventhough the consideration was paid off by the
Allottees as per the specific disclosures of the Promoter. Moreover, as on date due to
the increase in the number of wings/towers and the total covered the entire
demographics, density etc of the project stands changed. The agreement to sell executed
and the total sale consideration paid off as on date was strictly basis the initial
specifications of the project, layout/specifications of the unit, demographics, density
19 | P a g e
187
etc . First the Promoter has carried out the said changes arbitrarily and thereafter has
failed to either refund the excess consideration and/or duly compensate the financial
agony borne by the allottees on account of such incorrect disclosures. In terms of
Section 12 of the Act the same amounts to violation of the RERA Act, 2016.
D. Section 14 of the RERA Act, 2016: As per the information available on the portal of
the Authority the sanctioned plans uploaded on the portal date as recent as 2016, 2019 ,
2021 and so on whereas the initial sanctioned plans as obtained from the Competent
Authority date back to 2014 and so on. In the said scenario it is outrightly clear that the
sanctioned plans have been changed/revised/altered and that too after the enactment of
the RERA Act, 2016. Section 14 provides for disclosure of approval and reasoning for
such changes/alterations in the sanctioned plan. It also provides that any such changes
except minor alterations shall not be effectuated without the prior consent of 2/3rd
Allottees of the subject project. There is nothing on record to show the existence of
these mandatory requirements of the law.
E. Section 60 of the RERA Act, 2016: Section 60 of the Act provides for punitive action
wherein the Promoter is liable to be penalised upto 5% of the total project cost for
providing false information under section 4 of the Act. In the instant case as elaborated
the Promoter has deliberately concealed relevant information and failed to provide
absolute disclosure on the said count the Authority shall initiate action under this
provision.
F. Section 61 of the RERA Act, 2016: The Promoter has bypassed provisions of section
11, 12 & 14 of the Act for the said action shall be initiated under section 61 and the
Promoter shall penalised upto 5% of the estimated cost of the project.
20 | P a g e
188
Analysis of Safety Hazards from the point of view of Structural Safety in the subject
project.
1. Proposed Building layout has been changed, balcony(s) sizes have been changed and
the building profile has been tampered with. The total Built Up Area has been
increased which may result in additional dead load and live load on the structure and
same may also adversely affect the foundation system.
2. Attached wings/towers i.e. Wing –A, D & E have been majorly changed with respect
to the height of the towers/wings as has been pointed out in the extracts mentioned in
the above sections. Initially, the proposed Buildings were 11 storeyed and now the
same stand as 13 storeyed. Two additional Floors have been added. It is highly
probable that such addition in number of floors may affect the structural safety and
life of the structure. As a matter of fact, the number of tower/wings in the project
scheme has also been increased it is obvious that such change will effect the entire
demographics and density in the project.
3. Build Up Area has been changed, initially the Built up area of the Wing – C was
4120.80 Sq. Mts. And now as per the latest plans uploaded on the portal of
Maharashtra RERA the same stands at 4357.34 Sq. Mts. Thereafter, the total Built
Up Area of the project has been increased from 27604.54 Sq. Mts. to 29919.79 Sq.
Mts. That the said change amounts to a total increase of 8%.
4. As is visible from the perusal of sanctioned plans in the current sanctioned plans a
basement has also been added in the other wings such as Wing – E and Wing –A
which will peripherally affect the structure and foundation system of other wings
including but not limiting to the Wing – C.
5. That the structural changes pointed out herein more so without the consent of subject
allottees amounts to criminal liability as the lives and the valuables of these allottees
have been subjected to grave risk without their explicit consent and without them
being aware of the gravity of such high risks involved.
6. As per the sanctioned plans if the height of the adjacent towers is increased then it
may affect availability of sun light, fresh air, proper ventilation, access to the
building and various other logistical obstacles to the allottees occupying Wing – C.
7. It also a matter of concern that it remains unclear whether the promoter has obtained
requisite NOCs and Approvals from the structural safety point of view when
21 | P a g e
189
basements have been added in the other towers/wings thereafter height has also been
increased.
8. Even if such Approvals/NOCs have been obtained by the Promoter, the Promoter has
failed to disclose or adduce relevant plans/sanctions to showcase the various safety
measures/structural safeguards that the Promoter has taken keeping in mind the
structural safety of other towers/wings in which basements have not been added/
height has not been increased.
10. In the present case one of the wings/towers is downward with no basement and the
other towers/wings being are in upward strata due to unequal pressure and effects of
soil erosion the building may not sustain during an earthquake and against any other
lateral forces.
22 | P a g e
190
At the outset it is relevant to point out that the expert opinion formulated herein is for the
purpose of evaluation and assessment of various legal and structural safety concerns
revolving around the subject project. The opinion of the concerned experts is independent
and has not been influenced by any favours, benefits, allurements, misrepresentations etc.
The concerned project and its sanctioned plans were approved by the concerned Competent
Authority(s) in strict compliance with the applicable laws including but not limiting to the
Building Code, Building By-Laws, Local Laws etc. Thereafter, based on the said approved
plans the said project was marketed and sold to the public at large. The allottees based on
such plans and approvals agreed to invest and purchase units/tenements in the subject
project.
