Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( Speciliazed Training on Women Elected
1 2025-06-23,[Link] 2025-06-25,[Link] Conducted 36 0 0 0 11
DISTRICT - Sri Potti Representatives Sullurpet/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Speciliazed Training on Women Elected
2 2025-06-23,[Link] 2025-06-25,[Link] Conducted 36 0 0 0 0
DISTRICT - Sri Potti Representatives Sullurpet/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( Speciliazed Training on Women Elected
3 2025-06-23,[Link] 2025-06-25,[Link] Conducted 50 0 0 0 14
DISTRICT - Sri Potti Representatives Gudur/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Speciliazed Training on Women Elected
4 2025-06-23,[Link] 2025-06-25,[Link] Conducted 45 0 0 0 6
DISTRICT - Sri Potti Representatives Gudur/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( Speciliazed Training on Women Elected
5 2025-06-26,[Link] 2025-06-28,[Link] Conducted 48 2 2 3 17
DISTRICT - Sri Potti Representatives Kavali/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Speciliazed Training on Women Elected
6 2025-06-26,[Link] 2025-06-28,[Link] Conducted 44 0 0 0 7
DISTRICT - Sri Potti Representatives Kavali/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( Speciliazed Training on Women Elected
7 2025-06-26,[Link] 2025-06-28,[Link] Conducted 91 13 14 16 51
DISTRICT - Sri Potti Representatives Atmakur/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Speciliazed Training on Women Elected
8 2025-06-26,[Link] 2025-06-28,[Link] Conducted 19 2 2 2 9
DISTRICT - Sri Potti Representatives Atmakur/Batch : 2
Sriramulu Nellore )
Institute wise Scheduled Activity Tracker Report (2025-2026) of Andhra Pradesh (Sponsor: Rashtriya Gram Swaraj Abhiyan)
Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( Speciliazed Training on Women Elected
9 2025-07-02,[Link] 2025-07-04,[Link] Conducted 32 0 0 0 11
DISTRICT - Sri Potti Representatives Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Speciliazed Training on Women Elected
10 2025-07-02,[Link] 2025-07-04,[Link] Conducted 27 0 0 0 4
DISTRICT - Sri Potti Representatives Nellore/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( District Level Workshop on PAI Versin 2-0 SPSR
11 2025-07-05,[Link] 2025-07-05,[Link] Conducted 46 18 19 31 35
DISTRICT - Sri Potti Nellore District/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( District Level Workshop on PAI Versin 2-0 SPSR
12 2025-07-05,[Link] 2025-07-05,[Link] Conducted 47 14 16 37 38
DISTRICT - Sri Potti Nellore District/Batch : 3
Sriramulu Nellore )
District Panchayat
Resource Center( District Level Workshop on PAI Versin 2-0 SPSR
13 2025-07-05,[Link] 2025-07-05,[Link] Conducted 52 12 15 24 41
DISTRICT - Sri Potti Nellore District/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( ATMAKUR MADNAL - PAI VERSION - MANDAL LEVEL
14 2025-07-09,[Link] 2025-07-09,[Link] Conducted 63 10 11 14 33
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( KAVALI MANDAL - PAI VERSION - MANDAL LEVEL
15 2025-07-09,[Link] 2025-07-09,[Link] Conducted 69 4 4 6 38
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Kaluvoya Mandal - PAI Version - Mandal Level Training
16 2025-07-09,[Link] 2025-07-09,[Link] Conducted 40 22 22 26 30
DISTRICT - Sri Potti /Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Kaluvoya Mandal - PAI Version - Mandal Level Training
17 2025-07-09,[Link] 2025-07-09,[Link] Conducted 19 1 1 1 13
DISTRICT - Sri Potti /Batch : 2
Sriramulu Nellore )
Institute wise Scheduled Activity Tracker Report (2025-2026) of Andhra Pradesh (Sponsor: Rashtriya Gram Swaraj Abhiyan)
Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( Ananthasagaram Mandal - PAI Version - Mandal Level
18 2025-07-09,[Link] 2025-07-09,[Link] Conducted 73 28 29 29 48
DISTRICT - Sri Potti Training -Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( UDAYAGIRI MANDAL PAI VERSION MANDAL LEVEL
19 2025-07-09,[Link] 2025-07-09,[Link] Conducted 36 0 0 0 19
