3 Power and Energy Potential Study
3 Power and Energy Potential Study
3000.00 10.0
20.0
2500.00
30.0
Volume, MCM
2000.00
Area, Km2
40.0
1500.00
50.0
1000.00
60.0
500.00 70.0
0.00 80.0
220 230 240 250 260 270 280 290 300 310 320 330 340 350
Elevation
Volume Area
Fig: Volume Elevation and Area Elevation Curve at Dam Site of Proposed Kaligandaki-2
Storage Hydropower Project
Flow Duration Curve
• If the discharge data of the river is plotted with the time such that the
discharge is plotted in Y-axis and the probability of exceedance of that
discharge is plotted in X-axis, then the resulting curve is called flow
duration curve. Probability of exceedance is the percentage time at
which the flow equal to or more than the given flow is expected to occur.
Discharge
Q40
Flow Duration Curve
Q50
40 50 Probability of exceedance %
Flow Duration Curve of a Nepalese River
Flow Duration Curve Continued…………
As the probability of exceedance increases, the discharge decreases.
Uses of the Flow Duration Curve:
1. To know the variation of the discharge pattern in the river.
2. To Assess the primary and the secondary power that can be generated
from the river.
3. To fix the designed discharge for any Run of River or Storage Plants.
4. To fix the installed capacity for any hydropower plant.
5. To calculate the storage volume required for the storage projects.
6. Flow duration curve is used to select the number and the types of
turbines.
7. After generating the flow duration curve, we can assess the different
capacities that can be generated from the given river source. It helps us
to select the suitable option among them as which is suitable for the
power market or the energy demand.
8. Flow duration curve is the primary parameter which helps a decision
maker to formulate plans regarding the development of hydropower
projects,.
9. Flow duration curve can be combined with the sediment data which is
very much useful to access the sediment load that is expected to enter
the reservoir of any storage project.
Design Discharge:
• The discharge at which the given hydropower is designed is the design
discharge. It is different than the discharge available in the river. It is the
maximum discharge which the turbines of the hydropower plants can
withdraw (except the case of overloading). It is fixed either by the
economic considerations (mostly) or by the other requirements (like the
requirements of the power demand, plant type, etc).
• The installed capacity of a plant is fixed based on the design discharge.
Installed capacity, P = η*γ *Q*H,
where, η = efficiency,
γ = specific weight of water
Q = design discharge
H = Head
Installed Capacity:
• The maximum power that can be generated from a particular power
plant is called installed capacity. It is the most economical capacity
of the plant, i. e; the benefit from the plant is optimum if the plant
capacity is fixed at installed capacity. A pant can not generate more
power than the installed capacity. The installed capacity of a plant
can be calculated by:
• Installed capacity, P = η*γ *Q*H,
where, η = efficiency,
γ = specific weight of water
Q = design discharge
H = Head
Power Duration Curve:
• The curve obtained by plotting the power generated on Y-Axis and
the probability of exceedance of that power on X-Axis is called the
power duration curve. The power duration curve is similar to the
flow duration curve. The power duration curve for a RoR project is a
declining curve because the discharge in the river does not remain
constant all the time and the discharge decreases with increase in
probability of exceedance. The power duration curve of a storage
projects is also a declining curve because although the discharge
can be maintained in a storage project, the head shows the
fluctuation due to change in reservoir level.
Power The Power Duration Curve of Storage and RoR Project
Probability of exceedance
The figure shows that the power produced from a RoR project changes
drastically after certain time whereas the power generated from storage
project also decreases but ay very slow rate. A comparison of power
duration curve for a storage project and RoR project constructed on the
same river is shown on above figure. A power duration curve is also
generated on the same way as flow duration curve.
Firm Power/Primary Power:
• The power, which can be produced from the plant in any time of the year is called firm
power. It is the minimum power which can be produced from the plant.
Secondary Power:
• The power which can be produced from the plant in excess of the firm power is called
secondary power. The plant can deliver secondary power for only a certain part of a year.
• Secondary power = Actual power – primary power.
