NTPC Lara Project Overview and Status
NTPC Lara Project Overview and Status
2
Project Closure Status - Client
Sl. No. Description FY’25 Arbitration Demobilised WIP Status
16 Naomundi Township
Total 5 8 9 6
NTPC Lara Dt: 16th Jul 2024
Dt: 16th Jul’2024
Executive Summary- Lara
1 Brief Scope 3 Schedule & LD
Engineering, Procurement, Construction and Commissioning Contractual start date 26-Aug-2014
Scope of Work (Brief Description)
of Coal Handling Plant
Original Contract duration (in Months) 25-Jun-2017 (34)
Capacity 2 X 800 MW
Location Lara Forecast Duration (in Months) Closed
Customer NTPC
POCM % 99.1%
Type of Contract EPC
Original Contract Value (INR Cr) 326.12 Cr CB Margin % 1.9% [Link]./Delays(Max Value in INR Cr) 16.3 (5%)
[Link]./Performance(Max Value in INR Cr) 81.5(25%)
Total Contract Value (INR Cr) 322.40 Cr CTC Margin % -33.1%
[Link]./Overall completion(Max Value in INR Cr
Bonus (in INR Cr)
2 Key Highlights
5
Dt:16th Jul’2024
Balance Works - Lara
CCP-01 Certificate of Final Amendment It is under discussion with NTPC for 20.09.2024 Sowjanya /Surya - TPL
to the Contract finalization (Rebate on RDSO approval
deviation for track hopper and supply of
mandatory spares)
CCP-09C Customs Reconciliation File with Customs Audit and under final 30.07.2024 PREMIER CLEARING AGENCY
Certificate of Imported Supply process (Clearance from Nava Siva port PVT LTD
expected 19.07.2024)
CCP-11 No Demand Certificate by Will be submitted after completion of 30.09.2024 Sowjanya /Surya - TPL
Contractor above two CCPs
6
Dt:16th Jul’2024
Financial Progress - Lara ₹ in
Cr
Billed/
Description Total Balance Remarks
Incurred
Contract Value 326.12 Support Required
Claims+Variations -3.72
Claims in Arbitration
TCV 322.40 320.81 1.59 To be finalised along with order amendment CCP1
CTC 429.13 425.87 3.26
UBR/(AB) 0/ 2.34
Inventory 0.00
GCA 6.06
NWC -2.71
Original Contract Value (INR Cr) 376.81 Cr CB Margin % 2.0% [Link]./Delays(Max Value in INR Cr) 18.8 (5%)
[Link]./Performance(Max Value in INR Cr) 94.2(25%)
Total Contract Value (INR Cr) 424.48 Cr CTC Margin % -15.2%
[Link]./Overall completion(Max Value in INR Cr
Bonus (in INR Cr)
2 Key Highlights
COF Unit-I 01.03.2020
10
Dt:16th Jul’2024
Balance Works - Darlipali
[Link] Description of Action Point Present Status Target Date Responsibility
11
Dt:16th Jul’2024
Financial Progress - Darlipali ₹ in
Cr
Billed/
Description Total Balance Remarks
Incurred
Contract Value 326.12 Support Required
Claims+Variations -3.72
Claims in Arbitration
TCV 322.40 320.81 1.59 To be finalised along with order amendment CCP1
CTC 429.13 425.87 3.26
UBR/(AB) 0/ 2.34
Inventory 0.00
GCA 6.06
NWC -2.71
Risk Register
Total Probabilit Risk Likely
Sr. Short Estimated
ID Detailed Description Status Estimate y% Owner Month of
No Description Value
d Value (P) Occurrence
De-scope of
1 Erection work Stacker reclaimer erection work de-scoped 70lakhs 100%
13
Dt: 27th Jun 2024
Executive Summary - NSL
1 Synopsis 3 Key Contract
Terms