The acts and omissions of the Promoter are such that even the structural safety, the life of
the structure, safety and security of the allottees/prospective allottees inhabiting the subject
project have been subjected to grave risk. That the said acts are not just illegal but un-
compoundable.
As has been pointed out in various above mentioned sections the actions of the Promoter
call for suitable legal actions under the regime of applicable laws and it is high time that the
concerned Competent Authority(s) including but not limiting to the Authority appointed
under the MOFA Act, 1963, the Maharashtra RERA, the Town Planning & Valuation
Department, Pune so and so forth shall forthwith initiate appropriate action/investigation
into the affairs of the subject project and its Promoter.
23 | P a g e
22.06.2023
191
Versus
5. The Complainants want to add following reliefs apart from the reliefs
sought under the Complaint, the details of the same is as under,
Vs.
INDEX
S. No. Particulars Pg. No.
APPLICATION UNDER ORDER VI RULE 17 OF
THE CIVIL PROCEDURE CODE, 1908 FOR
AMENDMENT IN PLEADINGS
ANNEXURE A/1
A copy of the Pune Times Advertisement dated
18.03.2016
DATE:
PLACE:
COMPLAINANTS
Through Counsel:
ARUL PRAKASH
Advocate
OCULUS Legal
Office No. 103, LSC Pankaj Tower
Mayur Vihar Phase - 1
New Delhi - 110091
8826516187
[email protected]
204
Vs.
That the captioned Complaint and Application are pending before this Learned Authority
and are listed for final hearing on 06.02.2025. The Complainant seeks to bring on record
these submissions and by way of this present Application amend the Prayer Clause in the
captioned Complaint to appropriately assist this Learned Authority to adjudicate the
present Complaint. The same may be taken on record.
I. SUBMISSIONS:
1.3. It is pertinent to note that after the passing of the order dated 04.08.2020, being
aggrieved the Respondent herein had filed an Appeal No. AT005000000052662 before
Hon’ble MahaREAT which was dismissed on 18.03.2021 for want of compliance with
Proviso of Sec. 43 (5) of the RERA Act, 2016. Thereafter, the Respondent filed a Second
Appeal No. 423 of 2021 before the Hon’ble High Court, Mumbai and by order dated
2.2. Further the Respondent has submitted that the delay in the project is attributable to
the Litigation that the Respondent had to pursue before the Hon’ble Bombay High Court
against PMRDA & Ors for non-issuance of Occupation Certificate. As per the
Respondent’s own Admission, the Respondent had to pursue WP-DB-LD-VC No. 32 of
2020 (WP/95407/2020) before the Hon’ble Bombay High Court titled as “M/s Vedant
Estate & Properties vs. Chief Executive Office, PMRDA & Ors.” against the various
orders/communications received from the concerned Competent Authority for non-
issuance of Occupation Certificate. The said Writ Petition was disposed off by the
Hon’ble Bombay High Court vide Order dated 15.10.2020 (Refer Pg. 18-21 of the
Rejoinder of the Complainant) wherein the concerned Competent Authority was
directed to issue Occupation Certificate to the Respondent subject to deficiencies (if
any). Pursuant to the said Order PMRDA issued Partial Occupation Certificate to the
concerned tower of the Respondent (Wing - C) on 11.12.2020. Even after such issuance
of the Partial Occupation Certificate the Respondent did not offer possession to the
Complainant. It is noteworthy, that on no given occasion the said litigation or the
circumstances therein were communicated to the Complainants.
2.3. In complete derogation to the safeguards granted under the provisions of the RERA
Act, 2016 at no stage whatsoever the Respondent duly intimated the Complainants of
207
2.4. Further as per the provisions of Section 18 of the RERA Act, 2016 the Respondent
is duty bound to appropriately compensate the Complainants for failing to adhere to the
terms of the Agreement to Sell dated 16.04.2016. But the Respondent being well aware
of the repercussions conveniently did not even inform the Complainants about the
extended date of delivery, the ongoing litigation and disputes with the Competent
Authority. That the said information has come to the knowledge of the Complainant at
this belated stage when the Respondent filed its reply leaving no choice for the
Complainants but to file this present Application.
and Development) Act, 2016. These violations not only compromise the structural
integrity and safety of the project but also expose a deliberate disregard for statutory
norms.
3.2. On 09.05.2023, Complainant No. 2, Mr. Charles Suresh Kumar, attempted to inspect
the flat along with an expert evaluator. However, he was wrongfully restrained,
threatened, and intimidated by officials acting on the instructions of Respondents, that
the Representatives of the Respondents categorically stated that the access would be
denied due to the Complainants’ decision to approach the Maharashtra RERA authority.
This blatant act of intimidation reflects the Respondents’ intent to suppress the
Complainants' rightful claims and coerce them into abandoning their grievances. In
response to these actions, the Complainants lodged a police complaint on 11.05.2023
with P.S. Hadapsar and later escalated the matter to the Deputy Commissioner of Police
(DCP), Zone 5, on 03.02.2024. Under the intervention of the DCP during a meeting on
23.02.2024, the Respondents reluctantly agreed to allow inspection of the flat. The
Complainants, through a rightful notice dated 24.02.2024, sought a detailed assessment
of the flat and related permissions, while simultaneously requesting police protection for
the inspection scheduled on 26.02.2024 due to fear of repeated intimidation. Despite
these efforts, the Respondents continued to act in bad faith and obstruct the process.