Firm Energy:
• The energy, which can be produced from the plant in one year if the plant operates at the
firm power for whole year is called firm energy. It is equal to the firm power multipiled
with one year.
• Firm Energy = Firm power * 1 year
Secondary Energy:
• The energy, which is in excess to the firm energy is called secondary energy.
• Secondary Energy is equal to the total energy minus the firm energy. Secondary energy =
Total Energy- Firm Energy
Spill Energy:
• The energy, which is in excess to the demand is called the spill energy. When the total
energy in the grid is more than the demand, then it is called spill energy. The energy will
spill during the wet season when all the plants run at full capacity.
• Also in other terms, the energy of river water that had not been utilized is called spill
energy.
Load Curve:
Load
• There is basic difference between the load and demand. Load is the power that the generator
has to produce in order to meet the power requirements. In electrical terms, a load can be a fan,
heater, bulb,etc.
• Demand will be equal to load if the power supply is sufficient to meet the demand.
• Load curve is the curve showing load and time. The daily load curve in Nepalease power system
shows peak during morning and evening as compared to the day and night. This is mainly
because, the major load in Nepal is the domestic load. If there are sufficient industries that run
during the day time, the load curve would show the peak during the day time.
The typical load curve of Nepal is shown in the figure above. The load
curve shows the hourly variation of load within a day. The load curve
of Nepal as recorded by Integrated National Power System(INPS) is
shown in following slides.
Types of Load Variation:
1. Daily Load Variation: The variation of load within a day is called daily load
variation. The load in Nepalease power system is more in morning and evening than
the days and night. The evening peak is more than the morning peak.
2. Weekly Variation: The variation of load within a day of week is called weekly
variation. Normally, the load is more in Saturday than other days of the week.
3. Monthly Variation: The variation of load in different months is called monthly
variation. The load is more in the winter months as compared to other months.
4. Seasonal Variation: The variation of load in the seasons is called seasonal
variation. The load is more in the winter season than other seasons.
Plant Outage: Plant outage is the situation when the power plant remains shut.
Outage may be of two types.
a) Planned Outage: The outage which is already known is called planned outage. It
is scheduled outage for settlilng basin flushing, maintenance of the
electromechanical works, etc.
b) Forced Outage: The forced outages are emergency outages. This type of outage
occurs suddenly due to the huge problem in the system like failure of transmission
line, damage of headworks, etc. The forced outage is emergency situation and it
causes huge loss to the system.
Important Terms and Factors:
(i) Connected load: It is the sum of continuous ratings of all the equipment
connected to supply system. A power station supplies load to thousands of
consumers. Each consumer has certain equipment installed in his premises.
The sum of the continuous ratings of all the equipment in the consumer’s
premises is the “connected load” of the consumer. For instance, if a consumer
has connections of five 100-watt lamps and a power point of 500 watts, then
connected load of the consumer is 5 × 100 + 500 = 1000 watts. The sum of
the connected loads of all the consumers is the connected load to the power
station.
(ii)Maximum demand: It is the greatest demand of load on the power station
during a given period. The load on the power station varies from time to
time. The maximum of all the demands that have occurred during a given
period (say a day) is the maximum demand. Maximum demand is generally
less than the connected load because all the consumers do not switch on
their connected load to the system at a time. The knowledge of maximum
demand is very important as it helps in determining the installed capacity of
the station. The station must be capable of meeting the maximum demand.
(iii) Demand factor: It is the ratio of maximum demand on the power station
to its connected load i.e;
Demand factor = Maximum demand/Connected load . The value of demand factor
is usually less than [Link] is expected because maximum demand on the power
station is generally less than the connected load. If the maximum demand on the
power station is 80 MW and the connected load is 100 MW, then demand factor =
80/100 = 0·[Link] knowledge of demand factor is vital in determining the capacity
of the plant equipment
(iv) Average load: The average of loads occurring on the power station in a given
period (day or month or year) is known as average load or average demand.
