Nit 06 Recall
Nit 06 Recall
, - 517507
NIT
06/EE/Tirupati/e-Tender/2025-26 (Recall)
NIT – INDEX
Name of Work: Construction of 150 KLD Capacity Sewage Treatment Plant including
SITC of E&M works and distribution lines for treated water at CRPF Campus, Kalikiri,
Chittoor Dist., A.P.
1 Part A 1 – 60
11 PART-B 61 – 209
12 Special conditions 62 – 88
13 Additional conditions (Civil component) 89 – 106
14 Special Conditions for Green Building 107 – 114
15 Particular Specifications (Civil component) 115 – 157
List of Field Tests and Equipment for Testing of Materials &
16
Concrete at Site Laboratory 158 – 159
Plant And Equipment Required to Be Owned / Taken on Lease
17 160
By The Contractor
18 Guarantee Bonds. 161 – 162
19 Seigniorage Fee 163 – 172
Standard Operating Procedures (SOPs) and Guidelines for
20 173 – 177
Construction Sites for COVID-19 Outbreak
List of Preferred brand / Manufacturer/ Make (Civil
21 178 – 209
component)
22 PART C 210 – 238
23 Schedule A to F (E & M component) 211 – 216
24 Special conditions& Eligibility criteria for E&M works 217 – 220
iii
Notice Inviting Tender is approved for Rs. 1,55,95,507/- (Rupees one crore fifty five
lakhs ninety five thousand five hundred and seven only).
Executive Engineer
Central PWD, Tirupati
PART A 1
PART – A
PART A 2
The Executive Engineer, CPWD, Tirupati on behalf of the President of India invites
online percentage rate composite bids in two bid system from CPWD enlisted contractors of
appropriate class in Buildings & Roads (erstwhile Composite/Building/Infrastructure)
category and firms/contractors of repute in two bid system for the following work: -
Sl.
Description Details
No.
1 NIT No. 06/EE/Tirupati/e-Tender/2025-26 (Recall)
2 Name of Work Construction of 150 KLD Capacity Sewage
Treatment Plant including SITC of E&M
works and distribution lines for treated water
at CRPF Campus, Kalikiri, Chittoor Dist., A.P.
3 Estimated Cost Put to Tender Rs. 1,55,95,507/-
(Composite)
Civil Work (Major Component) Rs. 1,21,58,876/-
Electrical Work (Minor Component) Rs. 34,36,631/-
4 Earnest Money (EMD) Rs.3,11,910/-
5 Period of Completion 180 days
6 Date of Pre-bid meeting
(Will be held in the O/o Executive
Engineer, CPWD, CPWD office At 11:00 Hours on 14.07.2025
Building, Nehru Nagar, Tirupati, AP
– 517507.
7 Last time & date of online submission
of bid, original EMD, copy of receipt
for deposition of original EMD, and Up to 15:00 Hours on 28.07.2025
other documents as specified in the
NIT.
8 Time & date of online opening of At 15:30 Hours on 28.07.2025
Eligibility cum technical bid
documents (Mandatory documents)
9 Time & date of online opening of This will be intimated later.
financial bids.
10 Last date & time of submission of To be submitted during office hours within a
hard copies of Experience Certificates week from the date of opening of the
if any, Registration Certificates, Financial Bid. In case the last day happens to
PART A 3
Sl.
Description Details
No.
Affidavit if any, Undertaking and be closed holiday, these documents shall be
other Documents as specified in the submitted on the next working day.
press notice to Division Office by the
Lowest Tenderer Only.
Joint ventures/consortium and Special Purpose vehicle are not accepted [1(b), 1(c)
& 1(d) are not applicable for CPWD enlisted contractors of appropriate class. 1(a)
and 1(e) are applicable for CPWD enlisted contractors also].
a) Should have satisfactorily completed the works as mentioned below during the last
seven years ending the last day of the month previous to the one in which tenders are
invited.
(i) Three similar completed works each costing not less than Rs. 62.38 lakhs, or two
similar completed works each costing not less than Rs.93.57 lakhs, or one similar
completed work costing not less than Rs.124.76 lakhs.
The works of specialized E &M services included in definition of similar work will
be considered even if these have been executed under a separate contract.
However, these, E &M services executed under a separate contract shall be
considered for the purpose of assessing technical competence only without adding
its monetary value for determining the eligibility as required above.
The bidder shall submit copy of final bill paid along with bill of quantities
and experience certificate issued by an officer not below the rank of Executive
Engineer / Project Manager or equivalent.
The value of executed works shall be brought to current costing level by enhancing
the actual value of work at simple rate of 7% per annum; calculated from the date of
completion to previous day of last day of submission of tenders. (Applicable to
CPWD enlisted contractors of appropriate class also)
(ii) ln case, the eligible work has been executed by a Joint Venture through one or more
individual firm(s), then cost of completed work shall be distributed among the
PART A 4
individual firm(s) in proportion to their share in Joint Venture and that will be
considered as work experience for individual firm(s) for prequalification in bidding.
c) Should not have incurred any loss (profit after tax should be positive) in more than
two years during the last five years ending 31st March 2024.
d) Should have a Banker's Certificate from a commercial Bank for Rs.62.38 lakhs or
Net Worth certificate from CA with Unique Document Identification Number
(UDIN) of minimum amount of Rs.15.60 lakhs. (Scanned copy of original to be
uploaded).
e) Should have bidding capacity equal to or more than the estimated cost of the work
put to tender. The bidding capacity shall be worked out by the following formula:
Where,
A = Maximum turnover in construction works executed in any one year during the
last seven years taking into account the completed as well as works in progress. The
value of completed works shall be brought to current costing level by enhancing at a
simple rate of 7% per annum.
Or
In case, if bidders are from the categories of Retired Govt. Engineer /Architect, then
“A” shall be as per Rule 6.1.7 of enlistment Rules 2024
Or
In case if the bidders is a newly enlisted director/ Partner then “A” shall be taken as
proportionate share as per rule 9.6.3 and 9.6.4 of Enlistment Rules 2024
N = Number of years prescribed for completion of work for which bids have been
invited.
2. The intending bidder must read the terms and conditions of CPWD-6 carefully. He
should only submit his bid if he considers himself eligible and he is in possession of
all the documents required.
3. This information and instructions for bidders posted on website shall form part of bid
document.
PART A 5
5. But the bid can only be submitted after deposition of original EMD either in the
office of Executive Engineer inviting bids or division office of any Executive
Engineer, CPWD within the period of bid submission and uploading the
mandatory scanned documents such as Insurance Surety Bonds, Account
PayeeDemand Draft or Banker’s Cheque or Fixed Deposit Receipts or/ and Bank
Guarantee including e- Bank Guarantee (for balance amount as prescribed) from any
of the commercial bank towards EMD in favour of Executive Engineer, Tirupati
Central Division, CPWD, Tirupati, receipt for deposition of original EMD to division
office of any Executive Engineer (including NIT issuing EE/AE), CPWD and other
documents as specified.
6. Those contractors who are not registered or have not updated their profile on the
website mentioned above, are required to get registered / update their profile
beforehand. The necessary training materials including the videos with step-to-step
process are available on download section of https://etender.cpwd.gov.in.
7. The intending bidder must have valid class-III digital signature certificate with
encryption key (Combo type) to perform any operations / transactions on the e-
tendering portal / Website and the bidder should download and install the
eMsigner on their system as per instructions available on download section of
https://etender.cpwd.gov.in.
8. On opening date, the contractor can login and see the bid opening process. After
opening of bids, he will receive the competitor bid sheets.
9. Contractor can upload documents in the form of JPG format and PDF format.
10. Certificate of Financial Turn over: At the time of submission of bid contractor may
upload Affidavit/Certificate from CA with UDIN number mentioning Financial
Turnover of last 7 years or for the period as specified in the bid document and further
details if required may be asked from the contractor after opening of technical bids.
There is no need to upload entire voluminous balance sheet.
11. Contractor must ensure to quote rate of each item. The column meant for quoting
rate in figures appears in Yellow colour and the moment rate is entered, it turns
sky blue.
In addition to this, while selecting any of the cells a warning appears that if any cell is
left blank the same shall be treated as "0" (ZERO). Therefore, if any cell is left blank
and no rate is quoted by the bidder, rate of such item shall be treated as "0" (ZERO).
However, if a tenderer quotes nil rates against each item in item rate tender or does
not quote any percentage above/below on the total amount of the tender or any
PART A 6
section / sub head in percentage rate tender, the tender shall be treated as invalid and
will not be considered as lowest tenderer.
In addition to this, while selecting any of the cells a warning appears that if any cell is
left blank the same shall be treated as “0” (ZERO).
However, if a bidder quotes nil rate, the bid shall be treated as invalid and he will not
be considered as lowest bidder. The intending bidders are not permitted to quote the
rate or modified their quoted rates in any physical format whatever. The bids
submitted online shall only be considered for evaluation.
12. The Technical Bid shall be opened first on due date and time as mentioned above.
The time and date of opening of financial bid of contractors qualifying the technical
bid shall be communicated to them at a later date.
13. Pre-Bid conference shall be held in the O/o the Executive Engineer, CPWD, CPWD
office Building, Nehru Nagar, Tirupati, AP – 517507 at 11:00 Hours on 14.05.2025 to
clear the doubts of intending bidders, if any.
14. The Department reserves the right to reject any prospective application without
assigning any reason and to restrict the list of qualified contractors to any number
deemed suitable by it, if too many bids are received satisfying the laid down criteria.
15. The Existing enlisted contractor either himself or his authorized representative shall
take compulsory ERP training through any of the CPWD Regional Training Institutes
(RTIs) at Delhi, Mumbai, Chennai and Kolkata, National CPWD Academy (NCA)
Ghaziabad, Training arranged by Graduates of ERP “Train the Trainers Programme”
conducted by NCA, Ghaziabad or through any other special training arranged by
ERP Unit of CPWD. Training will be valid only when participants are registered and
a certificate is issued through LMS (Learning Management System) in ERP. The
enlisted contractor will not be allowed to participate in the tendering process without
uploading the certificate of the above training.
In case of a Non-Enlisted contractor being the first lowest in the tender, then
either contractor himself or his authorized representative shall take compulsory ERP
(Enterprise Resource Planning) training through any of the CPWD Regional Training
Institutes (RTIs) at Delhi, Mumbai, Chennai and Kolkata, National CPWD Academy
(NCA) Ghaziabad, Training arranged by Graduates of ERP “Train the Trainers
Programme” conducted by NCA, Ghaziabad or through any other special
training arranged by ERP Unit of CPWD within two months from the date of issue of
intent letter. Training will be valid only when a non-enlisted contractor is registered
in LMS of ERP and a certificate is issued through LMS of ERP. Failure to do so, a
recovery of Rs. 10,000/- per week shall be made from the R/A bill without giving any
show cause notice in this regard. The bidders have to submit an undertaking that they
will secure the certificate within two months from the date of issue of the intent letter.
PART A 7
16. List of Mandatory Documents to be scanned and uploaded within the period of bid
submission:
applicable, within one month from the date of receipt of the award letter or before
release of any Payment by CPWD, whichever is earlier, failing which I/we shall be
responsible for any delay in payments which will be due towards me/us on account of
the work executed and/or for any action taken by CPWD or GST department in this
regard".
15. Receipt for deposition of original EMD issued from the division office of any Executive
Engineer (Including NIT issuing EE, CPWD) (Form–H).
16. Declaration about site inspection (Form ‘I’)
17. Undertaking on structural stability and soundness of already completed buildings and
infrastructure projects (Form ‘J’).
18. Undertaking regarding obtaining the certificate through LMS portal of ERP after
attending “Training the Trainers Programme” conducted by NCA, Ghaziabad or
through any other special training arranged by ERP Unit of CPWD within two months
from the date of issue of intent letter / Certificate secured through LMS portal of ERP
for attending the “Train the Trainers Programme” conducted by NCA, Ghaziabad or
through any other special training arranged by ERP Unit of CPWD if they already
possess one. (Form ‘J1’)
19. Details of Firm Proprietor or Power of Attorney for Partnership Firm with a copy of
Partnership Deed or Power of Attorney with a copy of the Memorandum of Articles of
Association for Limited Company or a Corporation.
Note:
1. All affidavits shall be made in current date after the date of invitation of tender.
2. Copy of work experience and other documents as specified in the press notice shall be
scanned and uploaded to the e-tendering website within the period of bid
submission. Online bid document submitted by the intending bidders shall be opened
only of those bidders, whose scanned and uploaded documents are found in order.
However, certified copy of all the scanned and uploaded documents as specified in
bid document shall have to be submitted by lowest bidders within a week, physically
in the office of tender opening authority.
3. CPWD Enlisted contractors shall upload the declaration on their letterhead in
respect of any not-required Mandatory documents as “we are CPWD Enlisted
Contractors and we are not required to upload this document”. Uploading of these
two letters is mandatory otherwise system will not clear mandatory fields.
PART A 10
4. The Postal address of the Executive Engineer, CPWD, Tirupati may be noted as below
for correspondence and submission of Physical documents: - O/o The Executive
Engineer, CPWD, CPWD office Building, Nehru Nagar, Tirupati, AP – 517507.
(Email id: [email protected], [email protected]).
Executive Engineer
CPWD, Tirupati
PART A 11
1. Online Percentage rate bids are invited on behalf of President of India from CPWD
enlisted contractors of appropriate class in Buildings & Roads (erstwhile
Composite/Building/Infrastructure) category and firms/contractors of repute in two
bid system for the work of “Construction of 150 KLD Capacity Sewage Treatment
Plant including SITC of E&M works and distribution lines for treated water at
CRPF Campus, Kalikiri, Chittoor Dist., A.P.”
The enlistment of the contractors should be valid on the last date of submission of
bids.
In case the last date of submission of bid is extended, the enlistment of contractor
should be valid on the original date of submission of bids.
1.1 The work is estimated to Cost Rs.1,55,95,507/-. This estimate, however, is given
merely as a rough guide, the bidders are required to conduct their own market
survey to obtain latest prevailing rates in the market and to work out their tendered
rates accordingly.
1.1.1 The eligibility of bidders will correspond to the combined estimated cost of
different components put to bid.
1.2 Intending bidders is eligible to submit the bid provided he has definite proof from the
appropriate authority, which shall be to the satisfaction of the competent authority, of
having satisfactorily completed similar works of magnitude specified below: -
a) Should have satisfactorily completed the works as mentioned below during the last
Seven years ending last day of the month previous to the one in which tenders are
invited.
Three similar completed works each costing not less than Rs. 62.38 lakhs, or two
similar completed works each costing not less than Rs.93.57 lakhs, or one similar
completed work costing not less than Rs.124.76 lakhs.
The works of specialized E &M services included in definition of similar work will
be considered even if these have been executed under a separate contract.
However, these, E &M services executed under a separate contract shall be
considered for the purpose of assessing technical competence only without adding
its monetary value for determining the eligibility as required above.
PART A 12
The bidder shall submit copy of final bill paid along with bill of quantities
and experience certificate issued by an officer not below the rank of
Executive Engineer / Project Manager or equivalent.
The value of executed works shall be brought to current costing level by enhancing
the actual value of work at simple rate of 7% per annum; calculated from the date of
completion to previous day of last day of submission of tenders. (Applicable to
CPWD enlisted contractors of appropriate class also).
To become eligible for issue of bid, the bidders shall have to furnish an affidavit as
under: -
I/We undertake and confirm that eligible similar works(s) has/have not been got
executed through another contractor on back-to-back basis. Further that, if such a
violation comes to the notice of Department, then I/we shall be debarred for bidding
in CPWD in future forever. Also, if such a violation comes to the notice of
Department before date of start of work, the Engineer-in-Charge shall be free to
forfeit the entire amount of Earnest Money Deposit/Performance Guarantee.
(Scanned copy to be uploaded at the time of submission of bid).
1.3 The Minimum eligibility criteria for Specialized work wherever applicable for
Civil and E&M Works.
Component of
Sl. Estimated
Civil / E&M Eligibility
No. cost in Rs.
works
1. Waterproofing 5,08,996/- The Main contractor should associate with an agency
treatment who should have satisfactorily completed the said
work specialized work of the amount mentioned below
during the last 7 (Seven) years ending the previous
date of the last date of submission of bids.
Three similar works each costing not less than Rs. 2.04
lakhs of the estimated cost.
OR
Two similar works each costing not less than Rs.3.05
lakhs of the estimated cost.
OR
One similar work each costing not less than Rs.4.07
lakhs of the estimated cost.
2. 150 KLD STP - 34,36,631/- The main contractor shall have to associate with
E&M works agency fulfilling the following eligibility criteria
PART A 13
Component of
Sl. Estimated
Civil / E&M Eligibility
No. cost in Rs.
works
having successfully completed during last seven years
ending last date of month previous to the one in
which tender is invited, as given below with
completion certificate issued by an officer not below
the rank of Executive Engineer or equivalent duly
attested.
Three similar completed works each of value not less
thanRs.13.75 Lakhs
or
Two similar completed works each of value not less
than Rs.20.62 Lakhs
or
One similar completed work of value not less
thanRs.27.49 Lakhs
Similar work shall mean "SITC of Sewage Treatment
Plant"
However, the Composite category contractor shall
also be eligible to carry out himself without
associating any specialized agency provided:
(a) He fulfills the prescribed eligibility criteria
respectively for this work.
Note:
i) The value of executed works shall be brought to the current costing level by
enhancing the actual value of work at a simple rate of 7% per annum calculated from
the date of completion to the last date of submission of tender.
ii) The main contractor has to submit consent letters as per Form “K”, given in this
tender document from the eligible associate agency of the respective component of
Specialized Civil and / E&M work for each of the components of work by clearly
indicating the component of work specified as above.
iii) The main contractor will submit MOU signed with an eligible associated contractor.
The MOU in the enclosed Form “L” shall be signed by both the contractors, i.e., main
contractor as 1st party and associated contractor as 2nd party, independently for EACH
specialized Civil and / E&M component, specified as above.
iv) If the main contractor fails to associate agency for execution of specialized Civil and/
E&M work or furnishes incomplete details or furnishes details of ineligible agencies
even after the tenderer is given due opportunity, the entire scope of such component
PART A 14
of work shall be withdrawn from the tender and the same shall be got executed by the
Engineer-in –Charge at the risk and cost of the main contractor.
vi) Self-attested GST registration documents in respect of the associated agencies shall be
submitted within 15 days of award of work OR before start of specialized Civil and/
E&M component of works whichever is earlier.
2. Agreement shall be drawn with the successful bidder on prescribed Form No. CPWD
7 (or other Standard Form as mentioned) which is available at Govt. of India
Publication and also available on website www.cpwd.gov.in. Bidders shall quote his
rates as per various terms and conditions of the said form which will form part of the
agreement.
3. The time allowed for carrying out the work will be 180 days from the date of start as
defined in Schedule ‘F’ or from the first date of handing over of the site, whichever is
later, in accordance with the phasing, if any, indicated in the bid documents.
ii) The architectural and structural drawings shall be made available in phased
manner, as per requirement of the same as per approved programme of
completion submitted by the contractor after award of work.
6. After submission of the bid the contractor can re-submit revised bid any number of
times but before last time and date of submission of bid as notified.
7. While submitting the revised bid, contractor can revise the rate of one or more item(s)
any number of times (he need not re-enter rate of all the items) but before last time
and date of submission of bid as notified.
8. Earnest Money Rs.3,11,910/- in the form of Insurance Surety Bonds, Account Payee
Demand Draft, Fixed Deposit Receipt, Banker’s Cheque or Bank Guarantee including
e- Bank Guarantee (for balance amount as prescribed) from any of the Commercial
Banks (drawn in favour of Executive Engineer, Tirupati Central Division, CPWD,
Tirupati shall be scanned and uploaded on the e-Tendering website within the period
of bid submission. The original EMD should be deposited either in the office of
the Executive Engineer inviting bids or the division office of any Executive Engineer,
CPWD within the period of bid submission. The EMD receiving Executive Engineer
(Including NIT issuing EE/AE) shall issue a receipt of deposition of earnest money
PART A 15
A part of earnest money is acceptable in the form of bank guarantee also. In such
cases, minimum 50% of earnest money or Rs.20 lakhs, whichever is less, will have to
be deposited in shape prescribed above, and balance may be deposited in shape of
Bank Guarantee including e- Bank Guarantee of any Commercial bank having
validity for a period of 180 days or more from the last date of receipt of bids which is
to be scanned and uploaded by the intending bidders.
The earnest money given by all the tenderers except the lowest tenderer shall be
refunded immediately after the expiry of stipulated bid validity period or
immediately after acceptance of the successful bidder, whichever is earlier. However,
in case of two/ three bid system, earnest money deposit of bidders unsuccessful
during technical bid evaluation etc. should be returned within 30 days of declaration
of result of technical bid evaluation.
Online bid documents submitted by intending bidders shall be opened only of those
bidders, who has deposited EMD with any division of CPWD and other documents
scanned and uploaded are found in order.
9. The bid submitted shall become invalid and e-Tender processing fee (if applicable)
shall not be refunded if:
ii) The bidder does not upload scanned copies of all the documents stipulated in
the bid document.
iii) If any discrepancy is noticed between the documents as uploaded at the time of
submission of bid and hard copies as submitted physically by the lowest bidder
in the office of bid opening authority.
iv) If a tenderer quotes nil rates against each item in item rate tender or does not
quote any percentage above/below on the total amount of the tender or any section /
sub head in percentage rate tender, the tender shall be treated as invalid and will not
be considered as lowest tenderer.
10. The contractor, whose tender is accepted, will be required to submit an irrevocable
performance guarantee at specified percentage of the tendered amount as mentioned
in schedule E and within the period specified in Schedule F. This guarantee shall be in
PART A 16
the form of Insurance Surety Bonds, Account Payee Demand Draft, Fixed Deposit
Receipt or Bank Guarantee from any of the Commercial Banks in accordance with the
prescribed form. In case the contractor fails to deposit the said performance guarantee
within the period as indicated in Schedule 'F’, including the extended period if any,
the Earnest Money deposited by the contractor shall be forfeited automatically
without any notice to the contractor. The earnest money deposited along with bid
shall be returned after receiving the aforesaid performance guarantee. The contractor
whose bid is accepted will also be required to furnish either copy of applicable
licenses/ registrations or proof of applying for obtaining labour licenses, registration
with EPFO, ESIC and BOCW Welfare Board including Provident Fund Code No. If
applicable and also ensure the compliance of aforesaid provisions by the sub-
contractors, if any engaged by the contractor for the said work within the period
specified in Schedule F.
11. The site for the work of “Construction of 150 KLD Capacity Sewage Treatment
Plant including SITC of E&M works and distribution lines for treated water at
CRPF Campus, Kalikiri, Chittoor Dist., A.P.” will be made available on “as is where
is” basis.
Intending Bidders are advised to inspect and examine the site and its surroundings
and satisfy themselves before submitting their bids as to the nature of the ground and
sub-soil (so far as is practicable), the form and nature of the site, the means of access
to the site, the accommodation they may require and in general shall themselves
obtain all necessary information as to risks, contingencies and other circumstances
which may influence or affect their bid. A bidders shall be deemed to have full
knowledge of the site whether he inspects it or not and no extra charge consequent on
any misunderstanding or otherwise shall be allowed. The bidders shall be responsible
for arranging and maintaining at his own cost all materials, tools & plants, water,
electricity access, facilities for workers and all other services required for executing
the work unless otherwise specifically provided for in the contract documents.
Submission of a bid by a bidder implies that he has read this notice and all other
contract documents and has made himself aware of the scope and specifications of the
work to be done and of conditions and rates at which stores, tools and plant, etc. will
be issued to him by the Government and local conditions and other factors having a
bearing on the execution of the work.
The intending bidder should submit the declaration about site inspection in Form ‘I’.
12. The competent authority on behalf of the President of India does not bind itself to
accept the lowest or any other bid and reserves to itself the authority to reject any or
all the bids received without the assignment of any reason. All bids in which any of
the prescribed condition is not fulfilled or any condition including that of conditional
rebate is put forth by the bidders shall be summarily rejected.
PART A 17
17. The bid for the work shall remain open for acceptance for a period of Seventy-Five
(75) days from the date of opening of technical bids. Further,
i. If any tenderer withdraws his tender or makes any modifications in the terms and
conditions of the tender which is not acceptable to the department within 7days after
last date of submission of bids, then the Government shall without prejudice to any
other right or remedy, be at liberty to forfeit 50% of the earnest money absolutely
irrespective of letter of acceptance for the work is issued or not.
ii. If any tenderer withdraws his tender or makes any modifications in the terms and
conditions of the tender which is not acceptable to the department after expiry of
7days after last date of submission of bids, then the Government shall without
prejudice to any other right or remedy be at liberty to forfeit 100% of the earnest
money absolutely irrespective of letter of acceptance for the work is issued or not.
iii. In case of forfeiture of earnest money as prescribed in para (i) and (ii) above, the
bidder shall not be allowed to participate in the rebidding process of the same work.
18. This notice inviting Bid shall form a part of the contract document. The successful
bidders/contractor, on acceptance of his bid by the Accepting Authority shall within
7 days from the stipulated date of start of the work, sign the contract consisting of: -
PART A 18
i) The Notice Inviting Bid, all the documents including additional conditions,
specifications and drawings, if any, forming part of the bid as uploaded at the
time of invitation of bid and the rates quoted online at the time of submission of
bid and acceptance thereof together with any correspondence leading thereto.
ii) Standard C.P.W.D. Form 7 or other Standard C.P.W.D. Form as applicable.
19. For Composite Tenders
21.1. The Engineer-in-Charge of the major competent will call bids for the composite work.
The cost of bid document and Earnest Money will be fixed with respect to the
combined estimated cost put to tender for the composite bid.
21.2. The bid document will include following five components:
Part A: - CPWD-6, CPWD-7 including schedule A to F for the major component
(Civil) of the work, Standard General Conditions of Contract for Construction works-
2023 as amended/modified up to last date of submission of tender.
Part B: - Special conditions, Particular specifications and list of preferred makes
applicable to major component (Civil works) of the work.
Part C: - Schedule A to F for minor component (E & M) of the work, special additional
conditions and list of preferred makes applicable to minor component(s) of the work.
Part D: - Schedule of quantities for Civil & E&M component(s) of the work.
Part E: - Indicative Tender drawings.
21.3. The bidder must associate himself, with agencies as per NIT conditions.
21.4. The eligible bidders shall quote rates for all items of major component as well as for
all items of minor components of work.
21.5. After acceptance of the bid by competent authority, the EE in charge of major
component of the work shall issue letter of award on behalf of the President of India.
After the work is awarded, the main contractor will have to enter into one agreement
with EE in charge of major component and has also to sign two or more copies of
agreement depending upon number of EE's/DDH in charge of minor components.
One such signed set of agreement shall be handed over to EE/DDH in charge of
minor component(s).
EE of major component will operate Part A and Part B of the agreement. EE/DDH in
charge of minor component(s) shall operate Part- C along with Part A of the
agreement.
21.6. Entire work under the scope of composite tender including major and all minor
components shall be executed under one agreement.
21.7. Security Deposit will be worked out separately for each component corresponding to
the estimated cost of the respective component of works.
21.8. The main contractor has to associate agencies for specialized component(s)
conforming to eligibility criteria as defined in the bid document and has to submit
detail of such agency(s) to Engineer-in-Charge of relevant component(s) within
PART A 19
Executive Engineer
CPWD, Tirupati.
(For& on behalf of President of India)
PART A 20
uploaded). The value of annual turnover figures shall be brought to the current value
by enhancing the actual turnover figures at simple rate of 7% per annum.
(iii) Should not have incurred any loss (profit after tax should be positive) in more than
two years during the last five years ending 31st March 2024.
(iv) Should have a Banker's Certificate from a commercial Bank for Rs.62.38 lakhs or
Net Worth certificate from CA with Unique Document Identification Number
(UDIN) of minimum amount of Rs.15.60 lakhs. (Scanned copy of original to be
uploaded).
(v) Should have bidding capacity equal to or more than the estimated cost of the work
put to tender. The bidding capacity shall be worked out by the following formula:
Bidding Capacity = {[AxNx1.5]-B}
Where,
A = Maximum turnover in construction works executed in any one year during the
last seven years taking into account the completed as well as works in progress. The
value of completed works shall be brought to current costing level by enhancing at a
simple rate of 7% per annum.
Or
In case, if bidders are from the categories of Retired Govt. Engineer /Architect, then
“A” shall be as per Rule 6.1.7 of enlistment Rules 2024
Or
In case if the bidders is a newly enlisted director/ Partner then “A” shall be taken as
proportionate share as per rule 9.6.3 and 9.6.4 of Enlistment Rules 2024
N = Number of years prescribed for completion of work for which bids have been
invited.
B = Value of existing commitments and ongoing works to be completed during the
period of completion of work for which bids have been invited.
(vi) Evaluation of performance: Evaluation of the performance of contractors for
eligibility shall be done by NIT approving authority or a Committee constituted by
him. All the eligible similar works executed and submitted by the bidders in support
of eligibility and any one of the ongoing works, may be got inspected by a committee
which may consist of client or any other authority as decided by NIT approving
authority. The marks for the quality shall be given based on this inspection, if
inspection is carried out.
Scoring method of evaluation: - The scoring for evaluation mentioned in these
columns shall be done as given in Proforma - I.
PART A 22
PROFORMA - 1
Attributes Evaluation
(a) Financial strength (20 marks)
(i) Average annual 16 marks (i) 60% marks for minimum eligibility
turnover criteria.
(ii) Banker’s 4 marks (ii) 100% marks for twice the minimum
Certificate eligibility criteria or more.
In between (i) & (ii) - on pro-rata basis
(b) Experience in (20 marks) (i) 60% marks for minimum eligibility
similar class of criteria.
works (ii) 100% marks for twice the minimum
eligibility criteria or more.
In between (i) & (ii) - on pro-rata basis
(c) Performance on (20 marks)
works (time over
run)
Parameter Calculation For Score Maximum
points marks
If TOR = 1.00 2.00 3.00 >3.50 20
(i) Without levy of 20 15 10 10
compensation
(ii) With levy of compensation 20 5 0 0
(iii) Levy of compensation not 20 10 0 0
decided
TOR = AT/ST, where AT= Actual Time; ST= Stipulated Time in the
Agreement plus (+) justified period of Extension of Time
Note: Marks for value in between the stages indicated above is to be
determined by straight line variation basis.
(d Performance of works (Quality) as per Assessment in Form D-1. (40 marks)
)
Completed works Ongoing works (Total marks assessed)
(max. 25 marks) (max.15 marks)
NOTE: - 1. If in case, the bidder does not have any ongoing works then for the evaluation
under attribute (d), the completed similar works shall be assessed for 40 Marks.
To become eligible for shortlisting the bidder must secure at least 50 % (fifty percent) marks
in each (a, b, c & d above) and 60 % (sixty percent) marks in aggregate.
The department, however, reserves the right to restrict the list of such qualified contractors to
any number, as deemed suitable by it.
PART A 23
SECTION - I
Sl. Period of
Name of work Estimated cost
No. completion
A. Civil Component:
All tanks Equalization tank. MBBR tank, Tube settler tank, filter bed tank, treated
water tank and housing of all E& M portion are with RCC using M30 grade design
mix concrete walls.
B. Electrical component:
Supplying, installing, testing & commissioning of E&M components for 150 KLD
Effluent Treatment plant.
SECTION - II
INFORMATION & INSTRUCTIONS FOR BIDDERS
1. General:
1.1. Letter of transmittal and forms for deciding eligibility are given in Section III.
1.2. All information called for in the enclosed forms should be furnished against the
relevant columns in the forms. If for any reason, information is furnished on a
separate sheet, this fact should be mentioned against the relevant column. Even if no
information is to be provided in a column, a "nil" or "no such case" entry should be
made in that column. If any particulars/query is not applicable in case of the bidder,
it should be stated as "not applicable". The bidders are cautioned that not giving
complete information called for in the application forms or not giving it in clear terms
or making any change in the prescribed forms or deliberately suppressing the
information may result in the bid being summarily disqualified. Bids made in any
other method than specified e-tendering process and those received late will not be
entertained.
1.3. References, information and certificates from the respective clients certifying
suitability, technical knowledge or capability of the bidder should be signed by an
officer not below the rank of Executive Engineer or equivalent.
1.4. The bidder may furnish any additional information which he thinks is necessary to
establish his capabilities to successfully complete the envisaged work. He is, however,
advised not to furnish superfluous information.
1.5. No information/documents shall be entertained after submission of bid unless it is
required to clarify the query raised by employer. No fresh/revised mandatory
documents is remitted at this stage.
2. Definitions:
2.1. In this document the following words and expressions have the meaning hereby
assigned to them.
2.2. Employer: Means the President of India, acting through the Executive Engineer,
CPWD, Tirupati.
2.3. Bidder: Means the individual, proprietary firm, firm in partnership, limited company
private or public or corporation.
2.4. "Year" means "Financial Year" unless stated otherwise.
3. Method of application:
3.1. If the bidder is an individual, the application shall be signed by him above his full
type written name and current address.
3.2. If the bidder is a proprietary firm, the application shall be signed by the proprietor
above his full typewritten name and the full name of his firm with its current address.
3.3. If the bidder is a firm in partnership, the application shall be signed by all the
partners of the firm above their full typewritten names and current addresses, or,
alternatively, by a partner holding power of attorney for the firm. In the latter case a
certified copy of the power of attorney should accompany the application. In both
cases a certified copy of the partnership deed and current address of all the partners
of the firm should accompany the application.
PART A 25
3.4. If the bidder is a limited company or a corporation, the application shall be signed by
a duly authorized person holding power of attorney for signing the application
accompanied by a copy of the power of attorney. The bidder should also furnish a
copy of the Memorandum of Articles of Association duly attested by a Public Notary.
4. Final decision-making authority.
The employer reserves the right to accept or reject any bid and to annul the process
and reject all bids at any time, without assigning any reason or incurring any liability
to the bidders.
5. Particulars provisional
The particulars of the work given in Section - 1 are provisional. They are liable to
change and must be considered only as advance information to assist the bidder.
6. Site visit
The bidder is advised to visit the site of work, at his own cost, and examine it and its
surroundings to himself collect all information that he considers necessary for proper
assessment of the prospective assignment.
7. Initial Criteria for eligibility
(A) Technical Eligibility criteria:
7.1. The Bidder should have satisfactorily completed similar works during the last Seven
years ending last date of the month previous to the one in which tenders are invited.
For this purpose, cost of work shall mean gross value the completed work including
cost of material supplied by the Government/Client but excluding those supplied
free of cost. This should be certified by an officer not below the rank of Executive
Engineer/Project Manager or equivalent
(i) Three similar completed works each costing not less than Rs. 62.38 lakhs, or two
similar completed works each costing not less than Rs.93.57 lakhs, or one similar
completed work costing not less than Rs.124.76 lakhs.
Similar work shall mean works of “Construction of minimum 40 KLD Capacity
Sewage Treatment Plant including SITC of E&M works, all composite executed
under one agreement in India.”
The works of specialized E &M services included in definition of similar work will
be considered even if these have been executed under a separate contract.
However, these, E &M services executed under a separate contract shall be
considered for the purpose of assessing technical competence only without adding
its monetary value for determining the eligibility as required above.
Godowns / Warehouses/ factory sheds/ buildings shall not be considered as
eligible similar works.
For similar works, works executed in India only shall be considered.
The bidder shall submit copy of final bill paid along with bill of quantities
and experience certificate issued by an officer not below the rank of
Executive Engineer / Project Manager or equivalent.
PART A 26
The value of executed works shall be brought to current costing level by enhancing
the actual value of work at simple rate of 7% per annum; calculated from the date of
completion to previous day of last day of submission of tenders. (Applicable to
CPWD enlisted contractors of appropriate class also)
(B) Financial Eligibility Criteria:
7.2. The bidder should have had Average Annual Financial Turnover of Rs.46.79 lakhs on
Civil/Electrical construction work during the last three consecutive years ending 31st
March 2024 as per the balance sheets duly audited and certified by Chartered
Accountant. Year in which no turnover is shown would also be considered for
working out the average. The value of annual turnover figures shall be brought to
current value by enhancing the actual turnover figure at simple rate of 7% per
annum.
7.3. The bidder should not have incurred any loss (profit after tax should be positive) in
more than two years during available last five consecutive balance sheets (standalone
financial statement) ending 31st March 2024, duly certified and audited by the
Chartered Accountant.
7.4. The bidder should have a Banker's certificate from a Commercial Bank for Rs.62.38
lakhs certified by his Bankers. (Not required if applicant is a CPWD registered
contractor of appropriate class) or the bidder should submit Net worth Certificate of
minimum amount of Rs.15.60 lakhs issued by the certified Chartered Accountant (on
the format prescribed in form B-1).
7.5. The bidder should have sufficient number of Technical and Administrative
employees for the proper execution of the contract. The bidder shall have to submit a
list of these employees stating clearly how these would be involved in this work
within 15 days of award of work.
7.6. Bidding Capacity (applicable for CPWD enlisted contractors also): The bidding
capacity of the contractor should be equal to or more than the estimated cost of the
work put to tender. The bidding capacity shall be worked out by the following
formula:
Bidding Capacity = {[AxNx1.5]-B}
Where,
A = Maximum turnover in construction works executed in any one year during the
last seven years taking into account the completed as well as works in progress. The
value of completed works shall be brought to current costing level by enhancing at a
simple rate of 7% per annum.
N = Number of years prescribed for completion of work for which bids have been
invited.
B = Value of existing commitments and ongoing works to be completed during the
period of completion of work for which bids have been invited. The amount of works
which are stuck up due to local body clearance, environmental clearance, Court
decisions etc., shall not be considered for calculation of “B”. NIT approving authority
may take a final decision on other justified reasons.
Note:
1. The bidder should submit bidding capacity as per Form ‘C3’
2. Bidding capacity is applicable for all the contractors including CPWD enlisted
PART A 27
contractors.
3. Bidding capacity formula for CPWD Contractors who are enlisted based on rule
6.1.7 of Enlistment Rules – 2024 i.e. Government retired Engineer / Architect for
three years from the date of issue of enlistment order, is as follows –
Bidding Capacity = {[AxNx1.5]-B}
Where,
A = Banker’s certificate figure as submitted by applicant (i.e. Government Retired
Engineer/ Architect) at the time of enlistment for first year of enlistment and
subsequent fresh bankers’ certificate for second and third year respectively. Value
of A for first year will be mentioned in the enlistment order by the member
secretary of advisory committee for enlisting authority.
N = Number of years prescribed for completion of work for which bids have been
invited.
B = Value of existing commitments of ongoing works during the period of
execution to be completed during the period of completion of work for which bids
have been invited. This value is for newly enlisted entity.
Within three years from the date of issue of enlistment order, the newly enlisted
entity has to develop its own bidding capacity and thereafter the general bidding
capacity formula being used for other entities shall be applicable to it for
calculation of bidding capacity.
Newly enlisted entity may like to follow general bidding capacity formula even
before period of three years if it so chooses.
