Claim and dispute
management
1
Definitions of claims
In the day to day progress of the works misunderstandings
may occur between the parties to a contract.
These misunderstandings may be a result of interpretation
of contract documents, request for compensations for
damages sustained or request for time extension as a result
of delays caused by one party etc.
These requests for compensation are called claims
In general claims in construction industry are defined as
demands for compensation in terms of money, time
extension or a combination of these that a party rightly or
wrongly believes that he is entitled to
2
Claim could be disputable or non-disputable
Disputable claim arises when a claim of
one party is not accepted by the other
contracting party or when the decision of a
neutral party is not being accepted by any
or all the contracting parties.
Non-disputable claims are claims
acceptable by the contracting parties
3
Claim Administration Procedures
Clause 53 FIDIC:
The contractor give his intention to claim within 28 days after
the event giving rise to the claim has first arisen
The contractor shall keep temporary records on the claim issue
The engineer examines such contemporary records
The contractor shall submit detailed particulars of the amount
claimed and the grounds upon which the claim is based
The engineer makes determination based on the available
records and evidences and arguments produced
If the parties to contract agree to this decision, then the claim is
resolved
If the parties to the contract do not agree to the decision, then
the claim will be disputed claim
4
Types of claims
Contractual claims
Extra-contractual claims
Ex-Gartia claims
5
Contractual Claims
Claims made under the expressed provisions of
contract fall under this category
This type of claim forms the largest part of
claims and the terms of contract define the
situations in which they may be made and how
they may be handled
6
Extra-Contractual Claims
Claims which have no basis in the contract
documents. These could have their basis in common
law or statue law.
These could include a claim for damage for:
breach of contract
breach of warranty
breach of an implied term
They could be under the law of contract or tort.
7
Ex-Gartia Claims
Claims where there is no contractual provision to
rely on, nor any breach or tort by the client.
An Ex-gartia claim might be made to recover cost
incurred by the contractor, the expenditure of which
gave benefit to the employer, but for which there
are no grounds for recovery under the contract.
8
Major causes of claims
Variations
Defect in contract document
Unforeseen condition
Failure in contract administration
9
Claims may be for:
An extension in time for completion of the
works, or
Extra payment, or
An extension in time and extra payment,
10
The majority of claims involve delay of some form.
Time is particularly important since a contractor is
bound by the contract to construct the works in a
specified time, and is liable to pay liquidated
damages for late completion,
Acceptance by the Engineer of the validity of a
claim for extension of time means that the contract
completion date is extended.
11
Event-claim-dispute range
Event occurs
Discussion/
Claim arises Consultation
Contractor gives notice
of intention for claim
Engineer determines
the sum due to contractor
Contractor
disagrees
Dispute exists
Either party gives Contractor agrees
notice of dispute Claim resolved
Dispute resolution
procedure
Dispute resolved
12
Settlement of Dispute Procedure
Clause 67 FIDIC
Submission of details by contractor,
Review of the dispute by the engineer,
The Engineer gives decision,
Amicable settlement, or
ADR resolution system will be Implemented,
13
Construction Disputes Resolution Systems
There are several methods of resolving disputes in the
construction industry. Mainly they are categorized as:
Preventive,
Non-judgmental (amicable),
Judgmental,
14
Construction Disputes Resolution Systems
(Cont…)
Preventive
This method is a mechanism of avoiding disputes
rather than allowing issues to grow until they
become real dispute,
Partnering:
Partnering It is a process which aims to create a
good principal-contractor relationship from the
outset, which aims on encouraging contracting
parties to have operative team based approach
15
Construction Disputes Resolution Systems
(Cont…)
Dispute Review Board (DRB) involves a panel
of expert neutral persons being setup at
the beginning,
DRB members made an independent assessment
and visits the site regularly during construction &
they keep on advising the parties and solve the
dispute among them.
16
Construction Disputes Resolution Systems
(Cont…)
The non-judgmental
The non-judgmental methods bring the disputants to a
round table and mutually resolve their dispute
Negotiation is a common dispute resolution process in which
parties themselves, or their representatives, try to solve the
dispute without involving any neutral third party.
As negotiation is consensual, it requires willingness by both
parties to attempt resolution by this method.
17
Construction Disputes Resolution Systems
(Cont…)
Mediation is a dispute resolution mechanism in which a neutral
third party meets with the disputants and facilitates negotiation to
the parties to come to their own solution.
The mediator controls the processes, but he/she does not impose
any resolution or opinion on the merits of the case,
Promoting a win/win situation, leaving the disputants themselves
to control the outcome,
Mediation can occur by contractual agreement or after a dispute
18
arises,
Construction Disputes Resolution Systems
(Cont…)
Conciliation is a process similar to mediation except that the
mediator can express an opinion on the merits of the case, and
is required to recommend a solution if the parties fail to agree,
Mini-trial Neutral third party brings together senior decision
makers from each disputant to hear presentations by junior
representatives or their respective legal representatives and
help them to negotiate on resolution at private, The
representative should have full settlement authority,
19
Construction Disputes Resolution Systems
(Cont…)
Judgmental
Adjudication is a process in which the decision of a third party
neutral, named in the contract, is binding upon the parties with respect
to any matter in dispute until the contract is complete. Adjudication
decision could be challenged through arbitration or litigation,
Arbitration is a process where a third party who is independent of
parties, but may be selected by them, makes an award determining the
dispute,The award is binding and can be enforced at courts,
20
Construction Disputes Resolution Systems
(Cont…)
Litigation is a dispute resolution method whereby the
disputant initiates legal action against the other party by
going to court,
It has a win/lose outcome,
It is usually initiated when the disputants cannot agree to
other forms of dispute resolution,
21
Resolve Claims and Disputes
Amicably
THANK YOU!
22
Thank you!
23