Average load = Total energy consumed within a time period/time
V) Load factor: The ratio of average load to the maximum demand during a given
period is known as load factor i.e.,
Load factor = average load/peak load
The load factor may be daily load factor, monthly load factor or annual load factor
if the time period considered is a day or month or year. Load factor is always less
than 1 because the average load is smaller than the maximum demand. The load
factor plays a key role in determining the overall cost per unit generated. Higher
the load factor of the power station, lesser will be the cost per unit generated.
vi) Diversity factor: The ratio of the sum of individual maximum demands to
the maximum demand on power station is known as diversity factor
i.e., diversity factor = sum of individual maximum demands/maximum
demand on the power station
vii) Plant factor or capacity factor: It is the ratio of actual energy produced to
the maximum possible energy that could have been produced during a given
period. In other words, it is the ratio of average load to the installed capacity.
i.e. plant/capacity factor = average load/installed capacity
viii) Reserve capacity: It is the difference between installed capacity and peak
load. Reserve capacity = Installed capacity – peak load
Reserve capacity factor = installed capacity/peak load.
Utilization factor = peak load/installed capacity
Relation between load factor, utilization factor factor and plant factor
Plant factor = Load factor*Utilization Factor
2075 Chaitra/1a
Given,
Head = 30 m
Q = 25 cumecs
Load factor = 65 %
η = 60 %
Peak load hours = 4 hr
The power that is produced with given discharge of 25 cumecs is considered as average
load.
Laverage = ηүQH = 0.6*9.81*25*30 = 4414.5 KW = 4.41 MW
The peak load can be estimated by:
Load Factor =
So, Peak load = 4.41/0.65 = 6.79 MW
The question does not speak about the reserve capacity to be provided. So, we assume
the installed capacity of the plant or the capacity of generator should be 6.79 MW.
Second Part:
No. of peak hours = 4
Let Qpeak = Discharge required during peak hours.
So, Peak Load = ηү Qpeak *H
Or, 6.79*1000 = 0.6*9.81* Qpeak *30
Or, Qpeak = 38.45 m3/sec
Defficient discharge during peak hours
= 38.45 – 25
= 13.45 m3/sec
The storage volume required for 4 hours
= 13.45*4*3600
= 193680 m3
2076 Aswin 1a
Solution: Q = 40 m3/sec
ηturbine = 80 %, ηgenerator = 90 %
Overall efficiency, η =80%*90% = 72%
The day when the most storage is required is Sunday. In Sunday the storage required is
categorized as follows.
1. Discharge of Saturday is stored. The volume would be
V1 = 40*24*3600 = 3.45 Mm3
2. The inflow discharge within Sunday is also non uniform. So, the volume required to adress
this fluctuation is:
V2 = 30 % of volume of inflow
= 0.3*40*24*3600
=1.04 Mm3
3. Supply discharge is not uniform as the plant is supplying at load factor of 50 %. For this
supply variation, the storage is required.
Mean flow to the turbine = daily flow + discharge of Saturday allocated for a particular day
= 40 + = 46.67 m3/sec
Storage required, V3 = 0.2*46.67*24*3600 = 0.806 Mm3
The total storage required for Saturday is V = V1 + V2 + V3 = 5.3 Mm3
Allowable fluctuation = 1 m
If A is the surface area, then
A*1 = 5.3*106
Or A = 5.3 Km2 = 530 hectares
Average Output:
Average flow to the turbine = 46.67 cumecs
Average head = =24.5 m
Average power produced = P = ηүQH = 0.72*9.81*46.67*24.5 =
8076.16 KW
The weekly energy output = 8076.16*6 days = 8076.16*6*24 =
1.16*106 KW-h
2075 Aswin 3a
Solution:
Q = 30 m3/sec
H = 70 m
η = 85 %
a) i) if the plant is designed as pure RoR plant
P = ηүQH = 0.85*9.81*30*70/1000 = 17.51 MW
a) ii) let x = design discharge of the single unit.
