BOQ Sample
BOQ Sample
Say ₹ 77,17,700.00
In Words:-
SEVENTY SEVEN LAKHS SEVENTEEN THOUSANDS SEVEN HUNDREAD ONLY.
Note:- This Estimate is as per SOR of Bihar w.e.f 01.01.2022.
GROUND FLOOR
Item
Ref. Item Unit Quantity Rate Amount
No.
CONSTRUCTION OF RESIDENTIAL BUILDING.
Page 1
Item
Ref. Item Unit Quantity Rate Amount
No.
8 Reinforced cement concete work in beams,
suspended floors, roofs having slope upto 15,
landings, balconies, shelves, chajjas, lintels bands,
5.3 & plain windows sills, staircase and spiral stair cases
cum 27.29 5719.70 156110.23
5.33B.4 upto floor five level excluding the cost of centring,
shuttering, finishing and reinforcement with 1 : 1.5 : 3
( 1 cement : 1.5 coarse sand : 3 graded stone
aggregate 20 mm nominal size).
9 Extra for providing and mixing water prooding per 50
4.12 material in cement concrete work in the proportion kg 299.75 57.16 17133.53
recommended by the manufacturers. cement
10 Centring and shuttering including strutting, propping etc. and removal of form for all
5.9
height.
Foundations, footings, bases of columns etc. for mass
A 5.9.1 sqm 40.91 211.60 8656.56
concrete.
Lintels, beams, plinth bams, griders, bressumers and
B 5.9.5 sqm 85.75 375.10 32165.58
contilevers.
Suspended floors, roofs, landings, balconies and
C 5.9.20 sqm 91.16 437.50 39881.10
access platform with proof ply 12mm thick.
D 5.9.6 Columns, pillars, piers, abutments, posts and struts. sqm 69.84 437.50 30553.25
Stairs, ( excluding landings) excepted spiral-staircase.
E 5.9.7 sqm 8.90 404.70 3601.75
11 Providing and laying damp-proof course 50mm thick
with cement ( [Link]) ( 1 cements : 2 coarse sand : 4
4.11 sqm 20.46 245.60 5023.75
graded stone aggregate 20 mm nominal size.
Page 2
Item
Ref. Item Unit Quantity Rate Amount
No.
14 Providing and fixing circular/hexagonal cast iron or
M.S sheet box for ceiling fan clamp 140mm internal
dia, 73mm height, 5 mm thick rim bottom and top
lids, 1.5 mm thick M.S sheet with its top surface
10.18 hacked for proper bonding top lid shall be shall be Each 10 165.4 1654.00
screwed into the cast iron box by means of 3.3 mm
dia rounded headed screws, one lock at the corners.
Clamps shall be made of 12 mm dia M.S bar bent to
shape as per standard drawing.
15 Providing and fixing M.S grills of required pattern in
frames of windows etc. with M.S flats, square or
9.48.1 kg 337.47 144.50 48764.34
rounded bars etc. including priming coat with
approved steel primer all complete.
TOTAL FOR STEEL WORK = 593468.71
Page 3
Item
Ref. Item Unit Quantity Rate Amount
No.
22 Providing and fixing glazing in aluminium door,
window, ventilator shutters and partitions etc. with
EPDM / neoprene gasket etc. complete as per the
21.3.1 architectural drawings and the directions of Engineer- sqm 9.95 809.30 8055.93
in-charge. ( Coat of aluminium snap beading shall be
paid in basic item): With float glass panes of 4.0 mm
thickness.
TOTAL FOR WOOD & ALUMINIUM WORK = 200969.45
Page 4
Item
Ref. Item Unit Quantity Rate Amount
No.
30 Cement per/bag 599.02 11.61 6954.67
per/1000
31 Bricks Nos
20031.28 747.6 14975.39
Page 5
DETAILED ESTIMATE OF GROUND FLOOR
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
1 Earth work excavation in foundation
Total 84.70
Total 4.59
4
Providing Brick flat soling in trenches.
Page 1
4
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
Brick flat soling for grade beam sqm 81.82 0.23 18.82
Brick flat soiling inside for P.C.C sqm 7.92 12.27 97.18
Total 158.35
5 Brick work with bricks of class designation 100A
in foundations and plinth in : Cement motar 1 : cum 40.38 0.23 0.6 5.57
4 ( 1 cement : 4 coarse sand ).
