Classic Mistakes in Software Development and Maintenance

…the only difference between experienced and inexperienced developers is that the experienced ones realize when they’re making mistakes.
Jeff Atwood, Escaping from Gilligan’s Island

An important part of risk management, and responsible management at all, is making sure that you aren't doing anything obviously stupid. Steve McConnell’s list of Classic Mistakesis a place to start: a list of common basic mistakes in developing software and in managing development work, mistakes that are made so often, by so many people, that we all need to be aware of them.

McConnell originally created this list in 1996 for his book Rapid Development (still one of the best books on managing software development). The original list of 36 mistakes was updated in 2008 to a total of 42 common mistakes based on a survey of more than 500 developers and managers. The mistakes that have the highest impact, the mistakes that will most likely led to failure, are:

  1. Unrealistic expectations
  2. Weak personnel
  3. Overly optimistic schedules
  4. Wishful thinking
  5. Shortchanged QA
  6. Inadequate design
  7. Lack of project sponsorship
  8. Confusing estimates with targets
  9. Excessive multi-tasking
  10. Lack of user involvement

Most of the mistakes listed have not changed since 1996 (and were probably well known long before that). Either they’re fundamental, or as an industry we just aren't learning, or we don’t care. Or we can't find the time or secure a mandate to do things right, because of the relentless focus on short-term results:

Stakeholders won’t naturally take a long-term view: they tend to minimize the often extreme down-the-road headaches that result from the cutting of corners necessitated by the rush, rush, rush mentality. They’ll drive the car without ever changing the oil.
Peter Kretzman, Software development’s classic mistakes and the role of the CTO/CIO

The second most severe mistake that a development organization can make is to staff the team with weak personnel: hiring fast or cheap rather than holding out for people who have more experience and better skills, but who cost more. Although the impact of making this mistake is usually severe, it happens in only around half of projects – most companies aren't stupid enough to staff a development team with weak developers, at least not a big, high-profile project.

Classic Mistakes in Software Maintenance

But a lot of companies staff maintenance teams this way, with noobs and maybe a couple of burned out old-timers who are putting in their time and willing to deal with the demands of maintenance until they retire.

You get stuck in maintenance only if you are not good enough to work on new projects. After spending millions of dollars and many developer-years of effort on creating an application, the project is entrusted to the care of the lowest of the low. Crazy!
Pete McBreen, Software Craftsmanship

Capers Jones (Geriatric Issues of Ageing Software 2007, Estimating Software Costs 2008) has found that staffing a maintenance team with inexperienced people destroys productivity and is one of the worst practices that any organization can follow:

Worst Practice Effect on Productivity
Not identifying and cleaning up error-prone code – the 20% of code that contains 80% of bugs -50%
Code with embedded data and hard-coded variables – which contributes to “mass update” problems when this data changes -45%
Staffing maintenance teams with inexperienced people -40%
High complexity code that is hard to understand and change (often the same code that is error-prone) -30%
Lack of good tools for source code navigation and test coverage -28%
Inefficient or nonexistent change control methods -27%

Many of these mistakes are due to not recognizing and not dealing with basic code quality and technical debt issues, figuring out what code is causing you the most trouble and cleaning it up.

The rest are basic, obvious management issues. Keep the people who built the system and who understand it and know how and why it works working on it as long as you can. Make it worth their while to stay, give them meaningful things to work on, and make sure that they have good tools to work with. Find ways for them to work together efficiently, with each other, with other developers, with operations and with the customer.

These simple, stupid mistakes add up over time to huge costs, when you consider that maintenance makes up between 40% and 80% of total software costs. Like the classic mistakes in new development, mistakes in maintenance are obvious and fixable. We know we shouldn't do these things, we know what’s going to happen, and yet we keep doing them, over and again, and we're surprised when things fail. Why?

Tuesday, November 20, 2012

Predictability - Making Promises you can Keep

Speed – being first to market, rapid innovation and conducting fast cheap experiments – is critically important to startups and many high tech firms. This is where Lean Startup ideas and Continuous Deployment come in. And this is why many companies are following Agile development, to design and deliver software quickly and flexibly, incorporating feedback and responding to change.

But what happens when software – and the companies that build software – grow(s) up? What matters at the enterprise level? Speed isn't enough for the enterprise. You have to balance speed and cost and quality. And stability and reliability. And security. And maintainability and sustainability over the long term. And you have to integrate with all of the other systems and programs in your company and those of your customers and partners.

Last week, a group of smart people who manage software development at scale got together to look at all of these problems, at Construx Software’s Executive Summit in Seattle. What became clear is that for most companies, the most important factor isn’t speed, or productivity or efficiency – although everyone is of course doing everything they can to cut costs and eliminate waste. And it isn’t flexibility, trying to keep up with too much change. What people are focused on most, what their customers and sponsors are demanding, is predictability – delivering working software when the business needs it, being a reliable and trusted supplier to the rest of the business, to customers and partners.

Enterprise Agile Development and Predictability

Steve McConnell’s keynote on estimation in Agile projects kicked this off. A lot of large companies are adopting Agile methods because they’ve heard and seen that these approaches work. But they’re not using Agile out of the box because they’re not using it for the same reasons as smaller companies.

Large companies are adapting Agile and hybrid plan-based/Waterfall approaches combining upfront scope definition, estimating and planning, with delivering the project incrementally in Agile time boxes. This is not about discovery and flexibility, defining and designing something as you go along – the problems are too big, they involve too many people, too many parts of the business, there are too many dependencies and constraints that need to be satisfied. Emergent design and iterative product definition don’t apply here.

