Rigger II Main Test 02

The document outlines various scenarios involving the use of a Grove Crane RT65S and RT755S, detailing the required boom lengths, gross capacities, and weights of load handling devices for different setups. Each scenario includes multiple-choice questions related to crane operations, emphasizing safety and operational limits. The content serves as a training or assessment tool for riggers and crane operators.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
82 views44 pages

Rigger II Main Test 02

The document outlines various scenarios involving the use of a Grove Crane RT65S and RT755S, detailing the required boom lengths, gross capacities, and weights of load handling devices for different setups. Each scenario includes multiple-choice questions related to crane operations, emphasizing safety and operational limits. The content serves as a training or assessment tool for riggers and crane operators.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

RIGGER II

NAME: ID#: DATE:

allow 5 ft for
hook block & 15 ton
hoist line 1 sheave
hook block

32 ft boom
[Link]

new
load
50' weight

40 ton 3
sheave
hook 5'

5'

35' 20'

50'

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED 360* .

1. WHAT IS THE BOOM LENGTH IS REQUIRED AT NEW LOCATION ?

A. 80 FT B. 112 FT C. 74 FT D. 68 FT

1
RIGGER II 02
RIGGER II

allow 10 ft for
hook block & 10 ton
hoist line H/ACE BALL

32 ft boom
[Link]

new
load
50' weight

40 ton 3
sheave
hook 5 ft

5 ft

30' 25'

50'

USING GROVE CRANE RT65s ON OUTRIGGERS FULLY EXTENDED 360* .

2. WHAT IS THE GROSS CAPACITY AT NEW LOCATION ?

A. 9,390 lbs B. 8,560 lbs C. 16,300 lbs D. 10,270 lbs

2
RIGGER II 02
RIGGER II

allow 6 FT for
hook block & 10 ton
hoist line headache
ball

32 FT
boom

load
weight
new
pic up point
30

40 ton 3
sheave
hook 10 FT

10

30 FT 25

50 FT

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED 360* .

3. WHAT IS WEIGHT OF LOAD HANDLING DEVICES ?

A. 3,814 LBS B. 1,140 LBS C. 2,090 LBS D. 1,445 LBS

3
RIGGER II 02
RIGGER II

allow 10' ft for


hook block &
hoist line

32 ft boom
[Link]
15 ton
1
sheave load
hook weight
new block
pick up point
55

40 ton
3
sheave 5'
hook
block
10'

35' 40'

60

USING GROVE CRANE RT65S, 35 METRIC TON CAP, RANGE DIAGRAM OVER FRONT .

[Link] ANGLE IS THE BOOM TIP AT THE PICK UP POINT?

A. 67° B. 70° C. 56° D. 60°

4
RIGGER II 02
RIGGER II

Allow 3m for hook Aux boom head


block and hoist line
clearance installed

10 ton 7.3m jib 30


degree offset
Headache
ball

43.3 boom EXT


3m

50 ton 4
sheave
hook block
Load weight 10 m
4,768 KG

10 m

USING GROVE CRANE RT75S ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

5. WHAT IS WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 6,477 KG B. 7,944 KG C. 3,262 KG D. 8,032 KG

5
RIGGER II 02
RIGGER II

Allow 5 ft for hook


block and hoist line
clearance
load weight 2,500
lbs
5' 24 ft jib 5
degree offset

5 ton H/ache 32 ft boom Ext


ball

15 ton 1
85' sheave hook
block

45'

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

6. WHAT BOOM LENGTH IS REQUIRED AT THE PICK UP POINT ?

A. 112 FT B. 80 FT C. 80 FT + 56 FT D. 112 FT + 24 FT

6
RIGGER II 02
RIGGER II

Allow 10 ft for hook


block and hoist line
clearance
load weight 1000
lbs
10' 24 ft jib 5
degree offset

5 ton H/ache 32 ft boom Ext


ball

15 ton 1
60' sheave hook
block

80'

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

7. WHAT IS THE GROSS CAPACITY AT THE PICK UP POINT ?

A. 6,500 LBS B. 4,810 LBS C. 5,320 LBS D. 4,520 LBS

7
RIGGER II 02
RIGGER II

Allow 2 m for hook block and


hoist line clearance

load weight 2000 kg


3m 7.3m jib 17*
degree offset

7.5 ton 43.3m boom Ext


H/ache ball

15 ton 1
24 sheave hook
block

21

USING GROVE CRANE RT755 ON OUTRIGGERS FULLY EXTENDED 360* .