DISTRICT - Sri Potti TRAINING SPSR NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( KODAVALUR MANDAL-PAI VERSION- MANDAL LEVAL
20 2025-07-09,[Link] 2025-07-09,[Link] Conducted 41 15 15 16 31
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( KODAVALUR MANDAL-PAI VERSION- MANDAL LEVAL
21 2025-07-09,[Link] 2025-07-09,[Link] Conducted 41 3 3 3 9
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( Kondapuram Mandal PAI Verison - Mandal Level
22 2025-07-09,[Link] 2025-07-09,[Link] Conducted 67 0 0 0 13
DISTRICT - Sri Potti Training Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( SYDAPURAM MANDAL-PAI VERSION -MANDAL LEVEL
23 2025-07-09,[Link] 2025-07-09,[Link] Conducted 40 23 23 25 28
DISTRICT - Sri Potti TRAINING-NELLORE /Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( SYDAPURAM MANDAL-PAI VERSION -MANDAL LEVEL
24 2025-07-09,[Link] 2025-07-09,[Link] Conducted 45 1 1 1 23
DISTRICT - Sri Potti TRAINING-NELLORE /Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( Venkatachalam Mandal - PAI Version -Mandal Level
25 2025-07-09,[Link] 2025-07-09,[Link] Conducted 47 40 40 44 40
DISTRICT - Sri Potti Training-Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Venkatachalam Mandal - PAI Version -Mandal Level
26 2025-07-09,[Link] 2025-07-09,[Link] Conducted 40 36 36 38 37
DISTRICT - Sri Potti Training-Nellore/Batch : 2
Sriramulu Nellore )
Institute wise Scheduled Activity Tracker Report (2025-2026) of Andhra Pradesh (Sponsor: Rashtriya Gram Swaraj Abhiyan)
Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( Allur Mandal - PAI Version - Mandal Level Training
27 2025-07-09,[Link] 2025-07-09,[Link] Conducted 31 0 0 0 16
DISTRICT - Sri Potti Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Vakadu Mandal-PAI Version-Mandal Level Training-
28 2025-07-08,[Link] 2025-07-08,[Link] Conducted 54 26 26 29 34
DISTRICT - Sri Potti Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( BOGOLE MANDAL-PAI VERSION -MANDAL LEVEL
29 2025-07-09,[Link] 2025-07-09,[Link] Conducted 73 17 17 17 42
DISTRICT - Sri Potti TRAINING- NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( CHEJERLA MANDAL - PAI VERSION MANDAL
30 2025-07-09,[Link] 2025-07-09,[Link] Conducted 43 12 12 13 26
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( CHEJERLA MANDAL - PAI VERSION MANDAL
31 2025-07-09,[Link] 2025-07-09,[Link] Conducted 19 2 2 2 7
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( Jaladanki Mandal PAI-version -Mandala Level Training -
32 2025-07-09,[Link] 2025-07-09,[Link] Conducted 51 41 41 46 42
DISTRICT - Sri Potti Nellore/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( KALIGIRI MANDAL -PAI VERSION- MANDAL LEVEL
33 2025-07-08,[Link] 2025-07-08,[Link] Conducted 50 0 0 1 30
DISTRICT - Sri Potti TRAINING /Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( MUTHUKUR MANDAL - PAI VERSION - MANDAL LEVEL
34 2025-07-09,[Link] 2025-07-09,[Link] Conducted 37 14 14 15 32
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( MUTHUKUR MANDAL - PAI VERSION - MANDAL LEVEL
35 2025-07-09,[Link] 2025-07-09,[Link] Conducted 37 4 4 4 17
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 2
Sriramulu Nellore )
Institute wise Scheduled Activity Tracker Report (2025-2026) of Andhra Pradesh (Sponsor: Rashtriya Gram Swaraj Abhiyan)
Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( BUCHIREDDYPALEM MANDAL - PAI VERSION MANDAL
36 2025-07-09,[Link] 2025-07-09,[Link] Conducted 60 1 1 1 41
DISTRICT - Sri Potti LEVEL TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( DAGADARTHI MANDAL - PAI VERSION - MANDAL
37 2025-07-09,[Link] 2025-07-09,[Link] Conducted 34 1 2 4 20
DISTRICT - Sri Potti LEVEL TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( TPGUDUR MANDAL - PAI VERSION - MANDAL LEVEL
38 2025-07-09,[Link] 2025-07-09,[Link] Conducted 44 0 0 0 30
DISTRICT - Sri Potti TRAINING/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( TPGUDUR MANDAL - PAI VERSION - MANDAL LEVEL
39 2025-07-09,[Link] 2025-07-09,[Link] Conducted 42 0 0 0 5