Peak hours = 6hr
Off peak hours = 18 hr
Available continuous flow = 30 m3/sec
The amount of water that will be stored during off peak hours
= (30-x)*18*3600
The amount of water lost in evaporation = 5 % of (30-x)*18*3600
The amount of water actually stored = 95 % of (30-x)*18*3600
Discharge available for peak hours
= 30 +
= 30 + 2.85(30-x)
But actually two units are running with design discharge of x m3/sec
So, 30 + 2.85(30-x) = 2x
Or x = 23.81 m3/sec
The total discharge the plant will utilize during peak hours = 2x = 2*23.81 = 47.62
m3/sec
Therefore, installed capacity of the plant = ηүQH
= 0.85*9.81*47.62*70/1000 = 27.8 MW
Solution:
Q = 30 cumecs
H = 70 m
η=85%
a. Case 1
Considering the plant as pure RoR
Power generated,
P = ηүQH = 0.85*9.81*20*70/1000 = 17.51 MW
b. Case b
Considering the plant as PRoR plant
Peaking hours = 6 hrs
Off-Peaking hours = 24-6 = 18 hrs
Let, the design discharge of a single unit is x m3/sec
The volume of water stored in off peak hours
= (30-x)*18*60*60 (Because single unit is running
at x m3/sec, 30-x m3/sec will be stored).
= 64800(30-x) m3
The volume of water lost = 5 % of stored water
= 0.05*64800(30-x) m3 = 3240*(30-x) m3
Volume of water that will be available for peak
hours = 64800(30-x) m3 -3240*(30-x) m3
= 61560* (30-x) m3
The discharge that the plant is using during peak
hours = 2x m3/sec (Because two units are running)
Volume available for peaking hours = volume
due to continuous flow + stored water volume
2x*6*60*60 = 30*6*60*60+ 61560(30-x)
Or, x = 23.81 m3/sec
Therefore design discharge of the plant = 2x
= 2*23.81 = 47.62 m3/sec
The installed capacity of the plant as PRoR
= P = ɳүQH = 0.85*9.81*47.62*70/1000
= 27.79 MW
Mean inflow volume
= 6671/12 = 555.92 MCM (MCM = 106 m3)
See the monthly deficit in the table.
Total deficit = 1802.44 MCM
Therefor storage capacity of the reservoir =
1802.44 MCM
3 b solution
Month Inflow volume (106 Demand Deficit
m3)
1 296 555.92 259.92
2 386 555.92 169.92
3 504 555.92 51.92
4 714 555.92 -
5 810 555.92 -
6 1154 555.92 -
7 746 555.92 -
8 1158 555.92 -
9 348 555.92 207.92
10 150 555.92 405.92
11 223 555.92 332.92
12 182 555.92 273.92
Total Inflow Vol. 6671 Total deficit 1802.44 MCM
Desc. Rank Exc.
order Prob.
Month t Qt
1 8.33
oct 1 94.3 329.5
nov 2 59.7 252.2 2 16.67
dec 3 36.4 186.1 3 25
jan 4 24.3 131.2 4 33.33
feb 5 23.3 94.3 5 41.67
mar 6 33.5 87.4 6 50
apr 7 54.9 59.7 7 58.33
may 8 87.4 54.9 8 66.67
jun 9 131.2 36.4 9 75
jul 10 186.1 33.5 10 83.33
aug 11 252.2 24.3 11 91.67
sep 12 329.5 23.3 12 100
Calculation of Q40
1. Arrange the discharge data in descending order.
2. Assign rank to the discharge data. Provide rank 1
to the highest discharge.
3. Probability of exceedance = *100 %
4. Interpolate for Q40
5. Q33.33 = 131.2 cumecs, Q41.67 = 94.3
By interpolation, Q40 = 101.7 m3/sec
So, the design discharge is 101.7 m3/sec
Installed capacity,
P = ɳүQH = 0.85*9.81*101.7*150/1000 =127.2 MW
Firm Capacity = minimum capacity
Minimum capacity will be obtained with minimum
discharge
Qmin = 23.3 cumecs
Firm capacity = ɳү* Qmin *H
= 0.85*9.81*23.3*150/1000
= 29.14 MW
Firm energy = energy produced in 1 year if the
plant runs at firm capacity.
