1. Project Name: Website Redesign for XYZ Corp.
2. Work Breakdown Structure (WBS) Activities:
- 2.1.1: Gather requirements (Duration: 5 days)
- 2.2.1: Create wireframes (Duration: 7 days)
- 2.2.2: Develop mockups (Duration: 6 days)
- 2.3.1: Develop backend (Duration: 10 days)
- 2.3.2: Develop frontend (Duration: 8 days)
- 2.4.1: Conduct unit tests (Duration: 4 days)
- 2.4.2: Conduct user acceptance tests (Duration: 5 days)
- 2.5.1: Deploy website (Duration: 3 days)
- 2.5.2: Monitor website (Duration: Ongoing)
3. Sequencing:
- 2.1.1 (Gather requirements) → 2.2.1 (Create wireframes) → 2.3.1 (Develop
backend)
- 2.3.1 → 2.4.1 (Conduct unit tests)
- 2.3.2 (Develop frontend) → 2.4.2 (Conduct user acceptance tests)
- 2.4.1 → 2.5.1 (Deploy website)
4. Critical Path:
- 2.1.1 → 2.2.1 → 2.3.1 → 2.4.1 → 2.5.1