Interior work
Kitchen
Modular kitchen(5*7 )
Chimney
Electrical wiring
Light fittings (according to design)
Steel Basket (3+1)
Glass rack
Lofting and paneling
Bedroom 1
Bed (6*7 feet)
False ceiling
Side table
Wordrobe (5*6 feet)
Dressing table
Electrical wiring
Lights fittings(according to design)
Strips light
Door mica change(if need)
pg. 1
Bedroom 2
Bed (6*7 feet)
False cielling
Side table
Wordrobe (4*6 feet)
Study table folding
Dressing table
Electrical wiring
Lights fittings (according to design)
Strips light
Paint interior
Wall paint
False ceiling
Iron structure
Window net
Hall room
False cielling
Electrical wiring
Lights fittings (according to design)
Strips light
Fridge layout(electrical)
Tv cabinet
Tv Cabinet(6*6)
Electrical wiring
Lights fittings (according to design)
Switches and socket
Strips light
pg. 2
Main gate
Both side laminate
Lock(if needed)
Camera view
Out side framing
Clabsible gate
Shoe rack
3*4 shoe rack
2 palla door
Window grill extent
Balcuny grill extend *2 no
Window grill extend *2 no
Mandir
2*6 mandir (according to design)
Ply work
Wall paper
3 place wall paper
(according to design) in full flat
Tiles change (only kitchen)
2*1 feet tiles change in kitchen
Bathroom cabinet
2*2 feet bathroom cabinet in each bathroom
Door mica change into pvc laminate
Sofa set
3+1 sofa set with fabric material (square base)
Center table (2*1.6)
pg. 3
Materials specification
S Particulars Details
n
1 Electrical All electrical material from Havells/mescab
materials
2 Furniture Hettich ,Green ply/commercial ply, fevicol, pvc
laminate/glass /mica
3 Paints Asian paint apcolite
4 Chimney Glen (auto clean)
Rate final : Rs 760,000/-( this above work and materials are providing under this budget only)
Sign ……………………………….
Date……………………………….
pg. 4
Rules & Regulation
1. Need permission to bring materials and machinery at work
place without giving any extra charges to the authority .
2. Client will provide place to dump rubbish cleaning and
dumping with there own way.
3. Any work out of the contract will be charged extra.
4. Site will be properly cleaned after completion of total job as
per contract.
5. Client will pay for any kind of extra fitting like decorative
items,clips, flower stand or pots,hanger,cotton stand,bathrooms
fittings or anything apart from job work as per contract.
6.After finishing all work left over materials will be take out by
the contractor in his own expense.
Payment terms
This standard terms and condition is in between
(AKBAR ALI ANSARI & ANU SOMANI).
Contractor and Customer here by agrees as follow
Time frame 5 months + 15 days grace from the date of this Agreement
as per contract.
PAYMENTS SHEDULE
1):- 45% upfront.
2):- 45% before the second phase start.
3):- 10% after finishing all interior works as per contract.
Signature…………………………………
Date………/………./…………………….