= 29.14MW*1year
= 29.14/1000 GW*365*24 hr = 255.27 GW-hr
b. Solution
Available flow = Q40 = 101.7 cumecs
Peaking hours = 6 hours
Off-peak hours = 18 hours
Discharge that will be stored during off-peak hours = 50 % of 101.7 =
50.85 cumecs
Volume stored during off peak hours = 50.85*18*3600 = 3.29*10 6 m3
Additional discharge in the peak hours due to stored water
= = 152.55 m3/sec
Therefore design discharge = 101.7 +152.55
= 254.25 m3/sec
So, the installed capacity,
P = ɳүQH = 0.85*9.81*254.25*150/1000
= 318 MW
2070 Chaitra
Rank Exc. Prob. Flow for Power, No. Energy, Power Energy
power MW of GW-hr Potential Potenti
generati days of river al of
on river
Desc.
Month Discharge Order
8.33 100 83.39 31 62.04 83.39 62.04
Jan 100 2500 1
16.67 120 100.06 28 67.24 100.06 67.24
Feb 120 2100 2
25 140 116.73 31 86.85 116.73 86.85
Mar 140 2000 3
33.33 300 250.16 30 180.11 250.16 180.11
Apr 300 1800 4
41.67 320 266.83 31 198.52 266.83 198.52
May 320 900 5
50 1080.2 900.72 30 648.52 1500.93 1080.7
Jun 1800 500 6
58.33 1080.2 900.72 31 670.14 1667.7 1240.8
Jul 2000 320 7
66.67 1080.2 900.72 31 670.14 2084.6 1551
Aug 2500 300 8
75 1080.2 900.72 30 648.52 1751.1 1260.8
Sep 2100 300 9
83.33 900 750.46 31 558.35 750.46 558.35
Oct 900 140 10
91.67 500 416.93 30 300.19 416.93 300.19
Nov 500 120 11
100 300 250.16 31 186.12 250.16 186.12
Dec 300 100 12
Total Energy, GW-hr 4276.74
i.
Calculation of Q40
Q33.33 = 1800
Q41.67 = 900
By interpolation,
Q40 = 1080.21 cumecs
a. RoR operation Mode at Q40
Power generated, P = ηүQH
For January,
P = 0.85*9.81*100*100/1000
= 83.39 MW
For September,
P = 0.85*9.81*1080.2*100/1000 = 900.72
Energy Generated = Power*time
For January,
Energy = 83.39/1000*31*24 GW-hr = 62.04 GW-hr
For September,
Energy = 900.72/1000*30*24 = 648.52GW-hr
Firm Energy = firm power*1 year = minimum power*1 year
= 83.39/1000 * 365*24 = 730.5 GW-hr
Total Energy = 4276.74 GW-hr
Installed capacity = Maximum of the power generated = 900.72 MW
b. If the whole water of river is utilized as RoR Plant:
Power potential of the river will be same as the power produced as RoR for following
months.
Jan, feb, march, april, may, oct, nov, dec.
For June, July, August and September, the plant did not utilize the total available flow in
river.