6 Brick work in superstructure cement motar (1:6) a complete job.
115mm Brick Work, Outer Wall cum 14.94 0.115 2.50 4.29
Page 2
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
Total 27.95
i.e cum 27.95 0.115 3.21
Deduction door and window in wall. 34.18 3.21 30.97
7 R.C.C work below foundation level.
Total 24.98
8 R.C.C work above foundation level.
Page 3
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
Total 27.29
per 50 kg
9 Extra for providing & mixing W.P.M 24.98 0.6 1000 299.75
cement
Total 85.75
C Roofing slab sqm 7.92 12.27 97.18
Total 91.16
Total 105.15
Circular/hexagonal cast iron or M.S sheet box
14 Each 10 10
for ceiling fan
15 M.S Grills kg 12.55 12.55 sqm x 26.89Kg/sqm 337.47
Page 4
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
Bright finished brass hanging type floor door
20 Each 5.00 5.00
stopper with necessary srews etc.
Page 5
QUANTITY STAGE BY STAGE OF GROUND FLOOR
Concrete CEMENT SAND AGGREGATE STEEL QUANTITY
SR NO. WORK UPTO
Cum Bags cum cum STEEL 8mm 10mm 12mm 16mm 20mm 25mm
2 Grade / Plinth Beam 5.11 41.11 2.15 4.30 536.94 134.24 53.69 349.01
3 Column Upto First floor Lvl. 5.31 42.73 2.23 4.46 558.05 111.61 167.41 279.02
4 Lintel & Other Work 3.11 25.03 1.31 2.62 326.93 65.39 98.08 163.46
5 Beam at First floor Lvl. 6.56 52.72 2.75 5.51 688.47 137.69 206.54 344.24
6 Slab at First floor Lvl. 13.12 105.45 5.51 11.02 1377.13 1377.13
Page 1
Material Statement of Ground Floor
S no. Items of work Qty. Cement (cum) [Link](cum) Stone chips(cum) Local Sand(cum) Bricks(Nos)
599.02 Bags
FIRST FLOOR
Item
Ref. Item Unit Quantity Rate Amount
No.
CONSTRUCTION OF RESIDENTIAL BUILDING.
Page 1
Item
Ref. Item Unit Quantity Rate Amount
No.
Providing and fixing circular/hexagonal cast iron or M.S
sheet box for ceiling fan clamp 140mm internal dia, 73mm
height, 5 mm thick rim bottom and top lids, 1.5 mm thick
M.S sheet with its top surface hacked for proper bonding
6 10.18 top lid shall be shall be screwed into the cast iron box by Each 17 165.4 2811.80
means of 3.3 mm dia rounded headed screws, one lock at
the corners. Clamps shall be made of 12 mm dia M.S bar
bent to shape as per standard drawing.
Page 2
Item
Ref. Item Unit Quantity Rate Amount
No.
TOTAL FOR WOOD & ALUMINIUM WORK = 211073.02
Page 4
DETAILED ESTIMATE OF FIRST FLOOR
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
1
Brick work in superstructure cement motar (1:6) a complete job.
Total 27.05
Page 1
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
Total 27.83
Total 76.24
B Roof slab sqm 7.92 12.27 97.18
Deduction staircase Area sqm -1 4.51 2.16 -9.74
Total 89.30
C Centring and shuttering of column sqm 13 0.25 0.45 3.00 54.60
D Stairs sqm 2 0.94 4.89 9.19
Deduction (total Slab area - stair area) cum 97.18 21.6 75.58
Page 3
QUANTITY STAGE BY STAGE OF FIRST FLOOR
Concrete CEMENT SAND AGGREGATE STEEL QUANTITY
SR NO. WORK UPTO
Cum Bags cum cum STEEL 8mm 10mm 12mm 16mm 20mm 25mm
1 Column from First to 2nd floor Lvl. 4.51 36.24 1.89 3.79 473.28 94.66 236.64 141.98
2 Lintel & Other Work 3.88 31.20 1.63 3.26 407.48 81.50 122.24 203.74
3 Beam at second floor Lvl. 6.33 50.88 2.66 5.32 664.48 132.90 199.34 332.24
4 Slab at second floor Lvl. 13.12 105.45 5.51 11.02 1377.13 1377.13
Page 1
Material Statement of First Floor
S no. Items of work Qty. Cement (cum) [Link](cum) Stone chips(cum) Bricks(Nos)
296.41 Bags
SECOND FLOOR
Item
Ref. Item Unit Quantity Rate Amount
No.
