The Federal Democratic Republic of Ethiopia
Sugar Corporation,
Addis Ababa
Ref: Arjo-Didessa Sugar Development Project
(Supervision of 4369ha Irrigation, Drainage and Road Infrastructure Works)
Subject: Sending Annual Progress Report for 2007EFY (June 2015)
Dear Sir/Madam,
On the basis of the Amended Contract Agreement signed with your esteemed Corporation for the
Contract Administration and Supervision of the Arjo-Didessa Sugar Development Project (Supervision of
4369ha Irrigation, Drainage and Road Infrastructure Works) on August 8, 2014, we have been delivering
the Consultancy Services to the project.
Please find two copies of 19 pages of Progress Report with 18 pages of appendixes for the year 2007EFY
(June 2015) attached to this letter.
With Regards.
C.C
Chief executive office (W/O Enclosure)
Chief Operation Office(W/O Enclosure)
Construction Supervision core Process Office(With Enclosure)
Technical Works Coordination Office(W/O Enclosure)
Planning, Business Development & Contract Administration Process(W/O Enclosure)
Irrigation & Drainage Construction Supervision Sub-Process(With Enclosure)
Arjo-Dhidhessa Sugar Development Construction Supervision Project Office(With
Enclosure)
OWWDSE
Finfinne
Arjo-Didessa Sugar Development Project(4369ha) CAS Resident Office(With Enclosure)
Arjo-Dhidhesa