8. WHAT IS WEIGHT OF LOAD HANDLING DEVICES ?

A. 3,112 kg B. 277 kg C. 1,470 kg D. 821 kg

8
RIGGER II 02
RIGGER II

Allow 10 ft for hook block


and hoist line clearance

Load
5 ton
weight
24 ft jib 30
Headache
5.000 degree offset
ball final
lbs
placement of
load
50'
32ft boom Ext

40 ton 3
sheave hook
9'
block

25'
20'
30'

USING GROVE CRANE RT65S, 35 METRIC TON CAP, RANGE DIAGRAM 360.

9. WHAT ANGLE IS THE BOOM TIP AT THE FINAL PLACEMENT OF LOAD?

A. 58° B. 70° C. 67° D. 55°

9
RIGGER II 02
RIGGER II

Allow 3m for hook


block and hoist line
clearance

5 ton
7.3m jib 30
Headache
ball
degree offset

Load
12m 9.7m boom Ext
weight
3356
kg 15 ton 1
sheave hook
block

9m
7
16m

USING GROVE CRANE RT75S ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

10. WHAT IS THE WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 3,565 KG B. 2,840 KG C. 6,196 KG D. 4,729 KG

10
RIGGER II 02
RIGGER II

Allow 5 FT for hook block


and hoist line clearance

7.5 ton 24 FT jib 17


degree offset
Headache
ball

32 FT boom
EXT
10'

15 ton 1
sheave hook
block
Load weight 80'
3,250 LBS

70 FT

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED 360°.

11. WHAT IS BOOM LENGTH REQUIRED AT THE PICK UP POINT ?

A. 112 FT+ 24 FT B. 112 FT+ 80 FT C. 112 FT D. 112 FT + 32 FT

11
RIGGER II 02
RIGGER II

Allow 10' for hook


block and hoist line
clearance

5 ton 24ft jib 17


degree offset
Headache ball

32ft boom EXT


10ft

40 ton 3
sheave hook
block
Load weight 40ft
2500 lbs

45'

USING GROVE CRANE RT65s ON OUTRIGGERS FULLY EXTENDED 360* .

12. WHAT IS THE GROSS CAPACITY AT THE PICK UP POINT ?

A. 12,520 lbs B. 10,330 lbs C. 12,000 lbs D. 10,270 lbs

12
RIGGER II 02
RIGGER II

Allow 3 M for hook Aux boom head


block and hoist line
clearance installed

10 ton 7.3 M jib 30


degree offset
Headache
ball

43.3 M boom
EXT
3M

50 ton 4
sheave hook
block
Load weight 10 M
5500 KG

10 m

USING GROVE CRANE RT75S ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

13. WHAT IS WEIGHT OF LOAD HANDLING DEVICES ?

A. 545 KG B. 3,632 KG C. 3,176 KG D. 631 KG

13
RIGGER II 02
RIGGER II

crane set up: on outriggers fully extended

Allow 10' for hook


block and hoist line
clearance

5 ton
24 ft jib 30
Headache
ball
degree offset final
placement of
load
Load
80' 32 ft boom Ext
weight
800 lbs
15 ton 1
sheave hook
block

50'
35'
60'

USING GROVE CRANE RT65S, 35 METRIC TON CAP, RANGE DIAGRAM .