CONSTRUCTION OF RESIDENTIAL BUILDING.
Page 1
Item
Ref. Item Unit Quantity Rate Amount
No.
Providing and fixing circular/hexagonal cast iron or M.S
sheet box for ceiling fan clamp 140mm internal dia, 73mm
height, 5 mm thick rim bottom and top lids, 1.5 mm thick
M.S sheet with its top surface hacked for proper bonding
6 10.18 top lid shall be shall be screwed into the cast iron box by Each 17 165.4 2811.80
means of 3.3 mm dia rounded headed screws, one lock at
the corners. Clamps shall be made of 12 mm dia M.S bar
bent to shape as per standard drawing.
Page 2
Item
Ref. Item Unit Quantity Rate Amount
No.
TOTAL FOR WOOD & ALUMINIUM WORK = 211073.02
Page 4
DETAILED ESTIMATE OF SECOND FLOOR
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
1
Brick work in superstructure cement motar (1:6) a complete job.
Total 27.05
Page 1
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
Total 27.83
Total 76.24
B Roof slab sqm 7.92 12.27 97.18
Deduction staircase Area sqm -1 4.51 2.16 -9.74
Total 89.30
C Centring and shuttering of column sqm 13 0.25 0.45 3.00 54.60
D Stairs sqm 2 0.94 4.89 9.19
Deduction (total Slab area - stair area) cum 97.18 21.6 75.58
Page 3
Material Statement of Second Floor
S no. Items of work Qty. Cement (cum) [Link](cum) Stone chips(cum) Bricks(Nos)
296.41 Bags
QUANTITY STAGE BY STAGE OF SECOND FLOOR
Concrete CEMENT SAND AGGREGATE STEEL QUANTITY
SR NO. WORK UPTO
Cum Bags cum cum STEEL 8mm 10mm 12mm 16mm 20mm 25mm
1 Column from First to 2nd floor Lvl. 4.51 36.24 1.89 3.79 473.28 94.66 236.64 141.98
2 Lintel & Other Work 3.88 31.20 1.63 3.26 407.48 81.50 122.24 203.74
3 Beam at second floor Lvl. 6.33 50.88 2.66 5.32 664.48 132.90 199.34 332.24
4 Slab at second floor Lvl. 13.12 105.45 5.51 11.02 1377.13 1377.13
Page 1
THIRD FLOOR
Item
Ref. Item Unit Quantity Rate Amount
No.
CONSTRUCTION OF RESIDENTIAL BUILDING.
Page 1
Item
Ref. Item Unit Quantity Rate Amount
No.
Providing and fixing circular/hexagonal cast iron or M.S
sheet box for ceiling fan clamp 140mm internal dia, 73mm
height, 5 mm thick rim bottom and top lids, 1.5 mm thick
M.S sheet with its top surface hacked for proper bonding
6 10.18 top lid shall be shall be screwed into the cast iron box by Each 17 165.4 2811.80
means of 3.3 mm dia rounded headed screws, one lock at
the corners. Clamps shall be made of 12 mm dia M.S bar
bent to shape as per standard drawing.
Page 2
Item
Ref. Item Unit Quantity Rate Amount
No.
TOTAL FOR WOOD & ALUMINIUM WORK = 211073.02
Page 4
DETAILED ESTIMATE OF THIRD FLOOR
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
1
Brick work in superstructure cement motar (1:6) a complete job.
Total 27.05
Page 1
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
Total 27.83
Total 76.24
B Roof slab sqm 7.92 12.27 97.18
Deduction staircase Area sqm -1 4.51 2.16 -9.74
Total 89.30
C Centring and shuttering of column sqm 13 0.25 0.45 3.00 54.60
D Stairs sqm 2 0.94 4.89 9.19
Deduction (total Slab area - stair area) cum 97.18 21.6 75.58
Page 3
QUANTITY STAGE BY STAGE OF THIRD FLOOR
Concrete CEMENT SAND AGGREGATE STEEL QUANTITY
SR NO. WORK UPTO
Cum Bags cum cum STEEL 8mm 10mm 12mm 16mm 20mm 25mm
1 Column from First to 2nd floor Lvl. 4.51 36.24 1.89 3.79 473.28 94.66 236.64 141.98
2 Lintel & Other Work 3.88 31.20 1.63 3.26 407.48 81.50 122.24 203.74
3 Beam at second floor Lvl. 6.33 50.88 2.66 5.32 664.48 132.90 199.34 332.24
4 Slab at second floor Lvl. 13.12 105.45 5.51 11.02 1377.13 1377.13
Page 1
Material Statement of Third Floor
S no. Items of work Qty. Cement (cum) [Link](cum) Stone chips(cum) Bricks(Nos)
296.41 Bags
MUMTY & PARAPET
Item
Ref. Item Unit Quantity Rate Amount
No.