After nearly eight years of delay, the Respondents issued a possession notice on
16.03.2024. The Complainants, while reserving their legal rights, agreed to take
possession through an email dated 06.04.2024 (Refer Document specifically ‘Email
dated 06-04-2024’ uploaded to the Complaints’ portal). Despite this, the Respondents
failed to deliver peaceful and vacant possession of the flat, further underscoring their
fraudulent intent. That since the said Offer of Possession the Complainants on various
occasions by way of written communication have requested the Respondents to reinstate
the initial sanctioned plans in strict coherence to the mutually executed Agreement to
Sell dated 16.04.2016 but the Respondents have taken no measure(s) in the said
direction. Therefore, the Complainants have no other option but to file the present
Application.
4.1. The allottees booked a unit in the subject project as per the limited information/
documents disclosed by the Respondent which turned out to be falsified and fraudulent
including the floor Plan of the Fifth Floor, C-Wing wherein the dimensions of the unit in
question, the limited common areas etc. have been pointed out and also the layout plan
of the subject project. Compared to the said information as available in the Agreement to
209
Sell the sanctioned plans as uploaded on the portal of the Authority there are specific
changes in the area of the unit in question, even though the consideration was paid off by
the Allottees as per the specifically misplaced falsified disclosures of the Promoter.
Moreover, as on date due to the increase in the number of wings/towers and the total
covered area the entire demographics, density etc. of the project stands changed and
substantially conceded valuation, livability and marketability of the said unit C-503. The
agreement to sell executed and the total sale consideration paid off as on date was
strictly basis the initial specifications of the project, layout/specifications of the unit,
demographics, density etc. First the Promoter has carried out the said changes arbitrarily
and thereafter has failed to either refund the excess consideration and/or duly
compensate the financial agony borne by the allottees on account of such incorrect
disclosures. In terms of Section 12 of the Act the same amounts to violation of the
RERA Act, 2016. Further, on careful perusal of the Agreement to Sell dated 16.04.2016
it is revealed that under Recital (p) & (s) (Refer Pg. 30 of the Agreement to Sell dt.
16.04.2016 uploaded to the Complaint Portal herein as ‘Annexure A/3 Copy of
Agreement for Sale’) the Respondent has willfully disclosed wrong details of the
sanctioned plans and undertaken to complete the construction and development of the
project as per the said sanctioned plans whereas as per the credentials provided therein
there is no such sanctioned plan bearing no. PMH/NA/SR/310/2014 dated 05.03.2014. It
is noteworthy to point out herein, that the promoter has provided the correct details of
the sanctioned plans in the model agreement uploaded on the portal of the Learned
Authority at the time of registration but to deliberately dupe the Complainants stated
wrong credentials in the Agreement dated 16.04.2016. That from a bare perusal of the
model agreement uploaded by the Respondent at the time of Registration of project, it
can be seen that the Respondent has uploaded the Model Agreement as Document 35,
further at Pg. 30 of the said Agreement the sanctioned plan has been mentioned as PMH/
NA/SR/320/2014 dated 05.03.2015 which are the correct credentials of the actual
sanctioned plan whereas in the Agreement dated 16.04.2016 a fake and fictitious plan
bearing no. PMH/NA/SR/310/2014 dated 05.03.2014 has been mentioned. It is relevant
to point out herein that the Respondents have categorically not mentioned the correct
details in the agreement executed with the Complainants and also conveniently
restrained from mentioning the details of the actual sanctioned plan in the entire
Agreement dated 16.04.2016 executed with the Complainants. For the sake of the safety
of the allottees the Learned Authority must initial suo moto cognizance of the entire
project. An appropriate forensic audit of the project shall be conducted, further
allotments shall be stayed and if found fit the Registration of the project shall be
suspended/revoked. That the said details have come to the knowledge of the
210
Complainants at this belated stage when the Respondents filed their said reply as a
consequence of which the Complainants had to move the present Application.
determine the issues at hand and the very purpose of Order VI, Rule 17 would be
unfortunately defeated.
6.2. That the Respondent offered the possession of the flat in question in April 2024 but
the said offer of possession was an afterthought as the present Complaint has been
pending since 2023. That despite offering the said possession the Respondent has failed
to facilitate the Complainants to enter into the said flat and evaluate if the said flat has
been constructed as per the agreed terms under the Agreement dated 16.04.2016. That by
way of various emails, legal notices and other communications the Complainants have
been urging the Respondent to reinstate the original sanctioned plan based on the
promise of which the booking was made and the subsequent Agreement to Sale was
entered into but the said efforts of the Complainants have been of no avail.
6.3. At the risk of being repetitive it is reiterated herein that the Respondent has heavily
flouted around the sanctioned plans and the project has not been constructed as per the
original sanctioned Plans. Further all the revisions have been obtained and sanctioned by
PMRDA without obtaining requisite consent from the Complainants in complete
derogation to the provisions of the RERA Act, 2016 and other applicable laws. That at
the time of booking and entering into the Agreement to Sale a bogus floor plan was
shown to the Complainants and the Complainants being simple citizens were duped and
made to part with their hard-earned monies.
