Conceptual Design of the Al-Khair Petrochemical Zone/Port
High Level Milestone Schedule
SR> ACTIVITY DESCIPLINE DURATION
(Working
days)
Wk-1 Wk-2 Wk-3 Wk-4 Wk-5 Wk-6 Wk-7 Wk-8 Wk-9 Wk-10 Wk-11 Wk-12
1 KOM / MOM/ Needlist Preparation Client / Consultant 5 Days
2 Advance Payment Processing & Release Client 5 Days
3 Input data - As per Needlist /Survery Client 5 Days
4 Preparation of Sizing Data Consultant 10 Days
5 Block Flow Daigrams/ Process Flow Diagram Consultant 10 Days
6 Conceptual Plan Preparation /Plot Plan Consultant 10 Days
7 Utility Requirement Consultant 10 Days
8 Operational Manual Consultant 10 Days
9 Technical Report & Costing Consultant 15 Days
Notes:
1 It is assumed that all the data as per needlist shall made available by client post award of project, prior to KOM.
2 It is assumed that the available Survey map,Urban plan is latest & is detailed enough to design facilities of the project.
3 Client's Review Cycle is considered as 2 days considering tight schedule