Contract No.
Generator Room
ITEM DESCRIPTION UNIT BOQ QTY Unit Rate BOQ Amount
02. EXCAVATION & EARTHWORK
Excavation & get out
01 Remove top soil depth 20cm m2 98.00 14.00 1,372.00
Pit & Trench excavation
02 Not exceeding 1.5m m3 11.00 73.00 803.00
03 Trench not exceeding 1.5m m3 5.00 73.00 365.00
Fill
04 Selected excavated fill m3 2.00 91.00 182.00
05 Selected borrowed fill m3 29.00 270.00 7,830.00
06 Disposal m3 20.00 72.00 1,440.00
Sub base
07 25 cm thick hardcore m2 59.00 173.00 10,207.00
TOTAL SUMMARY BIRR 22,199.00
03. CONCRETE WORK
In situ concrete
01 Plain blinding concrete C-5 m3 2.00 2,259.00 4,518.00
Reinforced sub structure concrete
02 C-25 in Footing m3 4.00 3,525.00 14,100.00
03 C-25 in Sub grade column m3 1.00 3,525.00 3,525.00
04 C-25 in grade beam m3 5.00 3,525.00 17,625.00
05 C-25 in G.F slab & ramp m3 6.00 3,250.00 19,500.00
Reinforced super structure concrete
06 C-25 in elevation column m3 2.00 3,525.00 7,050.00
07 C-25 in beams m3 4.00 3,525.00 14,100.00
FORMWORK -
Sub structure normal finish to:- -
08 Footing m2 43.00 201.00 8,643.00
09 Sub grade column m2 10.00 224.00 2,240.00
10 Grade beam m2 35.00 201.00 7,035.00
11 Steps m2 1.00 261.00 261.00
Super structure normal finish to:- -
12 Elevation column m2 33.00 224.00 7,392.00
13 Beams m2 37.00 249.00 9,213.00
Reinforcement steel bar -
Sub structure -
14 Diameter, 8mm kg 426.00 41.00 17,466.00
15 Diameter, 12mm kg 180.00 41.00 7,380.00
16 Diameter, 14mm kg 351.00 41.00 14,391.00
Super structure -
17 Diameter, 8mm kg 174.00 41.00 7,134.00
18 Diameter, 14mm kg 418.00 41.00 17,138.00
Concrete ancillaries -
Expansion Joint -
19 In 8mm thick chip wood depth 10cm m 57.00 47.00 2,679.00
TOTAL SUMMARY BIRR 181,390.00
04. MASONRY WORK -
Stone wall -
In cement Mortar -
01 Concealed from view m3 10.00 1,780.00 17,800.00
Concrete block work -
Above grade walls -
Class "B" in cement mortar above grade walls -
03 20 cm thick both faces for plaster m2 78.00 529.00 41,262.00
TOTAL SUMMARY BIRR 59,062.00
06. ROOFING & WALL CLADDING
Galvanized steel sheet & accessories
Galvanized corrugated steel sheet
Roofing
01 Gauge 28 m2 88.00 322.00 28,336.00
Ridge Cap -
Galvanized flat steel sheet & accessories -
02 0.4mm thick m 10.00 185.00 1,850.00
TOTAL SUMMARY BIRR 30,186.00
07. CARPENTRY & JOINERY
Eucalyptus truss
01 Dia. 10 cm m 130.00 34.00 4,420.00
02 Dia. 8 cm m 85.00 34.00 2,890.00
Purlin -
Sawn Eucalyptus -
03 Size :- 5x7 cm m 115.00 101.00 11,615.00
Soffit under eave -
05 Mosquito wire mesh m2 32.00 362.50 11,600.00
Fascia board -
06 2.5x20cm sawn Eucalyptus m 36.00 98.00 3,528.00
TOTAL SUMMARY BIRR 34,053.00
10. METAL WORK
Window
Metal louver window
01 Type W1, Size:- 428x150cm No 1.00 11,197.00 11,197.00
02 Type W2, Size:- 335x150cm No 1.00 8,764.00 8,764.00
03 Type W3, Size:- 325x150cm No 1.00 8,503.00 8,503.00
04 Type W4, Size:- 100x90cm No 1.00 1,570.00 1,570.00
Wire mesh cover -
05 Type W5, Size:- 150x200cm No 1.00 5,232.00 5,232.00
Door -
06 Type D1, Size:- 200x250cm No 1.00 9,370.00 9,370.00
07 Type D2, Size:- 120x250cm No 1.00 6,622.00 6,622.00
08 Type D3, Size:- 120x312cm No 1.00 7,645.00 7,645.00
TOTAL SUMMARY BIRR 58,903.00
11. FINISHING
11.1 PLASTERING & POINTING
Two coats of plaster in cement mortar to internal surface of
01 Hollow concrete block m2 106.00 171.00 18,126.00
02 Concrete vertical surface m2 53.00 180.00 9,540.00
Cement mortar to external surface of -
03 Hollow concrete block wall m2 79.00 180.00 14,220.00
04 Concrete vertical surface m2 17.00 190.00 3,230.00
Fine coat cement plaster to:- -
05 Internal Plastered vertical surface m2 159.00 90.00 14,310.00
Cement pointing -
Recessed pointing -
07 Stone wall surface m2 10.00 102.00 1,020.00
TOTAL SUMMARY BIRR 60,446.00
11.2 FLOOR & WALL FINISH
Cement screed floor finish and cement tile skirting
01 5cm thick smooth finish m2 54.00 262.00 14,148.00
Steps -
Treads -
02 3cm thick terrazo m2 2.00 931.00 1,862.00
Riser -
03 2cm thick terrazo m2 1.00 652.00 652.00
Sill -
Shaped & throated Terrazzo tile -
04 Size 28x3cm m 14.00 232.00 3,248.00
Concrete paving -
05 10cm thick precast concrete in C-15 m2 41.00 739.00 30,299.00
Curb -
08 C-20 concrete curb stone Size 30/10cm m 32.00 290.00 9,280.00
TOTAL SUMMARY BIRR 59,489.00
12. PAINTING
Plastic Emulsion paint to:-
01 Internal plastered vertical surface m2 159.00 39.00 6,201.00
03 Chipwood ceiling m2 54.00 43.00 2,322.00
TOTAL SUMMARY BIRR 8,523.00
13. GLAZING
Transparent glass
Clear sheet
01 4mm thick clear glass m2 4.00 335.00 1,340.00
TOTAL SUMMARY BIRR 1,340.00
15. ELECTRICAL INSTALLATION
Light points
01 Light points in conduit of 13.5mm fed by pvc conductor of [Link] No 4.00 478.50 1,914.00
Switch with detachable frame -
02 Single pole No 2.00 155.00 310.00
03 Double pole No 1.00 186.00 186.00
Socket outlet -
04 Socket 2p+e out No 4.00 478.50 1,914.00
Extra Over socket outlet -
05 16A , 1ph No 4.00 188.50 754.00
Type of light fittings -
Mounting-ceiling surface, Lamp type- fluorescent, Number of lamps-1, Lamp
06 wattage-36watts, Luminare material- steel, Ingress protection-20, size- Length No 4.00 3,190.00
1224mm, width 146mm and 73mm height, control gear-electronic type-batten
12,760.00
Cable tray thickness 0.8mm with bracckets at every 200cm. Size
07 m2 10.00 1,740.00
250x40(WxD)mm 17,400.00
TOTAL SUMMARY BIRR 35,238.00