For September, the power potential
= P = ɳ*ү*Q*H
= 0.85*9.81*2100*100/1000 = 1751.1 MW
Energy potential for september = power*time
= 1751.1/1000*30*24 = 1260.8 GW-hr
Total annual energy potential of the river
= sum of energy potential of all months
= 6772.72 GW-Hr
Alternatively, the energy potential of river may be estimated by:
Average flow: Qavg =
=
= 927.17 cumecs
Average annual power
= 0.85*9.81*927.17*100/1000
= 773.12 MW
Annual energy potential
= Average power*1 year
= 773.12/1000* 365*24
= 6772.59 GW-Hr
Spill Energy = Annual energy potential of river – Energy produced from given
RoR plant
= 6772.72 – 4276.74 (We used the energy calculated from Table for energy
potential)
= 2495.98 GW-hr
ii) For a storage project with full regulation of annual
hydrograph,
Design discharge = average monthly flow
=
= 923.33 cumecs
Therefore, installed capacity
= 0.85*9.81*923.33*100/1000 MW
= 769.92 MW
Storage requirement/volume = Cumulative of deficits
= 12307.62 MCM
iii) Annual energy generation
= 6744.5 GW-Hr
Flow for Power, No. Energy, Deficit Deficit
power MW of GW-hr Discharge Volume
generatio days MCM
n
Month Discharge
Jan 100 923.33 769.92 31 572.82 823.33 2205.21
Feb 120 923.33 769.92 28 517.39 803.33 1943.42
Mar 140 923.33 769.92 31 572.82 783.33 2098.07
923.33 769.92 30
Apr 300 554.34 623.33 1615.67
923.33 769.92 31
May 320 572.82 603.33 1615.96
Jun 1800 923.33 769.92 30 554.34
Jul 2000 923.33 769.92 31 572.82
Aug 2500 923.33 769.92 31 572.82
Sep 2100 923.33 769.92 30 554.34
923.33 769.92 31
Oct 900 572.82 23.33 62.49
923.33 769.92 30
Nov 500 554.34 423.33 1097.27
923.33 769.92 31
Dec 300 572.82 623.33 1669.53
Total Energy, GW-hr 6744.5 Storage 12307.61
Vol.
2072/Chaitra/ 3
Solution:
ɳturbine = 0.93, ɳhydraulic = 0.95, ɳgenerator = 0.99, ɳtransformer = 0.99
Overall efficiency, ɳ = 0.93*0.95*0.99 *.99 = 0.865 = 0.87
Design Discharge = 18 m3/sec
Sample for January
Flow available for power = 4.06 m3/sec
Total Head loss = 0.63
Gross Head = 600 m
Net Head = 600-0.63 = 599.37 m
Power, P = ɳ*ү*Q*H
= 0.87*9.81*4.06*599.37/1000
= 20.77 MW
Energy = Power*Time
= 20.77/1000*31*24 GW-Hr
= 15.45 GW-Hr
Installed Capacity = 90.27 MW
Firm/Primary Power = 15.66 MW
Firm/Primary Energy = Firm/Primary Power*1 year
= 15.66/1000*365*24
= 137.18 GW-hr
Secondary Energy
= Total Energy – Firm Energy
= 456.7 – 137.18
= 319.52 GW-Hr
Plant Factor =
=
= = 0.58
In other way, Average load =
= = 52.13 MW
Therefore, plant factor =
= 52.13/90.27 = 0.58
Energy Table
Month Discharg d/s Flow for Net Power No of Energy
e release power Head Days
Jan 4.4 0.34 4.06 599.37 20.77 31 15.45
Feb 3.9 0.34 3.56 599.51 18.22 28 12.24
Mar 3.4 0.34 3.06 599.64 15.66 31 11.65
Apr 4.2 0.34 3.86 599.43 19.75 30 14.22
May 5.6 0.34 5.26 598.94 26.89 31 20.01
June 16.5 0.34 16.16 589.99 81.37 30 58.59
July 78.1 0.34 18 587.58 90.27 31 67.16
Aug 108.9 0.34 18 587.58 90.27 31 67.16
Sep 52.8 0.34 18 587.58 90.27 30 64.99
Oct 22 0.34 18 587.58 90.27 31 67.16
Nov 9.9 0.34 9.56 596.50 48.67 30 35.04
Dec 6.4 0.34 6.06 598.59 30.96 31 23.03
Total Energy in GW-Hr 456.7
Head Loss calculation is shown in following table
Given Data:
ftunnel 0.014 Ltunnel 4Km Dtunnel 3m
fpenstock 0.012 Lpenstock 1Km Dpenstock 2.2m
Gross Head = FSL - Turbine Center Level 600m
Total Head Net
Month Flow for power Vtunnel hftunnel Vpenstock hfpenstock
Loss, hf Head
8.33
E1
8.33 3.96
16.67
E2 3.96
E3 3.96
25.00
6.67
40 E5 3.96
1.67
41.67
E6 3.84
50 8.33 E7
3.57
58.33 E8 3.23
E9
8.33 8.33
66.67 323
is same
E10
8.33
75 3.06
E11
83.33 2.7
E12
are same because the
91.67 2.18
power and time interval
E13
The energy E1, E2, E3, E4
8.33 8.33
100 1.65
% Time
Reservoir and Storage Zones of Reservoir
Normal Pool Level or Maximum Conservation Level: It is the
maximum elevation upto which reservoir water level will rise
during normal operating conditions. This is the designed storage
level.