4. Bidding capacity for CPWD contractors who are enlisted based on 9.6.3 & 9.6.4 of
Enlistment Rules – 2024 i.e. new entity based on previous enlisted entity for three
years from date of issue of enlistment order, is as follows: -
Annual turnover of newly enlisted entity shall be in proportion to the
shareholding of partners/directors in the original enlisted entity at the time of
enlistment of the newly enlisted entity.
Within three years from the date of issue of enlistment order, the newly enlisted
entity has to develop its own bidding capacity and there after the general bidding
capacity formula being used for other entities shall be applicable to it for
calculation of bidding capacity. Newly enlisted entity may like to follow general
bidding capacity formula even before period of three years, if it so chooses.
Bidding capacity formula for newly enlisted based on rules 9.6.3 or 9.6.4
Enlistment Rules – 2024 shall be as follows: -
Bidding Capacity = {[A’xNx1.5]-B}
Where,
A’ = Proportionate share of newly enlisted director/partner in originally enlisted
company/firm multiplied by the factor A, as given below. Value of A’ will be
mentioned in the enlistment order by the Member Secretary of Advisory
Committee for Enlistment Authority. It will remain same for three years.
PART A 28
A = Maximum turnover in construction works executed in any one year during the
last seven years taking into account the completed as well as works in progress.
The value of completed works shall be brought to current costing level by
enhancing at a simple rate of 7% per annum. This value is originally enlisted entity
at the time of enlistment of newly enlisted entity.
N = Number of years prescribed for completion of work for which bids have been
invited.
5. Enlisted entities based on rules 6.1.7, 9.6.3 & 9.6.4 of enlistment rules – 2024 can
submit MoU from agency having requisite experience for structural system
technology if enlisted entity does not have required experience.
8. Evaluation criteria
8.1. The detailed submitted by the bidders will be evaluated in the following manner:
8.1.1. The initial criteria prescribed in Para 7.0 above in respect of experience of eligible
similar works completed, loss, Banker's certificate, financial turnover and bidding
capacity etc. will first be scrutinized and the bidder's eligibility for the work be
determined.
8.1.2. The bidders qualifying the initial criteria as set out in Para 7.0 above will be evaluated
for following criteria by scoring method on the basis of details furnished by them.
(a) Financial strength (Form 'A' & 'B' or B-1) Maximum 20 marks
(b) Experience in eligible similar nature of work Maximum 20 marks
during last seven years (Form 'C')
(c) Performance on works - Time over run Maximum 20 marks
(d) Performance on works (Form ‘D’-1) - Quality Maximum 40 marks
Total 100 marks
To become eligible for shortlisting the bidder must secure at least fifty percent (50%)
marks in each (Section a, b, c & d) and sixty percent (60%) marks in aggregate.
The department, however, reserves the right to restrict the list of such qualified
contractors to any number deemed suitable by it.
Note: The average value of performance of works for time over run and quality shall
be taken on the basis of performance report and eligible similar works.
9. Financial information
Bidder should furnish the Annual financial statement for the last five years in (Form
"A1"). Banker’s Certificate in (Form "B") or Net worth Certificate in (Form "B-1").
PART A 29
Executive Engineer
CPWD, Tirupati.
(For& on behalf of President of India)
PART A 30
SECTION – III
INFORMATION REGARDING ELIGIBILITY
FORM ‘A’
LETTER OF TRANSMITTAL
From:
To:
Executive Engineer
CPWD, Tirupati.
Subject: - Submission of bids for the work of “Construction of 150 KLD Capacity Sewage
Treatment Plant including SITC of E&M works and distribution lines for treated
water at CRPF Campus, Kalikiri, Chittoor Dist., A.P.”.
Sir,
Having examined the details given in Bid document for the above Work, I/we
hereby submit the relevant information.
1. I/We hereby certify that all the statement made and information supplied in the
enclosed forms A to O and accompanying statement are true and correct.
2. I/We have furnished all information and details necessary for eligibility and have
no further pertinent information to supply.
3. I/We submit the requisite certified solvency certificate or Net worth Certificate
and authorize the Executive Engineer, CPWD, Tirupati to approach the Bank
issuing the solvency certificate to confirm the correctness thereof. I/we also
authorize Executive Engineer, CPWD, Tirupati to approach individuals,
employers, firms and corporation to verify our competence and general
reputation.
4. I/We submit the following certificates in support of our suitability, technical
knowledge and capability for having successfully completed the following
eligible similar works:
Name of work Experience Certificate issued by
FORM ‘A-1’
FINANCIAL INFORMATION
UDIN No:
SIGNATURE OF BIDDER(S)
Note:
1. The bidder should give information strictly in the above format.
2. The annual turnover Figures are to be furnished for the last seven years for the
purpose of working out bidding capacity of the bidder.
PART A 32
FORM ‘B’
To,
Executive Engineer
CPWD, Tirupati.
This is to certify that to the best of our knowledge and information that
M/s./Shri……………………………………… having marginally noted address,
…………………………………………………... as a customer of our bank are / is respectable
and can be treated as good for any engagement up to a limit of Rs……………..........
(Rupees……… ………………………………………………..…).
This certificate is issued without any guarantee or responsibility on the bank or any of
the officers.
NOTE:
1) Banker’s certificate should be on letter head of the Bank addressed to Executive
Engineer, CPWD, Tirupati.
2) In case of partnership firm, certificate should include names of all partners as recorded
with the Bank.
PART A 33
FORM ‘B-1’
To,
Executive Engineer
CPWD, Tirupati.
“It is to certify that as per the audited balance sheet and profit and loss account
during the financial year ..............., the net worth of M/s ...........................................
certified that the net worth of the individual/firm/company has not eroded by more
FORM ‘C’
back basis?
YES / NO
YES/ NO
Sl. No.
1 2 3 4 5 6 7 8 9 10
* Indicate gross Amount Claimed and Amount Awarded by the Arbitration tribunal.
Note:
The bidder is required to submit Form ‘D’ in respect of all the works listed out by the
bidder in the Form ‘C’.
2
Name of work / project and location
3
Owner or sponsoring organization
4
Cost of work in crores of rupees.
5
Date of commencement as per contract
6
Stipulated date of completion
(With stamp)
officer to whom reference may be made.
Remarks
PART A 35
FORM “C-1”
1
Sl. No.
Total (B)
above list.
2
Certificate:
Name of work / project and location
4
Contract value in crores of rupees.
:
:
:
:
:
7
Upto date percentage progress of work
Rs.
Rs.
Rs.
Rs.
Remaining work in percentage
8
(100 – Column 7)
…………….
Existing commitment
CALCULATION OF BIDDING CAPACITY
(With stamp)
to whom reference may be made for verification
DETAILS OF EXISTING COMMITMENTS AND ONGOING WORKS
I certify that all the awarded and ongoing works have been included in the
Remarks
PART A 36
FORM “C-3”
PART A 37
FORM ‘D’
FORM ‘D-1’
ASSESSMENT OF QUALITY FOR COMPLETED AS WELL AS ONGOING WORKS
Name of Work:
Date of Inspection:
Date of submission of report:
FORM ‘E’
STRUCTURE & ORGANISATION
Date:
Place:
Signature of Bidder (s)
PART A 41
Form ‘G’
I/We undertake and confirm that eligible similar work(s) has/have not been got
executed through another contractor on back-to-back basis. Further that, if such a
violation comes to the notice of Department, then I/we shall be debarred for bidding in
CPWD in future forever. Also, if such a violation comes to the notice of Department
before date of start of work, the Engineer-in-Charge shall be free to forfeit the entire
amount of Earnest Money Deposit/Performance Guarantee.
Note:
1. Affidavit to be furnished on a Non-Judicial Stamp paper worth of Rs.100/-.
(Scanned copy of this notarized affidavit to be uploaded at the time of
submission of bid).
PART A 42
Form ‘H’
FORM ‘I’
To,
The Executive Engineer,
CPWD, Tirupati.
Dear Sir,
I /We bidder shall be responsible for arranging and maintaining at own cost all
materials, tools & plants, water, electricity, access, facilities for workers and all other
services required for executing the work unless otherwise specifically provided for in
the contract documents. Submission of a bid by me/us implies that I / We have read
this notice and all other contract documents and has / have made myself /ourselves
aware of the scope and specifications of the work to be done and local conditions and
other factors having a bearing on the execution of the work.
Yours faithfully
Form ‘J’
To,
The Executive Engineer,
CPWD, Tirupati.
Sir,
I/we undertake and confirm that any building / infrastructure constructed by
our firm /partnership firm/ company has not suffered any failure, making it unfit for
intended use, either due to structural design and defects or due to use of sub-standard
materials or execution of sub-standard work, poor workmanship or any other reason
during the last 25 (twenty-five) years.
l/we, further, undertake that if such information comes to the notice of CPWD,
then Engineer-in-Charge shall be free to terminate the bid/agreement and to forfeit the
entire amount of earnest money deposit, performance guarantee and security deposits.
l/we, also undertake that in addition to above, the Engineer-in-Charge shall be
free to debar us forever from tendering in CPWD.
The decision of Engineer-in-Charge or any higher authority shall be final and
binding.
FORM ‘K’
I / We will execute the work as per the specifications and conditions of the agreement
and as per directions of the Engineer-in-Charge for the corresponding minor work till
the completion of the work.
I / We will be responsible for necessary action to hand over the installations and for
rectification of defects and repair during the maintenance/warranty period.
Date:
FORM ‘L’
We state that M.O.U between us will be treated as an agreement and has legality as per
Indian Contract Act (amended up to date) and the department (CPWD) can enforce all the
terms and conditions of the agreement for execution of the above work. Both of us shall be
responsible for the execution of work as per the agreement to the extent this MOU allows.
Both the parties can be paid consequent to the execution as per agreement to the extent this
MOU permits. In case of any dispute, either of us will go for mediation by the Engineer in
charge. Any of us may appeal against the mediation to the Chief Engineer, CPWD,
Vijayawada. His decision shall be final and binding on both of us.
4. The site staff required for the Civil/E & M and specialized work shall be
arranged by the Associated Contractor as per terms and conditions of the
agreement.
5. Site order book maintained for the said work shall be signed by the main
contractor as well as by the Engineer of the Associated Contractor and by
Associated Contractor himself.
6. All the correspondence regarding execution of the Civil/E & M and
specialized work shall be done by the department with the Associated
Contractor with a copy to the main contractor. In case of non-compliance of
the provisions of agreement, the main contractor, as well as the associated
contractor shall be responsible. The action under clauses 2 and 3 shall be
initiated and taken against the main contractor.
Date:
Place:
FORM ‘J-1’
To,
The Executive Engineer,
CPWD, Tirupati.
Sir,
Having examined the details given in the bid document for the above work,
I/We hereby submit the following undertaking that
“If work is awarded to me, I/We shall undergo ERP training from CPWD
Regional Training Institutes as applicable and shall obtain and submit the
training certificate secured from the LMS portal of ERP within two months from
the date of receipt of the award letter and failure to do so, a recovery of rupees
ten thousand per week shall be made from my RA bill without giving any show
cause notice to me in this regard”.
Signature of bidder or
an authorized person of the firm
with stamp
PART A 49
C.P.W.D – 7
GOVERNMENT OF INDIA
CENTRAL PUBLIC WORKS DEPARTMENT
STATE : Andhra Pradesh ZONE: CE, Vijayawada
BRANCH : B& R Division: EE, Tirupati
Tender for the work of “Construction of 150 KLD Capacity Sewage Treatment Plant
including SITC of E&M works and distribution lines for treated water at CRPF
Campus, Kalikiri, Chittoor Dist., A.P.
TENDER
I / We have read and examined the notice inviting tender, schedule, A, B, C, D, E & F,
Specifications applicable, Drawings & Designs, General Rules and Directions,
Conditions of Contract, clauses of contract, Special conditions, Schedule of Rate & other
documents and Rules referred to in the conditions of contract and all other contents in
the tender document for the work.
I/ We hereby tender for the execution of the work specified for the President of India
within the time specified in Schedule ‘F’, viz., schedule of quantities and in accordance
in all respects with the specifications, designs, drawings and instructions in writing
referred to in Rule-1 of General Rules and Directions and in Clause 11 of the Conditions
of contract and with such materials as are provided for, by, and in respects in
accordance with, such conditions so far as applicable.
I/ We agree to keep the tender open for Seventy-Five (75) days from the date of opening
of bid and not to make any modification in its terms and conditions.
I/We have deposited EMD for the prescribed amount in the office of concerned
Executive Engineer as per the bid document.
ln respect of portion of EMD prescribed in the shape of BG, the scanned copy of original
Bank Guarantee including e-Bank Guarantee (as applicable) of any commercial bank
having validity for a period of 90 days for single bid and 180 days for two bid systems
or more from the last date of receipt of bids (strike out as the case may be), is to be
uploaded. If I/We, fail to furnish the prescribed performance guarantee within
prescribed period, I/We agree that the said President of India or his successors, in office
shall without prejudice to any other right or remedy, be at liberty to forfeit the said
earnest money absolutely. Further, if I/We fail to commence work as specified, I/ We
agree that President of India or the successors in office shall without prejudice to any
other right or remedy available in law, be at liberty to forfeit the said performance
PART A 50
ACCEPTANCE
The above tender (as modified by you as provided in the letters mentioned hereunder)
is accepted by me for and on behalf of the President of India for a sum of
Rs……………………..…………
(Rupees
………………………………………………………………………………………………)
The letters referred to below shall form part of this contract Agreement: -
(a)
(b)
(c)
For & on behalf of the President of India
Signatures: ……………………………..
Dated: ** Designation: **
PART A 51
PROFORMA OF SCHEDULES A to F
SCHEDULE ‘A’
SCHEDULE ‘D’
Extra schedule for specific requirements / documents for the work, if any-
SCHEDULE ‘E’
Definitions
2(v) Engineer-in-Charge Executive Engineer,
: CPWD, Tirupati or his successor
thereof.
2(viii) Accepting Authority : Chief Engineer,
CPWD, Vijayawada or his
successor thereof.
2(x) Percentage on cost of materials and : 15% (7.5% for Profits + 7.5% for
labour to cover all overheads and profits. overheads)
2(xi) Standard schedule of Rates : Delhi Schedule of Rates 2023 for
Civil component, DSR 2022 for
E&M component and Market
Rates.
2(xii) Department : Central Public Works Department.
9(ii) Standard CPWD contract Form GCC, : GCC 2023 for Construction works
CPWD-7 as modified & corrected up to & CPWD - 7 as amended/
modified up to last date of
submission of e-tender.
Clause I
(i) Time allowed for submission of : 7 days.
performance Guarantee, Programme
Chart (Time and Progress) and applicable
labour licenses, registration with EPFO,
ESIC and BOCW Welfare Board or proof
of applying thereof from the date of issue
of letter of acceptance.
(ii) Maximum allowable extension with late : 3 days.
fee at 0.1% per day of performance
Guarantee amount beyond the period as
provided in (i) above
Clause 2
Authority for fixing compensation under clause- : Chief Engineer, CPWD,
2. Vijayawada or his successor
thereof.
Clause 5
Number of days from the date of issue of letter of : 10 days
acceptance for reckoning date of start
PART-A 53
Sl. Description of
No. Time Allowed (from Amount to be withheld in case of
Milestone
date of start) non-achievement of milestone
(Financial)
1 1/4th of the 50 days 1.25 % of the total tendered amount
Tendered Amount of Civil work component.
2 1/2nd of the 90 days 1.25 % of the total tendered amount
Tendered Amount of Civil work component.
3 3/4th of the 135 days 1.25 % of the total tendered amount
Tendered Amount of Civil work component.
4 Completion in all 180 days 1.25 % of the total tendered amount
respects and of Civil work component.
handing over.
Time Period allowed for execution of Work: - 180 days.
Authority to decide:
i) Authority to convey the decision of shifting of : Executive Engineer, CPWD,
milestones and extension of time Tirupati or his successor thereof.
Part B-1 Portions of Layout plans& floor Campus Layout plan drawing shall
Architectural plans. be issued along with the letter of
Designs to be commencement of work. Other
issued drawings/ details required if any
will be issued in phased manner as
per the approved programme of
contractor and as per progress of
work.
Part B-2 Portions of Structural drawings Structural drawings/details
Civil Designs including structural analysis of all
to be issued the buildings and development
works etc., required as per the scope
of work to be submitted by the
contractor to the Engineer-in-charge
duly proof checked by the third
party as per agreement condition.
The structural drawings should be
approved by the competent
authority including
revisions/corrections if any within
30 days of date of start.
The site coordination drawings
between various services including
but not limited to stormwater drain,
sewage line, electrical line, HVAC
line, tactile lines, street light poles
etc. to be submitted 30 days prior to
expected date of start as per agency’s
program chart.
Internal plumbing layout of all
structures, irrigation water pipelines
layout to be submitted 30 days prior
to expected execution date as per
agency’s program chart.
Part B-3 Portions of IEI Necessary designs are required to be
E&M Designs submitted by the contractor for
to be issued approval of the Engineer-in-charge
within 30days of issue of award
letter or before commencement of
activity which is earlier.
Clause 5.4 Rs. 10,000/- per each day
Recovery per day for delay in submission of
revised programme
Clause 6: Computerized Measure Book : EMB
(CMB) / Electronic Measurement Book
(EMB)
Mode of Measurement:
PART-A 55
Clause 7
Gross work to be done together with net : 26.00 lakhs.
Payment/adjustment of advances for material
collected, if any since the last such payment
for being eligible to interim payment
Clause 7A
Whether clause 7A shall be applicable: : Yes.
Clause 7B
Whether clause 7B shall be applicable: : Yes.
Clause 8A
Authority to decide compensation on : Chief Engineer, CPWD, Vijayawada or
account if contractor fails to submit his Successor thereof
completion plans
Clause 10A
List of testing equipment to be provided by : Refer Page No.158 to 159.
the contractor at site lab.
Clause 10 B(ii)
Whether clause 10 B(ii) shall be applicable : Not Applicable
Clause 10C
Component of Labour expressed as percent : Applicable
of the value of work.
Clause 10CC : Not Applicable
Clause 11 CPWD Specifications 2019 Vol. - I & II
Specifications to be followed for execution : with up-to-date correction slips.
of work Particular specifications included in this
Bid document, Energy Conservation
Building Code (ECBC)-2017, NBC-2016
and all relevant BIS codes of practice
modified and corrected up to the last
date of submission of Bids.
Clause 12 : The Completion of Cost including extra
items, deviations and admissible
escalation shall, in no case, exceed 1.50
times the contract amount.
Contractor has to devise a system to
keep a watch on quantum of work
taken up vis-à-vis balance items
required to complete defined scope of
work and will give the alerts to
Engineer-In-Charge before taking up
extra items, deviations so that
completion cost including extra items,
deviations and admissible escalation
does not exceed 1.50 times the contract
value.
Work executed beyond above limit will
neither be recorded nor be paid
12.2 C : 100% (Hundred percent)
PART-A 56
Assistant Engineers retired from Government services those are holding Diploma will be treated at
par with Graduate Engineers.
Diploma holders with minimum 10-year relevant experience with a reputed construction co. can be
treated at par with Graduate Engineers for the purpose of such deployment subject to the condition
that such diploma holders should not exceed 50% of requirement of degree engineers.
Clause 38
(i) (a) Schedule / statement for determining theoretical quantity of cement & bitumen on
the basis of Delhi Schedule of Rates 2023 printed by C.P.W.D. with correction slips up to the
last date of submission of bids.
(b) Bitumen for all works : 2.5% plus only & nil on minus Side
Executive Engineer
CPWD, Tirupati
PART-A 58
Form ‘O’
Annexure I
On Non – Judicial stamp paper of minimum Rs. 100/-
(Guarantee offered by Bank to CPWD in connection with the execution of contracts)
Form for Bank Guarantee for Earnest Money Deposit/Performance Guarantee
/ Security Deposit / Mobilization Advance.
7. This guarantee will not be discharged due to the change in the constitution of
the Bank or the Contractor.
PART-A 60
Date ……………………….
Witness:
Note:
1. *Date to be worked out on the basis of validity period of 90 days where only
financial bids are invited and 180 days for two / three bid system from the date of
submission of tender.
2. ** In paragraph 1, strike out the portion not applicable. Bank Guarantee will be
made either for earnest money or performance guarantee/security
deposit/mobilization advance, as the case may be.
PART B 61
PART – B
SPECIAL CONDITIONS
1.0 General
1.1 Specifications & Order of preference:
1.1.1 Except for the items, for which Particular Specifications are given or where it is
specifically mentioned otherwise in the description of the items in the schedule
of quantities, the work shall generally be carried out in accordance with the
“CPWD Specifications 2019 Vol. I & II” with up-to-date correction slips,
additional / Particular Specifications, Architectural / structural drawings and as
per instructions of Engineer-in-Charge.
1.1.2 The several documents forming the tender are to be taken as mutually
complementary to one another. Detailed drawings shall be followed in
preference to small scale drawings and figured dimensions in preference to
scaled dimensions.
1.1.3 If there is any difference or discrepancy between the description of items as
given in the schedule of quantities, particular specifications for individual items
of work (including special conditions) and I.S. Codes etc., the following order of
preference shall be observed
(i) Description of items as given in Schedule of Quantities.
(ii) Particular Specifications, Special Conditions and Additional conditions,
if any.
(iii) Drawings.
(iv) CPWD Specifications.
(v) General conditions of contract for CPWD works.
(vi) Indian Standard Specifications of B.I.S.
(vii) Manufacturers’ specifications & as decided by Engineer-in-charge.
(viii) Sound Engineering practices.
“In the event of any variation/ discrepancy in the drawings, specifications and
tender documents etc. the decision of the Engineer-in-charge shall be final
binding and conclusive on the contractor and in the case the contractor have any
doubt and the same should be got clarified immediately from the Engineer-in-
charge and no claim of the contractor shall be entertained thereafter. Moreover,
the agency is not allowed to take benefit out of any clerical/ grammatical
mistake in the standard clauses/Schedule of Quantities/Specifications etc. being
used in the agreement”.
1.1.4 Any reference made to any Indian Standard Specifications, shall imply to the
latest version of that standard, including such revisions / amendments as issued
by the Bureau of Indian Standards up to last date of receipt of tenders. The
Contractor shall keep at his own cost all such publications including relevant
Indian Standard Codes applicable to the work at site.
PART B 63
1.2 Scope:
1.2.1 The works to be governed by this contract shall cover delivery and
transportation up to destination, safe custody at site, insurance, erection, testing
and commissioning of the entire works.
1.2.2 The works to be undertaken by the contractor shall inter alia include the
following:
i. Preparation of detailed SHOP drawings and AS BUILT drawings
wherever applicable.
ii. Obtaining of Statutory permissions wherever applicable and required.
iii. Pre-commissioning tests as per relevant standard specifications, code of
practice, Acts and Rules wherever required.
iv. Warranty obligation for the equipment and/or fittings/fixtures supplied
by the contractor.
1.2.3 Contractor shall provide all the shop drawings or layout drawings for all the
coordinated services before starting any work or placing any order for any of the
services etc. These shop drawings/layout drawings shall be got approved from
Engineer-in-charge before implementation and this shall be binding on the
contractor. The contractor shall submit material submittals along with material
sample for approval of Engineer-in-charge prior to delivery of material at site.
1.2.4 All the hidden items such as water supply lines, drainage pipes, conduits,
sewers etc. are to be properly tested as per the design conditions before covering
and their measurements in computerized measurement book duly test checked
shall be deposited with Engineer in charge or his authorized representative,
prior to hiding these items.
1.3 Deployment of Technical staff & skilled labour:
1.3.1 The quality of work is of paramount importance. Contractor shall have to
engage well experienced skilled labour and deploy modern T&P and other
equipments to execute the work to provide the desired quality.
The Contractor shall depute Site Engineer & skilled workers as required for the
work. He shall submit organization chart along with details of Engineers and
supervisory staff. It shall be ensured that all decision making powers shall be
available to the representatives of the contractor at site itself to avoid any likely
delays on this account. The contractor shall also furnish list of persons for
specialized works to be executed for various items of work. The Contractor shall
identify and deploy key persons having qualifications and experience in the
similar and other major works, as per the field of their expertise. If during the
course of execution of work, the Engineer-in-Charge is of the opinion that the
deployed staff is not sufficient or not well experienced; the Contractor shall
deploy more staff or better-experienced staff at site to complete the work with
quality and in stipulated time limit. The Project Manager of the contractor along
with all technical staff as mentioned in the clause 32 of the GCC, shall always be
available at the site during execution of work.
PART B 64
1.7.4 The contractor, his authorized representative, workmen etc. shall strictly
observe orders pertaining to fire precautions prevailing in the area.
1.7.5 The Contractor shall take all necessary precautions to prevent any nuisance or
inconvenience to the owners, tenants or occupants of the adjacent properties and
to the public in general. The Contractor shall take all care, as not to damage any
other adjacent property or other services running adjacent to the plot. If any
damage is done, the same shall be made good by the Contractor at his own cost
and to the entire satisfaction of the Engineer-in-Charge. The Contractor shall
use such methodology and equipments for execution of the work, so as to cause
minimum environmental pollution of any kind during construction, to have
minimum construction time and minimum inconvenience to road users and to
the occupants of the buildings on the adjacent plot and public in general, etc. He
shall make good at his own cost and to the entire satisfaction of the Engineer in
Charge any damage to roads, paths, cross drainage works or public or private
property whatsoever caused, due to the execution of the work or by traffic
brought thereon, by the Contractor. Further, the Contractor shall take all
precautions to prevent any pollution of streams and waterways. All waste or
superfluous materials shall be carted away by the Contractor, entirely to the
satisfaction of the Engineer-in-Charge. Utmost care shall be taken to keep the
noise level to the barest minimum so that no disturbance as far as possible is
caused to the occupants / users of adjoining buildings. No claim what so ever
on account of site constraints mentioned above or any other site constraints not
specifically stated here, shall be entertained from the Contractor. Therefore, the
Contractors are advised to visit site and get firsthand information of site
constraints. Accordingly, they should quote their tenders. Nothing extra shall
be payable on this account.
1.8. General cleanliness of the site and Stacking & Storage of Materials:
1.8.1 The site of work shall be always kept clean in general strictly adhering to
approved job layout and green building parameters. The Contractor shall take
all care to prevent any water- logging at site. The waste water shall not be
allowed to be collected at site. It may be directly pumped into the public
drainage system with prior approval of the concerned authorities. For discharge
into public drainage system, necessary permission shall be obtained from
concerned authorities after paying the necessary charges, if any, directly to the
authorities. The work shall be carried out in such a way that the area is kept
clean and tidy. All the fees/charges in this regard shall be borne by the
Contractor. Nothing extra shall be payable on this account.
1.8.2 The contractor shall take instructions from the Engineer-in-Charge regarding
collection and stacking of materials at any place. No excavated earth or building
rubbish shall be stacked on areas where other buildings, roads, compound wall,
services etc. are to be constructed.
1.8.3 For construction works which are likely to generate malba / rubbish, contractor
shall dispose of malba, rubbish & other unserviceable materials and wastes at
his own cost to the notified/specified dumping ground and under no
circumstances these shall be stacked / dumped even temporarily, outside the
construction premises.
PART B 66
1.8.4 The contractor shall construct suitable godowns, yard at the site of work for
storing all other materials so as to be safe against damage by sun, rain, damages,
fire, theft etc. at his own cost and also employ necessary watch and ward
establishment for the purpose at his cost.
1.9 Lab Equipment:
The contractor shall provide at his own cost suitable weighing, surveying and
levelling and measuring arrangements as may be necessary at site for checking.
All such equipment shall be got calibrated in advance from laboratory,
approved by the Engineer-in-Charge. Nothing extra shall be payable on this
account. A site laboratory with the minimum equipment as specified in NIT
shall be established, made functional and maintained within 21 days from the
award of the work without any extra cost to the department.
1.10 Setting Out
1.10.1 The contractor shall establish, maintain and assume responsibility for grades,
lines, levels and bench marks. He shall report any errors or inconsistencies
regarding grades, lines, levels, dimensions to the Engineer-in-Charge before
commencing work. Commencement of work shall be regarded as the
contractor’s acceptance of such grades, lines, levels and dimensions and no
claim shall be entertained at a later date for any errors found.
1.10.2 In order to set the alignment of buildings / foundations and to mark the same
on the ground, the agency is to adopt “total station” surveying method. The
agency is to engage a well versed and well experienced surveyor in “total
station” survey. Nothing extra for this total station survey is payable.
If at any time, any error in the respect of setting out appears during the progress
of the work, the contractor shall, at his own expense rectify such error if so
required, to the satisfaction of the Engineer-in-Charge.
(i) Though the site levels are indicated in the drawings, the contractor shall
ascertain himself and confirm the site levels with respect to GTS bench mark
from the concerned authorities. The contractor shall protect and maintain
temporary/ permanent benchmarks at the site of work throughout the
execution of the work. These bench marks shall be got checked by the
Engineer-in-Charge or his authorized representatives. The work at different
stages shall be checked with reference to bench marks maintained for the
said purpose. Nothing extra shall be payable on this account.
(ii) The approval by the Engineer-in-Charge, of the setting out by the contractor,
shall not relieve the contractor of any of his responsibilities and obligation to
rectify the errors/defects, if any, which may be found at any stage during
the progress of the work or after the completion of the work.
1.10.3 The contractor shall be entirely and exclusively responsible for the horizontal,
vertical and other alignments, the level and correctness of every part of the work
and shall rectify effectively any errors or imperfections therein. Such
rectifications shall be carried out by the contractor at his own cost to the
instructions and satisfaction of the Engineer-in-Charge.
PART B 67
1.10.4 The Contractor shall carry out survey of the work area, at his own cost,
setting out the layout of building in consultation with the Engineer-in-
Charge & proceed further. Any discrepancy between the architectural
drawings and actual layout at site shall be brought to the notice of the
Engineer-in-charge. It shall be responsibility of the Contractor to ensure
correct setting out of alignment. Total station survey instruments only shall
be used for layout, fixing boundaries, and center lines, etc., along with the
theodolites. Nothing extra shall be payable on this account.
1.10.5 Contractor shall provide permanent bench marks, flag tops and other reference
points for the proper execution of work and these shall be preserved till the end
of work. All such reference points shall be in relation to the levels and locations,
given in the Architectural and plumbing drawings.
1.11 Temporary Water, Electricity & Telephone Connections:
1.11.1 The contractor shall make his own arrangements for water including boring of
tube wells etc. if necessary and for electricity by obtaining electric connections
and by providing diesel generators of adequate capacity if required and make
necessary payments directly to the State Govt. departments concerned.
Necessary approval shall be taken by the contractor from the ground water
department for boring of tube wells. Nothing extra shall be paid on these
accounts. Contractor shall get the water tested from laboratory approved by the
Engineer-in-charge at regular interval as per the CPWD Specifications 2019. All
expenses towards collection of samples, packing, transportation and testing
charges etc. shall be borne by the contractor. The contractor shall obtain
environmental and pollution clearance for the diesel generators. Nothing extra
shall be paid on this account.
1.11.2 The Contractor shall arrange electricity at his own cost for testing of the various
electrical installations as directed by Engineer-in-Charge and for the
consumption by the contractor for executing the work. Also all the water
required for testing various electrical installations, fire pumps, wet riser /
firefighting equipment, fire sprinklers etc. and also testing water supply,
sanitary and drainage lines, water proofing of underground sump, overhead
tanks, water proofing treatment etc. shall be arranged by the contractor at his
own cost. Nothing extra shall be payable on this account.
1.11.4 The Contractor shall be responsible for maintenance and watch and ward of the
complete installation and water / electricity meter and shall also be responsible
for any pilferage, theft, damage, penalty etc. in this regard. The Contractor shall
indemnify the Department against any claim arising out of pilferage, theft,
damage, penalty etc. whatsoever on this account. Security deposit for the work
shall be released only after No Dues Certificates are obtained from the local
Authorities from whom temporary electric/ water / telephone connection have
been obtained by the Contractor. Nothing extra shall be payable on this
account.
1.11.5 The Department shall in no way be responsible for either any delay in getting
electric and/or water and/or telephone connections for carrying out the work or
not getting connections at all. No claim of delay or any other kind, whatsoever,
on this account shall be entertained from the Contractor. Also contingency
arrangement of stand-by water & electrical supply shall be made by the
Contractor commencement and smooth progress of the work so that work does
not suffer on account of power failure or disconnection or not getting connection
at all. No claim of any kind whatsoever shall be entertained on this account from
the Contractor. Nothing extra shall be payable on this account.
1.12 Architectural and structural Drawings:
1.12.1 Although concept architectural drawings are either uploaded in the web along
with NIT for reference to the bidder or made available in the office of the
Executive Engineer, CPWD, Tirupati, the main working & detailed architectural
drawings will be issued by the department in phased manner as per the
approved programme of contractor/progress of work and structural drawings
shall be submitted well in advance by the agency and get it approved well in
advance by the competent authority as per details given in Schedule ‘F’. It is
the duty of the contractor to intimate requirements of drawings reasonably
well in advance and no hindrance shall be allowed on this account.
1.12.2 The work shall be carried out in accordance with the Architectural drawings and
Structural drawings. Before the commencement of any item of work, the
contractor shall correlate all the relevant architectural and structural drawings
issued for the work, nomenclature of items, specifications etc. and satisfy
himself that the information available therefrom is complete and unambiguous.
The figures & the written dimensions of the drawing shall supersede the
measurement by scale. The discrepancy, if any, shall be brought to the notice of
the Engineer-in-Charge for immediate decision before execution of the work.
The contractor alone shall be responsible for any loss or damage occurring by
the commencement of work on the basis of any erroneous and/ or incomplete
information and no claim, whatsoever shall be entertained on this account. The
delay caused on account of non-timely action by the contractor in resolution of
the differences whatsoever shall not be considered as valid ground for extension
of time unless otherwise accepted by the Engineer-In-Charge.
1.12.3 The information and site data shown in the drawings and mentioned herein and
also elsewhere in the tender documents are being furnished for general
information and guidance only. The department shall not bear responsibility for
lack of such knowledge and also the consequences thereof. The Engineer-in-
charge in no case shall be held responsible for the accuracy thereof or any
interpretation/ or conclusions drawn there from by the contractor.
PART B 69
(vi) Co-ordinate with other Contractors for leaving inserts, making chases,
alignment of services etc. at site.
(vii) Adjust work schedule and site activities in consultation with the Engineer-
in-Charge and other Contractors to suit the overall schedule completion.
(viii) Resolve the disputes with other Contractor amicably and the Engineer-in-
Charge shall not be made intermediary or arbitrator. The department
shall not be responsible for the disputes between the subject work
contractor and associate contractor / other agencies working at site. No
claim shall be allowed by the department.
1.15 Procurement of materials:
1.15.1 All material shall only be brought at site as per program finalized with the
Engineer-in-Charge. Any pre-delivery of the material not required for
immediate consumption shall not be accepted and thus not paid for.
1.15.2 The contractor shall procure the required materials in advance so that there is
sufficient time for testing of the materials and approval of the same before use in
the work.
1.16 Protection of Existing Services & buildings and Materials:
1.16.1 Existing drains, pipes, cables, over-head wires, sewer lines, water lines and
similar services encountered in the course of the execution of work shall be
protected against the damage by the contractor at his own expense. The
contractor shall not store materials or otherwise occupy any part of the site in a
manner likely to hinder the operation of such services. In case temporary
supporting of such services is required to facilitate the work, the same shall be
done by the contractor at no extra cost.
1.16.2 In case the existing services are to be shifted permanently, then before
dismantling the existing services, alternate/diversion of service lines has to be
laid by the contractor so that there is no interruption in use of existing services.
The contractor has to plan the alternate suitable route for diversion/shifting of
service lines and get the same approved from the Engineer-in-Charge before
starting shifting of services. Nothing extra shall be paid except the payment of
dismantling and laying of new service lines as per conditions of contract.
1.16.3 All fossils, coins, articles of value of antiquity, structures and other remains or
things of geological or archaeological interest discovered on project location
during excavation/construction shall be the property of the Government, and
shall be dealt with as per provisions of the relevant legislation. The contractor
will take reasonable precaution to prevent his workmen or any other persons
from removing and damaging any such article or thing. He will, immediately
upon discovery thereof and before removal acquaint the Engineer-in-charge of
such discovery and carry out the official instructions of Engineer-in-charge for
dealing with the same, till then all work shall be carried out in a way so as not to
disturb/ damage such article or thing.
1.16.4 The contractor shall be responsible for the watch and ward / guard of the
buildings, safety of all fittings and fixtures including sanitary and water supply
fittings and fixtures provided by him against pilferage and breakage during the
PART B 71
period of installations and thereafter till the building is physically handed over
to the client department. No extra payment shall be made on this account.
1.16.5 The contractor shall be fully responsible for the safe custody of materials
brought by him/ issued to him even though the materials may be under double
lock key system.
1.17 Rates and other conditions for payment:
The rates quoted by the Contractor are deemed to be inclusive of the following-
1.17.1 Site clearance, setting out work, profile, establishment of reference bench
mark(s), taking spot levels, construction of all safety and protection devices,
barriers, barricading, signage, labour safety, welfare & training measures,
preparatory works, working during monsoon, working at all depths, height,
lead, lift and location etc. until / unless specified otherwise, implementation of
green building norms to achieve desired GRIHA ( 3 star) Rating etc. and any
other incidental works required to complete this work. Nothing extra shall be
payable on this account. Payment for centering & shuttering, however, if
required to be done for floor heights greater than 3.50m shall be admissible at
rates arrived in accordance with clause 12 of the agreement if not already
specified.
1.17.2 For works below ground level the contractor shall keep that area free from
water. If dewatering or bailing out of water is required the contractor shall do it
and nothing extra shall be paid except otherwise provided in the items of
schedule of quantities.
1.17.3 Any legal or financial implications resulting out of disposal of earth shall be sole
responsibility of the contractor. Nothing extra over the schedule shall be paid on
this account.
1.17.4 All labour, material, tools and plants and other inputs involved in the execution
of the item.
1.17.5 Providing sunk flooring in bath-rooms, kitchen, etc.
1.17.6 Performance test of the entire installation(s) before the work is finally accepted.
1.17.7 Any cement slurry added over base surface (or) for continuation of concreting
for better bond is deemed to have been built in the items.
1.17.8 The rates quoted by the tenderer, shall be inclusive of all taxes including GST
and levies applicable in respect of this contract shall be payable by the contractor
and Government will not entertain any claim whatsoever in respect of the same.
1.17.9 For completing the work in time, the Contractor might be required to work in
two or more shifts (including night shifts). No claim whatsoever shall be
entertained on this account, not with-standing the fact that the Contractor may
have to pay extra amounts for any reason, to the labourers and other staff
engaged directly or indirectly on the work according to the provisions of the
labour and other statutory bodies regulations and the agreement entered upon
by the Contractor with them.
