Container Office - Final 2

The document outlines construction specifications and requirements for a proposed office development, including details on dimensions, materials, and structural guidelines. Key points include reinforcement for walls, compliance with sanitary regulations, and specifications for windows and doors. It emphasizes the importance of adhering to the architect's details and the necessity for approvals of materials and fittings before work commencement.

Uploaded by

Mathias Nsimbe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
78 views1 page

Container Office - Final 2

The document outlines construction specifications and requirements for a proposed office development, including details on dimensions, materials, and structural guidelines. Key points include reinforcement for walls, compliance with sanitary regulations, and specifications for windows and doors. It emphasizes the importance of adhering to the architect's details and the necessity for approvals of materials and fittings before work commencement.

Uploaded by

Mathias Nsimbe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Notes:-

1. All dimensions to be checked on site, written


dimensions to be followed in preference to scaled
dimensions.

2. All walls less than 200mm thick to be reinforced with


6,300 6,700
hoop iron at every alternate course.
03

A
3. All reinforced concrete work is to be in accordance
200 200 2,850 200 2,850 200 200 with structural engineer's details.

200

200
6,100 4. All sanitary work to be in accordance with M.O.H rules
5,898 and regulations.

Foundation trench Container outline 5. Where drain passes under building or driveway

200
area,pipe to be of cast iron or encased in 150mm
concrete.

200
6. All waste pipes and soil pipes are to be in ducts and

2,352
200

Direction of flow
the bends to have all cleaning eyes accessible from
200 200 200

of rainwater
outside.

3,340
200 200 2,450 200 200 2,450 200 200 OFFICE SPACE 7. All windows and external glazed doors on ground floor

04

02
to have burglar proofing to Architect's detail.
2,640
2,440

1,840

2,240
(In a 20ft container)
HARDCORE HARDCORE 1500x2100mm 8. All door frames to be rebated & moulded & be full
1500x1200 mm (WxH) width of wall with moulded architrave to detail, provide
Steel & Glass door rubber door stops to all doors.

300
Steel & Glass window
Roof pitch - 3deg 9. Stair case and lobby doors to be self closing and 1/2

200
Galvanised roofing sheets hour fire resistant.

200
10. All internal plaster to be two coats steel float finished.

300
Foundation trench

200
11. All manholes within building area, driveway and
parking to have heavy duty air tight covers and double
Foundation trench GROUND FLOOR PLAN sealed.

200

200

300
RC Stub column the
01 ROOF PLAN 12. Provide G.I. 125 x 100 rainwater down pipes and125 x

A
100 [Link] gutter with brackets etc. where shown.
height of the plinth walls
FOUNDATION PLAN 13. All painting to be 3 coats.

14. Splash apron of 1000mm along the perimeter of


building.

15. Samples of fittings, materials etc. to be produced &


approved before commencing work.

16. All windows to have P.C. cills, built in reinforced


concrete Pelmet boxes & timber internal window cills &
Skirtings.

17. Steel trusses/portal frames & purlins to be painted


with 2 coats of oil paint.
ROOF LVL ROOF LVL
18. Fire fighting equipment to be provided and installed

Roof notes 1,500 1,000 1,500 by Building Fire Consultants where shown on plan.

Roof pitch 25 degrees [Link] architectural drawings shall be read in


conjunction with the Structural drawings,Electrical-
Clay roofing tiles Mechanical drawings, Bills of Quantities & Technical
1,200

Ridge caps to match roof type Specifications. Any discrepancy shall be reported
immediately to the Architect.
100x50mm timber purlins on

2,590

2,590
150x50mm rafters on

2,100
100x50mm Strut & Tie on
20. The Architect shall not accept any liability for works
150x50mm Tie beam on which he has not been expressly instructed to Supervise
150x75mm wall plate and in writing and has accepted to proceed in writing, or
225x25mm Fascia board for any ommissions or deviations from his
drawings/technical specifications.
Nor shall he take responsibility for works handled by

150

150
other nominated Consultants or Contractors.
ROOF LVL
GROUND FLOOR LVL GROUND FLOOR LVL

150

450

150

450
Client:

150

150
ELEVATION 01 ELEVATION 02
2,590

2,590

OFFICE
SPACE CLIENT'S SIGNATURE...............................................

ROOF LVL ROOF LVL


100

150

GROUND FLOOR LVL


150
350

150

Project Name and Address:


PROPOSED OFFICE DEVELOPMENT TO BE
BUILT ON PLOT , BLOCK , ENTEBBE,
2,590

2,590
600
200

WAKISO DISTRICT
Foundation notes
100mm thick concrete floor slab to SE's details on
1000g polythene sheet water proofing,
50mm thick on murram blinding on
well compacted hardcore fill
Foundation depth to be determined on site SECTION A-A

150
GROUND FLOOR LVL GROUND FLOOR LVL Drawing Title:
TECHNICAL DOCUMENTATION
450

150
150
Job no: Drwg no:
ELEVATION 03 ELEVATION 04
Scales: 1:20, 1:50,
1:100
REVISIONS
Drawn by: No: Date Descriptions
MA
Checked by:

Date:
MARCH - 2025