212
6.4. The Complainants have been waiting since 2015 to live in their dream home and
have spent enormously on rent and litigation while waiting to fulfil this dream. That
almost 10 years have elapsed and the Complainants are continually waiting. In the said
scenario a bogus offer of possession plagued with illegal clauses has no basis and is fit
to be discarded by this Learned Authority at the very outset. That merely because the
Respondent has offered the Possession in 2024 at this belated stage the Complainants
cannot be arm twisted into accepting the possession of the said flat by no stretch of
imagination. That the Complainants were awarded interest at 9% p.a. on the amounts
paid by this Learned Authority way back in 2020 and the said interest is accruing each
day the Respondent has failed to adjust the same in the final demand letter issued at the
time of offer of possession. That such action/inaction on part of the Respondents go
beyond any reasonable doubt as to the intent of the Respondents in complying with the
directions of this Ld. Authority and/or rightfully compensating the Complainants.
6.5. In the light of the said facts, it is apposite to state that the Respondent has
committed grave contraventions of the RERA Act, 2016 and other applicable laws along
with the provisions mutually agreed between the parties under the Agreement to Sale
dated 16.04.2016. That by virtue of Section 19(4) of the RERA Act, 2016 the
Complainants are entitled to claim refund of amount paid along with interest at such rate
as may be prescribed and compensation as provided under the Act. For ready reference,
the relevant provision of the Act are reproduced herein:
………(4) The allottee shall be entitled to claim the refund of amount paid along with
interest at such rate as may be prescribed and compensation in the manner as provided
under this Act, from the promoter, if the promoter fails to comply or is unable to give
possession of the apartment, plot or building, as the case may be, in accordance with the
terms of agreement for sale or due to discontinuance of his business as a developer on
account of suspension or revocation of his registration under the provisions of this Act
or the rules or regulations made thereunder…………”
6.6. Further in the matter of M/s Newtech Promoters and Developers Pvt. Ltd. vs. State
of UP & Ors. Etc. (Civil Appeal No(s). 6745-6749 of 2021) the Hon’ble Supreme Court
has held that the Allottees have unqualified right to claim refund under the Provisions of
the RERA Act, 2016. The relevant portion of the said judgment has been reproduced
herein:
213
“25. The unqualified right of the allottee to seek refund referred under Section 18(1)(a)
and Section 19(4) of the Act is not dependent on any contingencies or stipulations
thereof. It appears that the legislature has consciously provided this right of refund on
demand as an unconditional absolute right to the allottee, if the promoter fails to give
possession of the apartment, plot or building within the time stipulated under the terms
of the agreement regardless of unforeseen events or stay orders of the Court/Tribunal,
which is in either way not attributable to the allottee/home buyer, the promoter is under
an obligation to refund the amount on demand with interest at the rate prescribed by the
State Government including compensation in the manner provided under the Act with
the proviso that if the allottee does not wish to withdraw from the project, he shall be
entitled for interest for the period of delay till handing over possession at the rate
prescribed.”
Further, the Hon'ble Supreme Court in Kolkata West International City Pvt. Ltd. Vs.
Devasis Rudra, II (2019) CPJ 29 (SC), has clearly laid down that a flat purchaser cannot
be made to wait indefinitely for seeking possession. It is reiterated that the present
Application is bona fide, nothing material has been concealed and the balance of
convenience is also in the favour of the Complainants. Hence, the present Application.
214
PRAYER
DATE:
PLACE:
COMPLAINANTS
Through Counsel:
ARUL PRAKASH
Advocate
OCULUS Legal
Office No. 103, LSC Pankaj Tower
Mayur Vihar Phase - 1
New Delhi - 110091
8826516187
[email protected]
215
216
217
218
219
220
1
Vs.
That the captioned Complaint and the Application are pending before this
Learned Authority and are listed for final hearing on 27.01.2025. The
Complainant herein seeks to file these present Written Arguments along with
detailed submissions to appropriately assist this Learned Authority to
adjudicate the present Complaint. The same may be taken on record.
1.1. The Complainants booked a 2BHK Flat bearing No. 503, Fifth Floor, C-
Wing in the said project by paying a Booking amount of 50,000/- (Rupees
Fifty Thousand Only) through Cheque Bearing No. 000002 dated 16.11.2015
drawn on HDFC Bank for a total sale consideration of Rs. 40,53,400/-
(Rupees Forty Lakhs Fifty-Three Thousand Four Hundred Only) @ Rs.
38,280/- per Sq. Mt. For the total carpet area of the flat being 1115 Sq. Ft.
(103.62 Sq. Mt.).
9.3 of the said Agreement the possession of the said Flat was to be given
within 24 months from the date of execution of the agreement i.e. on or before
15.04.2018. The delivery of the said flat was delayed inordinately and the
Complainants having no other means had to approach this Learned Authority
vide Complaint bearing No. CC005000000054113 titled as “Poonam Mewalal
Gupta & Anr Vs. M/s Vedant Estate & Properties” seeking possession and
delay interest. The said Complaint was decreed in favour of the Complainants
vide Order dated 04.08.2020.
1.3. It is pertinent to note that after the passing of the order dated 04.08.2020,
being aggrieved the Respondent herein had filed an Appeal No.