PV Applicability Yes
Scope of Work (Brief Design , Engineering , Manufacturing, Supply, Erection, Testing & Advance 10 %
Description) Commissioning of 4500 m3 Blast Furnace Complex. 77.5 % within 30 days
Progressive RA bills
Payment
PAC-2.5%
terms
Location Nagarnar-Jagdalpur,Chhatisgarh Retention Commissioning-2.5 %
Customer NMDC Steel Limited(NSL) PG-5 %
FAC-2.5 %
PMC / Licensor Mecon Contractual Completion Definition Commissioning
Type of Contract Turnkey 12 M from the date of
DLP Commissioning or 18 M from
Original Contract Value (INR Cr) 1094.3 Cr CB Margin % 7.5 % the date of PAC
Total Contract Value (INR Cr) 1410.9 Cr CTC Margin % -13.5% O&M Period NA
PBG – 119.01Cr
BG Details ABG – 27.86Cr
SD – 0.30Cr
2 Schedule
Contractual Start Date 29-MAY-2011 Overall Actual Progress % 99% Overall Liq. Dam./Penal. Due to delay in
0.5% Per week of CV
completion ( i.e. INR Cr/ Week)
Original Contract duration 34 M (28-02-2014) POCM % 98.3% Overall Liq. Dam./Penal. to delay in
5 % of the CV
99% completion ( Max Value in INR Cr)
Contract duration with EOT 151 M (15-10-2023) Billing % (Excl Liq. Dam. due to Performance shortfall 7.5 % of The CV
Arbitration)
Overall Liq. Dam./Penal. for both delay in
10 % of the CV
Forecast Duration 164 M (30-11-2024) Time Elapsed 159 M completion & nonperformance (Max Value Cr)
Bonus (in INR Cr)
14
Dt: 27th Jun 2024
04 BG Collection of BG Dec-24
15
Dt:16th Jul’2024
Financial Progress - NSL ₹ in
Cr
Billed/
Description Total Balance Remarks
Incurred
Contract Value 326.12 Support Required
Claims+Variations -3.72
Claims in Arbitration
TCV 322.40 320.81 1.59 To be finalised along with order amendment CCP1
CTC 429.13 425.87 3.26
UBR/(AB) 0/ 2.34
Inventory 0.00
GCA 6.06
NWC -2.71
2 55 PG test Nov-24
3 28 FAC Mar-25
17
Dt: 27th Jun 2024
Executive Summary – COB 5
1 Brief Scope 3 Schedule & LD
Contractual start date 22-Jun-2015
Scope of Work (Brief Description) Coal and Coke handling system for COB-5 at RINL
Original Contract duration (in Months) 26 (22-Aug-2017)
Capacity 0.8MTPA
Contract duration with EOT (in Months) 113 (30-Sep-2024)
Location Visakhapatnam steel plant
Customer VSP RINL Forecast Duration (in Months) 116 (30-Dec-2024)
Type of Contract EPC
Time Elapsed (in Months) 110
Original Contract Value (INR Cr) 312.68 Cr CB Margin % 3.5% POCM 98.7%
PAC 08-Feb-2021
Total Contract Value (INR Cr) 328.87 Cr CTC Margin % -27.8% PrAC 24-Apr-2024
DLP/FAC 12M from PrAC
18
Dt: 27th Jun 2024
Balance Works – COB 5
02 As Built Drawings As Built drawing submitted and under review by Mecon Jul-24
03 Anti Profiteering for COB-5 Documents under review by Commercial team Jul-24
19
Dt:16th Jul’2024
Financial Progress – RINL COB-5 ₹ in
Cr
Billed/
Description Total Balance Remarks
Incurred
Contract Value 326.12 Support Required
Claims+Variations -3.72
Claims in Arbitration
TCV 322.40 320.81 1.59 To be finalised along with order amendment CCP1
CTC 429.13 425.87 3.26
UBR/(AB) 0/ 2.34
Inventory 0.00
GCA 6.06
NWC -2.71
21