14. WHAT ANGLE IS THE BOOM TIP AT THE FINAL PLACEMENT OF LOAD?

A. 55° B. 63° C. 50° D. 70°

14
RIGGER II 02
RIGGER II

crane load handling devices: 40 ton 3 sheave hook block


32 ft boom extinsion stowed
Auxillary boom head (15'')

allow 5 ft of hoist line clearance between boom


tip and hook block

40 ft

7 ft

30 ft

3 ft

60 ft

concrete slab+rigging = 12756 lbs

USING GROVE CRANE RT65s ON OUTRIGGERS FULLY EXTENDED 360* .

15. WHAT IS WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 13.891 lbs B. 13701 lbs C. 16260 lbs D. 1.135 lbs

15
RIGGER II 02
RIGGER II

Allow 3 m for hook


block and hoist line
clearance

5 ton 7.3m jib offset

Headache
ball

43.2 m boom
9.7 boom+33.5
2m
EXT

15 ton 1
sheave hook
block
Load weight 11m
2000 kg

20 m

USING GROVE CRANE RT755 ON OUTRIGGERS FULLY EXTENDED 360°.

16. WHAT IS BOOM LENGTH REQUIRED AT THE PICK UP POINT ?

A. 25.9m B. 33.5 m C. 22.9 m D. 35.7 m

16
RIGGER II 02
RIGGER II

Allow 10' for hook


block and hoist line
clearance

5 ton 24ft jib 17


degree offset
Headache
ball

32ft boom EXT


10ft

40 ton 3
sheave hook
block
Load weight 40ft
2500 lbs

45'

USING GROVE CRANE RT65s ON OUTRIGGERS FULLY EXTENDED 360* .

17. WHAT IS THE GROSS CAPACITY AT THE PICK UP POINT ?

A. 12,520 lbs B. 10,330 lbs C. 12,000 lbs D. 9,390 lbs

17
RIGGER II 02
RIGGER II

15"AUX BOOM
5 ton

Headache
ball
24 ft Jib, 5*
Load offset
weight
15 ton 1 32 ft boom
6500 LBS
sheave hook
75F
block

35FT
15F

40

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

18. WHAT IS THE WEIGHT OF LOAD HANDLING DEVICES ?

A. 790 LBS B. 6,650 LBS C. 650 LBS D. 3,324 LBS

18
RIGGER II 02
RIGGER II

load + rigging
weight
9.500 lbs

10'

40'
final
placement of
load

5' 15' 30'

crane load handling device: allow 5 ft of hoist


. 40ton, 3 sheave hook block line clearance
. 32ft boom ext stowed between boom tip
and hook block

USING GROVE CRANE RT65S, 35 METRIC TON CAP, RANGE DIAGRAM OVER FRONT

19. WHAT ANGLE IS THE BOOM TIP AT THE FINAL PLACEMENT OF LOAD?

A. 53° B. 60° C. 43° D. 75°

19
RIGGER II 02
RIGGER II

Allow 10' for hook 15" Aux boom


block and hoist line head
clearance
installed

5 ton 24 FT jib 17
degree offset
Headache
ball

32 FT boom
EXT
10'

40 ton 3
sheave hook
block
Load weight 60'
2500 LBS

30'