DISTRICT - Sri Potti TRAINING/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( Vidavalur Mandal - PAI Version -Mandal Level Training
40 2025-07-09,[Link] 2025-07-09,[Link] Conducted 69 10 11 16 41
DISTRICT - Sri Potti -Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( VARIKUNTAPADU MANDAL - PAI VERSION - MANDAL
41 2025-07-09,[Link] 2025-07-09,[Link] Conducted 51 14 14 22 32
DISTRICT - Sri Potti LEVEL TRAINING- NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( VINJAMUR MANDAL -PAI VERSION- MANDAL LEVEL
42 2025-07-09,[Link] 2025-07-09,[Link] Conducted 52 33 35 34 43
DISTRICT - Sri Potti TRAINING/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( ASPETA MANDAL-PAI Version-Mandal Level
43 2025-07-09,[Link] 2025-07-09,[Link] Conducted 35 21 21 24 25
DISTRICT - Sri Potti Training/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( ASPETA MANDAL-PAI Version-Mandal Level
44 2025-07-09,[Link] 2025-07-09,[Link] Conducted 24 21 21 23 22
DISTRICT - Sri Potti Training/Batch : 2
Sriramulu Nellore )
Institute wise Scheduled Activity Tracker Report (2025-2026) of Andhra Pradesh (Sponsor: Rashtriya Gram Swaraj Abhiyan)
Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( SR Puram Mandal - PAI Version - Mandal level
45 2025-07-09,[Link] 2025-07-09,[Link] Conducted 42 0 0 0 14
DISTRICT - Sri Potti Training - Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( MANUBOLU MANDAL - PAI VERSION - MANDAL LEVEL
46 2025-07-09,[Link] 2025-07-09,[Link] Conducted 40 21 21 22 29
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( MANUBOLU MANDAL - PAI VERSION - MANDAL LEVEL
47 2025-07-09,[Link] 2025-07-09,[Link] Conducted 43 10 10 11 16
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( MARRIPADU MANDAL-PAI VERSION-MANDAL LEVEL
48 2025-07-09,[Link] 2025-07-09,[Link] Conducted 60 0 0 0 39
DISTRICT - Sri Potti TRAINING-NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( RAPUR MANDAL -PAI VERSION-MANDAL LEVEL
49 2025-07-09,[Link] 2025-07-09,[Link] Conducted 60 0 0 0 28
DISTRICT - Sri Potti TRAINING -NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( PODALAKUR MANDAL - PAI VERSION - MANDAL LEVEL
50 2025-07-09,[Link] 2025-07-09,[Link] Conducted 49 12 12 15 30
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 1 MEETING HALL 1
Sriramulu Nellore )
District Panchayat
Resource Center( PODALAKUR MANDAL - PAI VERSION - MANDAL LEVEL
51 2025-07-09,[Link] 2025-07-09,[Link] Conducted 48 10 11 12 34
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 2 MEETING HALL 2
Sriramulu Nellore )
District Panchayat
Resource Center( INDUKURPET MANDAL PAI Version -Mandal Level
52 2025-07-09,[Link] 2025-07-09,[Link] Conducted 50 4 4 5 22
DISTRICT - Sri Potti Training-Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( INDUKURPET MANDAL PAI Version -Mandal Level
53 2025-07-09,[Link] 2025-07-09,[Link] Conducted 40 3 6 3 14
DISTRICT - Sri Potti Training-Nellore/Batch : 2
Sriramulu Nellore )
Institute wise Scheduled Activity Tracker Report (2025-2026) of Andhra Pradesh (Sponsor: Rashtriya Gram Swaraj Abhiyan)
Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( DUTTALUR MANDAL - PAI VERSION - MANDAL LEVEL
54 2025-07-09,[Link] 2025-07-09,[Link] Conducted 42 17 17 19 28
DISTRICT - Sri Potti TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( CHILLAKUR MANDAL PAI VERSION MANDAL LEVEL
55 2025-07-09,[Link] 2025-07-09,[Link] Conducted 50 20 21 22 31
DISTRICT - Sri Potti TRAINING NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( CHILLAKUR MANDAL PAI VERSION MANDAL LEVEL
56 2025-07-09,[Link] 2025-07-09,[Link] Conducted 47 8 8 9 29
DISTRICT - Sri Potti TRAINING NELLORE/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( KOTA MANDAL PAI VERSION MANDAL LEVEL
57 2025-07-10,[Link] 2025-07-10,[Link] Conducted 67 16 17 18 21
DISTRICT - Sri Potti TRAINING -NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Sangam mandal-PAI Version-Mandal Level Training-
58 2025-07-10,[Link] 2025-07-10,[Link] Conducted 78 23 23 25 49
DISTRICT - Sri Potti Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( NAIDUPETA MANDAL-PAI VERSION-MANDAL LEVEL