1.17.10 The Contractor shall keep himself fully informed of all acts and laws of the
Central & State Governments, all orders, decrees of statutory bodies, tribunals
PART B 72
having any jurisdiction or authority, which in any manner may affect those
engaged or employed and anything related to carrying out the work. All the
rules & regulations and bye-laws laid down by Collector / MC etc. and any
other statutory bodies shall be adhered to, by the contractor, during the
execution of work. The Contractor shall also adhere to all traffic restrictions
notified by the local authorities. It is clarified that the extra sewerage charges
(one time charges for commencement of work) required to be paid to the
Municipal Corporation / other statutory bodies shall be paid by the department
and need not be considered by the contractor. The water charges (for municipal
water connection as well as tanker water) shall be borne by the contractor. Also,
if the contractor obtains water connection for the drinking purposes from the
municipal authorities or any other statutory body, the consequent sewerage
charges shall be borne by the contractor. All statutory taxes, levies, charges
(including GST, water and sewerage charges, charges for temporary service
connections and / or any other charges) payable to such authorities for carrying
out the work, shall be borne by the Contractor. The Contractor shall arrange to
give all notices as required by any statutory / regulatory authority and obtain
all requisite licenses wherever required and shall pay to such authority all the
fees that are required to be paid for the execution of work. He shall protect and
indemnify the Department and its officials & employees against any claim and
/or liability arising out of violations of any such laws, ordinances, orders,
decrees, by himself or by his employees or his authorized representatives.
Nothing extra shall be payable on these accounts. The fee payable to statutory
authorities for obtaining the various permanent service connections and
Occupancy Certificate for the building shall be borne by the Department.
1.17.11 Royalty at the prevalent rates including contribution towards Mineral
Exploration Research and Innovation Trust (MERIT) @ 2% on Seigniorage fee
and District Mineral Foundation (DMF) @ 30% of Royalty / Seigniorage fee shall
have to be paid by the contractor (Rates of Seigniorage fee enclosed in the
document is for guidance only and no claims shall be entertained on account of
this) on all the boulders, stone aggregate, brick aggregate, shingle, coarse or fine
sand, earth, gravel, bajri etc. collected by him for the execution of the work,
directly to the Revenue Authority or authorized agent of the State Government
concerned or Central Government.
Royalty at the prevalent rates including contribution towards Mineral
Exploration Research and Innovation Trust (MERIT) @ 2% on Seigniorage fee
and District Mineral Foundation (DMF) @ 30% of royalty / Seigniorage fee shall
be paid by the contractor or the RMC supplier as per the terms of supply
between them, on all materials such as stone aggregate, coarse or fine sand etc.
collected by him for the execution of the work, directly to the revenue authority
of the State Government concerned. Further, contractor needs to submit proof of
submission of full royalty to the State Government or local authority. Nothing
extra shall be payable on this account.
However, if the contractor fails to submit the proof of payment of royalty /
seigniorage fee and other contributions to MERIT & DMF as stated above, the
same will be recovered from the bills payable without any further notice.
1.17.12 All ancillary and incidental facilities required for execution of work like labour
camp, stores, fabrication yard, offices for Contractor, watch and ward,
temporary ramp required to be made for working at the basement level,
PART B 73
temporary structure for plants and machineries, water storage tanks, installation
and consumption charges of temporary electricity, telephone, water etc.
required for execution of the work, liaison and pursuing for obtaining various
No Objection Certificates, completion certificates from local bodies etc.,
protection works, barricading, testing facilities / laboratory at site of work,
facilities for all field tests and for taking samples etc. during execution or any
other activity which is necessary (for execution of work and as directed by
Engineer-in-Charge), shall be deemed to be included in rates quoted by the
Contractor, for various items in the schedule of quantities. Nothing extra shall
be payable on these accounts. Before start of the work, the Contractor shall
submit to the Engineer-in-Charge, a site / construction yard layout, specifying
areas for construction, site office, positioning of machinery, material yard,
cement and other storage, steel fabrication yard, site laboratory, water tank, etc.
1.17.13 The Contractor shall assume all liability, financial or otherwise in connection
with this contract and shall protect and indemnify the Department from any and
all damages and claims that may arise on any account. The Contractor shall
indemnify the Department against all claims in respect of patent rights,
royalties, design, trademarks of name or other protected rights, damages to
adjacent buildings, roads or members of public, in course of execution of work
or any other reasons whatsoever, and shall himself defend all actions arising
from such claims and shall indemnify the Department in all respect from such
actions, costs and expenses. Nothing extra shall be payable on this account.
1.17.14 The Contractor shall make all necessary arrangements for protecting from rain
or likewise extreme weather conditions, the work already executed and for
carrying out the further work, during monsoon including providing and fixing
temporary shelters, protections etc. Nothing extra shall be payable on this
account. Also, no claims for hindrance shall be entertained on this account.
1.17.15In case of flooding of site on account of rain or any other cause and any
consequent damage, whatsoever, no claim financially or otherwise shall be
entertained not withstanding any other provisions elsewhere in the contract
agreement. Also, the Contractor shall make good, at his own cost, the damages
caused, if any. Further, no claims for hindrance shall be entertained on this
account.
1.17.16No payment shall be made for any damage caused by fire, rain, snowfall, flood
or any other natural calamity, whatsoever during the execution of the work. The
contractor shall be fully responsible for any damage to the govt. property and
the work for which payment has been advanced to him under the contract and
he shall make good the same at his risk and cost. The contractor shall be fully
responsible for safety and security of his material, T&P/Machinery brought to
the site by him. The contractor shall maintain all the work in good condition at
his own cost till the completion of the entire work.
1.17.17In case the same item appears more than once in the schedule of work under the
same sub head or among the different sub heads of works, the lowest rate
quoted for that item shall be taken for other items also and tender will be
evaluated accordingly.
1.17.18 The ESI and EPF contribution on the part of employer in respect of this contract
shall be paid by the contractor. These contributions on the part of employer paid
PART B 74
3.2 The Contractor shall display all permissions, licenses, registration certificates,
bar charts, other statements etc. under various labour laws and other regulations
applicable to the works, at his site office.
3.3 No site is available for labour huts. The contractor shall have to have his own
arrangements for hiring land for setting up labour huts. The contractor will be
provided space for watchman huts, site office etc. to a very limited extent inside
the campus but the space requirement and location, as assessed by Engineer-in-
Charge shall be final and binding.
3.4 If as per the rules of the local authority, the huts for labour are not to be erected
at the site of work by the contractors, the contractors are required to provide
such accommodation as is acceptable to local bodies and nothing extra shall be
paid on this account.
3.5 Contractor has to follow the security requirement of the campus and obtain
necessary entry passes for the labour and vehicles and follow security checks at
entry / exit gates, restriction on movement of vehicle, restricted timings of
working etc. The Department however shall assist the contractor in obtaining
such passes for movement of vehicles and labour. No claim whatsoever shall be
entertained on account of delay in entry of vehicles and labour including
restrictions in working hours, if there is any.
3.6 The contractor shall employ only Indian Nationals after verifying their
antecedents and loyalty. The contractor shall, on demand submit list of his
agents, employees and work people concerned & shall satisfy as to the bonafides
of such people.
3.7 The contractor & his work people shall observe all relevant rules regarding
security promulgated in which work is to be carried out by the Controlling
Administrative Authority of the campus/area (hereinafter referred to as
“Administrator”).
3.8 The contractor, his representative, workman shall be allowed to enter through
specified gates & timing as laid down by the controlling authority. They shall be
issued an identity card or an individual pass in accordance with the standing
rules & regulations & they should possess the same while working. The
contractor shall be responsible for the conduct & actions of his workmen,
agents/ representatives.
3.9 Normally contractor shall be allowed to carry out work between 7 AM to 6 PM.
However, he may also be allowed to carry out the work beyond 6 PM &upto 7
AM, if the site conditions / circumstances so demand with prior written
permission from the “Administrator”. However, if the work is carried out in
more than one shift or at night, no claim on this account shall be entertained.
3.10 Normally contractor’s material / vehicles etc. shall be allowed to move in / go-
out between 7 AM to 7 PM only & no movement of material / vehicles out of the
site of work shall be allowed during night hours unless specific permission is
obtained from the “Administrator”.
3.11 In case if a separate entry has been allowed, the contractor has to make all
arrangement for making a separate entry gate and barricading of the working
PART B 77
area to segregate/separate the same from other areas. All these have to be done
by the contractor at his own cost including safeguarding any untoward incident
in the restricted area due to separate entry gate and barricading arranged by the
contractor. No extra amount on this account shall be payable by the
department.
3.12 In the event of any restrictions being imposed by the Security agency, CPWD,
Traffic or any other authority having jurisdiction in the area on the working or
movement of labour /material, the contractor shall strictly follow such
restrictions and nothing extra shall be payable to the contractor on such
accounts. The loss of time on these accounts, if any, shall have to be made up
by augmenting additional resources whatever required. Nothing extra shall be
payable on this account.
4.0 OFFICE INFRASTRUCTURE:
4.1 The Contractor shall construct / provide one site office at his own cost on the
construction site consisting of One (1) room including one (1) attached toilet
with total built up area not less than 30 Sqm for CPWD staff. The location and
plan shall be got approved from Engineer-in-Charge. Specification for the site
office shall be portable type and or any other specification as per approval of
Engineer-in-charge.
4.2. The required nos. of light points (including plug points) with fittings, ceiling
fan/ exhaust fans, Furniture etc., shall have to be provided as per requirement
of Engineer in charge during the period of construction. Maintenance of the site
office will be responsibility of the contractor
4.3 For Quality Control Measures, Preparation of Bills and Monitoring the Quality,
the contractor shall provide one Computer having Intel core i7 processor, MS-
Windows-11, A-4 LaserJet Printers, Scanners, UPS etc. with data entry operator
in the site office of Engineer-in-Charge.
4.4 The contractor shall make arrangement for Helmets and leather shoes (meant of
construction work at sites) for all field staff of the department during the entire
period of construction for safety reasons. One helmet and two pairs of shoes per
staff member (maximum twelve members) of the departments per year shall be
arranged by the contractor.
5.0 DOCUMENTATION
The Contractor shall render all help and assistance in documenting the total
sequences of this project by way of photography, slides, audio / video recording
& other records etc. Nothing extra shall be payable to Contractor on this
account. However, cost of photographs, slides, audio / video graph etc. shall be
borne by the Department. The original films shall be the property of the
Department. No copy shall be prepared without the prior approval of the
Engineer- in – Charge.
6.0 PROGRESS CHART: -
6.1 The contractor shall submit a Time and Progress Chart for each mile stone. The
Engineer-in-charge may within 10 days thereafter, if required modify, and
communicate the program approved to the contractor failing which the
PART B 78
completion. The agency may deploy adequate equipment, machinery and labour
as required for the completion of the entire work within the stipulated period
specified. Also, ancillary facilities shall be provided commensurate with
requirement to complete the entire work within the stipulated period. Nothing
extra shall be payable on this account. Adequate number/sets of equipment in
working condition, along with adequate stand-by arrangements, shall be
deployed during entire construction period. It shall be ensured by the
Contractor that all the equipment, Tools & Plants, machineries etc. provided by
him are maintained in proper working conditions at all times during the
progress of the work and till the completion of the work. Further, all the
constructional tools, plants, equipment and machineries provided by the
Contractor, on site of work or his work shop for this work, shall be exclusively
intended for use in the construction of this work and they shall not be shifted /
removed from site without the permission of the Engineer-in-Charge.
7.6 All material shall only be brought at site as per program finalized with the
Engineer-in-Charge. Any pre-delivery of the material not required for
immediate consumption shall not be accepted and thus not paid for.
8.0 PROJECT REVIEW MEETINGS:
The contractor, immediately on award of work shall submit details of his key
personnel to be engaged for the work at site. In addition, he shall furnish the
Engineer-in-charge detailed organization involved with the work.
The contractor shall present the programme and status at various review
meetings as required.
Monthly Review Meetings: Shall be attended by Project - in - charge and the
Management Representative who can take independent decisions along with
CPWD, client’s representatives.
Agenda
a)Progress Status/Statistics.
b)Completion Outlook.
c)Major holdups/slippages.
d)Assistance required.
e)Critical issues.
f) Any decision on queries raised either by Contractor/PMC.
g) Anticipated cash flow requirement for next two months.
9.0 ENGAGING SPECIALISED AGENCIES FOR WORKS: -
9.1 The Contractor shall engage specialized agencies having adequate technical
capability and experience of having executed at least one work of similar items
for executing the following items of the work and/or any other items of work
where specialized firm is required to be engaged as per contract conditions.
As mentioned in Para 1.2 of CPWD-6 for e-Tendering in PART – A of this NIT
for Specialized works.
PART B 81
9.2 The Specialized agency for the work shall be got approved from the Engineer-
in-Charge well before actual commencement of the item of work. The
contractor shall submit the list of specialized agencies proposed to be engaged
by him along with their technical capability and necessary performance
certificates, within 30 days of the stipulated date of start to substantiate
technical capability and experience of the agency for prior approval of the
Engineer-in-Charge.
9.3 It shall be the responsibility of main contractor to sort out any dispute /
litigation with the Specialized Agencies without any time & cost overrun to the
Department. The main contractor shall be solely responsible for settling any
dispute / litigation arising out of his agreement with the Specialized Agencies.
The contractor shall ensure that the work shall not suffer on account of
litigation/ dispute between him and the specialized agencies / sub-
contractor(s). No claim of hindrance in the work shall be entertained from the
Contractor on this account. No extension of time shall be granted and no claim
what so ever, of any kind, shall be entertained from the Contractor on account of
delay attributable to the selection/rejection of the Specialized Agencies.
10.0 DEFECT LIABILITY PERIOD (REFUND OF SECURITY DEPOSIT):
10.1 The defect liability / maintenance period shall be 12 months after the date of
completion of work for this contract agreement. The Security Deposit shall be
released after the defect liability period of 12 months after completion of work
and for this, the contractor shall have to produce a certificate stating that no
defects are pending for rectification from the Engineer-in-charge, but subject to
other provisions specified elsewhere in the contract agreement.
11.0 SAFETY MEASURES
11.1 The issue of construction safety & standards has gained utmost importance in
recent times. This subject is to be dealt with in an integrated manner with an
approach to developing and establishing a safety culture at work sites. Broadly,
its components are:
(i) Creating awareness.
(ii) Education.
(iii) Training.
(iv) Implementation.
(v) Enforcement measures.
All workers of contractor and associate agencies, invariably and at all the times, must
follow all safety norms, adopt safe construction practices and use all required safety
gadgets in their working throughout the project duration.
11.2 The contractor shall issue Photo Identity Cards with unique numbers
containing salient information of workers for the labour& his staff.
11.3 The Contractor shall monitor and achieve the objectives of construction safety
continuously, progressively and through affirmative action, and shall oversee
implementation of safety program over the entire construction period.
PART B 82
16.1 The building work shall be carried out in the manner complying in all respects
with the requirements of relevant bye-laws of the local body under the
jurisdiction of which the work is to be executed or as directed by the Engineer-
in-Charge and nothing extra shall be paid on this account.
16.2 Some restrictions may be imposed by the local police etc. on the working time
and for movement of labour, materials etc. the contractor shall be bound to
follow all such restrictions/instructions and nothing extra shall be payable on
this account.
16.3 The contractor shall not stack building material/ malba on the road or on the
land owned by any other authority, as the case may be. In case, the Contractor
is found stacking the building material/ malba as stated above, he shall be liable
to pay the stacking charges as may be levied by local body or authority and also
to face penal action as per the rules, regulations and bye-laws of the said body or
authority. The Engineer-in-Charge shall be at liberty to recover the sums due but
not paid to the concerned authorities on the above counts from any sums due to
the contractor including amount of the Security Deposit or Retention Money in
respect of this contract or any other contract.
The Contractor shall demonstrate trouble free functioning of all the Civil and E
& M installations and services. The Engineer-in-Charge or his authorized
representatives shall carry out final inspection of the various Civil and E & M
services and installations. Any defect(s) noticed during demonstration shall be
rectified by the Contractor at his own cost to the entire satisfaction of the
Engineer-in-Charge. Nothing extra shall be payable on this account.
19.0 De-watering
(i) De-watering required, if any, shall be done conforming to BIS Code IS:
9759 (guide lines for de-watering during construction) and / or as per the
specifications approved by the Engineer-in-Charge. Design of an
appropriate and suitable dewatering system shall be the Contractor’s
responsibility. Such scheme shall be modified / augmented as the work
proceeds based on fresh information discovered during the progress of
work, at no extra cost. At all times during the construction work, efficient
drainage of the site shall be carried out by the Contractor and especially
during the laying of plain cement concrete, taking levels etc. The
Contractor shall also ensure that there is no danger to the nearby
properties and installations on account of such lowering of water table. If
needed, suitable precautionary measures shall be taken by the Contractor.
Also the scheme of dewatering adopted shall have adequate built in
arrangement to serve as stand-bye to attend to repair of pumps etc. and
disruption of power / fuel supply. Nothing extra shall be payable for all
the operations described in this para.
(ii) In trenches where surface water is likely to get into cut / trench during
monsoons, a ring bund of puddle clay or by any other means shall be
formed outside, to the required height, and maintained by the Contractor.
Also, suitable steps shall be taken by the Contractor to prevent back flow
of pumped water into the trench. Nothing extra shall be payable on this
account.
a. For works below ground level the contractor shall keep that area free
from water. If dewatering or bailing out of water is required the
contractor shall do the same at his own cost and nothing extra shall
be paid except otherwise provided in the items of Schedule of
Quantities.
b. The Contractor shall make all necessary arrangements for protecting
from rains, fog or likewise extreme weather conditions, the work
already executed and for carrying out further work, during monsoon
PART B 87
a. The contractor shall at his own expense and risk arrange land for
accommodation of labour, setting up of office, the storage of materials,
erection of temporary workshops, construction of approach roads to the
site of the work including land required for carrying out of all jobs
connected with the execution &completion of the work. However, the
departmental land, to the extent available may be allowed to be used for
the purpose free of rent without accepting any responsibility for the delay,
if any, on this account. The contractor shall have to abide by the
regulations of the authorities concerned and the directions of the Officer -
in-charge for the use of the land available at the site of work. If during
construction, it becomes necessary to remove or shift the stored materials
shed, workshop, access roads, etc., to facilitate execution of any other work
by any other agency, the contractor shall carry out the removal of shifting
as directed by the Officer – in – charge and no claim whatsoever, shall be
entertained on this account.
b. It shall be deemed that the contractor has satisfied himself as to the nature
and location of the work, transport facilities, availability of land for setting
up of camp, etc. the department will bear no responsibility for lack of such
knowledge & the consequences thereof.
21.0 No surplus land is available with the department for allotting to Contractor to
set up Labour Campus. The Contractor should make his own arrangement for
hiring suitable piece of land for making Labour Campus as per CPWD Model
Rules for protection of health and sanitary arrangements which is forming
part of GCC-2023, CPWD Specifications and Special Conditions of NIT.
The Contractor is required to complete one sample room and one sample toilet
with all finishes and services for the approval of Engineer-in-charge within 7
months from the date of start of work failing which a penalty of Rs. 5,000/- per
day will be levied on the contractor which is non-refundable.
23.0 The contractor shall prepare Architectural and 3D image of the building blocks
as per the 2D Elevation Drawing attached with tender documents. The
Consultant of the Contractor shall coordinate with Architect of CPWD,
Vijayawada for evaluating the 3D views and final 3D images shall be submitted
to Engineer-in-Charge within a period of 8 weeks from the date of award of
work for obtaining the approval of the Architect. The quoted rates of the
contractor are inclusive of the preparation of 3D images and nothing extra shall
be paid.
24.0 No land is available with the Department for setting up of Batch Mix Plant. The
work should be executed with Ready Mix Concrete (RMC). All columns shall
also be executed with RMC using Boomer Pump or crane supported bucket with
lever operated door for pouring concrete. Double handling of RMC, i.e. pouring
on a platform and lifting again with baskets to place in column boxes, is not
permissible.
PART B 89
(iii) All the test in field lab setup at Construction Site shall be carried out by the
Engineering Staff deployed by the contractor which shall be 100% witnessed by
representative of the Engineer in Charge.
(iv) All the entries in the registers will be made by the designated Engineering Staff
of the contractor and same should be regularly reviewed by Engineer in Charge
or his representative.
(v) Contractor shall be responsible for safe custody of all the test registers.
1.1.7 Extensive testing of the materials used for construction is a pre-requisite for
attaining high quality of the work. This shall also require specialized tests,
physical, chemical, ultrasonic, x-ray and various other types of tests which
cannot possibly be carried out in a site laboratory. These tests also require
specialized personnel who regularly deal in such testing. Therefore the need
arises for carrying out the tests in outside laboratories. These laboratories may
be in the Govt. sector, Semi Govt. or Private sector. All Govt. Institutes, Indian
Institute of Technology, National Institute of Technology, Central and State
funded laboratories stands approved. No approval is required for testing in
these laboratories/institutes. However, the outside private laboratories shall be
approved in the following manner: -
1. The SDGs/ADGs will approve the private lab irrespective of distance for tests
accredited by NABL or any other similarly placed accrediting government body
which operates in accordance with ISO/IEC 17011 and acridities labs as per
ISO/IEC 17025.
2. A lab will have to submit details of space available, equipment, staff (Technical
and Non-Technical), accreditation and approval from various
department/institutes. Lab must be NABL approved.
3. Initial approval of lab should for one year and can be revalidated for further one
year and so on.
4. Every lab will be audited for maintenance and calibration of equipment and
employment of staff prior to approval/revalidation.
However, testing of material in any Govt., Lab / Public Undertaking Lab / IIT
or NIT Lab / Govt. Engineering College may be allowed by Executive Engineer
without prior approval of Chief Engineer, Vijayawada or higher officers
provided these labs have all necessary facility to carry out the required tests.
1.1.8 Ultrasonic pulse velocity test shall be conducted on at least 5% of the total
number of RCC members in each category i.e., beam, column, slab and footing
for ensuring quality of concrete as per directions of Engineer- in charge. The
cost of the same shall be borne by the contractor.
1.1.9 In case there is any discrepancy in frequency of testing as given in list of
mandatory tests and that in individual sub-heads of work as per CPWD
Specifications higher of the two frequencies of testing shall be followed and
nothing extra shall be payable on this account.
PART B 91
1.1.10. The contractor shall ensure quality construction in a planned and time bound
manner. Any sub-standard material / work beyond set out tolerance limit shall
be summarily rejected by the Engineer-in-charge & contractor shall be bound to
replace / remove such sub-standard / defective work immediately. If any
material, even though approved by Engineer-In-Charge is found defective or
not conforming to specifications shall be replaced / removed by the contractor
at his own risk & cost.
1.1.11 In addition to the supervision of work by CPWD engineers, the Architects
deployed by the Client/CPWD, CPWD Quality Control/ Assurance Team and
Third party Quality Control/ Assurance Team shall also be carrying out regular
and periodic inspection of the ongoing activities in the work and deficiencies,
shortcomings, inferior workmanship pointed out by them shall be
communicated by CPWD engineers to the contractor. Upon receipt of
instructions from Engineer in Charge these are also to be made good by
necessary improvement, rectification, replacement upto his complete
satisfaction. Special attention shall be paid towards line and level of internal and
external plastering, exposed smooth surface of RCC members by providing
fresh shuttering plates, rubberized linings to all the shuttering joints, accurate
joinery work in wooden doors and windows, thinnest joints in stone/ tiling /
cladding work, non-hollowness in floor and dado tiles work, protection of
scratches over flooring by impounding layer of plaster of Paris, water tight pipe
linings, absence of hollow vertical joints in brick masonry, proper compaction of
filled up earth etc. to achieve an Institution of International standards and up
keeping of quality assurance shall be of paramount importance, as such.
1.1.12 The Contractor shall submit, within 15 days after the date of award of work, a
detailed and complete method statement for the execution, testing and Quality
Assurance, of such items of works, as directed by the Engineer-in-Charge. All
the materials to be used in the work, to give the finished work complete in all
respects, shall comply with the requirements of the specifications and shall pass
all the tests required as per specifications as applicable or such specifications /
standards as directed by the Engineer-in-Charge. However, keeping the Quality
Assurance in mind, the Contractor shall submit, on request from the Engineer-
in-Charge, his own Quality Assurance procedures for basic materials and such
items, to be followed during the execution of the work, for approval of the
Engineer-in-Charge.
1.2 FIELD LABORATORY
The contractor has to establish within 21 days from the award of work a field
laboratory at site including all necessary equipments and skilled manpower for
the Field Tests as indicated in the tender document at his own cost to have
proper quality control.Rs.5,000/-per day shall be recovered from the contractor
for any delay beyond the specified period. If contractor fails to establish lab
within additional period of 15 days, the Engineer in charge shall initiate action
as deemed fit under relevant clauses of the agreement.
For performing the above tests, the Field Testing Equipments and Instruments
as indicated in the tender document are to be arranged and maintained by the
contractor at his own cost.
PART B 92
1.2.1 The contractor shall ensure quality construction in a planned and time bound
manner. Any sub-standard material / work beyond set-out tolerance limit shall
be summarily rejected by the Engineer-in-Charge & contractor shall be bound to
replace / remove such sub-standard / defective work immediately.
1.2.2 The list of Laboratory/ Field equipment referred above is to be arranged and
maintained by the contractor at the site of work. In case the equipment required
for any test is not available at site, the department shall get the test conducted
from the third party. However, in that event, besides providing free materials of
sample, the cost of taking of sample, packing, transportation, testing charges etc.
shall be borne by the contractor irrespective of the results.
1.3 SAMPLE OF MATERIALS: -
1.3.1 All materials and fittings brought by the contractor to the site for use shall
conform to the samples approved by the Engineer-in-Charge which shall be
preserved till the completion of the work. If a particular brand of material is
specified in the item of work in Schedule of Quantity, the same shall be used
after getting the same approved from Engineer-in-Charge. Wherever brand /
quality of material is not specified in the item of work, the contractor shall
submit the samples as per List of Approved Makes given in the tender
document for approval of Engineer-in-Charge. For all other items, ISI Marked
materials and fittings shall be used with the approval of Engineer-in-Charge.
Wherever ISI Marked material / fittings are not available, the contractor shall
submit samples of materials / fittings manufactured by firms of repute
conforming to relevant Specifications or IS codes for the approval of Engineer-
in-Charge.
1.3.2 The Contractor shall procure and provide all the materials from the
manufacturers / suppliers as per the list attached with the tender documents, as
per the item description and particular specifications for the work. The
equivalent brand for any item shall be permitted to be used in the work, only
when the specified make is not available. This is, however, subject to
documentary evidence produced by the contactor for non-availability of the
brand specified and also subject to independent verification by the Engineer-in-
Charge. In exceptional cases, where such approval is required, the decision of
Engineer-in-Charge as regards equivalent make of the material shall be final and
binding on the Contractor. No claim, whatsoever, of any kind shall be
entertained from the Contractor on this account. Nothing extra shall be payable
on this account. Also, the material shall be procured only after written approval
of the Engineer-in-Charge.
1.3.3 To avoid delay, contractor should submit samples / as stated above well in
advance so as to give timely orders for procurement. If any material, even
though approved by Engineer-in-Charge is found defective or not conforming to
specifications shall be replaced / removed by the contractor at his own risk
&cost. Samples including brand / quality of materials and fittings to be used in
the work shall be got approved from the Engineer-in-Charge, well in advance of
actual execution and shall be preserved till the completion of the work.
PART B 93
1.3.4 BIS marked materials except otherwise specified shall also be subjected to
quality test besides testing of other materials as per the specifications described
for the item/material. Wherever BIS marked materials are brought to the site of
work, the contractor shall, furnish manufacturer’s test certificate or test
certificate from approved testing laboratory to establish that the material
procured by the contractor for incorporation in the work satisfies the provisions
of specifications relevant to the material and / or the work done.
BIS marked items (except cement & steel for which separate provisions have
been made) required on the work shall be got tested, for only important tests,
which govern the quality of the product, as decided by the Engineer-in-Charge.
The frequency of such tests (except the mandatory test) shall be 5% of the
frequency as specified in BIS. For mandatory test, frequency shall be as
specified in the CPWD Specifications.
1.3.5 For certain items, if frequency of tests is neither mentioned in the CPWD
Specifications nor BIS, then tests shall be carried out as per directions of
Engineer-in-Charge.
2.0 CEMENT & STEEL REINFORCEMENT
2.1 Contractor has to procure Cement and Steel and has to produce manufacturers
test certificate and challan for each lot of Cement & Steel Reinforcement
procured at site.
2.2 CEMENT: -
2.2.1 The contractor shall procure 43 grade ordinary Portland Cement (OPC)
conforming to IS: 269 / Portland Pozzolana Cement (PPC) conforming to IS:
1489 (Part-1) as required in the work as per specifications/particular
specifications of buildings from reputed manufacturers of cement as mentioned
in “List showing preferred brands / Manufacturers / Makes” or from any other
reputed cement manufacture having a production capacity not less than 1
million Ton per annum as approved by Chief Engineer, CPWD, Vijayawada.
The cement of approved make as aforesaid in 50 kg bags bearing manufacturer’s
name and ISI marking, along with manufacturers test certificate for each lot
shall be procured by the contractor. Portland Pozzolana Cement is to be used
for RCC works only subject to fulfillment of conditions of circular No. CDO/SE
(RR)/Fly ash (MAN) 02 dated 09.04.09. However, if the contractor uses higher
grade of cement or uses OPC only nothing extra shall be paid. The use of PPC
shall be regulated as per the following conditions stipulated in the circular dated
09.04.2009: -
Note: For STP Works, Sulphate-Resistant Cement shall be used and for the
remaining works, OPC/PPC can be used. (The agency must quote the rates
accordingly; no additional claims shall be admissible in this regard).
2.2.2 Samples of cement arranged by the contractor shall be taken by the Engineer-in-
Charge and got tested in accordance with provisions of relevant BIS Codes. The
cement for such testing purpose shall be supplied by the contractor free of
charge. In case test results indicate that the cement arranged by the contractor
does not conform to the relevant BIS Codes, the same shall stand rejected and
shall be removed from the site by the contractor at his own cost within a week’s
time of written order from the Engineer-in-Charge or his authorized
representative to do so. The cost of tests shall be borne by the contractor.
2.2.3 Cement shall be brought at site in bulk supply of approximately 200 tones or as
decided by the Engineer-in-Charge.
2.2.4 OPC & PPC bags shall be stored in separate godowns. Separate godowns for
tested cement and fresh cement (under testing) to be constructed by the
contractor at his own cost as per sketches given in C.P.W.D Specifications
having weather-proof roofs and walls. The size of the cement godown is
indicated in the sketches for guidance. The actual size of godown shall be as per
site requirements and nothing extra shall be paid for the same. Each godown
shall be provided with a single door with two locks. The keys of one lock shall
remain with Engineer-in-Charge or his authorized representative of the work
and that of other lock with the authorized agent of the contractor at the site of
work so that the cement is issued from godown according to the daily
requirement with the knowledge of both parties. The account of daily receipt
and issue of cement shall be maintained in a register in the prescribed proforma
and signed daily by the contractor or his authorized agent and Engineer-in-
Charge or his authorized representative in token of its correctness. The day to
day receipt and issue accounts of different grade/brand of cement shall be
maintained separately in the standard proforma by the contractor or his
authorized representative which shall be duly signed by the authorized
representative of the Engineer-in-Charge before issue to the work on day to day
basis.
Required number of cement godowns each having capacity as decided by the
Engineer-in-Charge shall be constructed by the contractor at site of work for
which no extra payment shall be made. The contractor shall be responsible for
the watch and ward and safety of the cement go-downs. The contractor shall
facilitate the inspection of the cement go-downs by the Engineer-in-Charge at
any time.
The pages of the register should be machine numbered and each page initialed
by the EE. The cement godown and the register are required to be checked by
the AE/EE in-charge of the work as mentioned below: -
a. At least weekly or fortnightly, respectively in case of works located at the
headquarters of AE/EE and.
b. Whenever they visit the site of work in case of works located outside the
Sub- Divisional/Divisional Head Quarters.
PART B 96
c. In the case of large concentrated projects like major bridges etc., the EE
should check the cement register at least fortnightly.
2.2.5 The actual issue and consumption of cement on work shall be regulated and
proper accounts maintained as provided in the contract. The theoretical
consumption of cement shall be worked out as per the procedure prescribed in
Clause-38 of the contract and shall be governed by the conditions laid therein.
2.2.6 If the quantity of cement actually used in the work is found to be more than the
theoretical quantity of cement including authorized variation, nothing extra
shall be payable to the contractor on this account. In the event of it being
discovered that after the completion of the work, the quantity of cement used is
less than the quantity ascertained as herein before provided (allowing variation
on the minus side as stipulated in Clause - 38), the cost of quantity of cement not
so used shall be recovered from the contractor as specified in schedule. Decision
of the Engineer-in-Charge in regard to theoretical quantity of cement which
should have been actually used as per the schedule and recovered at the rate
specified, shall be final and binding on the contractor.
For non-scheduled items, the decision of the Chief Engineer regarding
theoretical quantity of the cement, which should have been actually used, shall
be final and binding on the contractor.
2.2.7 Cement brought to site and cement remaining unused after completion of work
shall not be removed from site without written permission of the Engineer-in-
Charge.
2.2.8 Damaged cement shall be removed from site immediately by the contractor on
receipt of notice in writing from the Engineer-in-charge. If he does not do so
within three days of receipt of such notice, the Engineer-in-charge shall get it
removed at the cost of the contractor.
2.2.9 In case the contractor brings surplus quantity of cement the same shall be
removed from the site after completion of work by the contractor at his own cost
after approval of the Engineer-in-Charge.
2.2.10 In case cement has been stored for over six (06) months from the date of
manufacture or for any reason the stored cement shown sign of deterioration
and contamination it shall be tested prior to use in the work.
The sample shall be taken within three weeks of the delivery and all the tests
shall be commenced within one week of sampling and not later than 03 months
from the receipt of sample for testing.
After completion of previous test if cement is stored more than 03 months, it
shall be retested before use.
2.2.11 Compressive Strength of Cement
The average compressive strength of at least three mortar cubes (area of face 50
cm2) composed of one part of cement, three parts of standard sand (conforming
to IS 650:1996) by mass and P/4+3.0 percent (of combined mass of cement plus
PART B 97
sand) water, and prepared, stored and tested in the manner described in IS 4031
(Part 6): 1988, shall be as follows:
a) 72±1 hour not less than 23 MPa
b) 168±2 hour not less than 33 MPa
c) 672±4 hour not less than 43 MPa
NOTE: - P is the percentage of water required to produce a paste of standard
consistency (see as below)
Compressive strength of PPC
a) 72±1 hours, not less than 16 MPa
b) 168±2 hours, not less than 22 MPa
c) 672±4 hours, not less than 33 MPa
Consistency of Standard Paste: -
The quantity of water required to produce a paste of standard consistency, to be
used for the determination of the water content mortar for the compressive
strength tests and for the determination of soundness and setting time, shall be
obtained by the method described in IS 4031 (part 4) : 1988.
2.3 STEEL REINFORCEMENT: -
2.3.1 (a) The Contractor shall procure ISI-marked TMT bars of various grades from
the approved steel manufacturers as per the list of approved makes forming
part of this document or their authorized dealers having valid BIS license for IS:
1786-2008 and further confirming to the OM No. CSQ/SE (TAS)/steel/2024/262
(H), dated 14.08.2024.
The Agency has to be procured the Bar Set – I steel bars of having
the following qualities:
PART B 98
PART B 99
PART B 100
PART B 101
PART B 102
PART B 103
2.3.9 The steel brought to site and the steel remaining unused shall not be removed
from site without the written permission of the Engineer-in-charge.
2.3.10 The contractor shall submit original vouchers from the manufacturer for the
total quantity of steel supplied under each consignment to be incorporated in
the work. All consignment received at the work site shall be inspected by the
Site staff along with the relevant documents before acceptance. The contractor
shall obtain Original Vouchers and Test Certificates and furnish the same to the
Engineer-in-Charge in respect of all the lots of steel brought by him from
approved supplier to the site of work. The original vouchers and test certificates
shall be defaced by the Site staff and kept on record in the site office.
2.3.11 Reinforcement including authorized spacer bars and laps shall be measured in
length of different diameters as actually (not more than as specified in the
drawings) used in the work nearest to a centimeter. Wastage and unauthorized
overlaps shall not be measured.
2.3.12 The standard sectional weights referred to as in Table 5.4 in para 5.3.4 in CPWD
Specifications will be considered for conversion of length of various sizes of
M.S. Bars, Steel Bars and T.M.T. bars into Standard Weight.
2.3.13 Records of actual Sectional weights shall also be kept dia-wise and lot-wise. The
average sectional weight for each diameter shall be arrived at from samples
from each lot of steel received at site. The decision of the Engineer-in-Charge
shall be final for the procedure to be followed for determining the average
sectional weight of each lot. Quantity of each diameter of steel received at site of
work each day will constitute one single lot for the purpose. The weight of steel
by conversion of length of various sizes of bars based on the actual weighted
average sectional weight shall be termed as Derived Actual Weight. However,
for the stipulated issue of steel reinforcement up to and including 10mm
diameter bars, the actual weight of steel issued shall be modified to take into
account the variation between the actual and the standard coefficients and the
contractors’ accounts will be debited by the cost of modified quantity.
2.3.14 (a) If the Derived Weight as in sub-para (2.3.13) above is less than the Standard
Weight as in Sub-para (2.3.12) above then the Derived Actual Weight shall be
taken for payment provided, if it is within the following tolerances specified in
IS1786-2008, otherwise whole lot will be rejected.
Tolerances on Nominal Mass
Nominal Size in mm Tolerance on Nominal mass Percent
Batch Individual Individual
Sample* sample for coil**
Up to and including 10 +7 -8 +8
a) Over 10 up to and
Including 16 +5 -6 +6
b) Over 16 +3 -4 +4
* For individual sample plus tolerance is not specified.
**For coils batch tolerance is not specified.
PART B 105
c) If the Derived Actual Weight is found more than the Standard Weight, the
Standard Weight as per in sub-para (2.3.12) above shall be taken for
payment. In such case nothing extra shall be paid for the difference between
the Derived Actual Weight and the Standard Weight.
2.4 SAFETY IN CONSTRUCTION
2.4.1 The contractor shall employ only such methods of construction, tools and plants
as are appropriate.
2.4.2 The contractor shall take all precautions and measures to ensure safety of works
and work man and shall be fully responsible for the same.
2.4.3 Safety pertaining to construction such as centering & shuttering, scaffolds,
ladders, working platforms, gangway etc. shall be governed by CPWD safety
code, relevant safety codes and the directions of Engineer in charge.
2.4.4 All the staging to be either of tubular steel structure with adequate bracings as
approved or made of built-up structural sections made from rolled structural
steel sections.
2.4.5 Form work shall be properly designed for self-weight, weight of reinforcement,
weight of fresh concrete and in addition the various live loads likely to be
imposed during construction process.
2.4.6 The form work shall be designed & constructed so as to remain sufficiently rigid
during placing & compaction of concrete & shall be such as to prevent loss of
slurry from the concrete.
2.4.7 The vertical supports shall be adequately braced or otherwise secured in
position that these do not fall when the load gets released or the supports are
accidentally hit.