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

20. WHAT IS WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 5,364 LBS B. 3,790 LBS C. 3,480 LBS D. 9,290 LBS

20
RIGGER II 02
RIGGER II

Allow 4m for hook block


and hoist line clearance

5 ton
7.3m jib 17
Headache ball
degree offset

Load
12m 9.7m boom Ext
weight
+33.5 m
3200
KG 15 ton 1
sheave hook
block

10m

4
14m

USING GROVE CRANE RT755, ON OUTRIGGERS FULLY ETENDED 360°

21. WHAT IS BOOM LENGTH REQUIRED TO COMPLETE THE LIFT?

A. 19.8m B. 16.8m C. 25.9m D. 22.9m

21
RIGGER II 02
RIGGER II

Allow 3m for hook block


and hoist line clearance

5 ton
7.3m jib 30
Headache ball
degree offset

Load
12m weight 9.7m boom Ext
3500
KG final placment
15 ton 1
sheave hook
block

9m

7
16m

USING GROVE CRANE RT75S, ON OUTRIGGERS FULLY ETENDED 360°

22. WHAT IS THE GROSS CAPACITY AT THE PICK UP POINT?

A. 5,150 kg B. 6,585 kg C. 3.930 kg D. 2,085 kg

22
RIGGER II 02
RIGGER II

crane load handling devices: 40 ton 3 sheave hook


block
32 ft boom extinsion

allow 8 ft of hoist line clearance between boom


tip and hook block

40 ft

7 ft

20 ft

3 ft

60 ft

concrete slab+rigging = 14,250 lbs

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED 360* .

23. WHAT IS WEIGHT OF LOAD HANDLING DEVICES ?

A. 640 lbs B. 1,165 lbs C. 3,535 lbs D. 1.135 lbs

23
RIGGER II 02
RIGGER II

crane load handling devices: 40 ton 3 sheave hook


block
32 ft boom extinsion

allow 10 ft of hoist line clearance between


boom tip and hook block

NEW
LOCATION
20 ft

7 ft

25ft

3 ft

55 ft

concrete slab+rigging = 11,500 lbs

USING GROVE CRANE RT65S, 35 METRIC TON CAP, RANGE DIAGRAM.


OVER FRONT

24. WHAT ANGLE IS THE BOOM TIP AT THE NEW LOCATION?

A. 55° B. 43° C. 62° D. 50°

24
RIGGER II 02
RIGGER II

Allow 10' for hook block


and hoist line clearance

load weight 2000 lbs


24ft jib 5 degree
10'
offset

5 ton H/ache 32 ft boom Ext


ball

15 ton 1
80' sheave hook
block

70

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED 360* .

25. WHAT IS WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 6,460 LBS B. 460 LBS C. 3,134 LBS D. 2460 LBS

25
RIGGER II 02
RIGGER II

load + rigging
8000 lbs

12ft

48ft
final
placement of
load

5 15 ft 30 ft

crane load handling device: allow 5 ft of hoist


. 40ton, 3 sheave hook block line clearance
. 32 ft boom ext stowed between boom tip
and hook block

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED 360* .

26. WHAT BOOM LENGTH IS REQUIRED AT THE PICK UP POINT ?

A. 80 ft B. 112 ft C. 74 ft D. 68 ft

26
RIGGER II 02
RIGGER II

crane load handling devices: 40 ton 3 sheave hook


block
32 ft boom extinsion
stowed

allow 5 ft of hoist line clearance between boom


tip and hook block

NEW
LOCATION
40 ft

7 ft

30 ft

3 ft

60 ft

concrete slab+rigging = 13000 lbs

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

27. WHAT IS THE GROSS CAPACITY AT NEW LOCATION ?

A. 17,000 lbs B. 15,470 lbs C. 18,040 lbs D. 8,550 lbs

27
RIGGER II 02
RIGGER II

load + rigging
6,500 kg

3m

15m
final
placement of
load

2m 5m 7m

crane load handling device:


allow 2m of hoist
. 50ton, 4 sheave hook block
line clearance
. auxillary boom head
between boom tip
. 9.7m boom ext stowed
and hook block

USING GROVE CRANE RT75S ON OUTRIGGERS FULLY EXTENDED 360* .