59 2025-07-10,[Link] 2025-07-10,[Link] Conducted 60 26 27 30 36
DISTRICT - Sri Potti TRAINING -NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( SULLURUPETA MANDFAL - PAI Version - Level
60 2025-07-10,[Link] 2025-07-10,[Link] Conducted 43 14 14 15 25
DISTRICT - Sri Potti Program - SPSR NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Balayapalli Mandal - PAI Version - Mandal Level
Resource Center(
61 2025-07-10,[Link] 2025-07-10,[Link] Training - Nellore/Batch : 1 Balayapalli Mandal - PAI Conducted 57 54 54 62 55
DISTRICT - Sri Potti
Version - Mandal Level Training - Nellore
Sriramulu Nellore )
District Panchayat
Resource Center( CHITTAMURU MANDAL-PAI VERSION-MANDAL LEVEL
62 2025-07-10,[Link] 2025-07-10,[Link] Conducted 55 0 0 0 14
DISTRICT - Sri Potti TRAINING-NELLORE/Batch : 1
Sriramulu Nellore )
Institute wise Scheduled Activity Tracker Report (2025-2026) of Andhra Pradesh (Sponsor: Rashtriya Gram Swaraj Abhiyan)
Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( Ozili Mandal - PAI Version - Mandal Level Training -
63 2025-07-10,[Link] 2025-07-10,[Link] Conducted 49 2 2 3 37
DISTRICT - Sri Potti Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Gudur Mandal-PAI Version-Mandal Level Training -
64 2025-07-10,[Link] 2025-07-10,[Link] Conducted 50 38 38 40 42
DISTRICT - Sri Potti Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Gudur Mandal-PAI Version-Mandal Level Training -
65 2025-07-10,[Link] 2025-07-10,[Link] Conducted 25 12 12 13 12
DISTRICT - Sri Potti Nellore/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( TADA MANDAL -PAI VERSION-MANDAL LEVEL
66 2025-07-11,[Link] 2025-07-11,[Link] Conducted 80 5 6 6 68
DISTRICT - Sri Potti TRAINING /Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( DORAVARISATRAM MANDAL PAI VERSION 2 MANDAL
67 2025-07-11,[Link] 2025-07-11,[Link] Conducted 33 0 0 0 13
DISTRICT - Sri Potti LEVEL TRAINING NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Pellakuru mandal PAI Version Mandal level - Training -
68 2025-07-11,[Link] 2025-07-11,[Link] Conducted 56 26 27 31 53
DISTRICT - Sri Potti Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( VENKATAGIRI MANDAL - PAI VERSION - MANDAL
69 2025-07-11,[Link] 2025-07-11,[Link] Conducted 50 35 35 37 37
DISTRICT - Sri Potti LEVEL TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( VENKATAGIRI MANDAL - PAI VERSION - MANDAL
70 2025-07-11,[Link] 2025-07-11,[Link] Conducted 16 5 5 6 9
DISTRICT - Sri Potti LEVEL TRAINING - NELLORE/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( NELLORE RURAL MANDAL - PAI VERSION MANDAL
71 2025-07-11,[Link] 2025-07-11,[Link] Conducted 60 3 5 3 38
DISTRICT - Sri Potti LEVEL TRAINING - NELLORE/Batch : 1
Sriramulu Nellore )
Institute wise Scheduled Activity Tracker Report (2025-2026) of Andhra Pradesh (Sponsor: Rashtriya Gram Swaraj Abhiyan)
Total
Total No. of Participants Participants
Total No. of Total No. of e-
S.N Training Trainee Attempted Authenticate
Organization name Training From Date Training to Date Training Name Participants Certificate
o. Status submit PTA(Post d with
uploaded Issued
feedback Training Aadhaar
Assessment)
District Panchayat
Resource Center( DAKKILI MANDAL-PAI VERSION-MANDAL LEVEL
72 2025-07-11,[Link] 2025-07-11,[Link] Conducted 65 28 28 29 34
DISTRICT - Sri Potti TRAINING -NELLORE/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Kovur Mandal, PAI Version, Mandal Level Training -
73 2025-07-11,[Link] 2025-07-11,[Link] Conducted 50 19 19 19 42
DISTRICT - Sri Potti Nellore/Batch : 1
Sriramulu Nellore )
District Panchayat
Resource Center( Kovur Mandal, PAI Version, Mandal Level Training -
74 2025-07-11,[Link] 2025-07-11,[Link] Conducted 43 11 11 12 20
DISTRICT - Sri Potti Nellore/Batch : 2
Sriramulu Nellore )
District Panchayat
Resource Center( District Level Women ZPTC MPTC Specialized
75 2025-07-24,[Link] 2025-07-26,[Link] Conducted 29 6 6 8 9
DISTRICT - Sri Potti Training/Batch : 1
Sriramulu Nellore )
Total 3537 889 913 1042 2039