AT005000000052662 before Hon’ble MahaREAT which was dismissed on
18.03.2021 for want of compliance with Proviso of Sec. 43 (5) of the RERA
Act, 2016. Thereafter, the Respondent filed a Second Appeal No. 423 of 2021
before the Hon’ble High Court, Mumbai and by order dated 23.12.2021, the
Appeal No. AT005000000052662 was restored to the Hon’ble MahaREAT.
However, as admitted herein the Respondent deposited a sum of Rs. 85,541/-
(Rupees Eighty-Five Thousand Five Hundred Forty-One Only) before the
Hon’ble Appellate Tribunal and did not completely fulfill the statutory
requirement under Section 43(5) of the RERA Act, 2016. The decretal amount
was interest at 9% p.a. on Rs. 34,69,896/-, as directed in the MahaRERA order
dated 04.08.2020, which was never deposited. Thus, the Complainants had
filed a Misc. Application no. 918/22 before the Hon’ble Appellate Tribunal
seeking dismissal of the said appeal on the ground that Respondent has
fulfilled only part compliance of the proviso and in view of the provisions of
the Act, full compliance is a prerequisite to entertain the appeal. Whereas, the
requirement as per the order passed by the Hon’ble High Court and the
provisions of the RERA Act, 2016, complete compliance of the proviso is
mandatory for the said Appeal to have been entertained. The Respondent
being well aware that their Appeal is sans merits and that the same cannot be
entertained without complete compliance of the proviso of Section 43(5) of
the Act, despite ample opportunity, failed to appear hence, the Hon’ble
MahaREAT was pleased to dismiss the said appeal for want of appearance on
06.09.2023. That as on date the said Order dated 04.08.2020 continues to be
pending compliance as till date the Respondent has not come forward to
222
3
comply the directions of this Learned Authority in letter and spirit, the interest
decreed in favour of the Complainants is accruing each day.
2.1. In the reply of the Respondent the Respondent has shifted the onus on the
Architect for delay in issuance of the Letter for applying for Occupation
Certificate, it is to be submitted herein, that the said Architect had been hired
by the Respondent itself and the Respondent is solely responsible for the
actions of the said Architect and the same cannot be attributed to the delay in
the subject project. If at all the plea of the Respondent is to be taken into
consideration it is needful to bear in mind that the said Architect’s Letter is
dated 10.08.2019 the said Letter certifies that the construction has been
completed and the building is ready for occupancy. Even on 10.08.2019 if the
Respondent is deemed to have completed construction, there is an admitted
delay of 16 months from the due date of delivery (15.04.2018).
2.2. Further the Respondent has submitted that the delay in the project is
attributable to the Litigation that the Respondent had to pursue before the
Hon’ble Bombay High Court against PMRDA & Ors for non-issuance of
Occupation Certificate. As per the Respondent’s own Admission, the
Respondent had to pursue WP-DB-LD-VC No. 32 of 2020 (WP/95407/2020)
before the Hon’ble Bombay High Court titled as “M/s Vedant Estate &
Properties vs. Chief Executive Office, PMRDA & Ors.” against the various
orders/communications received from the concerned Competent Authority for
non-issuance of Occupation Certificate. The said Writ Petition was disposed
off by the Hon’ble Bombay High Court vide Order dated 15.10.2020 (Refer
Pg. 18-21 of the Rejoinder of the Complainant) wherein the concerned
Competent Authority was directed to issue Occupation Certificate to the
Respondent subject to deficiencies (if any). Pursuant to the said Order
PMRDA issued Occupation Certificate to the concerned tower of the
Respondent (Wing - C) on 11.12.2020. Even after such issuance of the
Occupation Certificate the Respondent did not offer possession to the
223
4
3.1. It is submitted herein that the Complainants in complete trust deficit with
the operations of the Respondent and their subsequent conduct approached the
offices of the Competent Authority(s) by way of RTIs and were able to
unearth various illegalities and plain lies the Respondent had stated to the
Complainants and other fellow allottees. The first sanctioned plan was
approved on 05.03.2015 as per which the proposed project had 5 towers/wings
namely A, B, C, D & E each of the said wings compromised of G+11 floors.
In furtherance of the same on 05.03.2015 Collector NA & Construction
Permission were obtained for the project i.e. Approval of
drawing/construction plan under section 18 of the Maharashtra Regional
Planning and Town Planning Act, 1966. Thereafter, the said sanctioned plan
was revised on 31.12.2016 i.e. post execution of the Agreement to Sell dated
16.04.2016 without obtaining any consent or providing any intimation to the
Complainants in complete contravention to the provisions of the RERA Act,
2016 and the provisions of the MOFA Act, 1963. The said sanctioned plans
224
5
were further revised on 07.06.2021 yet again without obtaining any consent
or providing any intimation to the Complainants in complete contravention to
the provisions of the RERA Act, 2016 and the provisions of the MOFA Act,
1963. On these grounds alone, the Respondent is liable to proceeded against
under the provisions of the RERA Act, 2016 and the rules and regulations
framed thereunder.