2.4.8 A thorough inspection of tubular steel centering is necessary before its erection
and members showing evidence of excessive rusting, kinks, dents or damaged
welds shall be discarded. Buckled or broken members shall be replaced. Care
shall also be taken those locking devices are in good working order and that
coupling pins are effectively aligned to frames. Tubes should have end to end
joints in adjacent tubes staggered. Sleeve couplers should be used in preference
to joint pins for axial connections.
2.4.9 Inclined forms which give rise to very high horizontal forces should be taken
care of by trussing and diagonal bracing
2.4.10 Vertical members should be placed centrally under the members to be
supported and over the member supporting them with no eccentricity exceeding
25mm
2.4.11 The centering frames shall be tied together with sufficient braces to make a rigid
and solid unit. It shall be ensured that struts and diagonal braces are in proper
position and are secured so that frames develop full load carrying capacity. As
erection progresses, all connecting devices shall be in place and shall be fastened
for full stability of joints and units.
2.4.12 Wedges under the supports shall be set on firm soil / PCC which assures
adequate stability for all props. Care shall be taken not to disturb the soil under
the supports. Adequate drainage shall be provided to drain away the water
PART B 106
coming due to rains, easing of forms or during the curing of the concrete to
avoid softening of the supporting soil strata.
2.4.13 During pouring of the concrete the centering shall be constantly inspected and
strengthened, if required wedges below the vertical supports tightened and
adjustment screws properly adjusted as necessary.
2.4.14 Only workmen actually engaged in the form work shall be allowed in the area
during operations. Those engaged in removing the form work shall wear
helmets, gloves and heavy soled shoes and approved safety belts etc.
2.4.15 The safety code as lay down in respective clauses of Agreement shall be strictly
followed.
PART B 107
(ii) Contractor shall get approved the location of disposal site prior to
commencement of the excavation on any section of the project location.
(iii) Contractor shall ensure that any spoils of material / construction waste
will not be disposed off in any municipality solid waste collection bins.
Procurement of Construction Materials
(i) All vehicles delivering construction materials to the site shall be covered to
avoid spillage of materials and maintain cleanliness of the roads.
(ii) Wheel Tyres of all vehicles used by of the contractor, or any of his sub-
contractor or materials suppliers shall be cleaned and washed clear of all
dust/mud before leaving the project premises. This shall be done by
routing the vehicles through tyre washing tracks.
(iii) Contractor shall arrange for regular water sprinkling at least twice a day
(i.e. morning and evening) for dust suppression of the construction sites
and unpaved roads used by his construction vehicles.
Water Pollution
(i) The Contractor shall take all precautionary measures to prevent the
wastewater during construction to accumulate anywhere.
(ii) The wastewater arising from the project is to be disposed off in the manner
that is acceptable to the CPCB.
Air and Noise Pollution
Contractor shall use dust screens and sprinkle water around the construction site
to arrest spreading of dust in the air and surrounding areas.
(i) Contractor shall ensure that all vehicles, equipment and machinery used
for construction are regularly maintained and confirm that emission levels
comply with environmental emission standards/norms.
(ii) For controlling the noise from Vehicles, Plants and Equipments, the
Contractor shall confirm the following:
(a) All vehicles and equipment used in construction will be fitted with
exhaust silencers.
(b) Servicing of all construction vehicles and machinery will be done
regularly and during routine servicing operations, the effectiveness
of exhaust silencers will be checked and if found defective will be
replaced.
(c) Noise emission from compactors(rollers) front loaders, concrete
mixers, cranes(movable), vibrators and saws should be less than 75
dB(A).
(d) As per the standards/guidelines for control of Noise Pollution from
Stationary Diesel Generator (DG) sets, noise emission in dB(A) from
DG Sets (2-1010 KVA) should be less than 94+10 log 10 (KVA). The
standards also suggest construction of acoustic enclosure around the
DG Set and provision of proper exhaust muffler with insertion loss
of minimum 25 dB(A) each as mandatory.
PART B 109
(v) Spills of dirt or dusty materials shall be cleaned up promptly so that the
spilled material does not become a source of fugitive dust and also to
prevent seepage of pollutant laden water into the ground aquifers. When
cleaning up the spill, ensure that the clean-up process does not generate
additional dust. Similarly, spilled concrete slurries or liquid wastes should
be contained / cleaned up immediately before they can infiltrate into the
soil/ground or runoff in nearby areas.
(vi) Clear vegetation only from areas where work will start right away.
Adopt measures to prevent air pollution in the vicinity of the site due to
construction activities. There is no standard reference for this. The best practices
should be followed (as adopted from international best practice documents and
codes).
Provide safety barricading of site by drawing ribbon band along the site
boundary, next to a road or other public area.
The contractor shall provide experienced personnel with suitable training to
ensure that these methods are implemented. Prior to the commencement of any
work, the method of working, plant equipment and air pollution control system
to be used on -site should be made available for the inspection and approval of
the Engineer -in-Charge to ensure that these are suitable for the project.
Employ measures to segregate the waste on-site into inert, chemical or hazardous
wastes. Recycle the unused chemical/hazardous wastes such as oil, paint,
batteries and asbestos. As per GRIHA 3 rating (inert and Hazardous waste must
be collected and storied separately from site. Proper training must be given to all
construction workers in order to train them to be able to handle different kind of
waste on site. In addition to segregating the inert and hazardous waste, it is also
important to either reuse the construction waste on site or safety dispose it off to
designated agencies for recycling.
To preserve the existing landscape and protect it from degradation during the
process of construction. Select proper timing for construction activity to minimize
the disturbance such as soil pollution due to spilling of the construction material
and its mixing with rainwater. The construction management plan including soil
erosion control management plan shall be prepared accordingly for each month.
The application of erosion control measures includes construction of gravel pits
and tyre washing bays of approved size and specification for all vehicular site
entry/exits, protection of slopes greater than 10%. Sedimentation Collection
System and run-off diversion systems shall be in place before the commencement
of construction activity. Preserve and protect the existing vegetation by not-
disturbing or damaging to specified site areas during construction.
The Contractor should follow the construction plan as proposed by the Engineer-
in-charge / landscape consultant to minimize the site disturbance such as soil
pollution due to spilling. Use staging and spill prevention and control plan to
restrict the spilling of the contaminating material on site.
PART B 112
Spill prevention and control plans should clearly state measures to stop the
source of the spill. Measures to contain the spill and measures to dispose the
contaminated material and hazardous wastes. It should also state the
designation of personnel trained to prevent and control spills. Hazardous wastes
include pesticides, paints, cleaners and petroleum products.
A Soil Erosion and Sedimentation Control Plan (ESCP) should be prepared
prior to construction and should be applied effectively.
The contractor shall prepare and submit ‘Spill prevention and control plans’
before the start of construction, clearly stating measures to stop the source of the
spill, to contain the spill, to dispose the contaminated material and hazardous
wastes, and stating designation of personnel trained to prevent and control
spills. Hazardous wastes include pesticides, paints, cleaners, and petroleum
products.
The contractor shall ensure that no construction leaches (Ex: cement slurry) is
allowed to percolate into the ground. Adequate precautions are to be taken to
safeguard against this including reduction of wasteful curing processes,
collection, basic filtering and reuse. The contractor shall follow requisite
measures for collecting drainage water run-off from construction areas and
material storage sites and diverting water flow away from such polluted areas.
Temporary drainage channels, perimeter dike/swale, etc. shall be constructed to
carry the pollutant -laden water directly to the treatment device or facility
(municipal sewer line).
All lighting installed by the contractor around the site and at the labour quarters
during construction shall be energy efficient fixtures of the appropriate
illumination levels.
All paints, adhesives and sealants should comply with the VOC limits prescribed
as a green initiative as follows:
The VOC (volatile organic compound) content of adhesives and sealants used on
the interior of the building must be less than VOC content limits mentioned
below. A list of all the adhesives and sealants used for the project is to be
submitted along with the manufacturer’s certificate supporting the VOC content.
Metal to Metal 30
Plastic Foams 50
Wood 30
Fibreglass 80
Contact Adhesive 80
Architectural 250
Roadway 250
Other 420
Sealant Primers
Other 750
Aerosol Adhesives
General purpose mist spray 65% VOC’s by weight
General purpose web spray 55% VOC’s by weight
All the building materials and systems used on site must be as per the
specifications and approved makes by the Engineer-In-Charge.
All required certificates explaining the properties of the building
material/system needs to be obtained from the manufacturer/vendor as
required by the green building rating authority. The final certificates would be
produced after the approval of green building consultant with necessary due
diligence. The purchase orders of all the materials made with the manufacturers
/ authorized vendors should be maintained and shall be provided for the
process with due diligence upon request.
Water saving measures as suggested by the consultants need to be followed on
site.
The contractor / subcontractor shall prepare and submit a Site Management
Plan (SMP) within 10 days of start, for approval by the Engineer -in-charge. This
SMP shall indicate the locations of godown, stockpiles, barricading, waste
storage, offices, vehicular movement routes etc. In short this SMP would
comprehensively represent how the site activities shall be managed conforming
to GRIHA 3 Star guidelines. Contractor will be penalized @ Rs. 1000/- per day of
delay on non-submission of SMP beyond due date to be recovered from next RA
bill.
Any other site management measures suggested by the Engineer-in-charge /
green building consultant shall be followed on site.
The contractor shall submit to the Engineer -in-Charge after construction of the
buildings, a detailed as built quantification of the following within 10 days of
recording of completion. Contractor will be penalized @ Rs. 1000/- per day of
delay in submission of “detailed as built quantification”.
(i) Total materials used
(ii) Total waste generated,
(iii) Total waste reused,
(iv) Total water used,
(v) Total electricity consumed, and
(vi) Total diesel consumed.
Evidence for the implementation of the all the above required measures shall be
provided to the Engineer-in-Charge in the form of photographs and templates
as required which is required for the submission to the green building rating
authority.
Nothing extra shall be payable for above provisions unless otherwise specified
in Schedule of Quantity.
PART B 115
PARTICULAR SPECIFICATIONS
(Civil Component)
1. GENERAL
1.1 The work shall be carried out as per CPWD Specifications 2019 Vol. I & II with
upto date correction slips.
1.2 The work shall be executed and measured as per metric dimensions given in the
Schedule of quantities, drawings etc. (F.P.S. units wherever indicated are for
guidance only).
1.3 Wherever any reference to any Indian Standard Specification occurs in the
documents relating to this contract, the same shall be inclusive of all
amendments issued thereto or revisions thereof, if any.
1.4 Unless otherwise specified in the schedule of quantities the rates for all items of
the work shall be considered as inclusive of pumping out or bailing out water if
required for which no extra payment will be made. This will include water
encountered from any source, such as rains, floods, and sub-soil water table
being high due to any other cause whatsoever.
1.5 Unless otherwise specified in the schedule of quantities, particular specifications
or CPWD specifications (subject to the order or preference) the rates tendered by
the tenderer shall be all inclusive and shall apply to all lifts, all heights and all
floor including terrace, leads and depths and nothing extra over and above the
schedule of quantity shall be payable on this account.
1.6 The work shall be carried out in accordance with the Architectural drawings,
structural drawings and approved shop drawings. The structural shop and
architectural drawings shall have to be properly correlated before executing the
work. In case of any difference noticed between architectural and structural
drawings, the contractor shall obtain final decision of the Engineer-in-charge. In
case of any discrepancy in the item given in the schedule of quantities appended
with the tender and architectural drawings related to the relevant items, the
former shall prevail unless and otherwise given in writing by the Engineer in
charge. Nothing extra shall be payable on this account.
1.7 Wherever any reference to any Indian Standards occurs in the documents
relating to this contract, the same shall be inclusive of all amendments issued
thereto or revisions thereof, if any, up to the date of receipt of tenders.
1.8 The following additional specifications shall apply:
1.8.1 All stone aggregate and stone ballast shall be of hard stone variety and to be
obtained from quarries near& around to site of work, approved by the
Department of Mines, Govt. of A.P. and as per direction of the Engineer in
charge
1.8.2 Coarse sand should be obtained from sand quarries of nearby rivers, approved
by the Department of Mines, Govt. of A.P. and as per direction of the Engineer
in charge and to be used for cement concrete work including RCC, mortar for
PART B 116
masonry and plaster work shall be of standard quality and screened as required.
It shall be clean sand.
In case of non-availability of sand, the agency may be permitted at the
discretion of Engineer-in Charge to use crushed stone sand on their request on
production of adequate proof of non-availability of the same, provided it
confirms to grading and other requirements given in CPWD specifications. The
change in sand type or source would require revision of Mix Design of Concrete
from the approved laboratories such as AU/Visakhapatnam or JNTU Kakinada
or NCCBM Hyderabad or any Government Engineering College /Institute, for
which nothing extra shall be paid nor any extra time will be granted. In case of
use of crushed stone sand, all necessary precautions for CC work, RCC work,
masonry work, plaster work and all other related works shall be taken by the
agency as per relevant CPWD specifications and BIS codes without any extra
cost.
1.9 The rates for all items of work shall unless clearly specified otherwise include
for all floor levels of building and cost of all operations and all inputs of labour,
material, T&P, scaffolding, wastages, watch and ward, other inputs, all
incidental charges, all taxes, GST, duties, levies etc. required for execution of the
work.
1.10 All crossings, embedment etc. in walls and floors for water supply, drainage and
sanitary pipes, fittings etc. shall be provided for individual walls and floors so as
to avoid cuttings of masonry work and floors. All such areas shall be made
good during finishing and nothing extra shall be payable on these accounts.
1.11 Product delivery, storage and handling of chemicals.
1.11.1 The contractor shall construct storage space for Chemicals to ensure that the
storage conditions are as recommended by the manufactures.
1.11.2 All the materials shall be procured and delivered in sealed containers with
labels legible and intact.
1.11.3 All the chemicals (polymers, epoxy, water proofing compound, plasticizer,
Polysulphide, all exterior and interior paints, polish etc.) shall be procured in
convenient packs say 20 liters/Kgs.} capacity packing only or as approved by
the Engineer-in-Charge, and not in bigger capacity containers, say 200 liter
(Kgs.) drums unless otherwise specifically permitted by the Engineer-in-Charge.
One sample from each lot of the chemical procured by the contractor shall be
tested in a laboratory as approved by the Chief Engineer.
1.11.4 All material required for the execution of the work shall be got approved,
procured and deposited with the Departmental supervisory staff. The materials
shall be kept in joint custody of the contractor and the Department. The watch
and ward of such material shall, however, remain to be the responsibility of the
contractor and no claim, whatsoever, on this account shall be entertained.
Different containers of each chemical shall be serially numbered on packing and
also consumed in that order. Day-to-Day account of receipt, issue and balance
shall be regulated by the Department and proper account shall be maintained at
site of work in the prescribed form as per the standard practice.
PART B 117
1.11.5 All the chemicals shall be procured by the contractor directly from the
manufacturer. In exceptional circumstances, the contractor may be allowed to
procure the materials from the authorized dealers of the manufacturers, if
specifically permitted by the Engineer-in-Charge.
1.11.6 The original copies of challan / cash memos towards the quantity of various
chemicals procured shall be made available by the contractor at the request from
the Engineer-in-Charge and a copy of the same shall be kept in record.
1.11.7 The Name of manufacturers, manufacturer’s product identification,
manufacturer’s mixing instructions, warning for handling and toxicity and date
of manufacturing and shelf life shall be clearly and legibly mentioned on the
labels of each container.
1.11.8 The contractor shall submit for the chemicals procured, manufacturer’s and / or
authorized dealer’s certificate regarding supplying and verifying conformance
to the material specifications, as specified.
1.11.9 All filled containers shall be handled in safe manner and in a way to avoid
breaking container seals.
1.11.10 Empty containers of the chemicals should not be removed from site till the
completion of work and shall be removed only with the written approval of the
Engineer-in-Charge.
1.11.11 All arrangements for measuring, dosing and mixing of material / chemicals at
site have to be made by the contractor.
1.11.12 Contractor shall suitably advise his site Engineer and all the workers as regards
safe handling of chemicals. Necessary protective and safety equipments in form
of hand gloves, goggles etc. shall be provided by the contractor and be also used
at site.
1.11.13 All incidental charges of any kind including cartage, storage and wastage and
safe custody of material etc. shall be borne by the contractor and no claim,
whatsoever, shall be entertained on this account.
1.11.14 The chemicals shall be tested in an independent laboratory as approved by the
Chief Engineer at the frequency as specified. If required, more samples may
have to be tested as per the directions of the Engineer-in-Charge. Nothing extra
shall be payable on this account. However, all the testing charges shall be borne
by the Contractor.
2 EARTH WORK: -
2.1 Earth work shall be executed as per CPWD specifications.
2.2 Measurement of excavation shall be done as per CPWD specification 2019 with
up-to-date correction slips.
2.3 All the major excavation shall be carried out by mechanical excavator. No extra
payment shall be made for that.
2.4 The contractor shall make at his own cost all necessary arrangements for
maintaining water level, in the area where works are under execution low
enough so as not to cause any harm to the works or problems in carrying out
with the execution and the rates for all items of work shall be considered as
PART B 118
inclusive of pumping out or bailing out water, if required and for which no extra
payment shall be made. This will include water coming from any source, such
as rains, accumulated rain water, floods, leakages from sewer and water mains
subsoil water table being high or due to any other cause whatsoever. The
contractor shall make necessary provision of pumping, dredging, bailing out
water coming from all above sources and excavation and other works shall be
kept free of water by providing suitable system approved by the Engineer-in-
Charge.
2.5 De-watering required, if any, shall be done conforming to BIS Code IS: 9759
(guide lines for de-watering during construction) and / or as per the
specifications approved by the Engineer-in-Charge. Design of an appropriate
and suitable dewatering system shall be the Contractor’s responsibility. Such
scheme shall be modified / augmented as the work proceeds based on fresh
information discovered during the progress of work, at no extra cost. At all
times during the construction work, efficient drainage of the site shall be carried
out by the Contractor and especially during the laying of plain cement concrete,
taking levels, etc. The Contractor shall also ensure that there is no danger to the
nearby properties and installations on account of such lowering of water table. If
needed, suitable precautionary measures shall be taken by the Contractor. Also,
the scheme of dewatering adopted shall have adequate built-in arrangement to
serve as stand-bye to attend to repair of pumps etc. and disruption of power /
fuel supply. Nothing extra shall be payable on this account.
2.6 In trenches where surface water is likely to get into cut / trench during
monsoons, a ring bund of puddle clay or by any other means shall be formed
outside, to the required height, and maintained by the Contractor. Also, suitable
steps shall be taken by the Contractor to prevent back flow of pumped water
into the trench. Nothing extra shall be payable on this account.
3.0 R.C.C. WORK: -
3.1 Design Mix Concrete.
3.1.1 The term machine batched, machine mixed and machine vibrated design mix
cement concrete used in the document shall mean the concrete produced in fully
automatic concrete batching & mixing plant, placed in position by the concrete
pump and vibrated by surface vibrator/ needle vibrator/ plate vibrator, as the
case may be to achieve the required strength and durability.
The RCC work shall be done with Design Mix Concrete. Wherever letter “M”
has been indicated, the same shall imply for the Design Mix Concrete. The
Design Mix Concrete will be designated based on the principles given in IS: 456,
10262 & SP 23. The Conditions & Specifications stated herein shall have
precedence over all conditions & specifications stated in relevant I.S. Codes /
C.P.W.D. Specifications. The concrete mix shall be designed for the specified
target mean compressive strength in order to ensure that work test result do not
fall below the acceptance criteria specified for the concrete mix. The cement shall
be actually weighed as presumption of each bag having 50kg shall not be
allowed. The Contractor shall design mixes for each class of concrete indicating
that the concrete ingredients and proportions will result in concrete mix meeting
the requirements specified. Nothing extra shall be paid on this account.
(a) The contractor has to submit design mix without use of admixtures.
PART B 119
3.2.4 For exercising such control, the Engineer-in-charge shall periodically depute his
authorized representative at the RMC plant. It shall be responsibility of the
contractor to ensure that all necessary equipment manpower & facilities are
made available to E-in-C and/ or his authorized representative at RMC plant.
3.2.5 Ingredients, admixtures & water declared unfit for use in production of mix
shall not be used. A batch mix found unfit for use shall not be loaded into the
truck for transportation.
3.2.6 All required relevant records of RMC shall be made available to the Engineer-in-
charge or his authorized representative. The E-in-C shall, as required, specify
guidelines & additional procedures for quality control & other parameters in
respect of materials and production & transportation of concrete mix, which
shall be binding on the contractor & the RMC plant.
3.3 Ingredients:
3.3.1 The sources of coarse aggregate, fine aggregate, water, admixture & cement to
be used in concrete work shall be identified by the contractor & he will satisfy
himself regarding their conforming to the relevant specifications & their
availability before getting the same approved from the Engineer-In-Charge.
(a) Coarse Aggregate: - As per CPWD Specifications
(b) Fine Aggregate: - As per CPWD Specifications
(c) Water: - It shall conform to requirements laid down in IS:456-2000 / Para
3.1.1 of CPWD Specifications (Vol. I 2019)
(d) Cement: - Portland Pozzolana Cement (Fly Ash based) conforming
to IS: 1489/ OPC of grade 43 shall confirm to IS: 269, required in the work
from reputed manufacturers of cement as per the approved make in 50 kg.
bags bearing manufacturer’s name and ISI marking, along with
manufacturers test certificate for each lot. Portland Pozzolana Cement is to
be used for RCC works only subject to fulfillment of conditions of circular
number CDO / SE (RR) / fly ash (MAN) 02 dated 09.04.09 shall be used
for design mix concrete and shall conform to IS-1489 (Part I). However, if
the contractor uses higher grade of cement nothing extra shall be paid.
(e) Admixture/ Plasticizer: - The admixture shall conform to IS: 9103. The
chloride content in admixture shall satisfy the requirement of BS: 5075.
The total amount of chlorides in admixture mixed concrete shall also
satisfy the requirements of IS: 456:2000. Admixtures shall not be used
without approval of Engineer-in-Charge. Whenever required, the
admixture of approved quality & approved make only shall be used to
attain the required workability. Nothing extra on account of use of
Admixture / Plasticizer shall be payable.
3.4. WATER CEMENT RATIO AND SLUMP
3.4.1 In proportioning a particular mix, the manufacturer/producer/contractor shall
give due consideration to the moisture content in the aggregates, and the mix
shall be so designed as to restrict the maximum free water cement ratio to less
than the 0.45.
3.4.2 Due consideration shall be given to the workability of the concrete thus
produced. Slump shall be controlled on the basis of placement in different
situations.
PART B 121
3.6 The Contractor shall engage one of the following approved laboratories / test
houses for designing the concrete mix in accordance with relevant IS Code and
to conduct laboratory tests to ensure the target strength & workability criteria
for a given grade of concrete: -
The contractor shall submit at his own cost, the mix design report from
approved laboratories such as AU/Visakhapatnam or JNTU Kakinada or
NCCBM Hyderabad or any Government Engineering College /Institute for
approval of Engineer-in-charge within 30 days from the date of issue of letter of
acceptance of the tender. No concreting shall be done until the mix design is
approved. Every time sources of materials/cement is changed mix design report
shall be got re- done and has to be got approved from Engineer In charge.
PART B 122
The various ingredients for mix design / laboratory tests shall be sent to the
lab/ test houses through the Engineer-in-charge and the samples of such
aggregates sent shall be preserved at site by the department. Nothing extra shall
be paid on this account.
In the event if all the above laboratories are unable to carry out the requisite
design/ testing, the contractor may have it done from any other NABL
accredited laboratory with prior approval of the Chief Engineer.
3.7 The contractor shall submit the report on design mix from any of above
approved laboratories for approval of Engineer in Charge within 30 days from
the date of issue of letter of acceptance of the tender. No concreting shall be
done until the design mix is approved. In case of the likely use of admixtures in
concrete, the contractor shall design and test the concrete mix by using trial
mixes with admixtures also, for which nothing extra shall be payable.
3.8 In case of change of source or characteristic properties of the ingredients used in
the concrete mix design during the work, the contractor as per the directions of
the Engineer-in-charge shall submit a revised concrete mix design report
conducted at laboratory established at site. Nothing extra shall be paid on this
account.
3.9 All cost of mix designing and testing, connected therewith, including charges
payable to the laboratory shall be borne by the Contractor including redesigning
of the concrete mix whenever required & as directed by Engineer-In-Charge.
3.10 The mix design for a specified grade of concrete shall be done for a target mean
compressive strength Tck = Fck + 1.65s
Where Fck = Characteristic compressive strength at 28 days.
S= Standard deviation which depends on degree of
quality control.
The degree of Quality Control for this work is “good” for which the standard
deviation obtained for different grades of concrete shall be as follows: -
However, actual standard deviation based on test strength of samples for each
grade of concrete shall be calculated separately as per procedure laid down in
clause 9.2.4 of Code of Practice IS 456:2000.
3.10.1 TRIAL BATCHES
(a) The designed mix proportions shall be checked for target mean
compressive strength by means of trial batches.
PART B 123
(b) Minimum three sets of separate preliminary tests shall be carried out for
each trial batch of concrete mix. Each test shall comprise of six specimens
and only one test-set of six specimens shall be made on any particular day.
(c) The quantities of materials for each trial mix shall be sufficient for at least
six specimens (cubes) and the concrete required for carrying out
workability tests.
(d) The workability of trial mix No.1 shall be measured and mix shall be
carefully observed for freedom from segregation, bleeding and its
finishing characteristics. The water content, if required, shall be adjusted
corresponding to the required changes in the workability.
(e) With the modified Water Content, the mix proportions shall be
recalculated by keeping with water cement ratio unchanged. The mix
proportion, as modified, shall form the Trial Mix No.2 and tested for the
specified strength and workability.
(f) In addition, trial mix No.3 and 4 shall be designed by keeping water
contents same as that determined for trial mix 2 but varying the water
cement ratio by + 10 percent of the specified value and tested for their
design characteristics.
(g) Out of the six specimens of each set, three shall be tested at seven days and
remaining three at 28 days. The preliminary tests at seven days are
intended only to indicate the strength to be attained at 28 days, while the
design mix shall be approved only on the basis of test strength at 28 days.
3.10.2 APPROVAL OF DESIGN MIX
The design mix shall be considered satisfactory and approved if at least three
preliminary test-sets individually satisfy the following strength and workability
criteria:
(a) The average strength of each test-set is not less than the specified target
mean compressive strength (Tck).
(b) The strength of any specimen cube is not less than 0.85 fck.
(c) The concrete mix is of required degree of workability and acceptable
concrete finish.
3.11 DESIGN MIX CONCRETE FROM FULLY AUTOMATIC COMPUTERISED
CONCRETE BATCHING AND MIXING PLANT
3.11.1 Proportioning Concrete
In proportioning cement concrete, the quantity of both cement and aggregates
shall be determined by weight. The cement shall be weighed separately from the
aggregates. Water shall either be measured by volume in calibrated tanks or
weighed. All measuring equipment shall be maintained in a clean and
serviceable condition. The amount of mixing water shall be adjusted to
compensate for moisture content in both coarse and fine aggregates. The
moisture content of aggregates shall be determined in accordance with IS: 2386
PART B 124
(Part III). Suitable adjustments shall also be made in the weights of aggregates to
allow for the variation in weight of aggregates due to variation in moisture
content.
3.11.2 Production of Concrete
3.11.2.1The concrete shall be produced in a central batching and mixing plant with,
computerized printing for contents and admixture dosage. The batching plant
shall be fully automatic. Automatic batcher shall be charged by devices which,
when actuated by a Single starter switch will automatically start the weighing
operation of each material and stop automatically, when the designated weight
of each material has been reached. The batching plant shall have automatic
arrangement for dispensing the admixture and shall also be capable of
discharging water in more than one stage. A print out from the batching plant
for every lot shall be submitted. A batching plant essentially shall consist of the
following components: Separate storage bins for different sizes of aggregates,
silo for cement; and water storage tank.
Batching equipment
Mixers
Control panels
Mechanical material feeding and elevating arrangements
3.11.2.2The compartments of storage bins for aggregates shall be approximately of
equal size. The cement compartment shall be centrally located in the batching
plant. It shall be watertight and provided with necessary air vent, aeration
fittings for proper flow of cement & emergency cement cut off gate. The
aggregate and sand shall be charged by power operated centrally revolving
chute. The entire plant from mixer floor upward shall be enclosed and insulated.
The batch bins shall be constructed so as to by self-cleansing during drawdown.
The batch bins shall in general conform to the requirements of IS: 4925.
3.11.2.3 WATER:
1. Water to be used in manufacturing and curing of Concrete shall be tested
before use. All such tests shall be submitted to the Engineer in charge for
his approval before water is used in work.
2. Contractor shall identify the location of source of water intended to be
used. Each such source of water shall be separately tested. In the event of a
change in source of water all tests specified herein shall have to be
repeated.
3. In the event of water is drawn from tube wells or open wells, water
samples shall be for seasonal fluctuations in water table or at intervals to
be directed by the Engineer in charge.
1. Water samples from each source shall be tested as under:
One test at commencement of work for approval of each source and there
after change of source and
PART B 125
Thereafter, water from each source shall be got tested during the dry
season before monsoon and again after the monsoon.
Time period between two tests shall not exceed six months.
2. Approved quality water shall be collected and stored in the Under Ground
sumps/elevated tanks for the day to day requirement of work and same shall be
used for all cement works and also for curing. Due care shall be taken in this
regard.
3.11.2.4 The batching equipment shall be capable of determining and controlling the
prescribed amounts of various constituent materials for concrete accurately
i.e., water, cement, sand, individual size of coarse aggregates etc. The accuracy
of the measuring devices shall fall within the following limits.
3.11.2.5Mixing Concrete
3.11.2.5.1 The mixer in the batching plant shall be so arranged that mixing action
in the mixers can be observed from the operator's station. The mixer shall be
equipped with a mechanically or electrically operated timing, signaling and
metering device which will indicate and assure completion of the required
mixing period. The mixer shall have all other components as specified in IS:
4925.
3.11.2.6 Transportation, Placing and Compaction of Concrete
3.11.2.6.1 Mixed concrete from the batching plant shall be transported to the point
of placement by transit mixers or through concrete pumps or steel closed bottom
buckets capable of carrying 0.6 cum concrete. In case the concrete is proposed to
be transported by transit mixer, the mixer speed shall not be less than 4 rev/
min. of the drum nor greater than a speed resulting in a peripheral velocity of
the drum as 70 m / minute at its largest diameter. The agitating speed of the
agitator shall be not less than 2 rev / min. nor more than 6 rev / min. of the
drum. The number of revolutions of the mixing drum or blades at mixing speed
shall be between 70 to 100 revolutions for a uniform mix, after all ingredients,
have been charged into the drum. Unless tempering water is added, all rotation
after 100 revolutions shall be at agitating speed of 2 to 6 rev / min. and the
number of such rotations shall not exceed 250. The general construction of
transit mixer and other requirements shall conform to IS: 5892.
3.11.2.6.2 In case concrete is to be transported by pumping, the conduit shall be
primed by pumping a batch of mortar / thick cement slurry through the line to
lubricate it. Once the pumping is started, it shall not be interrupted (if at all
possible) as concrete standing idle in the line is liable to cause a plug. The
operator shall ensure that some concrete is always there in the pump-receiving
hopper during operation. The lines shall always be maintained clean and shall
be free of dents.
PART B 126
lower velocities are obtained. If there are cracks, voids or flaws inside the
concrete which come in the way of transmission of pulse, lower velocities are
obtained.
3.12.7.2The quality of concrete in terms of uniformity, incidence or absence of internal
flaws, cracks and segregation etc. indicative of the level of workmanship
employed, can thus be assessed using the guidance given in table below, which
have been evolved for characterizing the quality concrete in structure in term of
the ultrasonic pulse velocity.
Velocity criterion for Concrete Quality Grading.
Pulse velocity by Cross
Sl. No. Concrete Quality Grading
Probing (km/sec)
1 Above 4.40 Excellent
2 4.40 to 3.75 Good
3 3.75 to 3.00 Doubtful
4 Below 3.00 Poor
3.12.7.5 The test results are to be examined in view of the above acceptance criteria
“Good” and “Excellent” and wherever concrete is found with less than required
quality as per acceptance criteria, repairs to concrete will be made.
Honeycombed areas and loose pockets will be repaired by grouting using
Portland Cement Mortar/Polymer Modifies Cement Mortar /Epoxy Mortaretc.
after chipping loose concrete in appropriate manner. In areas where concrete is
found below acceptance criteria and defects are not apparently visible on surface
,injecting approved grout in appropriate proportion using epoxy grout /acrylic
Polymer modified cements slurry made with shrinkage compensating cement /
plain cement slurry etc. will be resorted to for repairs.(refer relevant chapters
from CPWD Hand Book on Repairs and Rehabilitation of RCC Buildings).Repair
to concrete will be done till satisfactory results are obtained as per the
PART B 129
acceptance criteria by retesting of the repaired area. If satisfactory results are not
obtained dismantling and relaying of concrete will be done.
1 The term machine batched, machine mixed and machine vibrated design
mix cement concrete used in the document shall mean the concrete
produced at site in fully automatic concrete batching & mixing plant (IS
4925), placed in position by the concrete pump and vibrated by surface
vibrator/ needle vibrator/ plate vibrator, as the case may be to achieve
required strength and durability. (However, for small elements like lintels,
chajjas, shelves etc., the requirement of pumping would be dispensed with
as per direction of Engineer – in – charge and placement would be done
through alternative means).
2. Design mix concrete shall be used in the work for all structural members.
For design mix concrete revised CPWD specifications 2019 along with
relevant IS codes shall be followed in general along with the specific
provisions made herein.
3. Following parameters shall be adopted for mix design.
3.1
(xi)
a) Characteristic Greater than or Greater than or Greater than or
compressive equivalent to equivalent to equivalent to
strength fck+0.825xEstablishe fck+0.825xEstablished fck+0.825xEstablishe
compliance d standard deviation standard deviation d standard deviation
requirement. Or Or Or
(Mean of group of 4 Fck+3whichever is Fck+3whichever is Fck+3whichever is
non-overlapping more more more
tests and
consecutive test)
(N/Sqmm)
b) Individual test
Fck-3 Fck-3 Fck-3
(N/Sqmm)
Design parameters for M 10 & M15 Design mix concrete
Following parameters shall be adopted for mix design.
Sl.
Grade of Concrete M10 M15
No.
1 Nominal Max size of 20 mm angular as per 20 mm angular as per
aggregate CPWD specification CPWD specification
2 Degree of workability 25 - 75 25 - 75
(Slump) mm
3 Degree of quality control Good. Good.
4 Type of exposure Severe Severe.
5 Max free water cement/ 0.50 0.50
ratio
6 Type of cement used Portland Pozzolana Portland Pozzolana
cement or OPC- 43 cement or OPC- 43
grade grade
7 Minimum Cement Content 220Kg/cum and as 240Kg/cum and as
specified in the item. specified in the item.
8 Fine Aggregate Coarse sand as per Coarse sand as per
CPWD specifications. CPWD specifications.
9 Mix applicable Plain/Reinforced Plain/Reinforced
cement concrete cement concrete
10 Method application Pumping Pumping
11 Max Cement content 500 kg/Cum 500 kg/Cum
12 (A) Characteristic Greater than or Greater than or
compressive strength equivalent to equivalent to
compliance requirement. fck+0.825xEstablished fck+0.825xEstablished
(Mean of group of 4 non- standard deviation standard deviation
overlapping tests and Or Or
consecutive test) (N/Sq.mm) Fck+3whichever is Fck+3whichever is
more more
(B) Individual test Fck-3 Fck-3
(N/Sq.mm)
Sl. No.12 above is added for the purpose of operation of Clause 16 of IS 456 -
2000.
PART B 131
3.18.7 Concreting of upper floor shall not be done until concrete of lower floor has set
at least for 14 days but form work and reinforcement can be taken up after the
concrete has set at least for three days.
3.18.8 Double steel scaffolding having two sets of vertical supports shall be provided
for external wall finish, cladding etc. The supports shall be sound and strong,
tied together with horizontal pieces over which scaffolding platform shall be
fixed. Scaffolding shall have steel staircase for inspection of works at upper
levels. Nothing extra shall be paid on this account.
3.19. REINFORCEMENT: -
3.19.1. The reinforcement shall be done as per CPWD Specifications.
3.19.2. The rate of item of reinforcement of RCC work includes all operations including
straightening, cutting, bending, welding, binding with annealed steel or welding
and placing in position at all the floors with all leads and lift complete as per
CPWD Specifications.
3.19.3 The contractor shall provide approved type of support for maintaining the bars
in position and ensuring required spacing and correct cover of concrete to
reinforcement as called for in the drawings, spacer blocks of required shape and
size. Chairs and spacer bars shall be used in order to ensure accurate positioning
of reinforcement. Spacer blocks shall be cast well in advance with approved
proprietary pre-packed free flowing mortars (Conbextra as manufactured by
M/S Fosroc Chemicals India Ltd. or approved equivalent) of high early
strength and same colour as surrounding concrete. However, Cover Guard Bars
shall also be used to maintain proper cover of RCC Columns in addition to
spacer blocks as mentioned above. Pre-cast cement mortar/concrete
blocks/blocks of polymer shall not be used as spacer blocks unless specially
approved by the Engineer-in-charge. The rate of RCC items is inclusive of cost of
such cover blocks & Cover Guard Bars. Nothing extra shall be paid on this
account.
4.0 MASONRY WORK: -
4.1.1 The PCC block work shall be carried out with good quality Fly ash cement
blocks of class designation 7 (strength not less than 70kg/sq.cm)as per CPWD
Specifications.
4.1.2 The rate shall also include for leaving chases / notches for dowels / cramps for
all kinds of cladding to come over brick work.
4.1.3 Brick work provided around shaft or lift walls or around slab cutouts shall be
measured in the brick for corresponding floor level. Nothing extra shall be paid
on this account.
4.1.4 M.S. Strip/ Bar provided at every third course of half brick masonry shall be in
single piece. If required, welding joint can be used without overlaps. Nothing
extra shall be paid for welding and overlaps.
PART B 135
Contractor shall prepare the detailed shop drawings for the same and
commence work only after the approval by the Engineer-in-Charge. The rate
shall also include any consequent wastage, incidental charges involved in this
work. Nothing extra shall be payable on this account. For the purpose of
payment, the actual area of each type of granite/ marble or like stone as laid
shall be measured.
6.4 For the steps (risers and treads) in the linear profile, the granite/ marble or like
stone shall be provided in single pieces as per the architectural drawings, unless
otherwise specifically permitted by the Engineer-in-Charge. Wherever grooves
are required to be provided the same is to be done as per architectural drawings
and as directed by the Engineer-in-charge. Wherever required, the joints shall be
provided as per the architectural drawings. Nothing extra shall be payable on
these accounts.
