0% found this document useful (0 votes)
13 views1 page

Parkplace Billing No. 7

This document is Billing No. 7 for a proposed 3-storey residence in Parkplace Village, detailing various construction costs and accomplishments as of October 20, 2025. The total gross billable amount is ₱418,300.44, with a net billable amount of ₱276,501.43 after deductions for recoupment and retention. It includes a breakdown of costs for supervision, construction works, and materials, along with payment terms and conditions.

Uploaded by

Jonah Dave Vega
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views1 page

Parkplace Billing No. 7

This document is Billing No. 7 for a proposed 3-storey residence in Parkplace Village, detailing various construction costs and accomplishments as of October 20, 2025. The total gross billable amount is ₱418,300.44, with a net billable amount of ₱276,501.43 after deductions for recoupment and retention. It includes a breakdown of costs for supervision, construction works, and materials, along with payment terms and conditions.

Uploaded by

Jonah Dave Vega
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Billing No.

7
October 20, 2025
Proposed 3-Storey Residence with Roof Deck
Lot 7 Block 3, Neighborhood A, Parkplace Village, Anabu-1D, Imus, Cavite
Accomplishment %wt of
Item Amount %wt Total % Present Billable Amount
Previous Present To Date present
Supervision ₱506,000.00 6.44% 5.80% 0.64% 6.44% 100% 10% ₱50,600.00
Site Clearing, Layout & Temp. Fac. ₱217,800.00 2.77% 2.77% 0.00% 2.77% 100% ₱0.00
Soil Excavation ₱39,611.28 0.50% 0.50% 0.00% 0.50% 100% ₱0.00
Septic Tank Works ₱24,535.31 0.31% 0.31% 0.00% 0.31% 100% ₱0.00
Foundation: Formwork, Rebars, Concreting ₱266,584.65 3.39% 3.39% 0.00% 3.39% 100% ₱0.00
p; ₱335,603.29 4.27% 4.27% 0.00% 4.27% 100% ₱0.00
Soil Backfill ₱52,459.00 0.67% 0.67% 0.00% 0.67% 100% ₱0.00
Slab On Grade Works ₱230,295.70 2.93% 2.93% 0.00% 2.93% 100% ₱0.00
Stair: Formwork, Rebars, Concreting ₱108,672.17 1.38% 1.38% 0.00% 1.38% 100% ₱0.00
Ground Column: Formwork, Rebars, Concreting ₱225,196.25 2.87% 2.87% 0.00% 2.87% 100% ₱0.00
Second Floor Beams: Formwork, Rebars, Concreting ₱424,272.29 5.40% 5.40% 0.00% 5.40% 100% ₱0.00
Second Floor Slab: Formwork, Rebars, Concreting ₱231,299.90 2.94% 2.94% 0.00% 2.94% 100% ₱0.00
Second Floor Column: Formworks, Rebars, Concreting ₱225,196.25 2.87% 2.87% 0.00% 2.87% 100% ₱0.00
Third Floor Beams: Formworks, Rebars, Concreting ₱412,007.39 5.25% 5.25% 0.00% 5.25% 100% ₱0.00
Third Floor Slab: Formworks, Rebars, Concreting ₱235,558.16 3.00% 3.00% 0.00% 3.00% 100% ₱0.00
Third Floor Column: Formworks, Rebars, Concreting ₱225,196.25 2.87% 2.87% 0.00% 2.87% 100% ₱0.00
Miscellaneous Concreting Works (Canopy, etc) ₱45,838.70 0.58% 0.58% 0.00% 0.58% 100% ₱0.00
Roof Beams: Formwork, Rebars, Concreting ₱160,499.32 2.04% 2.04% 0.00% 2.04% 100% ₱0.00
Roof Framing ₱55,711.94 0.71% 0.71% 0.00% 0.71% 100% ₱0.00
Roofing Works ₱199,479.64 2.54% 2.54% 0.00% 2.54% 100% ₱0.00
Water Proofing Works ₱37,895.00 0.48% 0.48% 0.00% 0.48% 100% ₱0.00
Electrical Works ₱272,836.99 3.47% 3.47% 0.00% 3.47% 100% ₱0.00
Ceiling Works ₱55,230.00 0.70% 0.70% 0.00% 0.70% 100% ₱0.00
Plumbing Works ₱164,291.95 2.09% 2.09% 0.00% 2.09% 100% ₱0.00
CHB Laying ₱787,951.26 10.03% 10.03% 0.00% 10.03% 100% ₱0.00
CHB Plastering ₱409,254.55 5.21% 5.21% 0.00% 5.21% 100% ₱0.00
Stair Railings/Planks ₱110,220.00 1.40% 0.70% 0.70% 1.40% 100% 50% ₱55,110.00
Installation of Doors ₱255,024.00 3.25% 3.25% 0.00% 3.25% 100% ₱0.00
Installation of Windows ₱283,263.75 3.61% 3.25% 0.36% 3.61% 100% 10% ₱28,326.38
Floor Finishing Works ₱464,502.23 5.91% 5.32% 0.59% 5.91% 100% 10% ₱46,450.22
Interior Painting ₱336,034.12 4.28% 2.99% 1.28% 4.28% 100% 30% ₱100,810.23
Exterior Painting ₱456,678.68 5.81% 4.07% 1.74% 5.81% 100% 30% ₱137,003.61
₱7,855,000.00 100.00% 94.67% 5.33% 100.00% ₱418,300.44
30% Downpayment: ₱2,356,500.00
Gross Billable Amount: ₱418,300.44
Recoupment: (₱125,490.13)
5% Retention: (₱20,915.02) Total Retention: ₱ 392,750.00 (to be released 60 days upon acceptance of turnover
Previous Billing: ₱266,865.71 or release of occupancy permit whichever comes first)
Net Billable Amount: ₱276,501.43
Sliding Steel Door: ₱25,500.00 (excluded in the contract)
Prepared by: ₱302,001.43