3.2. Having no other means, the Complainants obtained the opinion by way
of a detailed report from Dr. Gyan Singh (Chartered Engineer & Structure
Consultant) dated 22.06.2023 (Refer Annexures to the Complaint). On bare
perusal of the said report, the Complainants realized that the Respondent has
violated various rules and regulations of applicable local laws and taken the
law into their hands as per their whims. According to the said report, it reveals
that the dimensions/specifications and the layout of the unit in question i.e.
the Complainant’s Flat have been changed more particularly the spatial layout
dimension and carpet areas of the said unit including terrace and balconies
have been altered without the consent of the Complainants. It is also important
to point out that major changes in the amenities and floor plans have also been
undertaken such as the location of Passenger & Service Lifts have been
changed in contradiction to the original sanctioned plans sanctioned vide
office communication no. pmh/na/sr/320/2014 dated 05.03.2015.
Furthermore, the Respondent undertook unsanctioned construction of the
project towers & buildings contrary to the original sanctioned plans
sanctioned vide office communication no. pmh/na/sr/320/2014 dated
05.03.2015, these illegal constructions have been subsequently regularized
through plan revisions by the Respondent without consent of the
Complainants and possibly other allottees in the project. That the said Report
was sent to the Respondent seeking clarifications and explanations regarding
the said illegalities and major non-compliances under applicable laws but till
date the Respondent has not responded or provided any suitable response to
the queries of the Complainants.
3.3. Further, it is apposite to draw the kind attention of this Learned Authority,
on the Architect Letter dated 10.08.2019, on which reliance has been placed
by the Respondent itself (Refer Pg. 15-17 of the Rejoinder of the
Complainants) that from a bare perusal of the said Letter it can be seen that
225
6
the Respondent has itself stated that the construction has been completed as
per sanctioned plans sanctioned vide office communication no.
pmh/na/sr/320/2014 dated 05.03.2015 which is post in time to the various
admitted revisions to the sanctioned plans. In fact, at the time of booking the
complainants were convinced to invest in the project based on the information
that the sanctioned plan has been obtained, dated 05.03.2015, which was never
shown to the Complainants. That only a bogus floor plan, as attached with the
Agreement was disclosed to the Complainants. Furthermore, at no given
instance the Complainants were informed about the revisions or sought
consent from in complete contravention to the provisions of the RERA Act
2016, MOFA Act 1963 and other applicable rules and regulations.
5.1. The provisions of Section 14 of the RERA Act, 2016 are outrightly clear
that no changes in the sanctioned plan(s) can take place without the promoter
first reaching 2/3rd (66%) consent of the Allottees of the project further under
the provisions of Section 7 of the MOFA Act, 1963 the consent has to be
received from all the Allottees (100%) of the project in question. Despite the
said mandate of the applicable laws the Respondent has gone forward to
change the sanctioned plan(s) on more than one occasion. The said revised
sanctioned plans are uploaded on the portal of this Learned Authority without
uploading/disclosing before this Learned Authority the initial/actual
sanctioned plans on the pretext of which the project was sold to the
Complainants.
5.2. The question that has to be adjudicated by this Learned Authority is this
that without obtaining the requisite consent in what circumstances the
Competent Authority(s) have sanctioned the revisions. In all probability such
facts reflect only two possibilities that is either forged/falsified consent of the
Allottees was filed before the Allottees or that the revisions/changes in the
sanctioned plans have been obtained without duly complying with the
provisions of the applicable laws. That the said fact(s) cannot be adjudicated
unless the said Competent Authority is impleaded in the present proceedings
and their appropriate submissions are filed.
5.3. Under the present Complaint the Complainants have clearly sought
appropriate action against the Promoter for contravention of the provisions of
Section 14 of the RERA Act, 2016 therefore for adjudicating the said relief
judiciously it is imperative that PMRDA is made party to the present
proceedings and due process of the law is met with. For the said reason(s) the
Complainants have already filed an Application for Amendment of Memo of
228
9
6.1. That during the time of booking the Complainants were lured into the
present project on the promise that the present project is being financed by
Axis Bank and that various lucrative schemes including but not limiting to
Housing Finance options to the Allottees. That based on such lucrative
schemes the Complainants booked the unit the project.
6.2. It is outrightly clear that Axis Bank has collaborated with the Respondent
in promoting, marketing and selling the project at hand to the Complainants.
Further, by funding the project at hand Axis Bank has acted as “Promoter”
within the meaning of section 2(zk) of the RERA Act, 2016 and benefitted
from the sale of the project and earned huge dividends.
6.3. Further, Axis Bank has also collaborated with the Respondents in duping
the Complainants of their hard-earned monies. As per the scheme offered to
the Complainants the Complainants had availed a loan facility of Rs.
32,79,000/- (Rupees Thirty-Two Lakhs Seventy-Nine Thousand Only) from
Axis Bank, East ASC Branch who assured the Complainants that they have
thoroughly conducted diligence regarding the project, sanctioned plans,
permissions etc and that the project is fit in all measures. That out of the said
loan facility by July 2018 the said Bank had already disbursed an amount of
Rs. 29,27,021/- (Rupees Twenty-Nine Lakhs Twenty-Seven Thousand
Twenty- One Rupees) i.e. 87% of the total loan amount. As per the Master
Circular issued by RBI bearing No. RBI/2015-16/46 DBR.No.
