This memo serves as a second and final reminder to various station managers regarding the urgent need to complete the shifting of bare HT/LT overhead lines from government establishments and public places by June 30, 2025. A completion or NIL report must be submitted within seven days, as failure to comply poses serious public safety risks. The memo emphasizes that negligence in this matter is unacceptable and requires immediate attention.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views1 page

Shifting

This memo serves as a second and final reminder to various station managers regarding the urgent need to complete the shifting of bare HT/LT overhead lines from government establishments and public places by June 30, 2025. A completion or NIL report must be submitted within seven days, as failure to comply poses serious public safety risks. The memo emphasizes that negligence in this matter is unacceptable and requires immediate attention.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

West BengalState Electricity Distribution Company Limited

(A GOVT. OF WEST BENGAL ENTERPRISE)

OFFICEOF THE DIVISIONAL MANAGER


PURULIA DIVISION

WBSEDLL TARIT BHAWAN, 2ND FLOOR, DESHBANDHU ROAD


PURULIA -723101(W.B)
E-MaillD-lm.prl.divn@gmail.com

Regd. Office: Vidyut Bhavan, Block -DJ, Sector - I1, Bidhannagar, Kolkata - 700091,

Memo No. DM/PRLD/ 989 Date:


nfoz025
To
The Station Manager
Purulia/ Telkalpara/ Chakda/ Joypur/ Jhalda/ Arsha/ Bagmundi Balarampur/ Barabazar/
Bandwan CCC
&
DE(Tech)/AE(Tech)-1/ AE(Tech)1-II

Sub: Reminder to complete of shifting of Bare HT/LT Overhead Lines from Government
Establishment and Public places
Ref: (i) () Office Order No.: I581Dated 27.02.2019 of the Director (HR), WBSEDCL
(i) Memo No.: CMD/09/260, Dated 08.01.2020 of the CMD, WBSEDCL
(ii) Memo No.: RM/PRO/Safety/53, Dated 21.04.2025
(iv) Memo No.: RM/PRO/Safety/284, Dated 12.06.2025 (1 Reminder)
Sir,
This is to bring to your notice,once again, that despite the issuance of the first reminder,
from RM,PRO andduly communicated to your end directing you to complete the work of shifting
bare HT/LT overhead lines from Government Establishments and Public Places by 30.06.2025
and submit the completion report., but no such report has been received till date.
It was also clearly mentioned in the first reminder that in case there is no such work
pending in your division, a NIL report must be submitted within the stipulated time. However,
your continued silence and failure to comply with this directive is a matter of serious concern.
This letter serves as the sccond and final reminder. You are hereby instructed to submit
the completion report (or NIL report, if applicable) within 7 (seven) days from the date of this
letter. This is urgently required so that the undersigned may submit the consolidated report to the
higher authority without further delay. The report may be furnished as per below format:
Name of the Status
Unit
NIL (if work is pending)
E-office or receive No. if proposal is initiated

Let it be clearly understood that such negligence in complying with official instructions
especially when public safety is involved is unacceptable. The presence of un-shifted bare HT/LT
lines in sensitive public areas and government establishments poses a grave risk and may invite
unwanted and potentially fatal accidents. This level of disregard for public safety cannot and will
not be tolerated.
Treat this matter with the utmost seriousness and engure strict compliance within the
specified time framc.
D.E. & Divisional Manager
Purulia Division