6.5 The granite/ marble or like stone slabs used for providing and fixing in the sills,
soffits and jambs of doors, windows, ventilators and similar locations shall be in
single piece unless otherwise directed by the Engineer-in-Charge. Wherever
stone slab other than in single piece is allowed to be fixed, the joints shall be
provided as per the architectural drawings and as per the directions of the
Engineer-in-Charge. Depending on the number of joints, as far as possible, the
stone slabs shall be procured and fixed in slabs of equal lengths as per the
architectural drawings and as directed by Engineer-in-Charge.
6.6 While fixing the granite/ marble or like stone slabs in sills, soffits and jambs of
doors, windows, ventilators etc., rebates shall be made by overlapping the
stones at the required places for fixing shutters for doors, windows and
ventilators etc. as shown in the architectural drawings and as per the directions
of the Engineer-in-Charge. Epoxy based adhesives shall be used for fixing the
granite/ marble or like stones to each other, or wherever required. The
authorized overlap as per the architectural drawings or as directed by the
Engineer-in-Charge shall be measured for payment under the same item.
However, any extra mortar thickness required due to the overlap arrangement
shall be deemed to have been included in the rate of this item. Nothing extra
shall be payable on this account. The stone shall have uniform thickness and
shall be provided in sizes as per the architectural drawings. The stone slab shall
have uniformly leveled surface after fixing. All the joints shall be finished
smoothly in a workmanlike manner.
6.7 The granite/ marble or like stone work shall be adequately protected by a layer
of Plaster of Paris, which shall be maintained throughout and removed just
before handing over of the works for which nothing extra shall be payable.
7.0 WOOD WORK
7.1 The wood work in general shall be carried out as per CPWD Specifications
(Volume-I) 2019, with up-to-date correction slips
7.2 The sample of timber to be used shall be deposited by the contractor with
Engineer-in-charge before commencement of work.
PART B 137
7.3 The shape and size of beading shall be as per drawings. The joints of beading
shall be mitred.
7.4 Timber shall be of specified species, good quality and well-seasoned. It shall
have uniform colour, reasonably straight grains and shall be free from knots,
cracks, shakes and sapwood. It shall be close grained. The contractor shall
deposit the samples of species of timber to be used with the Engineer-in-Charge
for testing before commencement of the work.
7.5 Wood work shall not be painted, oiled or otherwise treated before it has been
approved by the Engineer-in-charge. All portion of timber including architrave
abutting against masonry, concrete, stone or embedded in ground shall be
painted with approved wood preservative or with boiling coal tar.
7.6 The contractor(s) shall produce cash voucher and certificates from approved
Kiln Seasoning Plants about the timber used on the work having been kiln
seasoned and chemically treated by them, falling which it would not be accepted
as kiln seasoned and/or chemically treated.
7.7 Transparent sheet glass conforming to IS: 2835 shall be used. Thickness being
governed as under unless otherwise specified in the item in wood work/steel
work:
7.8 Factory made wooden flush door and paneled and wire gauge shutters shall be
manufactured and carried out as per CPWD specifications (Volume-I, 2019 with
upto date correction slips).
7.9 The work shall be executed through specialized agencies to be approved by the
Engineer –in- Charge.
7.10 The contractor shall propose well in advance to Engineer-in-Charge, the names
and address of the factory where from the contractor intends to get the shutters
manufactured along with the credential of the firm. The contractor shall place
the order for manufacturing of shutters only after obtaining approval of the
Engineer in Charge whose decision in this case shall be final & binding. In case
the firm is not found suitable he shall propose another factory. The factory may
also be inspected by a group of officers before granting approval; shutters shall
however he accepted only if these meet the specified test.
7.11 Contractor will arrange stage wise inspection of the shutters at factory by the
Engineer-in-Charge or his authorized representative. The contractor will have
no claim if the shutters brought at site in part or full lot are rejected by the
Engineer-in-Charge due to bad workmanship / quality. Such defective shutters
will not be measured and paid. The contractor shall remove the same from the
site of work within 7 days after the written instruction in this regard are issued
by the Engineer-in-Charge.
PART B 138
26 to 50 5 0
51 to 100 8 0
101 to 150 13 1
151 to 300 20 2
301 to 500 32 3
501 to 1000 50 5
(b)Criteria for conformity: - Any sample shutter failing in any one or more of
the requirements inspected for as above shall be considered as defective. A
lot shall be considered as having satisfied the requirements of the standard if
the number of defective shutters in the sample does not exceed the
corresponding permissible number of defectiveness given above.
(c) Testing: - The shutters shall be tested for species seasoning & treatment,
defects in the timber, panel material, construction & workmanship in the
approved Laboratory at the frequency mentioned in CPWD specification.
If shutters are found defective in any one of the criterion double the shutter
shall be tested & if found permissible can be accepted. If shutter is found
defective in more than one criterion, the whole lot shall be rejected.
(d) Finish
i) All components of door shutter shall have smooth finish.
ii) Panels of the door shutters shall be flat and well sanded to a smooth
and level Surface.
iii) All the surfaces of door shutters which are required to be painted or
polished or varnished shall be got approved from the Engineer in
Charge before applying protective coat of primer, polish or varnish.
8.2 Shutters
Flush door shutters shall have a solid core and may be of the decorative or non-
decorative (Paintable type as per IS 2202 (Part I). Nominal thickness of shutters
may be 30mm as mentioned in the BOQ. Thickness and type of shutters shall be
as specified.
Width and height of the shutters shall be as shown in the drawings or as
indicated by the Engineer-in-Charge. All four edges of the shutters shall be
square. The shutter shall be free from twist or warp in its plane. The moisture
content in timbers used in the manufacture of flush door shutters shall be not
more than 12 per cent when tested according to IS 1708.
8.3 Core
The core of the flush door shutters shall be a marine grade block board having
wooden strips held in a frame constructed of stiles and rails. Each stile and rail
shall be a single piece without any joint. The width of the stiles and rails
including lipping, where provided shall not be less than 45mm and not more
than 75mm. The width of each wooden strip shall not exceed 30mm. Stiles, rails
and wooden strips forming the core of a shutter shall be of equal and uniform
thickness. Wooden strips shall be parallel to the stiles.
8.4 End joints of the pieces of wooden strips of small lengths shall be staggered. In
a shutter, stiles and rails shall be of one species of timber. Wooden strips shall
also be of one species only but it may or may not be of the same species as that
of the stiles and rails. Any species of timber may be used for core of flush door.
However, any non-coniferous (Hard wood) timber shall be used for stiles, rails
and lipping.
8.5 Face Panel
The face panel shall be formed by gluing, by the hot-press process on both faces
of the core, either plywood or cross-bands and face veneers. The thickness of the
cross bands as such or in the plywood shall be between 1.0mm and 3.0mm. The
thickness of the face veneers as such or in the plywood shall be between 0.5mm
and 1.5mm for commercial veneers and between 0.4mm and 1.0mm for
decorative veneers, provided that the combined thickness of both is not less than
2.2mm. The direction of the veneers adjacent to the core shall be at right angles
to the direction of the wooden strips. Finished faces shall be sanded to smooth
even texture. Commercial face veneers shall conform to marine grade plywood
and decorative face veneers shall conform to type I decorative plywood in IS
1328.
8.6 Lipping
Lipping, where specified, shall be provided internally on all edges of the
shutters. Lipping shall be done with battens of first class hardwood or as
specified of depth not less than 25mm. For double leaved shutters, depth of the
lipping at meeting of stiles shall be not less than 35 mm. Joints shall not be
permitted in the lipping.
PART B 140
8.7 Rebating
In the case of double leaves shutters the meeting of stiles shall be rebated by 8
mm to 10 mm. The rebating shall be either splayed or square type as shown in
drawing where lipping is provided. The depth of lipping at the meeting of stiles
shall not be less than 30 mm.
8.8 Opening for Glazing
When required by the purchaser opening for glazing shall be provided and
unless otherwise specified the opening for glazing shall be as per drawings. The
bottom of the opening shall be at a height as shown in the drawings. Opening
for glazing shall be lipped internally with wooden batten of width not less than
25 mm.
8.9 Tolerance
Tolerance on width and height shall be + 3 mm and tolerance on nominal
thickness shall be ± 1.2 mm. The thickness of the door shutter shall be uniform
throughout with a permissible variation of not more than 0.8 mm when
measured at any two points.
Adhesive: - Adhesive used for bonding various components of flush door
shutters namely, core, core frame, lipping, cross-bands, face veneers, plywood
etc. and for bonding plywood shall conform to BWP type, phenol formaldehyde
synthetic resin adhesive conforming to IS 848.
8.10 Tests
As per CPWD Specifications.
8.11 Fixing
As per CPWD Specifications.
8.12 Measurements
As per CPWD Specifications.
9.0. STEEL WORK
9.1 All steel work shall be carried out as per CPWD Specifications. (Volume 1) 2019
with up-to-date correction slips.
9.2 All welded steel work shall be tested for quality of weld as laid down in IS 822:
1970 before actual execution.
10.0 FLOORING
10.1 All work in general shall be carried out as per CPWD Specifications (Volume 1)
2019 with up-to-date correction slips.
10.2 Whenever flooring is to be done in patterns of tiles and stones, the contractor
shall get samples of each pattern laid and approved by the Engineer-in-charge
before final laying of such flooring. Nothing extra shall be payable on this
account.
PART B 141
10.3 Different stones / tiles used in pattern flooring shall be measured separately as
defined in the nomenclature of the item and nothing extra for laying pattern
flooring shall be paid over and above the quoted rate. No additional wastage, if
any, shall be accounted for any extra payment.
10.4 Samples of flooring stones/ Tile (Kota/ Marble/ Granite/ Ceramic tiles/
Vitrified tiles etc.) shall be deposited well in advance with the Engineer-in-
Charge for approval. The sizes of stones for flooring shall be of a size not less
than 600mmx600mm or as approved by Engineer-in-Charge. Approved samples
should be kept at site with the Engineer-in-Charge and the same shall not be
removed except with the written permission of Engineer-in-Charge. No
payment whatsoever shall be made for these samples.
10.5 The Marble/ Kota/ Granite or any other stone shall be fully supported by the
details establishing the quarry and its location or source.
10.6 Full width Marble/ Kota/ Granite stone over kitchen platform shall be provided
except to adjust for closing pieces. The marble / stone flooring in treads and
risers of staircase is to be laid in single piece.
10.7 The rate of items of flooring is inclusive of Providing Sunken Flooring in
Bathrooms, Kitchen, W.C., etc. and nothing extra on this account is admissible.
10.8 Chasing of required width and thickness shall be made in brick work at skirting
location so as to flush the external surface of skirting with internal plastering.
No extra payment towards making chases in brick work at skirting shall be
made and the same is presumed to be inclusive of rate quoted for the item of
providing and fixing skirting.
10.9 Proper gradient shall be given to flooring for toilets, verandah, kitchen,
courtyard etc. so that the wash water flows towards the direction of floor trap.
Any reverse slope if found, shall be made good by the contractor by ripping
open the floor/grading concrete and nothing shall be paid for such
rectifications.
10.10 The flooring and skirting will be executed as per pattern shown in the
Architectural drawings and as per approval of Engineer-in-Charge and nothing
extra shall be payable on this account.
10.11 The rate shall include the cost of all materials and labour involved in all the
operations. Nothing extra shall be paid for use of cut/sawn stone/ tiles in the
work.
10.12 The flooring laid with stone slab / tile / marble / Granite/ Ceramic tiles /
vitrified tiles etc. shall be adequately protected by a layer of plaster of Paris,
which shall be maintained throughout and removed just before handing over
of the works for which nothing extra shall be payable.
11.0. VITRIFIED TILES FLOORING
11.1 The tiles of various types shall be of approved make and shall generally conform
to IS 15622 or any other IS code as applicable with corrections/amendments up
to the last date of bid submission. The Vitrified tiles of specified sizes shall be
PART B 142
used & sample of tiles shall be got approved from the Engineer – in – charge.
The Mandatory tests for vitrified tiles shall be got done as per CPWD
Specifications (volume – 1) / relevant BIS Code.
11.2 The vitrified shall be as specified in the item. The tiles shall be of specified
colours as shown in the drawings or as approved by Engineer – in – Charge and
will be laid in pattern as per architectural drawings. Nothing extra shall be paid
for laying tiles in specific pattern. The tiles shall be first quality of approved
make and to be procured from mother plant only.
11.3 The vitrified tile flooring / ceramic tile flooring or like tile flooring work shall
be adequately protected by a layer of plaster of Paris, which shall be
maintained throughout and removed just before handing over of the works
for which nothing extra shall be payable.
12.0 WATER PROOFING: -
12.1 The work shall be got executed as per CPWD or manufactures’ specifications
and from the specialized agency as approved by the Engineer in Charge.
12.2 Contractor shall also submit the names of water proofing specialist along with
information about their technical capabilities and list of similar works executed
by the specialized agency in the past for the approval of Engineer-in-charge
within 30 days from the date of award of work.
12.3 Total quantity of the water proofing compound required shall be arranged only
after obtaining the prior approval of the make by Engineer-in-charge in writing.
Materials shall be kept under double lock and key and proper account of the
water proofing compound used in the work shall be maintained. It shall be
ensured that the consumption of the compound is as per specified requirements.
12.4 The finished surface after water proofing treatment shall have adequate smooth
slope as per the direction of the Engineer-in-charge.
12.5 Before commencement of treatment on any surface, it shall be ensured that the
outlet drain pipes / spouts have been fixed and the spout openings have been
chased and rounded off properly for easy flow of water.
12.6 The entire execution of waterproofing work shall be video recorded and
submitted to Engineer-in-Charge on a DVD disc. Various toilets shall be indexed
and written with paint on the walls for reference and identification purpose.
12.7 GUARANTEE BOND FOR ALL WATER PROOFING ITEMS: -
Ten years Guarantee bond in prescribed proforma given in the tender
document shall be submitted by the contractor which shall also be signed by
both the specialized agency and the contractor to meet their liability / liabilities
under the guarantee bond. However, the sole responsibility about efficiency of
water proofing treatment shall rest with the building contractor. 10% (Ten per
cent) of the cost of water-proofing work shall be retained as Security Deposit
and the amount so deducted would be released after 10 (Ten) years from the
date after the expiry of maintenance period prescribed in the contract, if the
performance of the treatment is found satisfactory. If any defect is noticed
during the guarantee period, the contractor shall rectify it within 15 days of
receipt of intimation of defects in the work. If the defects pointed out are not
PART B 143
attended to within the specified period, the same will be got done from another
agency at the risk and cost of contractor. However, this security deposit can be
released in full, if bank Guarantee or FDR of equivalent amount for Full 10 (Ten)
years is produced and deposited with the department.
13.0. FINISHING: -
13.1 The work shall be done in accordance with CPWD Specifications -2019 Vol. I to
Vol. II with upto date correction slips and the manufacturer’s specifications
where CPWD specifications are not available.
13.2 The quantity of paint required as per the theoretical consumption including
wastages, if any, shall be procured from the approved manufacturer or his
authorized dealers and deposited with the representative of the Engineer-in-
Charge at site.
13.3 The paint shall be obtained in smaller packing (around 20 liters).
13.4 The paint shall be kept in the joint custody of the Department and the
Contractor and day-to-day account of receipt and issue shall be maintained.
However, the safe custody and watch and ward shall remain to be the
responsibility of the Contractor. Nothing extra shall be payable on this account.
13.5 The name of the manufacturer, manufacturer’s product identification,
manufacturer’s mixing instructions, warnings and instructions for handling and
application, toxicity and date of manufacturing and shelf life shall be clearly and
legibly mentioned on the labels of each container. These details shall be kept in
record. The material shall be consumed in the order of material brought to site,
first come first consume basis. The Contractor shall obtain and submit to the
Department the manufacturer’s certificate for compliance of the various
characteristics of the materials as per the manufacturer’s specifications and also
copy of the manufacturer’s test report for the record.
13.6 Empty containers of the paints shall not be removed from site till the completion
of the work unless otherwise permitted and shall be removed only with the
permission of the Engineer-in-Charge or his authorized representative at site of
work.
13.7 All arrangements for measuring, dosing etc. at site shall be made by the
Contractor. Nothing extra shall be payable on this account.
13.8 The Contractor shall apply samples of each kind of paint for the approval of
shade and colour as per the directions of the Engineer-in-Charge before
procuring the paint in mass.
13.9 All incidental charges of cartage, storage, wastage, safe custody, scaffolding,
cost of samples and mock ups etc. shall be borne by the Contractor and no claim,
whatsoever, shall be entertained on this account.
14.0 SANITARY INSTALLATIONS /WATER SUPPLY / DRAINAGE: -
14.1 The contractor shall be responsible for the protection of the sanitary and water
supply fittings and other fittings and fixtures against pilferage and breakage
during the period of installation and thereafter until the building is handed
over.
PART B 144
14.2 The contractor shall furnish all labour, materials and equipment, transportation
and incidental necessary for supply, installation, testing and commissioning of
the complete Plumbing / Sanitary system as described in the Specifications and
as shown on the drawings. This also includes any material, equipment,
appliances and incidental work not specifically mentioned herein or noted on
the Drawings/Documents as being furnished or installed, but which are
necessary and customary to be performed under this contract. The Plumbing /
Sanitary System shall comprise of following:
a. Sanitary Fixtures and Fittings.
b. Internal and External Water Supply.
c. Internal and External Drainage.
d. Balancing, testing & commissioning.
e. Test reports and completion drawings.
14.3 For the work of water supply and sanitary installations, the contractor shall
engage the approved licensed plumbers and submit the name of proposed
plumbing agencies with their credentials for approval of the Engineer-in-
Charge. For quality control & monitoring of workmanship, contractor shall
assign at least one engineer who would be exclusively responsible for ensuring
strict quality control, adherence to specifications and ensuring top class
workmanship for the installation.
14.4 The work in general shall be carried out as per CPWD Specifications (Volume II)
2019 with up-to-date correction slips.
14.5 The tendered rates shall include the cost of cutting holes in walls, floors, RCC
slabs etc. wherever required and making good the same for which nothing extra
shall be paid.
14.6 Nothing extra for providing & fixing CP Brass caps /extension pieces wherever
required for CP Brass fittings shall be paid beyond the rates payable for
corresponding CP Brass fittings.
14.7 The contractor shall examine all architectural, structural, plumbing, electrical
and other services drawings and check the as-built works before starting the
work, report to the Engineer In-Charge any discrepancies and obtain
clarification. Any changes found essential to coordinate installation of his work
with other services and trades, shall be made with prior approval of the
Engineer In-Charge without additional cost to the department.
14.8 All the shop drawings shall be prepared on computer through AutoCAD
System based on Architectural Drawings and site measurements within two
months of the stipulated date of start of the contract, contractor shall furnish, for
the approval of Engineer In-Charge, the two sets of detailed shop drawings of
complete work and materials including layouts for Plant room, Pump room,
Typical toilets drawings showing exact location of supports, flanges, bends, tee
connections, reducers, detailed piping drawings showing exact location and
type of supports, valves, fittings etc.; external insulation details for pipe
insulation etc.
14.9 These shop drawings shall contain all information required to complete the
work. These Drawings shall contain details of construction, size, arrangement,
PART B 145
services. In case the contractor fails to submit the completion plans as aforesaid,
security deposit shall not be released and these shall be got prepared at his risk
and cost.
14.16 The CCI/CI/PVC pipe and GI pipe etc. wherever necessary shall be fixed to
RCC columns, beams etc. with rawl plugs and nothing extra shall be paid for
this.
14.17 The variation in consumption of material shall be governed as per CPWD
specification and clauses of the contract to the extent applicable.
14.18 The pig led to be used in joints of 150mm,100mm, 75mm, 50mm dia of sand cast
iron, centrifugally cast (Spun) iron pipes shall be as per relevant CPWD
Specifications.
14.19 The contractor shall bear all incidental charges for cartage, storage and safe
custody of materials and shall construct suitable godowns, yards at the site of
work for storing materials so as to be safe against damage by sun, rain, fire or
theft etc., at his own cost and also employ necessary watch and ward
establishment for the purpose at his own cost.
14.20 All fixtures and fittings shall be provided with all such accessories as are
required to complete the item in working condition whether specifically
mentioned or not in the Schedule of Quantities, specifications, elsewhere in this
tender document & drawings. The quoted rates shall be deemed to be all
inclusive for a complete item fit for use including all materials, labour, T&P,
specials, equipment, testing & commissioning etc. Accessories shall include
proper fixing arrangement, brackets, nuts, bolts, screws and required connection
pieces. Nothing extra whatsoever shall be payable on this account.
14.21 Fixing screws shall be half round head chromium plated brass screws with C.P.
washers where necessary or otherwise as provided in the item.
14.22 Porcelain sanitary ware shall be glazed vitreous China of first quality free from
warps, cracks and glazing defects and shall conform to relevant BIS codes.
Colour of sanitary ware, shall be specified or as selected by the Engineer-in-
Charge. Nothing extra shall be payable on this account.
14.23 Horizontal pipes running along ceiling shall be fixed on structural adjustable
clamps of approved design. Horizontal pipes shall be laid to uniform slope and
the clamps adjusted to the proper levels so that the pipes fully rest on them and
are properly secured.
14.24 Contractor shall provide all nuts, bolts, welding material and paint the Clamps
with one coat of red oxide and two or more coats of black enamel paint.
14.25 Slotted angle/channel supports on walls shall be provided wherever shown on
drawings. Angles/channels shall be of sizes shown on drawings or specified in
schedule of quantities. Angles/channels shall be fixed to brick walls with bolts
embedded in cement concrete blocks and to RCC walls with suitable anchor
fasteners. The spacing of support bolts horizontally shall not exceed 1m.
14.26 Wherever M.S. clamps are required to be anchored directly to brick walls,
concrete slabs, beams or columns, nothing extra shall be payable for clamping
arrangement and making good with cement concrete 1:2:4 mix (1 cement: 2
PART B 147
15.2 Rate includes cost of all inputs of materials, labour, T&P, etc. involved in the
work and all incidental charges to execute this item. However, for the purpose
of payment only the actual weight of the stainless pipes and stainless steel plates
provided and fixed shall be measured in kg.
15.3 Guarantee Bond: The Contractor shall submit Guarantee Bond as per Proforma
given in the tender document. In addition, 5% (five percent) of the cost of this
item of work shall be retained as security deposit and the amount so withheld
would be released after five years from the date after the expiry of maintenance
period prescribed in the contract, if the performance of the work done is found
satisfactory. If any defect is noticed during the guarantee period, it shall be
rectified by the contractor along with any incidental repairs to structure,
flooring, finishing, fixtures and any other related damaged work within fifteen
days of receipt of intimation of such defects in the work. If the defects pointed
out are not attended to within the specified period, the same shall be got done
from another agency at the risk and cost of the contractor and the cost of
attending such repairs shall be deducted from any dues payable to the
contractors
16.0 Aluminium Work
16.1.1 The work shall be carried out as per specified CPWD Specifications in general
and as per directions of Engineer – in – charge.
16.1.2 Guarantee Bond: The Contractor shall submit Guarantee Bond as per Proforma
given in the tender document. In addition, 5% (five percent) of the cost of this
item of work shall be retained as security deposit and the amount so withheld
would be released after Five years from the date after the expiry of
maintenance period prescribed in the contract, if the performance of the work
done is found satisfactory. If any defect is noticed during the guarantee period,
it shall be rectified by the contractor along with any incidental repairs to
structure, flooring, finishing, fixtures and any other related damaged work
within fifteen days of receipt of intimation of such defects in the work. If the
defects pointed out are not attended to within the specified period, the same
shall be got done from another agency at the risk and cost of the contractor and
the cost of attending such repairs shall be deducted from any dues payable to
the contractors.
17.0 uPVC WINDOWS& VENTILATORS
All openable and fixed window system shall have minimum 3 hollow chambers
from front to back. The sliding system frames shall have minimum 3
chambers from front to back. The Sliding system Sashes shall have
minimum 2 chambers from front to back. The outer profile shall not be less
than 56mm.
All sections of the frame and sash shall be reinforced in accordance with the
system supplier’s recommendations us in galvanized mild steel in a single
continuous length.
GENERAL REQUIRMENT
Profile
The profile is to be extruded from a compound that has been blended to ensure
quality and consistency. The material shall be pristine white high impact
PART B 149
iv) The reinforcement shall be secured to the profile so that it does not move or
rattle and it maintains the structural integrity of the frame and satisfactory
thermal separation. Reinforcement is to be fixed at a maximum of 100mm from
the ends and then at a maximum of 300mm centers.
Glazing and Weather Seals
GLAZING
i) Window shall be such that glazing or re-glazing on site is possible without the
need to remove the outer frames from the structure of the building.
ii) All glazing is to be packed in accordance with the system supplier’s
recommendations to prevent any kind of damage during handling.
WEATHER SEALS
The weather seals shall be EPDM/Silicone seals. ASTM-D412 and ASTM-
D2240 are standard specifying test methods for Tensile strength and
Hardness of the gasket whereas the required value shall be specified
Ultimate tensile strength min >7.5/mm2
The weather seals are to be fitted in continuous lengths and grooves. The joints
in the vent weather seal are to be positioned at the bottom and in the
outer frames at the top.
Security and Safety
Fasteners shall be designed so that they cannot be released from the outside by
the insertion of a thin blade.
No opening light shall be openable or removable from the outside, when it
is fastened in the closed position, except by use of special tools or breaking
part of the window.
QUALITY CONTROL AND TESTING OF MATERIALS
Raw Material
The material from which the profiles are made shall consist substantially
from white polyvinylchloride as per BSEN 12608:20003. Only those additives
and pigments may be used that are needed for the manufacture of the
compound and its subsequent conversion into sound, durable extrusions of
good surface finish and mechanical strength, as assessed by the
requirements of this specification.
Profile Properties
Appearance and Finish
The color of the profile shall be uniform and the color of all profiles in a
system shall be uniform. The profile shall be free from foreign bodies, cracks
or sink marks when viewed by normal corrected vision at 90o to the surface
and at a distance of 1 meter in normal diffused north light.
Dimensions and Weights
The profiles shall be straight such that the longitudinal axis of the profile,
as measured on the face surfaces, may deviate from the straight line by no
more than 1 mm per meter.
PART B 151
The cross section of the profile shall conform in shape and dimensions and
may deviate by no more than + 0.5mm; glazing channels and seal grooves
may deviate by not more than + 0.3mm. The weight of the profile per
meter shall not be more than 5% below the nominal value.
Window properties
U-Value: The total Uw–U value of complete window shall be 3.3W/m2K
Resistance to wind load:
All load bearing members shall be adequately reinforced so as to resist the wind
load requirements of IS875: Part 3. Calculations shall be submitted for all
window designs.
AIR Tightness:
The air in filtration for windows shall not exceed 1 liters/second m2 @
75Pa for both positive and negative pressures (certified for use in air
conditioned buildings)
Water Tightness:
The water penetration for windows shall be minimum 15 minutes @ 150 Pa as
per AS 4420.5.
Installation of Frame
i. Before installation the Installation Team is to make sure that the opening has
been prepared and any repair work has been carried out. Allow a 5mm gap
between the frame and the opening. The new window shall be set in the
prepared opening. Allow for suitable packing blocks.
ii. The window shall be fixed into the aperture, by drilling and fixing through the
outer frame, to the existing structure using ‘Fischer’ fixings, F8 S type bolts.
iii. The fixings shall be no less than 150 mm from corners or transoms/mullions and
at no more than 600mm centers.
iv. When the frame is securely fixed in position then fit glass and glazing beads.
Allow for any necessary glazing blocks and glass lock devices.
v. Check windows for correct operation before proceeding with making good.
vi. No fixings are to penetrate the drainage channels.
vii. The windows shall be first treated with Polyurethane Foam (P U Foam) to
enhance insulation against heat and Noise. The gap between masonry and the
frame is to be filled with Neutral Cure Silicon (exposed to sun surface) and/or
Acrylic Sealant (only for the internal surface). The windows shall be first treated
with Polyurethane Foam (PU Foam) to enhance insulation against heat and
Noise.
viii. The silicone joints should be covered with Architraves/trims as per direction of
Engineer-in-charge.
PART B 152
Making Good
i) Making good to the external surface of the window frame and finish with a
compatible approved low modular silicone sealant to BS5889. All trims and
quadrants are to be approved by the Engineer-in-Charge prior to fixing.
ii) Allow for making good any disturbed plaster, brick work and decorations
internally and externally including color wash to brick work.
iii) Clean off excess material and check fittings and gearing.
iv) Leave installation clean and in good working order.
GENERAL ITEMS
i) This specification is to be read in conjunction with any other relevant documents
and drawings.
ii) Sizes are not to be scaled from any drawings or sketches but should be
measured on site prior to manufacture.
Window Accessories
i) Window should be designed and reinforced such that it can with stand the wind
load requirements by providing suitable strengthening accessories.
ii) The window shall meet the requirements of water tightness
Trims shall be used to cover the window to masonry joints
Window Hard ware
i) All slider door/windows are to be provided with multi point locking
arrangement with/without key locking facility as per the requirement. The
hardware shall be provided as per preferred list attached. The slider locking
mechanism handles are of projected/flush type.
ii) Casement window friction stays are to be of G-U or Securistyle or equivalent
make of appropriate size and weight bearing capacity, made of SS 304. The
stack height of friction stay is to be 16+0.5 mm.
iii) The casement windows are to be provided with multi point locking mechanism
of shall be provided as per preferred list attached.
Guarantee Bond:
The Contractor shall submit Guarantee Bond as per Proforma given in the
tender document. In addition, 5% (five percent) of the cost of this item of work
shall be retained as security deposit and the amount so withheld would be
released after Five years from the date after the expiry of maintenance period
prescribed in the contract, if the performance of the work done is found
satisfactory. If any defect is noticed during the guarantee period, it shall be
rectified by the contractor along with any incidental repairs to structure,
flooring, finishing, fixtures and any other related damaged work within fifteen
days of receipt of intimation of such defects in the work. If the defects pointed
out are not attended to within the specified period, the same shall be got done
from another agency at the risk and cost of the contractor and the cost of
attending such repairs shall be deducted from any dues payable to the
contractors.
PART B 153
14. FOUNDATION
a. The Contractor/Agency has to conduct the subsurface soil investigation
through an approved agency/institution, indicating vertical sections of the
strata, testing of soil samples on the site and in a laboratory for determining
shear strength parameters, bearing capacity of the soil, permeability, index
properties, water table, compressibility characteristics, swelling properties
type & classification of soil and other geophysical information in the field to
decide economical & sound foundation type.
b. Number of Trial Pits and Borings
At least one Bore hole for each block should be tested. Cone penetration tests
may be performed at every 50 m by dividing the area in a grid pattern and
number of bore holes or trial pits decided by examining the variation in the
penetration value curves
c. Depth of Exploration:
(i) The bore holes shall be made upto the required depths as per IS: 1892
(Latest Version)
(ii) In weak soils, the exploration should be continued to a depth at which the
loads can be sustained without undesirable settlement and shear failure.
(iii) Water level in the bore shall be determined in accordance with, IS : 6935
(Latest Version)
d. The cement concrete foundation (plain or reinforced) shall be designed in
accordance with IS 456 (Latest Version).
e. Masonry structures (foundation & superstructure) shall be designed in
accordance with IS 1905 (Latest Version).
f. Design Considerations for Spread or Strip foundation shall be as per I.S. 1080
(Latest Version).
15. Seismic considerations
a. Dynamic analysis shall be performed on the latest version of the STAAD PRO
model/ETAB/model considering the site of work falling under Zone II.
Dynamic analysis, if required, shall be performed by the Response Spectrum
method using the design spectrum specified under the relevant clause of IS code
1893 (Latest Version). RCC building frame system shall be designed and
detailed to provide ductile behaviour and shall comply with the requirements
given in IS 4326 and IS 13920. In the buildings with a Dual frame system, the
RCC frame, as well as the shear walls, shall be designed and detailed to provide
ductile behaviour and comply with the requirements given in IS 4326 and IS
13920.
b. Soft storey, if any, in the structure shall be treated as per the relevant clause of IS
1893 (Latest Version).
c. Time period of the structure shall be taken as per the relevant clause of IS 1893
(Latest Version)
PART B 155
d. Torsional forces in the structure arising out of mass or stiffness irregularity shall
be dealt as per relevant clause of IS 1893 (Latest Version)
e. For underground structures and foundations at depths of 30 m or below, the
design horizontal acceleration spectrum value shall be taken as half the value as
comes out as per relevant clause of IS 1893 part I (Latest Version). For structures
and foundations placed between the ground level and 30m depth, the design
horizontal acceleration spectrum value shall be linearly interpolated between
Ah and 0.5 Ah, where Ah is as specified in relevant clause IS 1893 (part-1)(Latest
Version). The design acceleration spectrum for vertical motions, when required,
may be taken as two-thirds of the design horizontal acceleration spectrum
specified.
f. To perform well in earthquake, the building shall be of simple & regular
configuration and of adequate lateral strength, stiffness and ductility. The
building shall be considered as irregular, if at least one of the conditions given
in Tables 4 & 5, of IS 1893 (part1) (Latest Version) is applicable.
g. Vertical cantilever projections like RCC parapets, Tanks, etc. and others attached
to the buildings projecting above the roof, shall be designed and checked for
stability for five times the design horizontal seismic coefficient A as specified in
relevant clause of IS 1893 (part1)(Latest Version). In the analysis of the building,
the weight of these projecting elements will be lumped with the roof weight.
The increased design forces specified are only for designing the projecting parts
and their connections with the main structures. For the design of the main
structure, such increase need not be considered.
16. Separation Between adjacent buildings:
Two adjacent buildings or two adjacent units of the same building with
separation Gap in between shall be separated by a distance equal to the amount
R times the sum of the calculated storey displacements calculated as per
relevant clause of IS 1893 (part-1) (Latest Version) each of them, to avoid
damaging contact when the two units deflect towards each other. When floor
levels of two similar adjacent units or buildings are at the same elevation levels,
factor R in this requirement may be replaced by R/2.In addition due allowance
for Thermal Expansion shall also be made.
17. Proof checking: Architectural drawings are issued by the Engineer in Charge.
The contractor shall design and submit the complete structural drawings,
calculations, soft copies on CDs and two set hard copies for proof checking.
Proof check to be got done from any one of the Government Institute. (i) IIT
Madras, Chennai (ii) NIT, Trichy (iii) NIT, Surathkal, (iv) IISC, Bengaluru, (v)
NIT, Warangal(vi) Andhra University, Visakhapatnam, (vii) JNTU,
Hyderabad (viii) JNTU Kakinada (ix) IIT, Tirupati or any other Engineering
Colleges of repute as per approval of Engineer-in-charge. After getting the
proof checking done the contractor shall submit corrected and faired structural
drawings in two set soft copies on CDs and eight set hard copies. The
consultancy fees for proof checking shall be borne by the contractor.
PART B 156
The following certificate is to be submitted along with the structural design before
acceptance of competent authority.
1. It is to certify that the structural design and drawings including safety from
natural hazards like seismic, wind, fire etc., shall be prepared by duly qualified
Structural Engineer as per norms prescribed in NBC/B.I.S/I.R.C./
APPLICABLE RECOGNISED CODES/STANDARDS.
2. Further to certify that the structural Consultant hired by us for carrying out the
structural design shall have experience as mentioned below:
a) Faculty at any reputed Government Engineering College like
IIT/NIT etc.
Or
b) Under the panel list of CDO/CPWD (mention as the case may be)
Or
c) The structural consultant will have at least a degree of M.Tech
(Structure) or equivalent and has got an experience of 10 years or more
in the field of structural design of similar nature of works. Documents in
support of the above will be submitted before proceeding with the
design work for approval of the department.
d) The work will be executed as per the particular specifications forming
part of the tender/agreement.
Address ------------------------
PART B 158
Sl. Numbers
Equipment
No. (Minimum)
23. Pruning Rods 2kg weight length 40 cm and ramming face 25 2 Nos.
Sqm.
24. Extra Bottom plates for 15 cm cube mould 6 nos.
25. Concrete temperature measuring thermometer with Brass 1 Nos.
protection sheath 0- 100 degree centigrade
26. Mortar Cube vibrator 1 No.
27. Iron Weight of 5 kg, 2 kg, 1 kg, 500 gm, 200 gm, 100 gm 1 No. each
28. Brass Weight of 50 gm, 20 gm, 10 gm, 5 gm, 2 gm, 1 gm 1 No. each
29. Hammer 1lb& 2lb 2 Nos. each
30. Soil Testing Equipment. As per requirement & as
decided by Engineer-in-
Charge.
31. Bituminous Road-Testing Equipment. As per requirement & as
decided by Engineer-in-
Charge.
32. Any other equipment for site tests as outlined in BIS and as As per requirement
directed by the Engineer-in-charge.
33. Tower Crane, Boom Crane of sufficient capacity As per requirement
Note:
1. The contractor has to establish within 21 days from the award of work a field laboratory
at site including all necessary equipments and skilled manpower for the Field Tests as
indicated in the tender document this own cost to have proper quality control.
Rs.5,000/-per day shall be recovered from the contractor for any delay beyond the
specified period. If contractor fails to establish lab within additional period of 15 days,
the Engineer in charge shall initiate action as deemed fit under relevant clauses of the
agreement.
2. A site laboratory with temporary structure of minimum 25 sqm area may be fabricated
at site by the contractor for accommodating above instruments and for conducting of
various tests for which no extra payment shall be made to the contractor.
3. One sample keeping room of minimum area of 20 sqm should also be fabricated at site
for keeping various material brought by the contractor at site and approved by the
Engineer-in-charge. No extra payment on account of this shall be made to the
contractor.
4. All the above structures should be decent looking and shall be fabricated as per
direction of Engineer-in-charge.
5. All the above structure shall be demolished after completion of work and the
dismantled material shall be the property of the contractor.
Third party quality assurance by technical team of any reputed institution such as
NCCBM/CBRI/IIT Chennai and like will be done and the report submitted by the
quality assurance team shall be communicated to the contractor by the Engineer-in-
charge. The contractor has to comply / rectify the defects/ shortcomings pointed out by
the quality assurance team at his own cost within the time specified by Engineer-in-
charge.
PART B 160
(TABLE – 2)
PLANT AND EQUIPMENT REQUIRED TO BE OWNED / TAKEN ON LEASE
BY THE CONTRACTOR
Sl.No. Equipment Numbers (Minimum)
1 Self-loading concrete mixer with digital print facility 1
of capacity not less than 1.00 cum per batch.
2 Excavator cum loader (JCB 3D model or equivalent) 1 No.
3 Compressor machine minimum 200 cfm with rock As per requirement and as
decided by Engineer-In-
breaker
charge.
4 DG set of capacity as per requirement 1
5 Needle Vibrators. 4
6 Plate Vibrators. 2
7 Reinforcement bending machine. 2
8 Reinforcement cutting machine. 2
9 Power driven earth rammer (Soil compactor). 2
10 Total station. 1
11 Auto level & staff. 1
12 Welding machine 400 Amere 2 Nos.
13 Tractor with trolley. 1
14 Water tanker. 2
15 Screener for coarse sand and fine sand 5
16 Centrifugal Mono block water pump minimum 3
Capacity 2 HP
17 Centering & Shuttering Minimum 1,000 Sqm
18 Double Scaffolding and staging materials As per requirement and as
decided by Engineer-In-
charge.
