Schedule

The document outlines the work breakdown schedule for the MANA SIRRESSA project, which includes the construction of a toilet and guard house with a total contract amount of 865,385.91 Birr. The project is contracted to ABDI BIYA CONST P.L.C and is scheduled to be completed in 3 months and 16 days, starting from April 1, 2016. It details various construction tasks, their respective costs, and timelines for completion.

Uploaded by

adaldigitalmaket
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views1 page

Schedule

The document outlines the work breakdown schedule for the MANA SIRRESSA project, which includes the construction of a toilet and guard house with a total contract amount of 865,385.91 Birr. The project is contracted to ABDI BIYA CONST P.L.C and is scheduled to be completed in 3 months and 16 days, starting from April 1, 2016. It details various construction tasks, their respective costs, and timelines for completion.

Uploaded by

adaldigitalmaket
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

KAROORA HOJII CACCABSAME/ WORK BREAKDOWN SCHEDULE

PROJECT: MANA SIRRESSA ,Toilet,Guard house CONTRACT AMOUNT 865,385.91


EMPLOYER:-MAKANIS OROMO WOREDA POLICE OFFICE CONTRACT TIME 3 months and 16 day
CONTRACTOR: ABDI BIYA CONST P.L.C COMMENCEMENT DATE 01/04/2016
CONTRACT AMOUNT WITH OUT VAT 865,385.91 100% COMPLETION DATE 25/06/2016
Value in Birr With Out VAT Execution period
Work Description
parcentage
start date
completion three months
date Month 1 Month 2 Month 3
amount % 1 2 3 4 1 2 3 4 1 2 3 4
A. Sub Structure 429,864.45 49.67 259615.773 259615.773
1. EXCAVATION & EARTH WORK 75,695.90 10,156.74 8.75 04/04/2016 10/04/2016 /
2. CONCRETE WORK 102,822.10 28,877.12 11.88 11/04/2016 15/04/2016 /
3. MASONRY WORK 251,346.45 21,298.08 29.04 20/04/2016 22/04/2016
B. Super Structure 435,521.46 50.33 346154.364 346154.364
1. CONCRETE WORK - 23/04/2016 30/04/2016
2. BLOCK WORK 131,398.07 24,595.07 15.18 01/05/2016 10/05/2016
3. ROOFING 106,068.96 28,570.64 12.26 11/05/2016 20/05/2016 259615.773 259615.773
4. CARPENTRY AND JOINERY 72,338.33 29,900.36 8.36 08/05/2016 12/05/2016
5. METAL WORK 56,000.00 17,000.00 13.03 12/05/2016 18/05/2016
[Link] 62,976.10 7.28 19/05/2016 22/05/2016
6. PAVING N FLOORING - - 23/05/2016 26/05/2016
7. PAINTING - - 26/05/2016 30/05/2016
[Link] 6,740.00 3,240.00 1.55 01/06/2016 10/06/2016
TOTAL Cost in (%) 865,385.91 100 259,615.77 346,154.36 259,615.77 865,385.91
VAT 129,807.89
Tot including Vat 995,193.80
PREPARED BY ________Guled hassen______________________ APPROVED BY____________________________
SIGNATURE___________________________________________ SIGNATURE_____________________
DATE______________30/11/23__________________________ DATE_______________________