28. WHAT IS WEIGHT OF LOAD HANDLING DEVICES ?

A. 945 kg B. 500 kg C. 1,550 kg D. 586 kg

28
RIGGER II 02
RIGGER II

crane set up: on outriggers fully extended

Allow 15' for hook


block and hoist line
clearance

5 ton
24 ft jib 30
Headache
ball
degree offset final
placement of
load
Load
60' weight
32 ft boom Ext
7,000
lbs
15 ton 1
sheave hook
block

35'

25'
40'

USING GROVE CRANE RT65S, 35 METRIC TON CAP, RANGE DIAGRAM. 360

29. WHAT ANGLE IS THE BOOM TIP AT THE PICK UP POINT?

A. 61° B. 67° C. 56.5° D. 90°

29
RIGGER II 02
RIGGER II

allow 8 ft for hook


block & hoist line
clearance

18" Aux
boom
head
32 ft boom
[Link]
15 ton
1
sheave load
hook weight
new block
pick up point
30

40 ton
3
sheave 5'
hook
block
10'

30' 15'

60

USING GROVE CRANE RT65s ON OUTRIGGERS FULLY EXTENDED 360* .

30. WHAT IS WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 10,788 lbs B. 6.950 lbs C. 8.114 lbs D. 7.170 lbs

30
RIGGER II 02
RIGGER II

crane load handling devices: 40 ton 3 sheave hook


block
32 ft boom extinsion

allow 5 ft of hoist line clearance between


boom tip and hook block

45 ft

7 ft

10 ft

3 ft

80 ft

concrete slab+rigging = 13,000 lbs

USING GROVE CRANE RT65S ON OUTRIGGERS FULLY EXTENDED 360* .

31. WHAT IS BOOM LENGTH REQUIRED TO COMPLETE THE LIFT?

A. 56 FT B. 50 FT C. 62 FT D. 44 FT

31
RIGGER II 02
RIGGER II

load + rigging
weight
10,000 lbs

6 ft

64 ft
final
placement of
load

5' 10' 30'

crane load handling device: allow 5 ft of hoist


. 40ton, 3 sheave hook block line clearance
. 32ft boom ext stowed between boom tip
and hook block

USING GROVE CRANE RT65s ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

32. WHAT IS THE GROSS CAPACITY AT THE PICK UP POINT ?

A. 17,000 LBS B. 19,590 LBS C. 12,000 LBS D. 12,870 LBS

32
RIGGER II 02
RIGGER II

Allow 2m for hook


block and hoist line
clearance

15 ton

Headache
ball 9.7m boom Ext
Load
weight
50 ton 4
600 kg
sheave hook
16
block

2m

10 m
5m

20

USING GROVE CRANE RT75S ON OUTRIGGERS FULLY EXTENDED 360* .

33. WHAT IS THE WEIGHT OF LOAD HANDLING DEVICES ?

A. 1,623 KG B. 1,003 KG C. 3,090 KG D. 495 KG

33
RIGGER II 02
RIGGER II

load weight
600 kg
Allow 2m for hook
block and hoist line
clearance

15 ton

Headache 9.7ft boom Ext


ball

15m

pick up point

50 ton 4
sheave hook
2m
block

10m

5
16m

USING GROVE CRANE RT755, 50 METRIC TON CAP, RANGE DIAGRAM. 360

34. WHAT ANGLE IS THE BOOM TIP AT THE PICK UP POINT?

A. 60°.5 B. 70° C. 50° D. 44°

34
RIGGER II 02
RIGGER II

allow 5m for
hook block & 7.5 ton
hoist line headache
ball

9.7m boom
[Link]

load weight
2,750 kg
new
pic up point
20

15 ton 1
sheave
hook 2m

3m

6m 3

10 m

USING GROVE CRANE RT75s ON OUTRIGGERS FULLY EXTENDED 360* .

35. WHAT IS WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 3,027 kg B. 4,191 kg C. 1,441 kg D. 5,658 kg

35
RIGGER II 02
RIGGER II

load + rigging
8000 lbs

NEW LOCATION

OVER FRONT

25ft

20ft

25 ft

crane load handling device: allow 10 ft of hoist


. 40ton, 3 sheave hook block line clearance
. 32 ft boom ext stowed between boom tip
and hook block

USING GROVE CRANE RT65S ON RUBBER CAPACITY 2.5 MPH .