19 Floor grinding / polishing machines 2
20 Granite cutting machine 2
21 Ceramic / Vitrified tile cutting machine 2
22 Granite land polishing machine 2
23 Any other machinery required for completion of the As per requirement and as
work as per decision of Engineer-in-Charge. decided by Engineer-In-
charge.
Note:
(i) The above list is only indicative and not exhaustive.
The above plant and equipment are to be brought to the site within 60 days from the date of
issue of the Commencement order, failing which, a penalty at Rs.5,000/- per day delay in
the mobilization of equipment will be levied on the agency. Such penalty levied will be
recovered from the immediate next RA bill of the contractor. However, if the work is
completed within the stipulated date of completion, then the amount recovered will be
refunded without any interest payment.
PART B 161
The decision of the Engineer-in-charge with regard to nature and cause of defect
shall be final and binding on Guarantor.
During this period of guarantee, the guarantor shall make good all defects and
in case of any defect being found render the building water proof to the satisfaction of
the Engineer-In-Charge calling upon him to rectify the defects failing which the work
shall be got done by the Department by some other contractor at the Guarantor’s cost
and risk. The decision of the Engineer-in-charge as to the cost payable by the Guarantor
shall be final and binding.
That if the guarantor fails to execute the water proofing or commits breach there
under, then the guarantor will indemnify the principal and his successor against all
loss, damage, cost expense or otherwise which may be incurred by him by reason of
any default on the part of the GUARANTOR in performance and observance of this
supplementary agreement. As to the amount of loss and/or damage and / or cost
incurred by the Government, the decision of the Engineer-in-charge will be final and
binding on both the parties.
IN WITNESS WHEREOF these presents have been executed by the obligator
.......................and ........................................ by ................................. for and on behalf of the
PRESIDENT OF INDIA on the day, month and year first above written.
1. ................................................ 2.
...........................................
1. ............................................... 2.
..........................................
PART B 162
1. ................................................... 2. ....................................
PART B 163
Mines & Minerals - Amendment to the Rule 10 of the Andhra Pradesh Minor Mineral
Concession Rules, 1966 Orders - issued.
--------------------------------------------------------------------------------------------------------------------
INDUSTRIES AND COMMERCE (M.II) DEPARTMENT
G.O.MS.No. 11 Dated: 11-02-2020
Read the following:
1. G.O.Ms.No.198, Industries & Commerce (M.I) Dept., dt:13.08.2009.
2. GSR No.423 (E), dt: l0.02.2015 from the Ministry of Mines, Govt. of India, New
Delhi.
3. G.O.Ms.No.100, Industries & Commerce (M.II) Dept., dt:31.10.2015.
4. G.O.Ms.No.105, Industries & Commerce (M.II) Dept., dt:13.11.2015.
5. G.O.Ms.No.38, Industries & Commerce (M.II) Dept., dt:17.03.2016.
6. G.O.Ms.No.156, Industries & Commerce (M.II) Dept., dt:03.11.2016.
7. G.O.Ms.No.131, Industries & Commerce (M.II) Dept., dt:04.10.2017.
8. G.O.Ms.No.18, Industries & Commerce (M.II) Dept., dt:29.01.2018.
9. G.O.Ms.No.28, Industries & Commerce (M.II) Dept., dt:17.04.2018.
10. G.O.Ms.No.49, Industries & Commerce (M.II) Dept., dt:21.02.2019.
11. Proposal from the Director of Mines & Geology, vide e-file No: INC04-
17021(34)/1/2019-PLANNING SEC-DMG received by the Government on dt.
11.12.2019
***
O R D E R:
After careful examination of the proposal received from the Director of Mines &
Geology, Andhra Pradesh, Ibrahimpatnam in the letter 11th read above, the
Government hereby decided to amend the Rule 10 of Andhra Pradesh Minor Mineral
Concession Rules, 1966 for enhancing the existing Seigniorage fee and Dead Rent in
respect of Minor Minerals.
2. The following notification will be published in the Extra-ordinary issue of the
Andhra Pradesh Gazette, dated: 11.02.2020.
NOTIFICATION
In exercise of the powers conferred by sub-section (1) of section 15 of the Mines
& Minerals (Development and Regulation) Act, 1957 (Central Act 67 of 1957), the
Governor of Andhra Pradesh hereby makes the following amendments to the Andhra
Pradesh Minor Mineral Concession Rules, 1966 issued in G.O.Ms.No.1172, Industries
and Commerce Department, dated. 04.09.1967 and subsequent amended from. time to
time.
AMENDMENT
In the said rules, under Rule 10 for Schedules I and II, the following shall be
substituted, namely
PART B 164
"SCHEDULE-I"
RATES OF SEIGNIORAGE FEE
iv. Colour Granite of other varieties M3/ Rs.2700 / Rs.2470 Rs.2300 Rs.1150
MT Rs.985 / / /
(Rs. Two Rs.900 Rs.835 Rs.420
Thousan (Rs. (Rs. (Rs. One
d Seven Two Two Thousan
Hundred Thousa Thousa d One
/ Rs. nd Four nd Hundre
Nine Hundre Three d Fifty /
Hundred d Hundr Rs. Four
Eighty- Seventy ed / Hundre
Five) / Rs. Rs. d
Nine Eight Twenty)
Hundre Hundr
d) ed and
Thirty-
Five)
v. Kuppam Grey Granite available M3/ Rs.1925 / Rs.1650 Rs.1375 Rs.1100
in Santhipuram & Ramakuppam MT Rs.700 / / /
mandals of Chittoor District (Rs. One Rs.600 Rs.500 Rs.400
Thousan (Rs. (Rs. (Rs. One
d Nine One One Thousan
Hundred Thousa Thousa d One
Twenty- nd Six nd and Hundre
Five / Rs. Hundre Three d / Rs.
Seven d Fifty Hundr Four
Hundred / Rs. ed and Hundre
) Six Sevent d)
Hundre y-Five
d / Rs.
Five
Hundr
ed)
vi. Chittoor Colour Granite (Other M3/ Rs.1925 / Rs.1650 Rs.1375 Rs.1100
than Silver-waves, Madanapalli MT Rs.700 / / /
white and Iscon white) (Rs. One Rs.600 Rs.500 Rs.400
Thousan (Rs. (Rs. (Rs. One
d Nine One One Thousan
Hundred Thousa Thousa d One
Twenty- nd Six nd and Hundre
Five / Rs. Hundre Three d / Rs.
Seven d Fifty Hundr Four
Hundred / Rs. ed and Hundre
) Six Sevent d)
Hundre y-Five
d / Rs.
Five
Hundr
ed)
PART B 167
SCHEDULE-II
RATES OF DEAD RENT
S. Name of the Minor Mineral Rate of Dead Rent
No. per hectare per
annum (In Rupees)
1 Black Galaxy Granite and Black Granite Rs. 1,30,000/-
(Rs. One Lakh
Thirty thousand)
2 All Colour Granite varieties Rs. 1,30,000/-
(Rs. One Lakh
Thirty Thousand)
3 Limestone other than classified as major minerals used for Rs. 65,000/-
lime burning for Building construction purpose, marble, (Rs. Sixty-Five
boulders, building stone including stone used for Road Thousand)
Metal, Ballast, Manufactured sand, concrete & other
construction purpose, Shale, Slate & phyllites, Mosaic
Chips, Fullers Earth/ Bentonite &Dimensional Stone Used
for Cubes and kerbs
4 Gravel, Morrum, Ordinary Earth, shingle, Limestone Slabs Rs. 52,000/-
used for flooring purpose Limekankar, Chalcedonypebbles (Rs. Fifty Two
used in the building purpose Limeshell for burning used Thousand)
for building purpose and Rehmati.
5 Barytes and Laterite Rs. 26,000/-
(Rs. Twenty Six
Thousand )
6 Agate, Corundum, Diaspore and fluorite Rs. 20,000/-
(Rs. Twenty
Thousand )
7 Mica Rs. 15,000/-
(Rs. Fifteen
Thousand )
8 All minor minerals which are not covered under Serial Rs. 20,000/-
number 1 to 7 above. (Rs. Twenty
Thousand )
PART B 169
4. This order issues with the concurrence of Finance Department vide their U.O No.
FMUOASD(IC)/. 2019-FMU-IIEIC, dt. 09.01.2020 (computer No 1063684)
K. RAMGOPAL
PRINCIPAL SECRETARY TO GOVERNMENT
(MINES)
To
1. The Commissioner of Printing , Stationary & Store purchase (Ptg. Wing),
Vijayawada. (He is requested to publish the above notification in the Extra-
ordinary issue of Andhra Pradesh, and arrange to send 1000 copies of the same
to Govt. Ind. & Com. (M.II) Department).
2. The Director of Mines & Geology, Andhra Pradesh, Ibrahimpatnam.
3. The Chief Executive Officer, SERP, Vijayawada.
4. All the Joint Director/ Deputy Director / Asst. Director of Mines & Geology
through the Director of Mines & Geology, Ibrahimpatnam.
Copy to:
1. The Secretary to Govt. Ministry of Mines, Govt. of India, Shastry Bhawan, New
Delhi.
2. The Law Department / The Finance Department.
3. The P.S to Minister for Mines & Geology. / The PS to Prl. Secretary to Govt,
(Mines).
4. SF/SC (e-file NO. INC04-17021(34)/1/2019-PLANING SEC-DMG, Comp. No.
1052464).
Note:
Rates of Seigniorage fee mentioned above in Schedule I & II is for guidance
only and Royalty / Seigniorage fee, DMF, MERIT etc., shall be deducted from the
running / final bills of Contractor as per the updated Seigniorage fee intimated by
the Industries and commerce (M.I) department, Government of Andhra Pradesh,
from time to time and nothing extra shall be payable in this regard and no claim in
this regard shall be entertained.
PART B 170
PART B 171
ABSTRACT
INDUSTRIES&COMMERCE(M.III)DEPARTMENT
G.O.MS.No.42 Dated: 07-06-2021
Read the following;
1. G.O.Ms.No.29,Ind.&Com.(Mines-II)Dept.dated15.02.2017
2. G.O.Ms.No.21,Ind.&Com.(Mines-III)Dept.dated25.03.2021
3. FromtheDirectorofMines&Geology,singlefileNo:4072/P/2021
****
ORDER:
Government, vide G.O.1st read above, have included a pre-emption clause to direct
the lessees to sell minerals to the processing industries duly paying the Consideration
Amount in addition to Seigniorage Fee, Contribution to DMF and MERIT to the State
Government.
2. In the G.O., 2nd read above, Government have ordered that the Silica Sand lease
holders shall also pay Consideration Amount of Rs.212/- per ton to the State
Government in addition to the Seigniorage Fee, DMF and MERIT and to use the
collected fund for the purposes as specified therein.
3. The DM&G, AP., in the single file 3rd read above, while referring to the
recommendations of the State Level Core Committee and keeping in view
thesuggestionsmadeduringreviewmeetingsonMineralRevenuereceiptsandPolicyaspe
ctsofDepartmentofMines&Geology,hasrequestedtheGovernmenttoissueofnecessaryor
dersforlevyofconsiderationamount,onthesimilarlinesofSilicaSandordersissuedvideG
O2ndreadabove,onthelease holders in addition to the Seigniorage Fee, DMF and
MERIT, duly fixing it as one time of Seigniorage fee for all minor minerals other than
granite and 0.5 time of Seigniorage fee for granite, since it is high value
mineral(Seigniorage fee ranges from Rs.3,452 to Rs.4,600 per cum) irrespective of the
mode of grant of leases.
5. The Director of Mines & Geology, A.P., shall take necessary action accordingly in
the matter.
(BYORDERANDINTHENAMEOFTHEGOVERNOROFANDHRAPRADESH)
GOPAL KRISHNA
DWIVEDIPRINCIPALSECRETARY
TO GOVERNMENT(M)
To
The Director of Mines & Geology, AP, Ibrahimpatnam, Vijayawada.(w.e.file) All the
District Collectors in the State.
The VC&MD, M/s APMDC Ltd, Kanur,
Vijayawada. Copy to:
The OSD to Hon’ble Minister (Mines &
Geology) The PS to Prl. Secy. To Hon’ble CM
The PS to Secretary to Govt (Mines)The Finance Department SF
/SC(CompNo:1420114)
//FORWARDEDBYORDER//
SECTIONOFFICER
PART B 173
Standard Operating Procedures (SOPs) and Guidelines for Construction Sites for
COVID-19 Outbreak
The agency shall follow the below mentioned standard operating procedures and
guidelines scrupulously at the construction site to contain the outbreak of COVID-
19, failure to adhere to the SoPs issued by CPWD and other orders & Guidelines
issued by Various Governments(Govt. of India and/or Govt. of AP and/or Dist.
Administration or Local Govt.) from Time to Time will result in levy of
nonrefundable penalty of Rs.5000/- per day on the agency by Engineer-in-charge
which shall be final and binding on the contractor. The quoted rates shall inclusive
of all such required measures and materials like Soaps, Detergents, Sanitizers,
Disinfectants, Masks, Gloves and other personal protection equipment’s to contain
COVID-19 and nothing extra shall be paid. All such penalties shall be recovered
from the respective Running account bills of the contractor.
In response to COVID-19 outbreak, the following Standard Operating Procedures
(SOPs) and guidelines to ensure safety of construction site workers are issued for field
units. In addition to trained Supervisor (s), a Site Safety Representative (SSR) will be
deployed at every site, to ensure the safety guideline is followed. Necessary trainings
will be given in advance to Supervisors and SSRs, so that they can train the workers
further.
a. General guidelines – Applicable to All
1. The workers coming from outside will be required to self-declare their health
profile as per Annexure 1 and shall be quarantined for a period of at least 15
days. Mandatory
2. Thermal Scanning of everyone entering and exiting a construction site will be
done for fever with thermal scanners. if anyone leaves and re-enters the site
during the shift, re-screening of the individual will be done prior to re-entry into
the work site.
3. PPE and Other material requirement shall be documented as per Annexure 2.
4. Provision for hand wash & sanitizer (touch free recommended) will be made at
all entry and exit points and common areas (including at distant locations like
higher floors). Everyone will be required to wash & sanitize his/her hands
before entering the site and using PPEs. Same procedure to be followed after
removing PPEs and exiting the premise. Sufficient quantities of all the items
should be available at the site.
5. All Protocol including Emergency Response will be laid out. Periodic tailgate
sessions will be arranged to review site protocols in view of highly dynamic
scenario ensuring social distancing norms. During these sessions, everyone
including workers will be informed about the safety guidelines and important
updates. Necessary arrangements for announcements shall be made at every
site.
6. Mandatory use of PPEs (face mask, hand gloves and other as applicable) by
everyone entering the premise. Re-usable PPEs should be thoroughly cleaned
and should not be shared with others.
7. Entire construction site including site office, labour camp, canteens, pathways,
toilets, and entry / exit gates will be disinfected on daily basis. Housekeeping
team should be provided with necessary PPEs.
8. There will be total Ban on non-essential visitors at sites (including from Head
office staff, consultants etc.).
9. There will be strict ban on Gutka, Tambaku, Paan etc. on site and spitting shall
be strictly prohibited.
10. Food should be consumed at designated areas only ensuring social distancing.
11. Common sitting arrangements should be removed.
12. Post lunch, waste should be disposed by individual in designated bins and area
should remain clean.
13. Areas with a probability of bigger gathering, for e.g., cleaning area, toilets etc.
should be identified and all arrangements should be made to ensure social
distancing.
PART B 174
14. A doctor will be present periodically (at least once a week) at site on allotted
time for any medical assistance.
15. Appropriate signage at construction site spelling out safety practices in the
language which is understood by all.
16. Hospital/clinics in the nearby area, which are authorized to treat COVID-'19
patients, should be identified and list should be available at Site all the time.
17. For any confusion, clarification and update, everyone should approach
designated authority or rely on authentic source.
18. Rumors shall be discouraged and offenders be warned.
19. An isolation room shall be created at site.
b. Guidelines for workers:
1. On day 0, before resuming the work on site post lockdown period, mandatory
medical check-up will be arranged for all workers. The workers coming from
outside will be quarantined for a period of at least 15 days. Only medically fit
workers will be deployed at site and medical assistance will be arranged for
unfit workers. Medical checkup camp should be arranged every month.
2. The labours staying at site will not be allowed to go outside. All the essential
items will be made available to labours at site only. If necessary, the workers can
go out wearing PPEs, after informing supervisor. Similarly, no outside labour
will be allowed at site without following proper procedure and instructions.
3. Start time on site will be staggered to avoid congestion at the entry gates.
Number of workers working at a particular time / place will be reduced by
making arrangements for different shifts / areas. Accordingly, additional staff
such as security guards, supervisors etc. will be deployed.
4. As in most cases, workers reside at the Sites, hence there is no need for any
travel. For Workers staying outside, (which are always nearby) special
transportation facility will be arranged without any dependency on the public
transport system.
5. During attendance, training and other sessions, social distancing guidelines will
be followed along with provision of no {ouch attendance.
6. Workers should not shake hands when greeting others and while working on
the site.
7. Workers shall avoid contact with sick people and avoid going to site if they are
feeling sick, have fever, cough or shortness of breath. In such case, supervisor
should be informed immediately.
8. Workers with such symptoms should not come to site and should be placed in
isolation and medical assistance will be provided on immediate basis.
9. Mandatorily wear face masks while working on site. While not wearing masks,
worker shall cover his mouth and nose with tissues.
10. Cough/sneeze should be done in the crook of one's arm and your elbow.
11. Avoid large gatherings or meetings of 10 people or more. Stay at least 6 feet
away from others on job sites and in gatherings, meetings, and training sessions.
12. Not more than 214 persons (depending on size) will be allowed to travel in lifts
or hoists. Use of staircase for climbing should be encouraged.
13. Workers should clean hands frequently by washing them with soap and water
for at least 20 seconds. When hand washing isn't possible, alcohol based hand
sanitizer with greater than 60% ethanol or 70% isopropanol should be used.
14. Workers should not share their belongings like food, water bottles, utensils,
mobile phones etc. with others.
15. The utensils should be washed properly post use at designated place.
16. Post work, workers should change their clothes before leaving the site and
clothing should not be shook out.
17. Avoid touching eyes, nose, or mouth with unwashed hands.
c. Guidelines for Material, Tools. Machinery, Vehicles etc.
1. Wipe down interiors and door handle of machines or construction vehicles, the
handles of equipment and tools that are shared, with disinfectant prior to using.
2. Non-ouch waste bin with disposable garbage bag should be installed for waste
collection at all common access areas.
PART B 175
Sl.
Designation Responsibility
No.
1 CPWD Nodal officer To coordinate efforts on behalf of Engineer in
as Designated by Charge and ensure compliance of these SOPs. He
Engineer in Charge shall send a daily confirmation of compliance of
SOPs.
2 Project Overall responsibility of ensuring compliance of
Manager of procedure and precautions in SOP.
Contractor To submit daily compliance report to CPWD Nodal
officer
To designate a senior person as COVID Marshal
and form a team under him
3 COVID To exclusively look after the implementation of all
Marshal the precautions and procedure at work site and
(Nodal labour camps
Officer) To intimate daily requirement of PPEs, sanitizers,
disinfectants etc in their respective sections
Regular attendance of workers to ensure no one
leaves the site
Permission from local authorities
Ensuring Timely payment to workers/ staff
PART B 176
Annexure 1
COVID-l9 (Coronavirus) Exposure Questionnaire for New workmen
Name: Native (State, District/City, Village)
Age:
Gender:
Please answer the following questions with as much detail as possible:
1. Location/Travel Declaration
a. Please provide your locations/travel patterns over the past 14 days in Table
below:
Country City/Village Date Arrived/Since Date departed
when you have been
in the location
2. Any cases of COVID-'19 in your in the locations where you have been for last 14
days?
YES NO
3. Are you, or have you been in close contact with anyone who has been quarantined
or who has been diagnosed with novel coronavirus (SARS-CoV-2/COVID-19)? If
yes, please provide details.
YES NO
4. Have you ever been quarantined due to a possible exposure to novel coronavirus
(SARS-CoV-2/COVID-19)? If yes, please provide dates and locations.
YES NO
5. Have you experienced any of the following symptoms within the last 14 days?
. Any fever
. Cough
. Shortness of breath
. Malaise (flu-like tiredness)
. Rhinorrhoea (mucus discharge from the nose)
. Sore throat
. Gastro-intestinal symptoms such as nausea, vomiting and/or diarrhoea
If yes, to any of these, please indicate which and provide full information.
6. Are you currently in good health?
YES NO
Declaration
I confirm that the answers I have given are, to the best of my knowledge, true, and that
I have not withheld any material information that may influence the assessment or
acceptance of this application.
I agree that this form will constitute part of my application for insurance(s) and that
failure to disclose any material fact known to me may invalidate my insurance(s).
Signature
Date
Time
Witness
PART B 177
Annexure 2
PPE and Other material requirement
Sl.
Material Description Brand Makes *
No.
A B Dinesh A B Dinesh
Areocon HIL
Bilt Bilt
Ecorex Ecorex
Fastbuilt Fastbuilt
Kncrete Koncrete
NCL NCL VEKA Ltd.
Nucon Green Way building materials
India Pvt. Ltd.
1 AAC Blocks
Renacon Renaatus Procon Pvt. Ltd.
Siporex SIPOREX
Xtralite Ultra Tech Cement Ltd
SMART BRIX M/s Smart Brix Infra
Technology Pvt. Ltd.,
Jaggaiahpet Mandal, Krishna
District, A.P. - 521175
Fusion Brand M/s Fusion Building Materials
(Vizag) Private Limited
PART B 179
Sl.
Material Description Brand Makes *
No.
Anutone Anutone Acoustics Ltd.
Himalyan Accoustics Himalyan Accoustics
Kanuf Knauf Gypsum India Pvt. Ltd.
2 Acoustic Insulation
Lloyd Insulation Lloyd Insulation (India) Ltd.
Saint Gobain Gyproc Saint Gobain Gyproc India
Twingerinsul U.P. Twiga fiber glass ltd.
Ardex endure Ardex endure
Actativ Bitumat Co Ltd Bitumat Co Ltd
polypropylene (APP) Ferrous crete Ferrous Crete (India) Pvt Ltd
3
Modified water proof Hydrotech ltd Hydrotech ltd
membrane Pidilite Pidilite industries
STP Shalimar tar products
Asian Tractor Premium Asian paint
emulsion
Berger (BISM) Berger Paints
4 Acrylic emulsion Dulux (Super Cover) ICI Dulux
Nerolac (Beauty Gold) Nerolac
SURFA M/s Surfa Coats (India) Pvt.,
Ltd., Bangalore
Apex (ACE) Asian Paints
Berger Berger
Dulux ICI duLux
Acrylic smooth
5 Nerolac Nerolac
exterior paint
Nippon Nippon
SURFA M/s Surfa Coats (India) Pvt.,
Ltd., Bangalore
Apex Duracast Asian Paints
Asian paints Asian Paints
Acrylic textured
6 Heritage Heritage Rajkamal Group
plaster
Nerolac Nerolac
Spectrum paints Spectrum paints Ltd.
Akzonobel Akzonobel
Asian paints Asian paints
Acrylic exterior
7 Berger Berger paints India ltd
Texture
Ebco Ebco
Nerolac Nerolac paints Ltd.
Asian Paints Asian Paints
CICO CICO Industries
Dunlop India Tyre & Rubber Co (India)
Ltd.
8 Adhesive
Finical Pidilite Industries
Proofex of Adhesive FOSROC India
Sika Sika India Pvt. Ltd
Vamorganic Vamorqanic Ltd.
PART B 180
Sl.
Material Description Brand Makes *
No.
AC-Tile Bond-N Apple Chemie(I) Pvt. Ltd
Ardex Endura/Gold Ardex Endura
star
Adhesive for AAC Ferrous Crete Ferrous Crete (India) Pvt Ltd
9
Block/Tiles Tile Adhesive Plus Berger Paints
Ultra tech Ultra tech cement ltd
Cool grills Cool grills, Pune
10 Air transfer grills Systemair India Systemair India Pvt Ltd.
Kartar Kartar valves private Ltd.
11 Air release valve Kirloskar Kirloskar brothers Ltd.,
RBM AFS Ltd
Bhoruka Bhoruka Aluminium Ltd.,
Hindalco Hindalco Industries Ltd..
Hydro Hydro Extrusion
Aluminium
INDAL Indian Aluminium Ltd.,
12 doors/windows
sections Jindal Jindal Aluminium Ltd,
Omalco Extrusion Omalco Extrusion Pvt Ltd.
Padmavati Exrusion Padmavath Extrusion Private
Ltd.
Bhoruka Bhoruka Aluminium Ltd.,
Define Define Overseas Pvt. Ltd.
Everite Everite Agencies
Hardima Hardima sales corporation
Aluminium system/ Jyothi Jyothi industries
Anodised Aluninium Kawneer Kawnear India
13
fittings for Schueco Schueco India Pvt. Ltd.,
doors/windows
Sigma Sigma Corporation
CROWN M/s Crown Industries
Global M/s Aluminium Udyog, New
Delhi (for non-ferrous metal
hardware)
Alpolic Alpolic
Alstone Alstone
Alstrong Alstrong
Alex panel M/s Alex Panels
Alucobond 3A composites India Pvt Ltd.
Aluminium Aludecor M/S Aludecor lamination Pvt
14
composite panels ltd.
Eurobond M/S Euro panel products Pvt
ltd.
Eurobond Eurobond pvt Ltd.
Hynadecor Hynadecor
Reynobond Reynobond
PART B 181
Sl.
Material Description Brand Makes *
No.
ALUTECH M/s Alutech Industries, New
Delhi
VIRGO M/s VIRGO Laminates Ltd.,
Chandigarh
MFE (MIVAN) (MIVAN)
Aluminium
15 MFS MFS
framework
S-form S-form
Anchor Anchor Ltd.
BOSCH BOSCH Ltd.
Canon Canon
Fischer Fischer India
Anchor/ SS Stone
Helfen Helfen Gmbh
16 Cladding Clamps/
Dash fasteners Hilti Hilti India Pvt. Ltd.
Nutech Nutech Concrete Products Pvt.
Ltd.
Trixel Axel India Pvt. Ltd.
Wurth Wuerth India Pvt. Ltd.
Bergar Berger paints India Ltd
Anti corrosive bit
17 Bituminous black Asian Paints
mastic paint
Shalimar Shalimar paints India Ltd.
Alu Alpha Alu Alpha India
Dorma Dorma India Pvt. Ltd.
Butt Hinges openable Dorset Dorset Industries Pvt. Ltd.
18
window shutters Earit Bihari Earit Bihari India Pvt. Ltd.
Hafele Hafele India Pvt. Ltd.
Helix Helix India
AMITEX AMITEX Enterprises, Delhi.
Eco green Flooring Jupiter Traders Bangalore.
Floor India Flooring India Company,
Bamboo Wood Panipat, Haryana.
19 Flooring and wall FLOSTO Tanks Devi Polymer Pvt. Ltd.,
paneling. Chennai.
VIVANTA VIVANTA Enterprises,
Mumbai.
EPITOME M/s Mutha Industries Pvt. Ltd.,
Mumbai
Ambuja Cement Ambuja Cements Ltd.
ACC ACC Cements Ltd
Bharathi Bharathi Cement Corporation
Ltd.
Cement
20 Birla Birla Corporation Ltd
OPC / PPC
Century Cement Birla Gold Cement
Chettinad Chettinad Cements Corporation
Ltd
Coromandal India Cements Ltd.
PART B 182
Sl.
Material Description Brand Makes *
No.
Dalmia Dalmia Cement Bharat Ltd.
Jaypee Cement Jaypee Cement Ltd
J.K. Cement J.K. Cement Pvt. Ltd.
Konark Cement Konark Cement
Maha Cement Myhome Industries Pvt. Ltd.
Penna Cement Penna Cement Industries Ltd.
Ramco Cement M/s Ramco Cement ltd.
Shree Cement Shree Cement
Ultra Tech Ultra Tech Cement Ltd
Zuari Zuari Cement Limited
Nagarjuna Cement M/s NCL Industries ltd.,
Secunderabad
NU VISTA / M/s NU Vista Ltd. (Formerly
INFRACEM M/s Emami Cements Limited)
SAGAR CEMENTS M/s SAGAR Cements Ltd.,
Hyderabad
Anjani M/s Anjani port land Cement
Ltd., Hyderabad
JSW M/s JSW Cement Ltd., Mumbai
Dazzle Dazzle Designer tiles Pvt Ltd
Eurocon Eurocon tiles india
Hindustan tiles Hindustan tiles, Ranchi Pune
NTC NTC Parking tiles
Cement Concrete NITCO NITCO Ltd
21
Parking Tiles Poddar Poddar Udyog
Ultra Ultra tile private Ltd
CEMTECH M/s Cemtech Tiles, Uppal,
Hyderabad
DEC M/s DEC Industries (P), Ltd.
Altek NCL Alltek & seccold Ltd.
Ardex Endura Ardex Endura India Pvt. Ltd.
Asian paints Asian paints Ltd
Berger Berger
Cement based wall
22 Birla Wall Care Birla Cements Ltd.,
putty
Ferrous Crete Ferrous Crete (India) Pvt. Ltd
J.K wall putty J.K. Cement Ltd
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
Bison Bison Group
23 Cement Board
Everest Everest Techno polis
Asian paints Asian Paints
Berger Berger paints India Ltd.
24 Cement Primer JK Primaxx JK Cement Ltd
SURFA M/s Surfa Coats (India) Pvt.,
Ltd., Bangalore
PART B 183
Sl.
Material Description Brand Makes *
No.
Kapilansh Kapilansh Dhattu Udyog (P)
Ltd.
NECO Jayaswal NECO Ltd.
Centrifugal Hubless
Raj (RPMF) Raj Pattern Makers and
25 Cast Iron Pipe &
Founders Pvt.,Ltd.
Fittings
SKF Singhaliorn Foundary Pvt.,Ltd.
BIC M/s Bengal Iron Corporation,
Kolkata
Electrosteel Electrosteel castings Ltd.
Centrifugally (Spun) Jindal Jindal saw Ltd.
26
cast Iran Kesoram Kesoram Industries ltd.
Lanco / Sripipes Electrosteel castings Ltd.
Bengal Iron Bengal Iron Corporation
Corporation
HEPCO HEPCO
Centrifugally Caste Kapilash Kapilash Dhatu Udyog (P) Ltd.
27
(Spun) Iron Soil Pipe Neco Jayaswal Neco Ltd
RPMF Raj Pattern Makers and
Founders Pvt. Ltd
SKF SKF industries
BASF BASF India Ltd.
Dr. Fixit Pidilite industries
Ferrous Crete Ferrous Crete (India) Pvt Ltd.
Fosroc Fosroc India
Latex shield 2K/Tank Berger Paints Ltd.
Chemical water shield PW
28
proofing system MC- Bauchemie MC- Bauchemie India Ltd.
Perma construction Aid Perma construction Aid Pvt Ltd
Sika Sika India
Smart Care Asian Paints Ltd.
Sunanda speciality Sunanda speciality coating Pvt
coating Ltd.
DURSBANTCT DE-NOCIL Ltd.
HILBAN Hindustan Insecticides Ltd.
NOBAN Chemtts Wets & Flows Pvt. Ltd
29 Chloropyriphos PIRAMID AMVAC AGRI RASAYAN Pvt.
Ltd.
Premise Agenda Bayer Ltd.
Sarups Pest Control Sarups Pest Control Ltd.
BURN BURN
IVS Indian Valves Private Ltd.
CI double flange
30 Kartar Kartar valves private Ltd.
sluice valve
Kirloskar Kirtoskar brothers Ltd.
Leader leader valves Ltd
PART B 184
Sl.
Material Description Brand Makes *
No.
RBM AF-S LL
Zoloto Zoloto Industries
Fluidtech Fluidtech
CI double flangad non
31 Kirloskar Kirloskar Brothers Ltd.
raturn valve
Zoloto Zoloto Industries
BIC Bengal iron corporation
HEPCO HEPCO India
Neco Jayaswal Neco Ltd..
32 CI Manhole cover
RPMF M/s Raj Pattern Makers &
Founders Pvt. Ltd.
SKF SKF Industries
Fischer Fischer India
Clamp, Rebar,
33 Hilti Hilti India Pvt.Ltd.
Chemical fastener
Wurth Wuerth
CERA M/s Cera Sanitaryware Ltd.
ESS Bathsense & Royal Asian Paints Ltd.
Hindware HSIL Ltd.
Jaquar Jaquar Group
34 C.P.Brass Fittings Johnson Prism Johnson Ltd.
KEROVIT M/s Kajaria Ceramic Limited
Kingston Kingston Brass India Pvt., Ltd.
MARC MARC Sanitation Pvt.Ltd.
Parryware Parryware Sanitaryware
Ashirwad Ashirwad PVC Pipes
Astral Astral Polytechnik Ltd..
Birla HIL Pipes HIL Ltd.
Finolex Finolex Industries Ltd.
Flowgard Flowgard
Prince Prince Pipes and finttings Ltd,
CPVC pipe and Supreme Supreme Industries Ltd.
35
fittings Truflo HIS Ltd.
SENTINI M/s Sentini Flopipes India Pvt.
Ltd, Hyderabad
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
SUDHAKAR M/s Sudhakar Irrigation
Systems Pvt., Ltd.
AKG M/s AKG Extrusions Pvt Ltd.,
Alu Alpha Alu Alpha India
Dorma Dorma India Pvt. Ltd.
36 Concealed tower bolt
Dorset Dorset Industries Pvt. Ltd.
Ingersolrand Ingersolrand (India) Ltd.
ACCO Proof ACC Cements Ltd
37 Damp Proof material
Asian Paints smart care Asian Paints Ltd.
PART B 185
Sl.
Material Description Brand Makes *
No.
damp proof
BASF BASF India Ltd.
CICO CICO Industries
Dr. Fixit Pidilite Industries
Duraseal Apurva India Pvt. Ltd.
Ferrous Crete Ferrous Crete (India) Pvt. Ltd.
Fosroc Fosroc Chemicals India Pvt. Ltd.
Impermo Snowcem Paints
MAPEI MAPEI Construction Products
India P Ltd
MYK MYK LATICRETE India Pvt.
Ltd.
PIDILITE Pidilite Industries
SIKA Sika India Pvt. Ltd.
Weather Coat Roof Berger Paints India Ltd.
Guard
Electro steel Electro steel
Jindal Jindal
38 DI Fittings Kapilansh Kapilansh
Keshoram Keshoram
Tata Ductura Tata Ductura
Electrosteel Electrosteel
Jindal Jindal
39 DI Pipes
Keshoram Keshoram
Tata Ductura Tata Ductura
Amstrong Amstrong flooring
Mikasa Real wood Grean Lam Industries
floors
Engineered wood
40 New wood Naw Wood India ltd
floor
Pergo Red floor India
Dura floor wemer GmbH
Werner
Amee Rubber Amee Rubber industries Pvt Ltd
Anand Anand NVI-I products (P) Ltd.,
Bohra Bohra rubber Pvt Ltd..
41 EPDM Gaskets
Hanu Hanu Industries
Roop Roop Polimers Ltd.,
Sl.
Material Description Brand Makes *
No.
CICO Poxy CICO Technologies Ltd.
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Fosroc Fosroc India
Shalibons Shalimar tar products
Ardex Endura Ardex Endura India Pvt. Ltd.
Asian epoxy Asian Paints
Berger Berger paints India Ltd.
Nerolac Nerolac
44 Epoxy Paint
Shalimar Shalimar paints India Ltd.
STP Ltd. Shalimar Tar Products
M/s Sunanda Specialty coatings
SUNANDA Pvt. Ltd., Mumbai
Ardex Endura Ardex Endura India Pvt. Ltd
BASF BASF India Ltd.
Epoxy tile joint
45 Ferrous Crete Ferrous Grete (India) Pvt. Ltd
cements
Fosroc Fosroc indd
Laticrete MYK Laticrete India
Dura Board HD100 Supreme Industries
Expansion Joint
46 DURAFILL Supreme Industries
Bitumen board
STP Shalimar Tar Products
Aerolite Andhra Polymers Pvt.
Ltd./Aarolite lndustnas Pvt.
Ltd.
Armstrong Armstrong Wond Indusvies
Diamond (GRG Ceiling Diamond International Inex Pvt.
Tiles) Ltd.
47 False Ceiling Griddsquare Gridsquare Ceilings
Gypframe steel British Gypsum
Knauf Knauf Gypsum India Pvt. Ltd.
Lloyd Lloyd Insulation (India } Ltd
Saint Gobain Saint Gobain Gyproc
DEC M/s DEC Industries (P) Ltd.,
Hyderabad
Aerolite Andhra Polymers Pvt.
Ltd./Aarolite Industries Pvt.
Ltd
Anutone Anutone Accoustics Ltd.
False ceilings
Members (Perimeter, Armstrong Amstrong World lndustries
48 Ceiling section, Gridsquare Gridsquare Ceilings
intermediates, angles Hunter Dougals Hunter Dougals
etc.,) Knauf Knauf Gypsum India Pvt. Ltd.
Saint Gobain Gyproc Saint Gobain Gyproc India
USG Boral USG Boral
DEC M/s DEC Industries (P) Ltd.,
PART B 187
Sl.
Material Description Brand Makes *
No.
Hyderabad
Access floor sytem Access Floor system
Hewetson Hewetson India
Kebao Inner Space (Distributors)
49 False Floor
PINNACLE PINNACLE
Unifloor Unifloor India Ltd.
Unitile Unitile office systems Pvt. Ltd.
Backers FS Backers FS
Dorma Dorma India Pvt. Ltd.
50 Fire Rated hardware Dorset Dorset Industries Pvt. Ltd.
Geze Geze GMBH
Ingersolrand Ingersolrand (India) Ltd.
Contra Flam / Saint Gobain India Pvt. Ltd.
Pyroswiss of Saint
Gobain
51 Fire rated glass Pilkinton Pilkinton India
Promat Promat Fire & Insulation (P)
Ltd.
Pyran of Schott Schott glass India Pvt. Ltd.
Akzonobel Dulex Akzonobel Paints
Asian paints Asian Paints
52 Fire retardant paint Htlti Hilti India Pvt. Ltd.
Jotun Jotun paints
STPL Ltd. STPL Ltd.
Atroflame Atroflame ltd.
Hilti Hilti India Pvt. Ltd.
53 Fire Smoke Seal Promat Promat Fire & Insulation (P)
Ltd.
Raven Raven Global
Saint Gobain Saint Gobain India Pvt. Ltd.
Asahi Asahi India Glass ltd.
Pilkinton Pilkinton India
54 Float Glass,
Modiguard Gujarat Guardian Ltd.
Gold Plus M/s Gold Plus Glass Industry
Ltd., New Delhi
Arco Arco valve Pvt ltd
IBP IBP industries
Float Valve (Ball
55 Leader Leader valve Ltd
valve)
Prayag Prayag Polymers Pvt Ltd.
