PCR Eyeplus Kalayn - New.

The Project Closure Report for EYEPLUS-Kalyan details the project's specifications, milestones, cost breakdown, and lessons learned. The project commenced on December 1, 2025, and was completed within 21 days, with various supporting documents and vendor performance ratings included. Key challenges faced during the project execution and recommendations for improvement are also outlined.

Uploaded by

rahulanand
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views21 pages

PCR Eyeplus Kalayn - New.

The Project Closure Report for EYEPLUS-Kalyan details the project's specifications, milestones, cost breakdown, and lessons learned. The project commenced on December 1, 2025, and was completed within 21 days, with various supporting documents and vendor performance ratings included. Key challenges faced during the project execution and recommendations for improvement are also outlined.

Uploaded by

rahulanand
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd

Project Closure Report

EYEPLUS- KALYAN
1
Sensitivity: Internal
Content
 Project Details

 Project Milestone

 Cost Breakup

 Assets list

 Photographs

 Lesson Learned

 HOTO Supporting
Documents

2
Sensitivity: Internal
Project Details
BRAND EYEPLUS REGION WEST

CITY MUMBAI LOCATION KALYAN


BUILT-UP AREA(SFT) SFT 745 RETAIL CARPET SFT 668
AREA(SFT)
PROJECT HEAD MR. ADIL SAYYED PROJECT ENGINEER PRATIKSHA Y PATIL

MEASUREMENTS TAKEN ON DRAWINGS /FULL KIT OCT 15 25


RECEIVED ON

PROJECT START DATE 1 DEC 2025 PROJECT 21 DEC 2025


COMPLETION DATE
NO. OF DAYS FOR EXECUTION 21 Days HANDED OVER ON 21 DEC 2025

BUSINESS MODEL COCO STORE TYPE HIGHSTREET

3
Sensitivity: Internal
Project Milestone

4
Sensitivity: Internal
Cost breakup
Incase not getting the final cost details from franchisee ,correspondence mail to ABM & cc to Project head, national
head & RBM under franchisee asking for the final cost – (Communication Email to be Enclosed Here )

WILL UPLOD THE COST BREACK


UP ONCE WE DONE FINAL
Billing .

5
Sensitivity: Internal
Photographs(Façade)

Existing Façade is Retain Façade Existing retain


6
Sensitivity: Internal
VIEW FROM STORE ENTRY

BEFORE FINAL
7
Sensitivity: Internal
VIEW OF CASH COUNTER

BEFORE FINAL
8
Sensitivity: Internal
VIEW FROM SERVICE RECEPTION

9
Sensitivity: Internal
VIEW FROM SERVICE RECEPTION

10
Sensitivity: Internal
Photographs(GPS co-ordinates)

11
Sensitivity: Internal
Lesson Learned
WHAT WHAT
WHAT
COULD COULD ACTION
WENT
NOT GO WE PLAN?
WELL?
WELL? IMPROVE?

IMPROVEMENT
SLNO CHALLENGES FACED QUALITY COST TIME
Highstreet Store we done within 13 days NA
1.

. NA
2.

NA
3.

NA
4.

NA
5.

NA
6.
12
Sensitivity: Internal
HOTO -Supporting Documents
ITEM DESCRIPTION ATTACHMENT (YES/NO/NA)
• As built drawing (FAÇADE,INTERIOR & SERVICES DRAWING 1. As per the request from franchise and confirmation
LAYOUT). with design team the washroom cancelled as mall
(BPM docket released link incase no changes) has hygienic washroom with proper lock & Key.
2. Location of Electrical DB inside of stock room as
per FR request and confirmation with design team.
3. Backside washroom location changes as per FR
request and confirmation with design team.