CONSTRUCTION OF RESIDENTIAL BUILDING.
Centring and shuttering including strutting, propping etc. and removal of form for
3 5.9
all height.
Lintels, beams, plinth bams, griders, bressumers and
A 5.9.5 sqm 7.45 375.10 2794.50
contilevers.
Suspended floors, roofs, landings, balconies and
B 5.9.20 sqm 11.96 437.50 5232.50
access platform with proof ply 12mm thick.
C 5.9.6 Columns, pillars, piers, abutments, posts and struts. sqm 10.40 437.50 4550.00
Page 1
Item
Ref. Item Unit Quantity Rate Amount
No.
S.H.-4 : WOOD & ALUMINIUM WORK.
Providing wood work in frames of doors, windows, clerestory windows and other frames,
9.1 wrought frames and fixed in position with hold fast lugs or with dash fasteners of required dia &
6 length ( hold fast lugs or dash fastener shall be paid for separately.
9.1.2 Kiln seasoned and chemically treated hollock wood. cum 0.30 95670.70 28672.51
Providing and fixing ISI marked flush door shutters conforming to IS : 2202 ( Part 1)
non- decorative type, core of block board construction with with frame of 1st clas
9.21
hard wood and well matched commercial 3 ply veneering with vertical grains or
7
cross bands and face veneers on both faces of shutters:
35mm thick including ISI marked stainless steel butt
9.21.1 sqm 2.56 1775.30 4537.67
hinges with necessary screws.
Providing and fixing aluminium tower bolts, ISI marked, anodised ( anodic coated
9.97 not less than grade AC 10 as per IS : 1868 ), transported or dyed to required colour
8 or shade, with necesssary screws etc. complete :-
9.97.1 300 x 10 mm Each 1.00 111.40 111.40
Providing and fixing bright finished brass 100 mm
mortic latch with one dead bolt and a pair of lever
9 9.77 Each 1.00 519.00 519
handles of approved quality with necessary screws
etc. complete job.
Providing and fixing bright finished brass hanging
10 9.82 Each 1.00 108.1 108.1
type floor door stopper with necessary srews etc.
Providing and fixing aluminium die cast body tubular
type universal hydraulic door closer ( having brand
logo with ISI, IS : 3564, embossed on the body, door
11 9.83 Each 1.00 979.5 979.5
weight upto 35 kg and door width upto 700 mm),
with necessary accessories and screws etc.
complete.
Providing and fixing glazing in aluminium door,
window, ventilator shutters and partitions etc. with
EPDM / neoprene gasket etc. complete as per the
12 21.3.1 architectural drawings and the directions of sqm 4.00 809.30 3233.96
Engineer-in-charge. ( Coat of aluminium snap
beading shall be paid in basic item): With float glass
panes of 4.0 mm thickness.
TOTAL FOR WOOD & ALUMINIUM WORK = 38162.14
Page 2
Item
Ref. Item Unit Quantity Rate Amount
No.
S.H.-6 : PLASTER WORK
Page 3
DETAILED ESTIMATE OF MUMTY & PARAPET
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
1 Brick work in superstructure cement motar (1:6)
cum 13.34 0.125 2.6 4.34
a complete job.
Brick Work of Parapet cum 40.24 0.125 0.95 4.78
Total 4.18
Total 3.03
Total 7.45
B
Roof slab sqm 4.6 2.6 11.96
Total 11.96
C
Centring and shuttering of column sqm 4 0.25 4 2.6 10.40
Page 1
Item MEASUREMENT
Description Units Qunatity
No. No. Length Breadth Height
Page 2
Material Statement of Mumty & Parapet
S no. Items of work Qty. Cement (cum) [Link](cum) Stone chips(cum) Bricks(Nos)
52.53 Bags