36. WHAT BOOM LENGTH IS REQUIRED TO COMPLETE THE LIFT ?

A. 56 ft B. 112 ft C. 74 ft D. 68 ft

36
RIGGER II 02
RIGGER II

allow 5 m for
hook block & 7.5 ton
hoist line H/ACE BALL
clearance

9.7 m boom
[Link]

load weight
new 2000 kg

20

15 ton 1
sheave
hook 2m

3m

6m 3m

12m

USING GROVE CRANE RT75S ON OUTRIGGERS FULLY EXTENDED 360* .

37. WHAT IS THE GROSS CAPACITY AT NEW LOCATION ?

A. 8020 kg B. 5850 kg C. 3920 kg D. 7045 kg

37
RIGGER II 02
RIGGER II

Allow 10m for hook Aux boom head


block and hoist line
clearance installed

7.5 ton 7.3 jib 30


degree offset
Headache
ball

43.3m boom
Load weight EXT

2000 kg
14

50 ton 4
sheave hook
block
2m

9m

USING GROVE CRANE RT755 ON OUTRIGGERS FULLY EXTENDED OVER FRONT .

38. WHAT IS WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 3,998 kg B. 3,898 LBS C. 3,480 LBS D. 5998 KG

38
RIGGER II 02
RIGGER II

Allow 10' for hook block


and hoist line clearance

5 ton 24ft jib 5


degree offset
Headache
ball

32ft boom EXT


10ft

40 ton 3
sheave hook
block
Load weight 40ft
3000 lbs

55'

USING GROVE CRANE RT65S, 35 METRIC TON CAP, RANGE [Link] FRONT

39. WHAT ANGLE IS THE BOOM TIP AT THE PICK UP POINT?

A. 47° B. 41° C. 63° D. 55°

39
RIGGER II 02
RIGGER II

Allow 2m for hook block


and hoist line clearance

AUX BOOM HEAD


INSTALLED
15 ton

Headache
ball 9.7m boom Ext
Load
weight
600 kg 50 ton 4
sheave hook
26
block

2m

20 m
10

28

USING GROVE CRANE RT75S ON OUTRIGGERS FULLY EXTENDED 360* .

40. WHAT IS THE WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 1,059 KG B. 459 KG C. 1,623 KG D. 1,145 KG

40
RIGGER II 02
RIGGER II

allow 10' ft for


hook block &
hoist line
clearance

32 ft boom
[Link]
15 ton
1
sheave load weight
hook 5,000 lbs
new block
pic up point
45

40 ton
3
sheave 10'
hook
block
10'

30' 40'

60

USING GROVE CRANE RT65S, 35 METRIC TON CAP, RANGE DIAGRAM. 360

[Link] ANGLE IS THE BOOM TIP AT THE NEW LOCATION?

A. 56° B. 70° C. 58° D. 65°

41
RIGGER II 02
RIGGER II

allow 10 ft for
hook block & 15 ton
hoist line 1 shaeve
hook block

32 ft boom
[Link]

new location

load weight
25' 5.000 lbs

40 ton 3
sheave
hook block 10 ft

10

40' 35'

60'

USING GROVE CRANE RT65s ON OUTRIGGERS FULLY EXTENDED 360* .

42. WHAT IS WEIGHT OF LOAD + LOAD HANDLING DEVICES ?

A. 5,000 lbs B. 8,624 lbs C. 3,624 lbs D. 6,390 lbs

42
RIGGER II 02
RIGGER II

1 A
2 A
3 A
4 C
5 D
6 A
7 C
8 B
9 C
10 C
11 A
12 A
13 C
14 D
15 A
16 A
17 A
18 C
19 B
20 D
21 D
22 C
23 B
24 C
25 D
26 A
27 C
28 D
29 C
30 A
31 A
32 C
33 D
34 A
35 A
36 A
37 C
38 D
39 B
40 A
41 A
42 B

43
RIGGER II 02
RIGGER II

44
RIGGER II 02