Mimimum Operating Level: The lowest water surface level
which has to be kept under normal operating conditions. The
water level should not fall below this level.
Maximum Pool Level or Full Reservoir Level: The maximum
water level upto which the water rises during the worst design
flood is called maximum pool level.
Useful Storage: The volume of water stored between minimum
pool normal pool level is called useful storage or active storage
or live storage.
Dead Storage: Water stored in the reservoir below dead storage
level is called dead storage.
Surcharge Storage: The volume of water stored between normal pool
level and maximum pool level is called surcharge storage. It is also
called flood storage.
Buffer Storage: The amount of storage between dead storage level and
minimum pool level is called buffer storage. This storage is for
submergence of intake.
Bank Storage: When the reservoir is filled up, certain amount of water
seeps into the permeable reservoir banks. This is called bank storage.
This storage increases the capacity of reservoir.
Valley Storage: Even before dam is constructed, certain amount of
water is stored in the stream channel called valley storage. After the
reservoir is formed, the storage increases and the actual net increase in
the storage is equal to the storage capacity of reservoir minus the
natural valley storage. The valley storage thus reduces the effective
storage of reservoir.
Effective storage for flood mitigation = useful storage + surcharge
storage – valley storage
The following figure shows different storage zones of reservoir.
Surcharge Storage
Normal Pool Level or Maximum Conservation Level
As water level in the reservoir shall not be allowed to go below the minimum
pool level, the firm commitments for power will continue to generate upto
this level of water.
Normal floods will be absorbed in the capacity laying below the normal pool
level. Severe flood shall be absorbed by the capacity lying between normal
pool level and maximum pool level. Spillway starts discharging water, as soon
as the water level starts rising above the normal pool level. Because of heavy
outflow for irrigation purpose and hydropower generation during dry season,
the reservoirs are almost in completely depleted state. Thus just before the
monsoon season, almost full capacity is available in empty form, not only for
conservation of water but also to control the flood that may occur during
rains.
hf
Initial Steady Level
Surge Tank hg
Tunnel
hnet
`
Pe
n
sto
ck
Tail Water
Power
x%
% of time
b. Installed Capacity Optimization Approach
This is trial and error approach and is adopted mostly for fixing installed capacity
of hydropower projects. In this method, following procedure is adopted.
i. The flow duration curve is developed and discharge is found for different
probability of exceedance.
ii. Power is calculated for different flows with exceedance probability from Q25
to Q65. The power should be calculated in the intervals of 5 %. That means
Power should be calculated for Q25, Q30’ Q35, Q40, Q45, Q50, Q55, Q60 and Q65.
For example, power corresponding to 40 % exceedance probability = P 40 =
ɳү Q40*H
iii. The project cost should be calculated corresponding to each percentile flow
ranging from Q25 to Q65. For different percentile flow, project cost will be
different. For example a project designed at Q65 will have least capacity and
minimum cost of electromechanical equipment as well as civil structures as
the design discharge is lowest whereas a project designed at Q 25 will have
highest capacity and maximum cost of electromechanical equipment as
well as civil structures as the design discharge is highest.
iv. The benefit is also calculated for different powers from P25 to P65.
v. Financial analysis shall be performed for each percentile power and
financial indicators like B/C ratio, IRR, NPV, Payback Period should be
calculated.
vi. The capacity with highest values of B/C ratio, IRR, NPV and lowest
Payback Period should be selected as the installed capacity
B/C
Maximum B/C