DIR.BC.13/08.12.001/2015-16 dated 01.07.2015 titled as “Master Circular -
Housing Finance” it is obligatory on part of the Banking Institutions providing
Housing Finance that disbursement of loan amounts shall be closely linked to
the stages of construction. Whereas in July 2018 the Respondents were far
from achieving 87% of Completion of the project and the same can be
ascertained by this Learned Authority by perusing through the Quarterly
Compliances the Respondents are to do within the meaning of the Act to
229
10
6.4. Further, as Axis Bank financed the subject project it was obligatory on
part of the Bank to ensure that all the requisite approvals, permissions,
sanctions have been
duly and lawfully obtained. From a bare perusal of the admitted facts of this
complaint it is outrightly clear that the respondents have flouted all sorts of
Rules, Laws applicable to them for the construction & development of the
project. Yet, the Bank has financed the subject project and even gone to the
extent of disbursing 87% of the loan amount way back in 2018 while having
no regard to the stages of construction. Hence, the Complainants require
clarification from the said Bank; hence, the Complainants want to add the
Axis Bank as a party to the present Proceedings. For the said reason(s) the
Complainants have already filed an Application for Amendment of Memo of
Parties bearing No. CC005000000228339/APP/AM/1 the same is pending
before this Learned Authority.
7.1. Section 4 of the RERA Act, 2016: As per Section 4 of the said Act the
Promoter is duty bound to disclose all the crucial details of the subject project
including but not limiting to the Sanctioned Plans, the consent of the allottees
as per MOFA obtained before the change/alteration in sanctioned plans, the
agreement to sell executed with the Allottees, the complete set of approved
building plans, the approval letter for revision/change in sanctioned plans, the
NOC from Fire Department, Fire Fighting Plans, the approval from concerned
competent authority along with policy documents for the additional FSI etc.
All these valuable disclosures have not been provided by the Promoter in its
application for registration of the Project.
7.2. Section 11 of the RERA Act, 2016: As per Section 11 of the said Act the
various obligations have been casted upon the Promoter. Under sub class (3)
the promoter is liable to provide the approved layout, sanctioned plans etc to
230
11
the prospective allottees along with allotment letter at the time of booking.
The said disclosures have not been provided by the Promoter.
7.3. Section 12 of the RERA Act, 2016: The allottees booked a unit in the
subject project as per the limited information/documents provided by the
Promoter including the floor Plan of the Fifth Floor, C-Wing wherein the
dimensions of the unit in question, the limited common areas etc have been
pointed out and also the layout plan of the subject project. Compared to the
said information as available in the Agreement to Sell the sanctioned plans as
uploaded on the portal of the Authority there are specific changes in the area
of the unit in question, eventhough the consideration was paid off by the
Allottees as per the specific disclosures of the Promoter. Moreover, as on date
due to the increase in the number of wings/towers and the total covered the
entire demographics, density etc of the project stands changed. The agreement
to sell executed and the total sale consideration paid off as on date was strictly
basis the initial specifications of the project, layout/specifications of the unit,
demographics, density etc . First the Promoter has carried out the said changes
arbitrarily and thereafter has failed to either refund the excess consideration
and/or duly compensate the financial agony borne by the allottees on account
of such incorrect disclosures. In terms of Section 12 of the Act the same
amounts to violation of the RERA Act, 2016. Further, on careful perusal of
the Agreement to Sell dated 16.04.2016 it is revealed that under Recital (p) &
(s) the Respondent has wilfully disclosed wrong details of the sanctioned
plans and undertaken to complete the construction and development of the
project as per the said sanctioned plans whereas as per the credentials provided
therein there is no such sanctioned plan. It is noteworthy to point out herein,
that the promoter has provided the correct details of the sanctioned plans in
the model agreement uploaded on the portal of the Learned Authority at the
time of registration but to deliberately dupe the Complainants stated wrong
credentials in the Agreement dated 16.04.2016.
7.4. Section 14 of the RERA Act, 2016: As per the information available on
the portal of the Authority the sanctioned plans uploaded on the portal date as
recent as 2016, 2019 , 2021 and so on whereas the initial sanctioned plans as
obtained from the Competent Authority date back to 2014 and so on. In the
said scenario it is outrightly clear that the sanctioned plans have been
231
12
changed/revised/altered and that too after the enactment of the RERA Act,
2016. Section 14 provides for disclosure of approval and reasoning for such
changes/alterations in the sanctioned plan. It also provides that any such
changes except minor alterations shall not be effectuated without the prior
consent of 2/3rd Allottees of the subject project. There is nothing on record to
show the existence of these mandatory requirements of the law.
7.5. Section 60 of the RERA Act, 2016: Section 60 of the Act provides for
punitive action wherein the Promoter is liable to be penalised upto 5% of the
total project cost for providing false information under section 4 of the Act.
In the instant case as elaborated the Promoter has deliberately concealed
relevant information and failed to provide absolute disclosure on the said
count the Authority shall initiate action under this provision.
7.6. Section 61 of the RERA Act, 2016: The Promoter has bypassed
provisions of section 11, 12 & 14 of the Act for the said action shall be
initiated under section 61 and the Promoter shall penalised upto 5% of the
estimated cost of the project.