Zoloto Zoloto industries
Dorma Donna lndia Pvt Ltd.
Floor spring (For non GEZE GEZE GmbH
56
DSR Items) Ingersolrand lngersolrand India Pvt Ltd
OZONE Ozone Hardware.
PART B 188
Sl.
Material Description Brand Makes *
No.
Bath sense Asian Paints
CERA CERA Sanitary ware Ltd.,
Hindware HSIL Ltd,
57 Flushing Cistern Jaquar Jaquar Group
Kohler Kohler
Parryware ROCA Bath Pvt. Ltd.,
Somany Somany
Concerned CE/SE’s will approve based on local
58 Fly ash cement bricks
availability.
Ambieance Ambieance
Cactus Cactus
Duroplast Duroplast Extrusion pvt ltd.
Jain doors Pvt. Ltd. Jain doors Pvt. Ltd.
FRP Door Frames &
59 Jayna Jain wood industries
shutters
Meena fibre glass Meena fibre glass
Polyline Polyline
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
Earl Bihari Earl Bihari Pvt. Ltd.
60 Friction stay hinges
KINLONG Kinlong lndustriss
Everlast Composites Everlast Composites Pvt.,Ltd.
Fibrocast Fibrocast FRP cover
61 FRP covers
manufacturer
Thermodrain Poly products (I) Pvt.,Ltd.
Bhushan Bhushan steel
Essar Essar Group
Galvalume sheet for JSW JSW
62 roofing, cladding,
Llyod metal craft Llyod Insulation
sandwich panel
Tata Blue Scope Tata Blue Scope
BIRLA AEROCON M/s HIL Ltd.
Jenco Jenco Group
63 Galvanising Karamtara Karamtara Engineering Pvt.,Ltd.
Steel liteS Galvanized Steel Ltd.
HB HB Industries
ICS Sgree samarth Englnears
Surya Surya Roshni Ltd.
64 G I Pipe fittings
TATA TATA Steel Ltd.,
Unik Unik malleable
Zoloto Zoloto Industfiea
HISSAR HISSAR
Jindal Jindal Pipes Ltd.,
65 G.I. Pipes
Surya Surya Roshni Ltd.
TATA TATA Steel Ltd.,
PART B 189
Sl.
Material Description Brand Makes *
No.
Zenith Zenith Birla (India) Ltd.
Classic Classic Hardware
Dorma Dorma India Pvt. Ltd.
Dorset Dorset Industries Pvt. Ltd.
Geze Geze GMBH
66 Glass door hardware Godrej Godrej
Hafele Hafele India Pvt. Ltd.
Kich Kich Architectural Products Ltd.
Ozone Ozone Hardware
Squash Squash glass doors
Birla White Birla Corportion Ltd.
Bisazza Bisazza Italy
Coral Coral tiles
Italia Tie italia mosaic Pvt Ltd
67 Glass mosaic tiles
JK White JK Cement ltd.
Mridul Mridut tiles
Paljadto Palladto Mosaics
PAVIT (Eco Tile) PAVIT Ceramics Pvt Ltd.
Aparna Vitero Tiles
AGL Asian Granite India Ltd.
CERA CERA Sanitaryware Ltd
Jonson Prism Jonson Ltd.
Kajaria Kajaria Ceramic Ltd.
NITCO NITCO Ltd.
Oasis M/s Oasis Vitrified Pvt.Ltd.
Orient Bell Orient Bell Ltd.
Glazed Ceramic tiles RAK RAK Ceramic India Pvt. Ltd.
68
(Also wall tiles)
Somany Somany Ceramic Ltd.
Varmora Granito Varmora Granite Granite Pvt.
Ltd.
Vitero Vitero Tiles Floor and Wall Tile
Manufactures India
Ultra Ultra Ltd.
NAVEEN M/s Murudeswar Ceramics
Ltd., Bangalore
Orient Bell Ltd M/s Orient Bell ltd
Ecovision Ecovision Industries Pvt ltd.
Mahesh GRC Mahesh Prefab Pvt Ltd.
69 GRC Jali & Tile Terrafirma Terrafirma GRC Industries
Unistone Unistone Interiors Pvt.,Ltd.
DEC M/s DEC Industries (P) Ltd.
GRP/SMC Panel AMITEX AMITEX Enterprises, Delhi.
70
Tank (New product in FLOSTO Tanks Devi Polymer Pvt., Ltd.,
PART B 190
Sl.
Material Description Brand Makes *
No.
the market Chennai.
performance is yet to PIPECO Tanks PIPECO Tanks
be established) VIVANTA VIVANTA Enterprises,
Mumbai.
Asian Paints - Smart Asian Paints Pvt. Ltd.
casre
Ardex Ardex Endura Adhesive India
Pvt. Ltd.
BASF BASF India Ltd.
CICO CICO Industries
Dr. Fixit Pidilite Industries
Ferrous Crete Ferrous Crete (India) Pvt. Ltd.
Fosroc GP2 FOSROC India
Fugabella, Porcelana Kerakoll India Pvt. Ltd.
Home shield super Berger Paints India Limited.
71 Grout grout
LATA POXY MYK LATICRETE India Pvt.
LTd.
MYK Schomburg MYK Arments Range of
products
SIKA Sika India Pvt.Ltd.
Weber Saint Gobain India Pvt. Ltd.
DEC ( Non Shrink M/s DEC Industries Pvt. Ltd.,
grout) Hyderabad
(Note: Subject to
statutory approvals)
AC-Grout-H1/RR Apple Chemie (I) Pvt. Ltd
Audco L&T Valves
Leader leader valves Ltd ,
72 Gun metal Valves
Sant Sant Valaves Pvt. Ltd.
Zoloto Zolota Industries
Armstrong Armstrong world Industries
Gyproc Saint Gobain Saint Gobain Gyprock India Ltd.
73 Gypsum Board
Lafarge Lafarge Gypsum India Pvt. Ltd.
USG Boral board USG Board India (P) Ltd.
Ferrous crete (Ferro- Ferrous crete manufacturers
500, Gypsum) Plaster)
Gyproc Saint Gobain The Saint-Gobain group
74 Gypsum plaster
(Elite 90)
Ultra tech Ultra Tech Cement Ltd.
Sl.
Material Description Brand Makes *
No.
Swastik Swastik Tiles
Thermatek Thermatek
Armstrong Armstrong world industries
High Desity (HDF) Ltd.
76 Green ply Green Ply Industries Ltd.
Prelaminated board
Pergo Red Floor India
Allura/ Graniza range Asian paints
High end exterior Berger Berger paints India ltd
77
Texture
SKK Brand SKK Ltd
Dorma Dorma India Pvt. Ltd.
Dorset Dorset Industries Pvt. Ltd.
Everite Everite agencies
Hydraulic door
78 Godrej Godrej locking solutioin &
closers/ Floor springs
systems
Hardwyn Hardwyn hardware
MAGNUM KIT Mukund Overseas
Basant Betons Basant Betons
BHARAT (NILSON) Bharat
Dazzie Dazzle Designer tiles Pvt Ltd
Hindustan tiles Hindustan tiles, Ranchi Pune
NITCO (ROCKARD) NITCO
REGENCY Regency
Interlocking Concrete
79 Shree Shree Bharat Paver blocks
Paver Blocks
Ultra Ultra tile private Ltd
Vyara Tiles VYARA Tiles Pvt. Ltd. / Surat
CEMTECH M/s Cemtech Tiles, Uppal,
Hyderabad
DEC M/s DEC Industries (P) Ltd.
Any alternative tiles as approved by CE/SE based on local
availability.
Archid ply Archid ply industries ltd.
A1 Teak A1 Teak Products Pvt.,Ltd.
Century Centuray laminates
Decolam Decolam India Pvt. Ltd.
Formica Formica Laminates (India) Pvt.
Ltd.
Green Lam Green lam Industries Ltd.
80 Laminate KANCHAN PLY M/s Vidya Ply & Board Pvt. Ltd
Kitmica Kitply Industries Ltd.
Merino Merino laminates
Royal touche Royal touche laminates
Sonear Sonear Laminates
Sunmica Sunmica Industries
DECO-MICA M/s Deco-Mica Ltd
PART B 192
Sl.
Material Description Brand Makes *
No.
Armstrong Armstrong flooring India Pvt.
Ltd.
Linoleum sorts Forbo Forbo Flooring India Pvt. Ltd.
81
flooring
Gerflor Gerflor flooring
Dorset Dorset Industries Pvt. Ltd.
Godrej Godrej locking solution &
systems
Hafele Hafele India Pvt. Ltd.
Harrison Harrison locks
82 Locks & Latches Hitech Globe Locks India
Helix Helix India
Link Link Locks
Plaza Bharat lock House
Yale ASSA ABOLOY India (P) Ltd.
3M 3M
Roop Roop Polymer Ltd.
83 Masking Tapes
Sun Sun
Wonder polymer Wonder Tape Industries
Asian paints Asian paints
84 Melamine Polish Melamine Gold Wudfin Pidilite industries
Polycure Polycure Malaysia
Dextra Dextra India Pvt Ltd.
Sanfield Sanfield India Ltd.
Mechanical coupler Alchemica Alchemica Ltd.
85
for reinforcement Ardex Endura Ardex Endura Ltd.
Smart care water proofing
Asian paints products
BASF BASF India Ltd.
Dr. Fixit Pidilite industries
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Hydro tech Hydro tech Ltd.
MYK Schomburg MYK Arments range of
Membarane water products
86
proofing system STP Ltd Shalimar tar products
Texsa Texsa India Ltd.
KRYTON M/s Kryton Buildmat Co. Pvt.
Ltd. Gurugram, Haryana
M/s Sunanda Specialty coatings
SUNANDA Pvt. Ltd., Mumbai
Godrej Godrej Security Solutions
Kenwood Kenwood Ply & Board
Metalic / Steel Fire
87 MPP Schodders MPP Technology Pvt. Ltd.
Door
NAVAIR NAVAIR International Pvt. Ltd.
Promot Promot fire & Insulation (P) Ltd.
PART B 193
Sl.
Material Description Brand Makes *
No.
Shakthi Hormann Shakthi Hormann Pvt. Ltd.
Signumfire Protection Signumfire Protection pvt. Ltd.
Sukri Sukri Fire Doors Pvt. Ltd.
ASES (Agni suraksha) M/s ASES Security Pvt. Ltd.,
Ghaziabad)
Ahlada M/s Ahlada Engineers Limited
DEC M/s DEC Industries Pvt. Ltd.
Essar Essar Steel Ltd.
JSW JSW Structural Metal Decking
88 Metal Deck Sheet Ltd
SAIL SAIL
TATA TATA steel
Amit Lovely metal Industries Pvt.
Ltd.
Deepak Deepak
Garg D.P. Garg & Company
Mild Steel Butt Jolly Jolly Engineering works
89
Hinges/ Piano hinges
Jyoti Jyoti Architectural Pvt. Ltd.
Saswat Saswat
Supreme Supreme Industries
Swift Swift screws
AIS Mirror Asahi India Glass Ltd.
Atul Autl Glass Industries Ltd.
Modi Guard Gujarat Guardian Ltd
90 Mirror
Saint Gobain Saint Gobain Glass India Ltd.,
Gold Plus M/s Gold Plus Glass Industry
Ltd., New Delhi
Evoke Evoke
Modular kitchen/ Godrej Godrej & Boyce co
91 wardrobes/Hardware
Sleek Asian Paints
and Accessories
Spacewood Spacewood
Apollo Appolo Tubes Ltd.
JINDAL JSW
Kalinga Kalinga Tubes Ltd.
92 M.S. Pipe, Tubes
SAIL SAIL
Surya Surya Roshi Ltd.
TISCO TATA STEEL
Multy walled Danapalon Danapal Light architecture
93 polycarbonate roofing Lexan GE GE lexan
sheets
Everest Everest Industries
HIL HIL Ltd.
94 Non Asbestos Sheets
RAMCO RAMCO Industries Ltd.
Everest M/s Everest Industries Ltd.
PART B 194
Sl.
Material Description Brand Makes *
No.
(Non-Asbestos Fibre
Cement Board -
Different Grade &
Type)
Godrej Godrej Security Solutions
Kenwood Kenwood Ply & Board
95 Non Metalic Fire door NAVAIR NAVAIR International Pvt. Ltd.
Promot Promat Fire & Insulation (P)
Ltd.
BASF BASF India Ltd
CICo CICO Technologies ltd
Fosroc Fosroc India
Non Metallic floor
96 Hardonite Hardonite
surface hardness
Ironite Ironite
Pidilite Pidilite Industries ltd
Sika Sika India
Berger (BISOM) Berger Paints
Dulux (Maxilite) Dulux
MG Polyplast Nerolac
97 Oil Bound Distemper
Tractor Aqalock Asian Paint
SURFA M/s Surfa Coats (India) Pvt.,
Ltd., Bangalore
Overdeck insulation Dowcorning Dowcorning
with extruded Owen scorning Owen scorning
98
polystyrene board Supreme Petrochemical Supreme Petrochemical Ltd.
(XPS board) Ltd.
Jain doors Jain Door Pvt. Ltd.
NCL Nagarjuna
Panel Doors/Wire
99 mesh Door shutters ASES (Agni suraksha) M/s ASES Security Pvt. Ltd.,
/Fire proof doors Ghaziabad)
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
PE-AL-PE Composite Kitec Kitec Industries (Índia) Pvt. Ltd.
100
Pipes
Berger Berger Paints
Dulex ICI dutax
Nerolac Nerolac Kansia Nerolac Pains
Ltd.
101 Pink primer
Nippon Nippon
Wood primer Asian paint
SURFA M/s Surfa Coats (India) Pvt.,
Ltd., Bangalore
BASF BASF India Ltd.
Plasticiser & Super Chryso-HP/ Delta / Chryso India Pvt. Ltd.
102
Plasticiser Optima
CICO CICO Industries
PART B 195
Sl.
Material Description Brand Makes *
No.
Contrament, Power MC Bauchemie (India) Pvt. Ltd.
flow
Conplast SP 430 FOSROC India
MYK Schomburg MYK Arments Range of
products
Plastiment, Sikament Sika India Pvt. Ltd.
Smart Care Techno Asian Paints Limited
Plast/Smart care
maximo plast.
Sunanda Chemicals Sunanda Chemicals Ltd.
DEC (Admixure(PC, M/s DEC Industries Pvt. Ltd.,
SNF) Hyderabad
(Note: Subject to
statutory approvals)
VISCOFLUX 2203/2208 Apple Chemie (I) Pvt Ltd
Accurate Buildcon Accurate Buildcon company
Plastic Encapsulated KGM KGM Exports
103
Foot Rest KK India KK Manhole and gratings Co
Pvt Ltd.
Koochie Play Koochie Play systems Pvt ltd.
104 Play Equipments
Play world systems Play world systems India.
BBR BBR (India) Pvt. Ltd.
CRUX Crux Processing systems Pvt.
Post tensioning Ltd.
105
System Ultracon Ultracon Structural Systems Pvt.
Ltd.
VSL VSL India pvt. Ltd.
Alcox Hindeggan Alcox Ltd.
Danapalan Danapal Light architecture
Sl.
Material Description Brand Makes *
No.
Polyethylene backer Supreme Supreme Industries
109
rod
BASF BASF
Ferrous Ferrous Crete ( India ) Pvt Ltd
110 Polyurea Ultra Pidilite Pidilite Industries
SIKA SIKA India
Smart care Asian paints
Akzonoble Akzonoble Coating Ltd.
111 Powder coating Berger Berger Paints India Ltd.
Jotun Jotun Group
Aura International Aura International Pvt.,Ltd.
Powder & PVDF
MJ coaters MJ Coaters Pvt.,Ltd.
112 Processer
SP Coating SP Architectural Coating
Pvt.,Ltd.
Archid ply Archid Ply Industries Ltd.
Associate Associate Décor Limited
Centuary Centuary MDF
Ecoboard Ecoboard Industries Ltd.
Green Lam Green lam Industries Ltd.
Kitlam Kit Ply Industries Ltd.
Prelaminated particle
113 Merino Marino laminates
board Exterior Grade
Novapan GVK Novapan Industries Pvt.
Ltd.
TESA Action Co. TESA Action Co.
GREEN PANEL M/s Green Panel Industries Ltd.
Bison Panel M/s NCL Industries ltd., (Board
division), Secunderabad
Berger Berger
Dulux ICI dulux
Premium Acrylic
Nerolac Nerolac
114 smooth exterior Paint
with silicon additives ULTIMA Asian paint
SURFA M/s Surfa Coats (India) Pvt.,
Ltd., Bangalore
PTMT/PVC water PEARL Precision Products
supply sanitary Prayag Prayag Polymers (P) Ltd
115 fittings, bibcocks, Supreme Supreme industries
pillar cock Angle
valve,
DP Wires DP Wires Ltd.
116 PT Strands TATA wiron TATA STEEL LTD.
Usha Martin Usha Martin Ltd.
Ambieance Ambieance
PVC Doors and
117 Accucel Accura Polytech Pvt. Ltd.
Frames
Duroplast Duroplast extrusion Pvt. Ltd.
PART B 197
Sl.
Material Description Brand Makes *
No.
Encraft Encraft India Pvt. Ltd.
Plastic Wood Plastic Wood
Polyline Polyline extrusion Pvt. Ltd.
Rajshri Rajshri Productions Pvt. Ltd.
Sintex Sintex Plastic technology Ltd.
VEKA M/s NCL Veka Ltd.
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
RAJSHRI M/s Rajshri Plastiwood,
Pithampur, M.P.
GIZA M/s Navratan Soeciality
Chemicals LLT., Ahmedabad –
380051, Gujarat
KAKA M/s Kaka Industries Limited
Sintex Sintex Plastic technology Ltd.
Supreme Supreme Industries Ltd.
PVC / HDPE water
118 Vectus Vectus Industries Ltd.
storage tanks
SUDHAKAR M/s Sudhakar irrigation system
(P) Ltd., Hyderabad
Akash Enterprises Akash Enterprises
Rex Polyextrusion Rex Polyextrusion ltd.
119 PVC Perforated Pipes
Supreme Supreme industries.
Zenplas Pipes Zenplas Pipes Pvt ltd.
Armstrong Armstrong world Industries
120 PVC flooring Ger flor Ger flor flooring
LG Hausys LG Hausys
Akzonoble Akzonoble Coating Ltd.
121 PVDC coating Valspar Valspar India Coating
Corporation Ltd.
BASF BASF
Fosroc Fosroc India
PU Coating (UV
Pidilite Pidilite industries
122 resistant Liquid
PU Roof Koat Berger Paints Ltd
Applied coating)
SIKA SIKA India
Smart care Asian paints
Akzonobel Akzonobel
PU Enamel Metalic Asian paints Asian paints
Paints on MS Berger Berger paints India Ltd.
123 Structure & Epoxy MRF MRF paints
paints ( Premium SKK SKK ltd
Quality) M/s Sunanda Specialty coatings
SUNANDA Pvt. Ltd., Mumbai
Access Floor systems Access Floor Systems
Raised / Cavity Tate Tate
124 Uni floor Uni floor India
flooring
Unitile Unitile India
PART B 198
Sl.
Material Description Brand Makes *
No.
Zt floor Zt floor Pvt.,Ltd
Indian Hume Pipes Indian Hume Pipe Ltd.,
Jain & Co Jain spun pipes Co.,
Lakahmi Sood & Sood Lakshmi Sood & Sood Pipa Co.
125 RCC Pipes Madurai spun pipe Madura spun pipe company
Vishnu Vishnu Spun Pipes.
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
Ferrous Crete Ferrous Crete (India) Pvt. Ltd.
Gyproc plasters Saint Gobain Gyproc India
Ready mix cement Ramco super plaster Ramco super plaster melamine
126 plaster melamine
Read Plast Ultratech cements Ltd
Ultra tech Ultra tech Cement Ltd
Berger Berger Paints
Dulex ICI dulex
High performance Asian Paint
Red Oxide Zinc yellow metal primer
127
Chromate primer Nerolac Nerolac
Nippon Nippon
SURFA M/s Surfa Coats (India) Pvt.,
Ltd., Bangalore
Asahi Asahi India Glass ltd.
Glaverbel Glaverbel India
Modifloat Gujarat Guardian Ltd.
Pilkinton Pilkinton India
Saint Gobain Saint Gobain India Pvt. Ltd.
128 Reflective glass
Gold Plus M/s Gold Plus Glass Industry
Ltd., New Delhi
Guardian Sun Guard M/s Gujarat Guardian Ltd.,
Gujarat
GUARDIAN M/s Gujarat Guardian Ltd.
SUNGUARD
ACC ACC Cements Ltd
A B Dinesh A B Dinesh Concrete India Pvt.,
Ltd.
Aparna Aparna Ready Mix concrete
Lafarge Lafarge India Pvt. Ltd.
RMC plants NUVOCO Nuvoco Vistas Corporation Ltd.
129
( Ready Mix Concrete)
RB Ready Mix RB Ready Mix
RDC RDC Concrete (India) Pvt.Ltd.
RMC (India) RMC (India) Pvt. Ltd.
Ultra Tech Ultra Tech Cement Ltd
Sarvani Industries Pvt. M/s Sarvani Industries Pvt.
PART B 199
Sl.
Material Description Brand Makes *
No.
Ltd., Ltd., Guntur
Plants at Autonagar, Gajuwaka
& Atchutapuram @
Visakhapatnam.
Plants at at – Ankireddy Palem,
Kolanukonda @ Guntur
JK Concrete M/s JK Ready Mix concrete,
Visakhapatnam
SCS Infra Concrete M/s SCS Infrastructures Pvt.
Ltd.,
SVK Ready Mix M/s Sai Venkata Krishna Reddy
mix Industry, Guntur
VNS Ready Mix VNS READY MIX
Icon Ready Mix Icon Infra Concrete Private
Limited, Tadepalli, Guntur
Liyod Insulation Liyod Insulation ltd.
Rockwool/Glass wool
130 Supreme Supreme Industries ltd.
insulation
Twiga fiber Twiga fiber glass ltd
Advent Advent concrete vision
BASF BASF
Danapalan Danapal Light architecture
Essar Essar Group.
Fosroc Fosroc
GE Plastic GE Silicones
Sandwich PUF GE Plastic GE Silicones
131 panelled roofing JINDAL MECTEC/ Mectec Pvt Ltd
sheets JINDAL
LEXAN LEXAN Ltd
Liyod Insulation Liyod Insulation (India) ltd
Lloyd Insulation Lloyd insulation (India ) Ltd
Pidilite Pidilite Industries ltd
Smart care Asian paints
Supreme Supreme ltd
AOS System AOS System
Grohe Grohe
Hindware HSIL Ltd
Sensor based Auto
132 Jaquar Jaquar Group
flush systems
Kochier Kochier
Parryware Parryware Sanitary ware
TOTO TOTO ltd.
Nu-TEC Nu-Tech concrete products (P)
Lld,.
SFRC Cover and
133 KK KK Manhole and gratings Co
grating
Pvt Ltd.,
Kutty Kutty Industries
PART B 200
Sl.
Material Description Brand Makes *
No.
Shear Stud/ KOCO KOSTER & CO
134
Connector
BASF BASF India Ltd.
Dow Corning Dow corning Indd
135 Silicon coating
GE GE Silicones
Wacker Wacker silicones
136 Silicon Gaskets Sree Geurev Sree Gaurav Rubber products
3M 3M Science
Solar studs/ Median Avery Dennison Avery Donnison India Pvt Ltd.
137 markers Nikkalite Nippon carbide Industires
(USA)
Dorma Dormakaba
hafele Hafele Ltd.
Spider patch fittings
138 Kich Kich india
for structural glazing
Ozone Ozone Ltd.
Sevax Saint Gobain Glass India ltd
Buildon Buildon
Spray applied Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
139 Readymade plaster/
Gyproc cute 100 Gyproc India.
Gysum plaster
Ultratech Ultratech cement ltd.
Neco JayaSwal Neco Ltd
Kartar Kartar valves private Ltd. ,
Electrosteel Electrosteel
140 Spun cast iron fittings
Kapilansh Centrifugal Kapilansh Dhatu Udyoo (P)Ltd.
SKF brand SINGHALIRON FOUNOARY
Pvt. Ltd.
Jagannath Sri Jaqannath iron Foundry Pvt.
Ltd
Spun cast iron covers Kapilansh Centrifugal Kapilansh Dhatu Udyoo{P)Ltd.
141
& gratings Neco Jayaswal Neco Ltd
SKF brand SINGHALIRON FOUNOARY
Pvt. Ltd„
Ark Product Pvt. Ltd. Ark Product Pvt. Ltd.
Connect Connect Ltd.
Jindal JSW
KINGSTON KINGSTON
142 Stainless Steel Salem SAIL
SAIL SAIL
DEC ( Stainless steel M/s DEC Industries Pvt., Ltd,
pipes*) Hyderabad
*with emboss /mark
“RM by JINDAL”
Alloy Alloy Ltd.
143 Stainless Steel screws
Atul Atul fasteners Ltd.
PART B 201
Sl.
Material Description Brand Makes *
No.
GKW GKW Limited
Helix Helix India
Kundan Kundan Industries Ltd.
Nettlefold Nettlefold Screws
Pooja Pooja Steel Corporation
Dorma Dorma India Pvt. Ltd.
Helix Helix India
Prayag Prayag Polymers (P) Ltd.
Stainless steel Butt
144 Ozone Ozone Hardware
hinges
DEC M/s DEC Industries (P) Ltd.,
Hyderabad
Global M/s Aluminium Udyog
Earl Bihari Earl Bihari India Pvt. Ltd.
EBCO EBCO
Stainless steel friction Hetich Hetich India
145
hinges Haffle Haffle India Pvt. Ltd.
ROTO ROTO Frank Asia
Securistyle Securityle India Pvt. Ltd.
Atul Atul fasterners Ltd.
Hilti Hilti India Pvt. Ltd.
Kundan Kundan Industries Ltd.
Stainless steel Bolts, Pooja Pooja Steel Corporation
146 DEC M/s DEC Industries (P) Ltd.,
washers, nuts
Hyderabad
GIZA M/s Navratan Specialty,
Chemicals LLT., Ahmedabad –
380051, Gujarat
Atul Atul fasterners Ltd.
Stainless steel Dorset Dorset Industries Pvt.Ltd.
147
pressure plate screws Kundan Kundan Industries Ltd.
Pooja Pooja Steel Corporation
CERA M/s Cera Sanitaryware Ltd.
Diamond Pheonix Appliances Pvt. Ltd.
Franke Franke India Ltd.
Futura Futura Kichen Sinks India Pvt.
Ltd.
Hindware HSIL Ltd
Stainless Steel Kitchen
148 Jhonson Prision Jhonson Ltd.,
sink
Jindal Centuary polytech
Joyna Joyna
Navkar Shri Navkar Metals Ltd
Nilkanth Nilkant
Nirali Jyoti (India) Matel Industries
Pvt Ltd
PART B 202
Sl.
Material Description Brand Makes *
No.
Silver Shine Blue stone sanitary Industries
Pvt. Ltd.
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
Accucel Accura polytech Pvt ltd.
Madhu industries Madhu industries, San Harvic,
NCL
Steel Windows/
149 NCL NCL Industries
Pressed steel frames
San Harvic San Harvic
DEC(CRCA Door M/s DEC Industries Pvt. Ltd.,
Frames) Hyderabad
APL Apollo Tubes Ltd
JSPL JSPL
JSW JSW
150 Structural Steel SAIL SAIL
TISCO TATA STEEL
VIZAG RINL
Asian paints Smart care sealant
BASF BASF India Ltd.
Dow corning Dow corning india
151 Structural sealant Fosroc Fosroc India
GE GE silicones
STP Ltd. Shalimar tar products
Wacker Wacker silicones
Berger Berger Paints
Dulex ICI dulex Ltd
Premium gloss enamel Asian paint Ltd
Synthetic enamel
152 Nerolac Nerolac Paints Ltd
Paint
Nippon Nippon Paint India Ltd.
SURFA M/s Surfa Coats (India) Pvt.
Ltd., Bangalore
Hollitex Hoilitex carper tilas
153 Synthetic Carpet tiles Standard Carpets Standard Carpets
TOLI TOLI Corporation
Armstrong Armstrong flooring
Synthetic Sports
155 Gerflor RMG Polyvinyl India Ltd.
Flooring
LG Wondorfloor LG Hausys India
Astral Astral poiytechnik Ltd.
Finolex Finolex Industries Ltd .
Flowgard Ashirwad PVC Pipes
SWR PVC Pipes & Nandi Nandi pipes Pvt., Ltd.
156
fittings
Prince Prince Pipes and fittings
Sudhakar Sudhakar PVC Pipes
Supreme Supreme Industries Ltd
PART B 203
Sl.
Material Description Brand Makes *
No.
SENTINI M/s Sentini Flopipes India Pvt.
Ltd., Hyderabad
Brila HIL Pipes M/s HIL Ltd.
AKG M/s AKG Extrusion Pvt. Ltd.,
Asahi Asahi India Glass ltd.
FUSO FUSO Glass India Pvt. Ltd.
Gurind Gurind India
Imapct Safety Impact Safety glass works Pvt.
Tempered reflective/ Ltd.
157
clear glass Modiguard Gujarat Guardian Ltd.
Pilkington Pilkington India Pvt. Ltd.
Saint Gobain Saint Gobain India Pvt. Ltd.
Gold Plus M/s Gold Plus Glass Industry
Ltd., New Delhi
Asian Asian Paints Ltd.
Elastospray BASF
Thermal Insulation
158 Pidilite Pidilite Industries
treatment
Rock India Pvt. Ltd Rock India Pvt. Ltd
Weather Kool & Seal Berger Paints India Ltd.
JSW JSW Steel Ltd.
SAIL Steel Authority of India Ltd.
TMT Bars
159 TISCO TATA STEEL LTD.
VIZAG Rastriya Inspat Nigam Ltd.
JSPL Jindal Steel & Power Ltd.,
AKG M/s AKG Extrusions Pvt. Ltd.,
Astral Astral polytechnik Ltd.
Ashirwad Aahirwad PVC Pipes
Finolex Finales Industries Ltd.
KSR KSR
Prepoly Premier PVC Industry
UPVC Pipes and Prince Pnnce pipes and fittings Ltd.
160
fittings Supreme Supeme industries Ltd.
SENTINI M/s Sentini Flopipes India Pvt.
Ltd, Hyderabad
DEC (UGD pipes (IS M/s DEC Industries Pvt. Ltd.,
15328) Hyderabad
Birla HIL Pipes M/s HIL Ltd.
SUDHAKAR M/s Sudhakar Polymers Pvt.
Ltd.
Aluplast Alu Alpha India
Duroplast Duro Plast Extrusion Pvt. Ltd.
UPVC doors, door
161
frames and windows
Encraft Encraft India Pvt. Ltd.
Fenesta Fenesta DCM Shriman
PART B 204
Sl.
Material Description Brand Makes *
No.
Komarlings Profile India Window
Technology Pvt. Ltd.
LG LG India Pvt. Ltd.
MARCOLINI M/s Mathura Poly pack Pvt, Ltd.
Prominance M/s Prominance Window
Systems
Rehau Rehau Unlimited Polymer
Solutions
Sintex Sintex Plastic technology Ltd.
Venster/ OKOTECH Aparna Enterprises limited
VEKA M/s NCL Veka Ltd.
Plast One M/s Plast One UPVC Profiles
Pvt., Ltd., Secunderabad
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
RAJSHRI M/s Rajshri Plastiwood,
Pithampur, M.P.
SIMTA ASTRIX M/s Simta Clear Coat Pvt. Ltd.,
Hyderabad
COAR COAR
DNV DNV Global Pvt.,ltd.
162 UPVC Hardware
HOPPE HOPPE
PULSE LGF SYSMAC (India) Pvt.,Ltd.
BATHSENSE Asian paints( Bath division)
CERA CERA Sanitaryware Ltd.,
Hindware HSIL Ltd.
Jaquar Jaquar Group
Vitreous Commodes/ Kerovit M/s Kajaria Ceramic limited
163
Washbasin Kohler Kohler world Wide
Parryware ROCA Bath Pvt. Ltd.,
Roca ROCA Bath room products
RAK Sanitaryware RAK Sanitaryware
Somany Somany Ceramic Ltd.
Durostone Ever stone International
Johnson Johnson India
164 Vitrified paving tiles
Kajaria Kajaria Ceramics
PAVIT PAVIT Ceramics Pvt. Ltd.
AGL Asian Granite India Ltd.
CERA M/s CERA sanitary ware Ltd.
Johnson Prism Johnson Ltd.
165 Vitrified Tiles Kajaria Kajaria Ceramic Ltd.
Marbito Marito tiles
NITCO NITCO Ltd.
Oasis M/s Oasis Vitrified Pvt.Ltd.
PART B 205
Sl.
Material Description Brand Makes *
No.
RAK RAK Ceramic India Pvt. Ltd.
Restile Restile Ceramic Ltd.
Somany Somany Ceramic Ltd.
Varmora Granito Varmora Granite Pvt. Ltd.
Vitero Aparna Enterprises limited
NAVEEN M/s Murudeswar Ceramics Ltd.,
Bangalore
Archidply Archid Ply Industries Ltd.
A1 Teak A1 teak Industries Pvt. Ltd.
Century ply Century Flush Doors
Duroply Duro Ply Industries Ltd.
Duroplast Duroplast
Dura sleek Dura sleek
Grassim ply Shree Ram Industries
Water Proof Plywood, Green panel Green panel Industries Lid.
Commercial ply, Fire Green Ply Green Ply Industries Ltd.
166 retardant ply and Jayna ply Jain Wood Industries
Block boards /
KANCHAN PLY M/s Vidya Ply & Board Pvt. Ltd
Shuttering ply
Kitply Kitply Industries Ltd.
Polyline Polyline
AAMODA M/s Jai Dayal Plywood Pvt. Ltd.,
Hyderabad
BLACK COBRA M/s Punjab Plywood Industries,
Yamunanagr, Haryana
Kalpataru M/s Shree Yantra Panels Pvt.
Ltd., (Sister concern of M/s V.K.
Patel&Co.)
Asian exterior wall Asian paint
primer
Water Proof cement Berger Bergar Paints
167 Cem Colour Snowcem Paints
paint
ICI DULUX ICI DULUX
Surfa Surfacoats (India) Pvt. Ltd.
ARCO Arco valves Pvt. Ltd ,
leader leader valves Ltd ,
168 Water supply Valves
Nanda Nanda Miller company
Zoloto Zoloto Industries
Advani Advani oerlikon Ltd.
ESAB ESAB India Pvt. Ltd.
ESS, BATHSENSE & Asian Paints (Bath Division)
169 Welding rods Premium Range :
Royale
HlNDWare HSIL Ltd.
Jaquar Jaquar Group
Water supply fixtures Johnson Prism Jhonson Ltd
170
like bibcock, Shower Kerovit M/s Kajaria Ceramic limited
PART B 206
Sl.
Material Description Brand Makes *
No.
panels Kingston Kingston brass India
MARC MARK Showers
Metro Metro sanitations Pvt. Ltd.,
Parryware ROCO bath roam products Pvt.
Ltd,
Prayag Prayag polymers Pvt Ltd ,
Seiko Seiko Sanitations
Watarman Kewal brothers
Accoproof ACC cement Ltd.
Alchemica Alchemica Ltd.
Ardex Endura Ardex Endura ( India ) Ltd.
Asian Paints Asian Paints
CICO CICO Technologies Ltd.
Cement Mix Berger Paints India Ltd.
Plus/Advanced Latex
Plus
Dr. Fixit Pidilite industries
Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Fosroc Fosroc India
Water proofing Impermo Snoweem paints
171
Compound
MYK Schomburg MYK Schomburg range of
products
Penetron Penetron India Pvt Ltd.
Shaliplast LW+ STP Ltd
Sika Sika India
KRYTON M/s Kryton Buildmat Co. Pvt.
Ltd. Gurugram, Haryana
DEC ( SBR Latex) M/s DEC Industries Pvt. Ltd.,
(Note: Subject to Hyderabad
statutory approvals)
M/s Sunanda Specialty coatings
SUNANDA Pvt. Ltd., Mumbai
Ardex Endura Ardex Endura Ltd.
BASF BASF India Ltd.
Dr. Fixit Pidilite industries
172 Water stops Ferrous Crete Ferrous Crete ( India ) Pvt Ltd.
Hydroswell Sika India
Hydrotite Sika India
KRYTON M/s Kryton Buildmat Co. Pvt.
Ltd. Gurugram, Haryana
Asian paints Smart care SC GP grout grey
BASF BASF
Water proofing Care Care
171
materials/ GP Grouts
Ferrous crete Ferrous Crete (India) Pvt Ltd
Home shield Super Berger Paints Ltd.
PART B 207
Sl.
Material Description Brand Makes *
No.
grout
Pidilite Pidilite Industries
SIKA SIKA India
KRYTON M/s Kryton Buildmat Co. Pvt.
Ltd. Gurugram, Haryana
DEC (Non-Shrink M/s DEC Industries Pvt. Ltd.,
grout) Hyderabad
(Note: Subject to
statutory approvals)
Weather silicon make Down corning Down corning india
173
and grade Momentive (GE) GE silicones
Birla Birla Corporation Ltd.
174 White Cement J.K. JK Cement Ltd.
Travancore Travancore Cements Ltd.
Alstone Alstone Industries Pvt., Ltd.,
Jaipur, Rajastan.
Century M/s Century Ply Boards (I)
Limited
Wood Polymer
Ecoste Ecoste wood polymer
composite material
composite, Delhi.
for door frames and
175 Echon Kumar Arch Tech, Pvt.Ltd.,
shutters, plain/pre
Rajastan.
laminated boards for
Green ply Greenply Industries Limited
wall linings etc.
Qute Qute Extractions Pvt.Ltd.,
Chennai.
Rajasree Rajeswari Products Pvt.,Ltd.,
Madya Pradesh.
Archiply Archiply
A1 Teak A1 Teak Products Ltd.
Century Century Flush Doors
Duro Flushdoors Dura Ply industries Ltd.
Greenlam Greenlam Ply Industries Ltd.
Indian Timber Products Indian Timber Products
Wooden Flush door Jain doors Pvt.Ltd. Jain doors Pvt.Ltd.
176
shutters Jayna Flush Doors Jain Wood Industries
Kailash Kailash Hi Tech Timber
Industries India pvt. Ltd.
KANCHAN PLY M/s Vidya Ply & Board Pvt. Ltd
Kenwood Kenwood Ply & Board
Kitply Kitply Industries Ltd.
Mayur Mayur Ply industries
PART B 208
Sl.
Material Description Brand Makes *
No.
MP Ply wood products MP Wood products
National plywood National plywood
Raavella door Raavella Industries (P) Ltd.
Shakthi Shree Shakthi Modern Flush
doors
Swatic ply Swatic ply
Vidya ply Vidya ply
AAMODA M/s Jai Dayal Plywood Pvt.
Ltd., Hyderabad
BLACK COBRA M/s Punjab Plywood
Industries, Yamunanagar,
Haryana
DEC M/s DEC Industries Pvt. Ltd.,
Hyderabad
NAGARJUNA M/s Nagarjuna Doors, W.G.