• Project vendor list YES


• Status of Vendor Payment NA
• Snag list signoff YES
• VPR YES

• Commissioning reports for all services Equipment's NA (FR Store)


(HVAC,UPS,DG )
• HOTO Checklist -Services YES
• Earthing Values Measured YES
• Warranty & DLP details NA(FR Store)
• Tentative week/Month of post walkthrough date (pls mentioned 17/10/2022
in Remark)
• Specific Do’s & Don’ts(details to be attached) Yes 13
Sensitivity: Internal
Vendor Details
• PROJECT VENDOR LIST
S.NO DESCRIPTION VENDOR NAME

1 CIVIL & INTERIOR ACE ENTERPRISES


2 LOOSE FURNITURE (Incl. Mould) MAGNET
3 ELECTRICAL ACE
4 AIRCONDITIONER A & I ENGINEERING
5 LIGHTING PMEA
6 PA SYSTEM - MUSIC PHOTRONICS
7 CCTV ESSS
8 FAS ESSS
9 UPS PANTECH
10 SPRINKLER -
11 FIRE EXTINGUISHER LAXMI FIRE
12 CHAIR - RETAIL AMMARDEEP

13 SIGNAGE EXISTING

14
Sensitivity: Internal
• HOTO

hoto eyeplus kalyan.pdf


15
Sensitivity: Internal
• VPR

TITAN COMPANY LIMITED - IRSG - Vendor Performance Rating (VPR) FORM V3

BRAND: EYEPLUS REGION WEST DATE OF RATING:

LAYOUT REQUEST NO LOCATION KALYAN

TYPE RENOVATION BUSINESS MODEL L1

GUIDLINE TO RATE VENDOR'S PERFORMANCE:


1. THIS TO BE FILLED BY RESPECTIVE PROJECT EXCEUTIVE(PE) AFTER STORE LAUNCH.

2. OVERALL VENDOR RATING TO BE DECIDE BASED ON OVERALL SCORE POOR FAIR GOOD

3. SCORE TO BE FILLED AS PER GIVEN CHART 1 2 3


4. IF OVERALL VENDOR SCORE IS LESS THAN 40. THIS SCORECARD WILL BE SHARED WITH THE
VENDORS WITH SPECFIC SCOPE FOR IMPROVEMENTS AND OPPURTUNITY FOR CONTINUATION OF
CONTRACTS IN FUTURE WORKS.

5. REMARKS IS MANDATORY FOR THE SCORES THE BOTH HIGH (5) and LOW (1, 2). PLEASE USE
ADDITIONAL REMARKS SPACE (AT THE BOTTOM OF SHEET) FOR WRITING ANY DETAILED REMARKS.

6. A- SUPPLY & INSTALLATION SCOPE VENDORS. RATING HAVE TO BE DONE BY PE, AS PER
CURRENT PROJECT SPECIFIC OBSERVATIONS / EXPERIENCE FOR OVER ALL SCOPE OF WORK DONE.

7. B- SUPPLY SCOPE VENDORS WHO IS HAVING OPPORTUNITY TO SCORE 5/5 FOR THEIR ON TIME
DELIVERY

ASSESSMENT
A-PROVIDING SUFFCIENT PROCESS ADHERANCE
(PROACTIVE
MANPOWER & ON TIME
VARIATION
WORK COMPLETION
QUALITY OF STATEMENT, ON TIME
WORK -RIGHT PERIODICAL JOINT SUBMISSION OF
FIRST TIME MEASUREMENTS & FINAL BILL)
B-ON TIME DELIVERY AS ADHERANCE OF EHS.
PER APPROVED SCHEDULE (ENVIRONMENT,
HEALTH & SAFETY)

25% 30% 20% 10%


SR.
PARTICULARS VENDOR NAME 30% 35% 20% NA (0)
NO.
25% 40% NA 15%

A. SUPPLY & INSTALLATION SCOPE VENDORS


1 CIVIL & INTERIOR ACE ENTERPRISES 5 4 4 4
16
Sensitivity: Internal
Supporting Documents
LUX MAPPING - ACTUAL

LUX MAPPING - DESIGN

Not Available

17
Sensitivity: Internal
Supporting Documents
LOAD BALANCING CHECKED

Façade renovation is done in last week ,


Updated details is yet to receive from vendor

Sensitivity: Internal
SAFETY & SECURITY INSTALLATIONS

• CCTV Monitor • MCB

• CCTV NVR

• CCTV 19
Sensitivity: Internal • Smoke Detector
SAFETY & SECURITY INSTALLATIONS

• Fire Extinguisher • Amplifire

• Signage

• Security Keypad 20
Sensitivity: Internal
• EPB
ELECTRICAL DB INSTALLATIONS

• MAIN DB • UPS & Batteries • SIGNAGE TIMER

21
Sensitivity: Internal