8.1. The Complainants made the booking in the present project in 2015 the
possession of the said project was due in 2018. The Respondent has made the
Complainants to part with almost 90% of the total sale consideration way back
in 2018. Since then the Complainants have been running from pillar to post
but their dream of living in their own house has not been fulfilled despite
various rounds of litigations. That even though a favourable Order was passed
by this Learned Authority way back in 2020 the Respondent has not taken
232
13
measures to handover the vacant, peaceful and legal possession of their flat.
That having invested close to 40 Lakhs in the project way back in 2018, the
Complainants have been living in rented accommodation while bearing the
burden of monthly EMIs without being able to realize the dream of living in
their own flat.
8.2. That the Respondent offered the possession of the flat in question in April
2024 but the said offer of possession was an afterthought as the present
Complaint has been pending since 2023. That despite offering the said
possession the Respondent has failed to facilitate the Complainants to enter
into the said flat and evaluate if the said flat has been constructed as per the
agreed terms under the Agreement dated 16.04.2016. That by way of various
emails, legal notices and other communications the Complainants have been
urging the Respondent to reinstate the original sanctioned plan based on the
promise of which the booking was made and the subsequent Agreement to
Sale was entered into but the said efforts of the Complainants have been of no
avail.
8.3. At the risk of being repetitive it is reiterated herein that the Respondent
has heavily flouted around the sanctioned plans and the project has not been
constructed as per the original sanctioned Plans. Further all the revisions have
been obtained and sanctioned by PMRDA without obtaining requisite consent
from the Complainants in complete derogation to the provisions of the RERA
Act, 2016 and other applicable laws. That at the time of booking and entering
into the Agreement to Sale a bogus floor plan was shown to the Complainants
and the Complainants being simple citizens were duped and made to part with
their hard-earned monies.
8.4. The Complainants have been waiting since 2015 to live in their dream
home and have spent enormously on rent and litigation while waiting to fulfil
this dream. That almost 10 years have elapsed and the Complainants are
continually waiting. In the said scenario a bogus offer of possession plagued
with illegal clauses has no basis and is fit to be discarded by this Learned
Authority at the very outset. That merely because the Respondent has offered
the Possession in 2024 at this belated stage the Complainants cannot be arm
twisted into accepting the possession of the said flat by no stretch of
233
14
8.5. In the light of the said facts, it is apposite to state that the Respondent has
committed grave contraventions of the RERA Act, 2016 and other applicable
laws along with the provisions mutually agreed between the parties under the
Agreement to Sale dated 16.04.2016. That by virtue of Section 19(4) of the
RERA Act, 2016 the Complainants are entitled to claim refund of amount paid
along with interest at such rate as may be prescribed and compensation as
provided under the Act. For ready reference, the relevant provision of the Act
are reproduced herein:
………(4) The allottee shall be entitled to claim the refund of amount paid
along with interest at such rate as may be prescribed and compensation in the
manner as provided under this Act, from the promoter, if the promoter fails to
comply or is unable to give possession of the apartment, plot or building, as
the case may be, in accordance with the terms of agreement for sale or due to
discontinuance of his business as a developer on account of suspension or
revocation of his registration under the provisions of this Act or the rules or
regulations made thereunder…………”
8.6. Further in the matter of M/s Newtech Promoters and Developers Pvt. Ltd.
vs. State of UP & Ors. Etc. (Civil Appeal No(s). 6745-6749 of 2021) the
Hon’ble Supreme Court has held that the Allottees have unqualified right to
claim refund under the Provisions of the RERA Act, 2016. The relevant
portion of the said judgment has been reproduced herein:
“25. The unqualified right of the allottee to seek refund referred under Section
18(1)(a) and Section 19(4) of the Act is not dependent on any contingencies
or stipulations thereof. It appears that the legislature has consciously
provided this right of refund on demand as an unconditional absolute right to
the allottee, if the promoter fails to give possession of the apartment, plot or
building within the time stipulated under the terms of the agreement
234
15
PRAYER
DATE: 27.01.2025
PLACE: Pune
COMPLAINANTS
Through Counsel:
ARUL PRAKASH
Advocate
OCULUS Legal
Office No. 103, LSC Pankaj Tower
Mayur Vihar Phase - 1
New Delhi - 110091
8826516187
[email protected]
PTL
235
To,
The Registrar
Hon. Maha RERA Appellate Tribunal
Mumbai
VAKALATNAMA
Sir/Madam,
I/ We Mr. Charles Suresh Kumar & Poonam Mewalal Gupta (Mrs.
Poonam Charles Kumar) the Appellants / hereinabove do hereby appoint,
assign, engage and nominate : Advocates of OCULUS Legal, Office No. 103,
LSC Pankaj Tower, Mayur Vihar Phase - 1, Mayur Vihar Phase 1, New Delhi-
110091 (Phone: +91- 8826516187) (hereinafter called the Advocate/s to be our
Advocate/s in the above-noted case and authorize him/them: Adv Arul Prakash,
to act, appear, represent, argue, plead, sign in our Appeal; And on our behalf is
also hereby empowered, permitted, allowed to appoint, assign, engage and
nominate Legal Counsel/s to appear / sign in the above proceedings, on our
behalf.
__________________________________________
Signature
ACCEPTED
ARUL
PRAKASH
Advocate