Kalpataru M/s V.K. Patel&Co.)
Precast Concrete DEC M/s DEC Industries Pvt. Ltd.,
177 Manhole covers and Hyderabad
Frame
HD PE pipes for DEC M/s DEC Industries Pvt. Ltd.,
178
water supply Hyderabad
Pre Painted DEC M/s DEC Industries Pvt. Ltd.,
Galvanized iron / Hyderabad
179
Steel Doors & APL APOLLO M/s APL Appllo Tubes Ltd.
Windows CHAUKHAT
RAJSHRI M/s Rajshri Plastiwood,
Pithampur, M.P.
DEC M/s DEC Industries (P) Ltd.,
180 WPC Doors Hyderabad
GIZA M/s Navratan Specialty,
Chemicals LLT., Ahmedabad –
380051, Gujarat
DEC M/s DEC Industries (P) Ltd.,
Hyderabad
181 WPC Frames GIZA M/s Navratan Specialty,
Chemicals LLT., Ahmedabad –
380051, Gujarat
Ess “ap Royale” and M/s Asian Limited (Bath
CP Bath Fittings & Bathsense Division)
182 Accessories
CORONET M/s Mohan Metal Industries
IoT based building WIS Spaces M/s Wenalytics IoT Solutions
183 Management System Pvt. Ltd.
(S.T. Open Protocols)
PART B 209
Sl.
Material Description Brand Makes *
No.
CEMTECH M/s Cemtech Tiles
CC Kerb Stones
184 DEC M/s DEC Industries (P) Ltd.
ALUTECH M/s Alutech Industries, New
HPL Sheets / Delhi
185
Laminates VIRGO M/s Virgo Laminates Ltd.,
Chandigarh
Stainless Steel Door DEC M/s DEC Industries (P) Ltd.,
186
Handles Hyderabad
DEC M/s DEC Industries (P) Ltd.,
187 Stainless Steel Aldrop
Hyderabad
188 Tower Bolts Global M/s Aluminium Udyog
189 Door Handles Global M/s Aluminium Udyog
New Products
Super Plasticizers AC-MENT -BV 430 A3 Apple Chemie (I) Pvt Ltd.
190
(Retarders)
APCP Based High Visco Flux 5507/6073 Apple Chemie (I) Pvt Ltd.
performance Hyper
Plasticizers for self-
191
compacting concrete
with Higher slump
Retention
Pentrative BI-Polar AC-Corroguard Apple Chemie (I) Pvt Ltd.
192 Corrosion Inhibiting
Admixture
Micro Silica Additives AC- Microsil-Si9+ Apple Chemie (I) Pvt Ltd.
193
(Pozzolanic Material)
Cystal Line water AC- Crystacrete Apple Chemie (I) Pvt Ltd.
194 proofing admixture
(PRAH Based)
195 Curing compounds AC- Cure R- (M) Apple Chemie (I) Pvt Ltd.
196 PU Sealant AC- Proseal 400 Apple Chemie (I) Pvt Ltd.
Coal Tar Epoxy AC- DUR-CT(S) Apple Chemie (I) Pvt Ltd.
197
coating
Ploy Urethane water AC-1K-PU Apple Chemie (I) Pvt Ltd.
198
proofing
Wireless Building Protech M/s Protech Technologies
199
Management System
200 Rapicon wall panel Everest M/s Everest Industries Ltd.
PART C 210
PART C
FOR E & M WORKS
(Minor Component)
PART C 211
PROFORMA OF SCHEDULES A to F
(E & M Components)
SCHEDULE ‘A’
Schedule of quantities (E & M works): (Pages from 251 - 255)
SCHEDULE ‘B’
Schedule of materials to be issued to the contractor
Sl. Description of item Quantity Rates in figures & words at Place of Issue
No. which the material will be
charged to the contractor
1 2 3 4 5
------------------------------------NIL---------------------------------
SCHEDULE ‘C’
Tools and plants to be hired to the contractor
Definitions:
2(v) Engineer-in-Charge Executive Engineer (E)(Vijayawada),
CPWD, Vijayawada.
or Successor thereof.
2(viii) Accepting Authority As per major component
2(x) Percentage on cost of materials and 15%
labour to cover all overheads and profits
9(ii) Standard CPWD contract form GCC GCC 2023 for Construction Works
2023, CPWD-7 as modified & corrected modified upto DG/CON/ Construction-
upto 2023/11 dated: 03/06/2024
PROFORMA OF SCHEDULES
Authority to Decide:
i) Extension of time As per major component
Clause 7 Gross work to be done together with 5.73 Lakhs or as per discretion of
net payment/adjustment of advances Engineer-in-charge.
for material collected, if any, since the
last such payment for being eligible
to interim payment.
Clause10B (i) Whether clause 10-B (i) shall be As per major component
applicable
Clause10B (ii) Whether clause 10-B (ii) shall be As per major component
applicable
Applicable
Clause 10C i)
Clause 10CA Whether clause 10CA shall be Not Applicable
Applicable
Clause 11
Specifications to be followed CPWD General specifications for
For execution of work Electrical Works,Part–I:Internal,
2023, Part-II: External, 2023,
Part-III(Lifts & Escalators), Part-IV: Substation;
Part –V: Wet Riser & Sprinkler System 2006,
Part-VI: Fire Detection and Alarm System - 2018
Part -VII: DG Sets 2013, HVAC Works-2024
with correction slips issued up to last date of
submission of tender
12.2 & 12.3 Deviation limit beyond which 100% (One Hundred per cent)
clauses 12.2 & 12.3 shall apply
for E & M work
12.5 (i) Deviation limit beyond which 100% (One Hundred per cent)
clauses 12.2 and 12.3 shall apply
for foundation work (except Earth
work).
(ii) Deviation limit for items in earth work 100% (One Hundred per cent)
Sub head of DSR or related items.
Clause 18 List of mandatory machinery, tools & As required for timely execution of
plants to be deployed by the work as per direction of Engineer-in-
contractor at site charge.
Clause 19C Authority to decide penalty for each As per major component
ddefault
Clause 19D Authority to decide penalty for each As per major component
ddefault
PART C 216
Clause 19G Authority to decide penalty for each As per major component
ddefault
Clause 19K Authority to decide penalty for each As per major component
ddefault
Clause 32: Requirement of Technical Representative (S) and Recovery Rate for each of
following E&M components - As per Major Component
1. The applicant should either himself meet the eligibility conditions for the respective
E&M components or otherwise he will have to associate with agencies, fulfilling the
eligibility requirements and hence consent letter from at least One eligible Associate
Agency of the respective components of E&M work shall also be submitted as per
attached Proforma asper Form “H”.
In case the main contractor is himself eligible (as per eligibility criteria) for executing any
specific minor component and intends doing the job himself, he may not be required to
associate with another agency for that minor component of work. In such cases the main
contractor also has to submit the documents as per eligibility criteria mentioned for
associated agency of individual E&M component.
However, the Composite category contractor shall also be eligible to carry out himself
any or all of these works without associating any specialized agency provided:
(a) He fulfills the prescribed eligibility criteria respectively for these work(s)
Or
(b) He directly procures the equipment of approved make from manufacturer and gets it
installed from authorized agency/service provider of the manufacturer/specialized
agency, all as per the eligibility criteria mentioned in NIT.
2. The main tenderer has to submit the following documents for association of contractor
within one month of award of work.
(i) In support of the eligibility conditions of the proposed Associated Contractor, copy of
their registration documents, Electrical License, GST Documents duly attested by the
applicants (Main Contractor) shall be submitted to the EE(C) who will submit these
documents to the Executive Engineer (Electrical)(Vijayawada), CPWD, Vijayawada,
for deciding the eligibility. Each such Associated Contractor will certify that they are
not debarred as on the day of application for sale of tender. Proposal for associating
agency for minor components of work shall be submitted in Form- “G” of this tender
document from each associate independently for all electrical and mechanical
components.
(ii) The main contractor will submit an Affidavit of MOU signed with eligible associated.
The Affidavit of MOU in the enclosed Form ‘I’ shall be signed by both the parties’
main contractor i.e.as 1st party and associated contractor as 2nd party. Independently
for all electrical and mechanical components.
3. In the event of the concerned E&M agency not performing satisfactorily or failure of
associate contractor to complete the E&M work, the main contractor on written
directions of the department, shall remove the Associate contractor deployed on the
work and shall submit name of new associate who fulfil the conditions mentioned in NIT
to execute the left-over work without any loss of time or variation in cost to the
department. Such associates shall also give an undertaking along with the main
tenderer but both of them together will stand guarantee for the equipments already
supplied for which payment has been released by the department in part. If any
equipment supplied for the work, during the currency of the earlier Associate contractor
and paid partly by the Dept., becomes redundant /not in a position to be installed and
commissioned and put to beneficial use due to change in agency for execution of E&M
PART C 218
work, the main contractor shall be liable for replacement of the equipment(s) at no cost
to Department. No change of Associated Contractor will be allowed without prior
approval of the Engineer-in-charge of the work.
In respect of all works Construction of 150 KLD Capacity Sewage Treatment Plant
including SITC of E&M works and distribution lines for treated water at CRPF
Campus, Kalikiri, Chittoor Dist., A.P. the materials shall be procured only from the
original equipment manufacturers/authorized dealers of OEM. The contractor shall
submit all documentary details in fulfillment of this conditions regarding procurement of
materials including relevant test certificates.
4. Executive Engineer (E) shall be the Engineer-in-charge as far as E & M works are
concerned.
Separate tender schedule abbreviated CPWD-7 and Special Conditions for E & M Work
are appended with this tender. It will be obligatory on the part of the
contractor/tenderer to sign the tender documents for all the component parts.
5. The main contractor shall be responsible and liable for proper and complete execution of
the E & M work and ensure coordination and completion of both civil and E & M work.
6. The main contractor has to enter into agreement with contractor associated by him for
execution of minor component. Copy of such agreement shall be submitted to Executive
Engineer (E) in charge of minor component as well as E.E. in-charge of major
component.
7. The associate contractor shall attend the inspection of the work by the Engineer-in-
Charge of E&M works as and when required.
8 In case of LED bulbs/fittings all the LED bulbs/fittings shall be guaranteed for a
period of 5 years. Before completion of defect liability period of One year, the
main contractor has to submit security deposit of 5% of price quoted by him for SITC
of LED fittings, for the remaining 4 years warranty period in acceptable form i.e.,
FDR/ Bank guarantee to concern Executive Engineer (E). The Security Deposit
deducted from the bills of contractor shall be refunded to the main contractor only
after submission of above security deposit for LED fittings by main contractor, failing
which this LED security deposit @ 5% as above shall be deducted from Security
Deposit deducted for total work and balance amount only will be refunded after
completion of defect liability period. The LED Security Deposit will be released pro-
rata basis each year
PART C 219
Note:
i) The value of executed works shall be brought to current costing level by enhancing
the actual value of work at simple rate of 7% per annum calculated from the date
of completion to last date of submission of tender. For other conditions, refer
special conditions specified in Part C.
ii) The applicant shall either himself meet the eligibility conditions for the respective
E&M packages or otherwise, he will have to associate an agency meeting the
eligibility requirements as given in this tender document and submit the details as
per Form “G” given in Part C of this tender document within 30 days of award of
work OR before start of minor component of work whichever is earlier.
iii) The applicant/ main contractor has to submit consent letters as per Form “H”,
given in Part C of this tender document from at least one eligible associate agency
of the respective component of E&M work for each of the component of E& M
works by clearly indicating the component of work within 30 days of award of
PART C 220
FORM –G
I/we hereby propose the following agencies as per mentioned against each for executing
corresponding minor components of work. Their consent letters are also attached.
Note: Self Attested photocopies of enlistment order, valid electrical contractor license, work
experience certificates of each agency for each component of E&M work shall be
submitted.
Signature of contractor
PART C 222
FORM –H
CONSENT LETTER FROM ELIGIBLE ASSOCIATE AGENCY OF MINOR
COMPONENT OF WORK
Name of work:
Construction of 150 KLD Capacity Sewage Treatment Plant including SITC of E&M
works and distribution lines for treated water at CRPF Campus, Kalikiri, Chittoor Dist.,
A.P.
1. I / We will execute the work as per specifications and conditions of the agreement and
as per directions of the Engineer –in-Charge for the corresponding minor work till the
completion of the work.
2. I / We will be responsible for necessary action to handover the installations and for
rectification of defects and repair during the maintenance / warranty period.
3. Also I / We will employ full time technically qualified Engineer / supervisor for the
minor component of the work as required for the work. I / We will attend inspection of
officers of the department as and when required.
Date:
Signature with date of Major component Signature with date of Associate/ Minor
Component
Contractor Contractor
Address Address
FORM-“I”
Name of work:
Construction of 150 KLD Capacity Sewage Treatment Plant including SITC of E&M
works and distribution lines for treated water at CRPF Campus, Kalikiri, Chittoor Dist.,
A.P.
We state that M.O.U between us will be treated as an agreement and has legality as
per Indian Contract Act (amended up to date) and the department (CPWD) can enforce all
the terms and conditions of the agreement for execution of the above work. Both of us shall
be responsible for the execution of work as per the agreement to the extent this MOU allows.
Both the parties can be paid consequent to the execution as per agreement to the extent this
MOU permits. In case of any dispute, either of us will go for mediation by the Engineer In
charge. Any of us may appeal against the mediation to the Chief Engineer, CPWD,
Vijayawada. His decision shall be final and binding on both of us.
We have agreed as under:
1. The Associated Contractor will execute all E & M works in the wholesome manner as per
terms and conditions of the agreement.
2. The Associated Contractor shall be liable for disciplinary action if he fails to discharge the
action(s) and other legal action as per agreement.
3. All the machinery and equipments, tools and tackles required for execution of the E & M
works, as per agreement, shall be the responsibility of the Associated Contractor.
4. The site staff required for the E & M work shall be arranged by the Associated Contractor
as per terms and conditions of the agreement.
5. Site order book maintained for the said work shall be signed by the main contractor as
well as by the Engineer of the Associated Contractor and by Associated Contractor
himself.
6. All the correspondence regarding execution of the E & M work shall be done by the
department with the Associated Contractor with a copy to the main contractor. In case of
non-compliance of the provisions of agreement, the main contractor, as well as the
associated contractor shall be responsible. The action under clauses 2 and 3 shall be
initiated and taken against the main contractor.
PART C 224
(From major component contractor side) (From minor component contractor side)
1 GENERAL
1.1 The work shall be generally carried out in accordance with tender/bid
specifications and the following specifications / rules with upto date amendments.
a) CPWD General Specifications for Electrical work Part I Internal – 2023, as amended
upto date
b) CPWD General Specifications for Electrical work Part II External– 2023, as amended
uptodate
c) CPWD General Specifications for Electrical work Part III (Lifts) as amended upto
d) date.
e) CPWD General Specifications for Electrical work Part IV (Substation) as amended
Upto date
f) CPWD General Specifications for Electrical work Part V (Wet Riser & Sprinkler
System) as amended upto date.
g) CPWD General Specifications Part-VI: Fire Alarm Systemas amended upto date.
h) CPWD General Specifications Part-VII (D.G Sets) as amended upto date.
i) CPWD General Specifications -2024 for HVAC Works as amended upto date.
j) Commercial and Additional conditions for this work.
k) The Indian Electricity Act, 2003, as amended upto date.
l) Indian Electricity Rules 1956 amended upto date.
1.3 This specification covers manufacture, testing as may be necessary before dispatch,
delivery at site, all preparatory work, assembly and installation, commissioning
putting into operation of equipment of all E&M components of the tender.
1.4 The tenderer should in his own interest visit the site and get familiarize with the site
conditions before tendering.
1.5 No T&P shall be issued by the Department and nothing extra shall be paid on
account of this.
PART C 226
2 COMMERCIAL CONDITIONS
Type of Contract: The work to be awarded by this tender shall be treated as
indivisible works contract.
Income tax, GST, labour cess& other statutory deductions etc. shall be made at
source as per the prevalent laws. The deductions of Security Deposit, Income-Tax
etc. shall be done as applicable on the gross payments and net payment shall be
paid accordingly.
3 RATES
The rates quoted by the tenderer, shall be firm and inclusive of all taxes (including
GST, labour cess etc.,). and all charges for packing forwarding, insurance, freight
and delivery, installation, testing, commissioning etc. at site including temporary
construction of storage, risks, overhead charges, general liabilities/obligations and
clearance from CEA. However, the fee for the CEA inspections shall be reimbursed/
borne by the department. EPF & ESI contributions are to be made by the contractor.
The department will not issue Octroy exemption certificate.
4
4.1 The contractor has to carry out maintenance as per CPWD General Specifications /
manufacturer’s standards for a period of 12 months or as decided by the Engineer –
in – Charge from the date of handing over. Nothing extra shall be paid on this
account.
4.2 In case of Specialized E&M works if Engineer-in-charge desires, the tenderer should
submit the following documents from OEM for that particular minor component
a) Authorization certificate.
b) The OEM is unconditionally support the lowest tenderer technically throughout the
execution of contract as well as for Maintenance/Comprehensive Maintenance
Contract for the useful life of the system, and
c) OEM is provide all the spares required for healthy functioning of the equipment for
at least seven years from the date of supply of equipment.
4.3 In case the same item appears more than once in the schedule of work under the
same sub head or among the different subhead of works, the lowest rate quoted for
that item elsewhere shall be considered for other items also during evaluation of
tender.
5 COMPLETENESS OF TENDER
All sundry equipment, fittings, unit assemblies, accessories, hardware items,
foundation bolts, termination lugs for electrical connections, and all other items
which are useful and necessary for efficient assembly and installation of equipment
and components of the work shall be deemed to have been included in the tender
irrespective of the fact whether such items are specifically mentioned in the tender
documents or not.
8 COMPLETION PERIOD
The completion period indicated in the tender documents is for the entire work of
planning, designing, approval of drawings etc., arrangement of materials
&equipments, delivery at site including transportation, installation, testing,
commissioning and handing over of the entire system to the satisfaction of the
Engineer-in-charge.
9 GUARANTEE
9.1 All equipments shall be guaranteed for a period of 12 months (except LED fittings
which shall be guaranteed for minimum 5 years), from the date of taking over the
installation by the department, against unsatisfactory performance and/or break
down due to defective design, workmanship or material. The equipments or
components, or any part thereof, so found defective during guarantee period shall
be repaired or replaced free of cost, to the satisfaction of the Engineer-in Charge. In
case it is felt by the department that undue delay is being caused by the contractor
in doing this, the same will be got done by the department at the risk and cost of the
contractor. The decision of the Engineer-in-charge in this regard shall be final &
binding on the contractor.
9.2 The tender shall guarantee among other things, the following:
a. Quality, strength and performance of the materials used as per manufacturers
standards.
b. Safe mechanical and electrical stress on all parts under all specified conditions of
operation. Satisfactory operation during the maintenance period.
10 POWER SUPPLY:
The contractor has to make its own arrangement for power supply required for
execution of the work.
11 WATER SUPPLY:
The contractor has to make its own arrangement for water supply required for
execution of the work.
14. The successful tenderer should furnish well in advance of start of work, three copies of
detailed instructions and manufacturer’s manuals of all equipments regarding
installation, operation and maintenance, preventive maintenance & trouble shooting
with all the relevant data sheets, spare parts catalogue, etc.
15.1 The work shall comprise of entire labour including supervision, all materials
necessary to make a complete installation, tests and adjustments and
commissioning, as may be required by the department. The term complete
installation shall not only mean major items of the plant and equipments covered by
specifications but all incidental sundry components necessary for complete
execution and satisfactory performance of installation with all layout charts whether
or not been mentioned in details in the tender document in connection with this
contract as this is a turnkey job.
15.2 The cables and all other items shall be brought to site only after taking correct
measurements as per actual requirement of work. Excess quantities shall not be
accepted and paid. i.e., Quantity of item brought to site and used in work as per
actual requirement shall only be measured and paid irrespective of quantities of
BOQ / work schedule. The item brought at site and paid, if not used in the project
have to be taken back by the contractor and deductions in the payment shall be
adjusted in subsequent bills. The decision of the Engineer-in-charge in this regard
shall be final & binding on the contractor.
15.3 In addition to supply, installation, testing and commissioning, of all E&M
equipment, following works shall be deemed tobe included within the scope of
work to be executed by the tenderer.
a) Minor building works necessary for installation of equipments, foundation, making
of opening in walls or in floors and restoring them to their original condition finish
and necessary grouting etc. as required.
b) All necessary supports may be arranged.
c) Testing of PTs/CTs for metering & protection purpose & relay calibration & setting.
d) Getting inspection done & obtaining approval from Central Electrical Authority and
local fire authority for energizing the installation. However, necessary fees for
inspection shall be borne by the Department.
the dates proposed for such tests to the department’s representative to facilitate his
presence during testing.
The Engineer-in-charge or his representative may witness such testing. The cost of
the Engineer’s visit to the factory will be borne by the Department. Equipments will
be inspected at the manufacturer/ Authorized Dealers premises, before dispatch to
the site by the contractor if so desired by the Engineer-in-charge. Engineer-in-charge
at his discretion may waive off inspection at factory /at the manufacturer’s works
before dispatch.
17.2 Copies of all documents of routine and type test certificates of the equipment, carried
out at the Manufacture’s premises shall be furnished to the Engineer-in-charge. The
decision of the Engineer-in-charge in this regard shall be final & binding on the
contractor.
17.3 After completion of the work in all respects the contractor shall offer the installation for
testing and operation. The contractor should submit all the related documents of
completed E&M equipment to the department for further handing over to client
department.
i) Factories Act.
ii) Indian Electricity Rules.
iii) B.I.S. & other standards as applicable.
iv) Workmen’s compensation Act.
v) Statutory norms prescribed by local bodies like CEA, Power Supply
Co., Fire authorities, etc.
18.2 After completion of the installation, the same shall be offered for inspection by the
representatives of the Central Electricity Authority if required and local fire
authority. The contractor will extend all help including test facilities to the
representatives of CEA/Local fire authority. The observations of CEA/Local fire
authority will be attended to by the contractor. The installation will be
commissioned only after getting clearance from CEA/Local fire authority.
Contractor should get inspection done & obtain approval from Central electrical
Authority and local fire authority, if applicable.
18.3 Nothing in this specification shall be construed to relieve the successful tenderer of
his responsibility for the design, manufacture and installation of the equipment
with all accessories in accordance with currently applicable statutory regulations
and safety codes.
19. INDEMNITY:
The successful tenderer shall at all times indemnify the department. Consequent on
this works contract, the successful tenderer shall be liable, in accordance with the
Indian Law and Regulations for any accident occurring due to any cause and the
contractor shall be responsible for any accident or damage incurred or claims
arising there during the period of erection, construction and putting into operation
the equipments and ancillary equipment under the supervision of the successful
tenderer to the extent the latter is responsible. The successful tenderer shall also
provide all insurance including third party insurance as may be necessary to cover
the risk. No extra payment would be made to the successful tenderer on account of
PART C 230
the above.
20. ERECTION TOOLS:
No tools and tackles either for unloading or for shifting the equipments for erection
purposes would be made available by the department. The successful tenderer shall
make his own arrangement for all these facilities.
21. COOPERATION WITH OTHER AGENCIES:
The successful tenderer shall co-ordinate with other contractors and agencies
engaged in the construction of buildings, if any, and exchange freely all technical
information so as to make the execution of this work/contract smooth. No
remuneration should be claimed from the department for such technical
cooperation. If any unreasonable hindrance is caused to other agencies and any
completed portion of the work has to be dismantled and re-done for want of
cooperation and coordination by the tenderer during the course of work, such
expenditure incurred will be recovered from the successful tenderer if the
restoration work to the original condition or specification of the dismantled portion
of the work was not undertaken by the tenderer himself.
The work will be carried out with least disturbance during shifting & shut down
taken in consultation with the client department.
22. INSURANCE AND STORAGE:
All consignments are to be duly insured upto the destination from warehouse at the
cost of the contractor. The insurance covers shall be valid till the equipment is
handed over duly installed, tested and commissioned.
24. PAINTING:
This shall include cost of painting of the entire installation. The major equipments
like HT panel, transformers, L T panel, bus duct, cable trays, HVAC equipment, etc.
shall be factory final finish painted. The agency shall be required to do only
touching to the damages caused to the painting during transportation, handling &
installation at site, if there is no major damage to the painting. However, hangers,
supports etc. of bus trunking& cable tray etc. shall be painted with required shade
including painting with two coats of anticorrosive primer paint at site.
25. TRAINING:
The scope of works includes the on job technical training of two persons of
Department at site as decided by Engineer – in - charge. Nothing extra shall be
payable on this account.
26. MAINTENANCE:
Sufficient trained and experienced staff shall be made available to meet any
exigency of work during the guarantee period of one year from the handing over of
the installation.
The maintenance, routine as well as preventive, for one year from the date of taking
over the installation as per manufacturer’s recommendation.
27. Approval of drawings, makes and models of equipment/materials for all E&M
components:
27.1. The agency shall submit drawings and details such as makes and models of the
PART C 231
28. Adequate care that only tested and genuine materials of proper quality are used in
work shall be ensured by firm. The firm shall also ensure that:
i. Material will be ordered & delivered at site only with the prior approval of the
department to ensure timely delivery.
ii. As and when the order is placed for the fittings/ fixtures, cables, switchgears,
poles, other main items etc, its copy shall be endorsed to the Engineer-in-charge
of work.
iii. The contractor will submit makes & brands of electrical fittings wires & cables,
conduits and switchgears, rising mains, poles , outdoor fittings etc. of preferred
make list as per tender documents for approval of Engineer-In-Charge, whose
decision will be final in the matter.
iv. The firm will be required to procure material directly from the manufacturer/
authorized dealers to ensure genuineness & quality and as per the approved
makes only. Proof in this regard shall be submitted by the contractor if required
by the department.
v. Inspection at factory or at godown, as required, shall be arranged by the firm for
a mutually agreed date.
vi. Delivery of material shall be taken up only with the consent of department, after
clearance of the material.
vii. Department shall reserve the right to waive off inspection in lieu of suitable test
certificate, at its discretion.
viii. All the materials to be supplied by the contractor shall be procured & brought to
site as per requirement at site of work in consultation with department so that
these materials are not damaged & their manufacturer’s warrantee.
Scope of work: -The scope of work includes Design, Supply, installation, Testing and
Commissioning of 150 KLD Sewage Treatment Plant based Moving Bed Bio Reactor
(MBBR) Technology including cost of all associated mechanical, electrical and
instrumentation items of work etc. including miscellaneous works associated with plant
on turnkey basis, with a defect liability period of 12 months after the date of
commissioning & Trial run.
Any other Items which have not been specifically mentioned in specifications but are
necessary for construction of the Plant as per good engineering practice, safety norms
and successful operation and guaranteed performance of the entire Plant shall be
deemed to have been included within scope of work and shall be provided by the
Contractor for which nothing extra shall be paid.
Setting out: The contractor shall set out the works in relation to original points, lines and
levels of reference required for execution of work. The contractor shall be responsible for
the correct positions of all parts of the works and shall rectify any error in the positions,
levels, the dimensions or alignment of works. Carrying out& confirming the detailed
topographical survey along finalized Gravity main/Rising main alignment and treatment
plant site, disposal of treated water and sludge and establishing benchmarks atleast two
locations within the STP site and one at pumping station site.
Supply, installation, testing & commissioning of all the piping, valves and specials etc.
as per detailed technical specification.
Water tightness(seepage)/ testing of all the water retaining structures as required.
Trail Run: The contractor shall initially operate the Sewage treatment plant for a period
of one month, after completion of work, for start-up/stabilization and for satisfactory
performance, by deploying experience staff in two shifts a day and the staff of the user
department shall be trained for operation of STP for which nothing extra shall be paid.
The main agreement shall be closed after successful completion of one month trial
period.
Supply of equipment drawings, technical specification/Catalogue. Supply of as built
drawings after Completion.
Supply of Operation & Maintenance manual including manufacturer manual of the
equipment supplied.
1. The tenderer has to make his own arrangement for the inspection of site and his stay
during the visits and no payments shall be made on this account.
2. The contractor shall get himself acquainted with the availability of materials, quarries,
kilns.
3. The water required for construction shall be arranged by the contractor and which shall
conform to CPWD specifications.
4. The pumps and machineries required to be supplied and installed shall be procured
from reputed and approved manufactures and shall be got approved and accepted by
the Executive Engineer (Elect), CPWD, Vijayawada.
PART C 233
5. The tenderer shall not sub-contract or assign any item of work without prior approval of
the Engineer – in – charge. The contractor is responsible for all the works.
6. Within 7 days of acceptance of tender, the contractor shall submit detailed design and
drawing for all components of work (civil, plant, structural, electrical, mechanical and
hydraulic) along with specifications, in duplicate. The department will scrutinize the
design and drawings and will be returned to the agency suggesting any alteration,
deviation and modifications etc., in the design and drawings and the same shall be
corrected by the agency and fresh designs/ drawings shall be submitted to respective
offices for final approval. In this connection, on request of the Engineer in charge, the
contractor shall depute the design Engineer to discuss about the details of design &
drawings.
7. The designs of Civil/ Electrical/ Mechanical portion shall be based on the latest relevant
IS codes, CPWD specifications, PH Engg. Manual, Indian Electricity Rules. Norms of
pollution control board, Local By – laws and WHO standards with up-to-date
amendments and correction slips and sound engineering practice. Each and every step of
the design calculations should be self-explanatory. Wherever formulae are adopted, they
may be printed clearly. Each factor/ parameter contained in the formula has to be stated
in clear terms regarding what for they stand/ their representation in the formula. Side
references along with calculations are to be given regarding adoption of references from
books/ manuals/ IS codes etc., including their page numbers.
8. The approval along with alteration in drawings/ design by the Executive Engineer in
charge shall not relieve the contractor of his responsibilities in terms of the contract for
soundness of design. The contractor shall be responsible for the structural safety of all
the components of work.
9. The tenderer shall submit the detailed drawings as given as below for approval from the
department.
a. Layout plan of the scheme.
b. Flow diagram, circuit diagram etc.
c. Detailed drawings and company’s catalogue etc., of all machineries,
pumps etc.,
d. Full list of all mechanical and electrical equipment with full technical
details including its quantities.
10. The tenderer shall be solely responsible for the receipt, transport and storage of any
materials, equipment etc., supplied by him until they are installed, tested and handed
over to the department. However, the material may be stored at work site at the
contractor’s own risk, cost and responsibility.
11. The department will not entertain any modification in the detailed technical parameters,
modifications in conditions, specifications and design criteria on the final accepted
technical specification based on which tender is called upon. Such modifications are not
acceptable and such tenders shall be liable for total rejection.
12. The design sheets and drawings once approved shall be the property of the CPWD. No
patent right and any other allied claim shall be entertained.
13. Any work shall be taken up for execution only after the final approval of designs and
drawing by the department. The department will not entertain any claim what – so –
PART C 234
ever in respect of works taken up for execution in anticipation of the approval for design
and drawings.
14. On commissioning of the Sewage treatment plant, a register shall be maintained for the
following details during trail run.
i. Name of operators,
ii. Working hours and shift details.
iii. Break down details and remedial measures taken.
iv. Copies of test results of the Sewage.
15. Samples of Sewage shall be tested every month during defect liability period at an
approved lab to ensure the satisfactory performance of the plant. The cost of sampling,
conveyance etc., shall be borne by the contractor. The sample shall be collected in the
presence of Engineer – in – charge or his authorized representatives. The said work is
covered under 12 months defect liability period for which nothing extra shall be paid.
16. All the materials brought to site for construction purposes shall be tested as per CPWD
specification/relevant IS code of practice.
17. The electrical works shall be got executed through electrical license holders.
18. All Electrical works shall conform to CPWD Specifications for electrical work.
19. Adequate provision shall be made in the equipment mounting to prevent excessive noise
transmission directly or through piping and structures.
20. All mechanical parts will be replaced and not repaired during defect liability period of
12 months from the date of completion of trial run.
21. After successful commissioning of the plant, the contractor shall conduct performance
tests on the equipment to satisfy the Engineer-in-charge that all equipment performs to
be rated outputs. Any or all equipment shall be replaced if the same is not working.
22. Guarantee: - The guarantee shall cover a period of 12 months from the date of expiry of
trial run of the plant.
23. On completion of the job the contractor shall handover the following to the Engineer-in-
charge.
a. One flow chart drawn in colour on a display board of 1.80m x1.20m
size made of acrylic sheet with frame showing the flow diagram of the
process including legend. Showing valves to be normally open or
closed and instruction for operation and maintenance of aerators,
diffusers, filters etc.,
b. Fivesetsofinstructionmanualsforoperatingandmaintenancewithsparep
artslistsandothermanufactureandorsuppliers.
c. Five sets of catalogues and drawing for all equipment supplied.
24. The process unit & equipment related to MBBR shall be supplied as per design
requirements/ and scope of work mentioned in tender.
25. The contractor will also provide luminous painted warning / caution notice boards with
flickering light arrangements, where the work is in progress.
26. The contractor shall have to make his own arrangements for labour stay at site.
PART C 235
27. The contractor shall take all precautions for the safety of existing nearby/adjoining main
or lateral sewers and dewatering equipment shall be kept as a standby in view the
existing sewer lines.
28. All the works for STP shall be executed in conformity, CPWD specifications, and
relevant/applicable BIS codes (latest revisions), with up-to-date correction slips.
29. The rate for STP item is for Design of STP and SITC of all E & M works and other
ancillary items including Biological Media (Except Civil construction Works) required
for satisfactory performance of 150 KLD STP as per the design and drawings to be
submitted by the contractor for approval from Engineer-in-charge. However,
drawings of required collection tanks showing dimensions and other civil works shall
be submitted within 7 days of award of work.
Executive Engineer(E)(Vijayawada)
PART C 236
1. The characteristics given are indicative and subject to change. The Sewage treatment
should be based on MBBR Technology. The treated Sewage shall be subjected to
tertiary treatment. Quality of Sewage after tertiary treatment shall be in conformity
with the standards laid down by Pollution Control Board for discharge in to a
stream.
2. The tenderers are free to adopt the sizes to suit the design requirements for final
approval from State Pollution Board/ Local authorities.
3. The Sewage treatment plant shall have followed characteristic or as per the state
pollution control board norms whichever is stringent.
a. Efficient
b. Low power consumption.
c. Minimum maintenance.
d. Minimum space requirement.
e. Self-operating system.
4. The scheme proposed shall be free from environmental hazard to the occupants and
neighboring tenants.
5. The tenderer shall obtain No-Objection Certificate or any other relevant
certificate from Pollution Control Board after execution of work.
6. All the electrical works shall be as per Indian Electricity Act.
Plumbing Works:
Full specification of pipelines, valves etc., have to be mentioned. For the valves, the
make, vendor and materials description size and numbers required to be mentioned.
The site being close proximity to sea enough care shall be taken to use the material
unsusceptible for corrosion.
Panel board, wires and instruments with its full description and specification etc.,are
to be furnished.
Note: -
1. Tenderers quoting for make & models other than above will be rejected.
2. Apart from the above makes, makes approved by ADG, RH-Hyderabad and/or SDG,
Chennai, satisfying the technical specifications of the item(s) mentioned in the tender
document are also acceptable. Also, preference will be given to Public Procurement
(Preference to Make in India) order compliant products.
3. The department reserves the right to add or delete any material/make/brand in the list of
approved material/make/brand subject to the recovery of financial implications.
4. The makes shall be approved by the competent authority of CPWD and /or client department
before procuring the material.
5. The department reserves to right to get the materials tested in a recognized laboratory/test
house for its conformity to the tender specifications.
PART - D
Schedule of Quantities
PART D 240
SCHEDULE OF QUANTITIES
Name of Work: Construction of 150 KLD Capacity Sewage Treatment Plant including
SITC of E&M works and distribution lines for treated water at CRPF Campus, Kalikiri,
Chittoor Dist., A.P.
Civil Component
Sl. No Description Quantity Unit Rate Amount
1 EARTH WORK
1.1 Earth work in excavation by
mechanical means (Hydraulic
excavator)/ manual means over areas
(exceeding 30 cm in depth, 1.5 m in
width as well as 10 sqm on plan)
including getting out and disposal of
excavated earth for all leads and lifts
within the campus, as directed by
Engineer-in-charge.
1.1.1 All kinds of soil 60.00 cum 186.52 11191.00
1.2 Earth work in excavation by
mechanical means (Hydraulic
excavator) / manual means over areas
(exceeding 30 cm in depth, 1.5m in
width as well as 10 sqm on plan)
including getting out and disposal of
excavated earth, lead up to 50 m and all
lift, as directed by Engineer-in-Charge.
1.2.1 Ordinary rock 240.00 cum 524.26 125822.00
1.2.2 Hard rock (blasting prohibited) 240.00 cum 1505.80 361392.00
1.3 Excavating trenches of required width
for pipes, cables, etc, including
excavation for sockets, depth up to 1.5
m, including getting out the excavated
materials, returning the soil as required
in layers not exceeding 20 cm in depth,
including consolidating each deposited
layers by ramming, watering etc.,
stacking serviceable material for
measurements and disposal of
unserviceable material as directed, for
all leads and lifts within the campus:
1.3.1 Ordinary rock :
1.3.1.1 Pipes, cables etc. exceeding 80 mm dia 20.00 metre 1049.42 20988.00
but not exceeding 300 mm dia.
1.4 Filling available excavated earth 300.00 cum 205.96 61788.00
(excluding rock) in trenches, plinth,
sides of foundations etc. in layers not
exceeding 20cm in depth, consolidating
each deposited layer by ramming and
watering, for all leads within the
campus and for all lifts.
PART D 241
Electrical Component
Total 34,36,631.00
Name of Work: Construction of 150 KLD Capacity Sewage Treatment Plant including SITC
of E&M works and distribution lines for treated water at CRPF Campus, Kalikiri, Chittoor
Dist., A.P.
ABSTRACT OF COST
Name of the Contractor
Percentage
above or
Sl. Estimated % In Total
Name of Component below the
No. Cost Figures Cost
estimated
cost
1 Construction of 150 KLD
Capacity Sewage Treatment
Plant including SITC of E&M
works and distribution lines for
treated water at CRPF Campus,
Kalikiri, Chittoor Dist., A.P.
Civil component 1,21,58,876/-
Electrical component 34,36,631/-
GRAND TOTAL 1,55,95,507/-
Important Note:
1. The estimated cost of tender has been worked out by taking into consideration the cost
index of Chittor District for DSR 2023 (Civil) & DSR 2022 (E&M) items and market rates
for NSR items; therefore, are adjusted accordingly.
2. The tenderer is to quote a single consolidated percentage only separately for Civil and
Electrical Component at par/above/below estimated cost to cover all the rates of all the
items under the schedule of composite tender.
3. If the percentage quoted is not clear, or if the rate is not quoted in percentage, the
tender shall be treated as invalid and will not be considered as lowest tenderer.
PART – E
TENDER DRAWINGS
(Indicative only)