Enterprise-level Agile development isn’t about speed either, or “early delivery of value”. It’s about reducing risk and uncertainty. Increasing control and visibility. Using story points and velocity and release Burn Up reporting and evidence of working software to get early confidence about progress on the project and when the work will be done.

The key is to do enough work upfront so that you can make long-term commitments to the business – to understand what the business needs, at least at a high level, and estimate and plan this out first. Then you can follow Agile approaches to deliver working software in small steps, and to deal with changes as they come in. As McConnell says, it’s not aboutresponding to change over following a plan”. It’s having a plan that includes the ability to respond to change.

By continuously delivering small pieces of working software, and calibrating their estimates with real project data using velocity, a team working this way will be able to narrow the “cone of uncertainty” much faster – they’ll learn quickly about their ability to deliver and about the quality of their estimates, as much as 2x faster than teams following a fully sequential Waterfall approach.

There are still opportunities to respond to change and reprioritize. But this is more about working incrementally than iteratively.

Kanban and Predictability

Enterprise development managers are also looking at Kanban and Lean Development to manage waste and to maintain focus. But here too the value is in improving predictability, to smooth work out and reduce variability by finding and eliminating delays and bottlenecks. It’s not about optimization and Just-in-Time planning.

As David Anderson explained in his keynote on Delivering Better Predictability, Business Agility and Good Governance with Kanban, senior executives care about productivity, cost and quality – but what they care about most is predictability. The goal of a good software development manager is to be able to make a customer promise that their organization can actually meet.

You do this by keeping the team focused on the business of making software, and trying to drive out everything else: eliminating delays and idle time, cutting back administrative overhead, not doing work that will end up getting thrown away, minimizing time wasted in multi-tasking and context-switching, and not starting work before you’ve finished the work that you’ve already committed to. Anderson says that managers like to start on new work as it comes in because “starting gives your customer a warm comfortable feeling” – until they find out you’ve lied to them, because “we’re working on it” doesn’t mean that the work is actually getting done, or will ever get done. This includes fixing bugs – you don’t just fix bugs right away because you should, you fix bugs as they’re found because the work involved is smaller and more predictable than trying to come back and fixing them later.

Teams can use Kanban to dynamically prioritize and control the work in front of them, to balance support and maintenance requirements against development work and fixed date commitments with different classes of service, and limit Work in Progress (WIP) to shorten lead times and improve throughput, following the Theory of Constraints. This lets you control variability and improve predictability at a micro-level. But you can also use actual throughput data and Cumulative Flow reporting to project forward on a project level and understand how much work the team can do and when they will be done.

What’s interesting to me is seeing how the same ideas and methods are being used in very different ways by very different organizations – big and small – to achieve success, whether they are focused on fast iterations and responding to rapid change, or managing large programs towards a predictable outcome.

Thursday, August 2, 2012

Fixing Bugs – there’s no substitute for experience

We've all heard that the only way to get good at fixing bugs in through experience – the school of hard knocks. Experienced programmers aren’t afraid, because they’ve worked on hard problems before, and they know what to try when they run into another one – what’s worked for them in the past, what hasn’t, what they’ve seen other programmers try, what they learned from them.

They’ve built up their own list of bug patterns and debugging patterns, and checklists and tools and techniques to follow. They know when to try a quick-and-dirty approach, use their gut, and when to be methodical and patient and scientific.They understand how to do binary slicing to reduce the size of the problem set. They know how to read traces and dump files. And they know the language and tools that they are working with.

It takes time and experience to know where to start looking, how to narrow in on a problem; what information is useful, what isn’t and how to tell the difference. And how to do all of this fast. We’re back to knowing where to tap the hammer again.

But how much of a difference does experience really make?

Steve McConnell’s Code Complete is about programmer productivity: what makes some programmers better than others, and what all programmers can do to get better. His research shows that there can be as much as a 10x productivity difference in the quality, amount and speed of work that top programmers can do compared to programmers who don't know what they are doing.

Debugging is one of the areas that really show this difference, that separates the men from the boys and the women from the girls. Studies have found a 20-to-1 or even 25-to-1 difference in the time it takes experienced programmers to find the same set of defects found by inexperienced programmers. That’s not all. The best programmers also find significantly more defects and make far fewer mistakes when putting in fixes.

What’s more important: experience or good tools?

In Applied Software Measurement, Capers Jones looks at 4 different factors that affect the productivity of programmers finding and fixing bugs:

  1. Experience in debugging and maintenance
  2. How good – or bad – the code structure is
  3. The language and platform
  4. Whether the programmers have good code management and debugging tools – and know how to use them.

Jones measures the debugging and bug fixing ability of a programmer by measuring assignment scope - the average amount of code that one programmer can maintain in a year. He says that the average programmer can maintain somewhere around 1,000 function points per year – about 50,000 lines of Java code.

Let’s look at some of this data to understand how much of a difference experience makes in fixing bugs.

Inexperienced staff, poor structure, high-level-language, no maintenance tools

Worst Average Best
150 300 500

Experienced staff, poor structure, high-level language, no maintenance tools

Worst Average Best
1150 1850 2800

This data shows a roughly 20:1 difference between experienced programmers and inexperienced programmers, on teams working with badly structured code and without good maintenance tools. Now let’s look at the difference good tools can make:

Inexperienced staff, poor structure, high-level language, good tools

Worst Average Best
900 1400 2100

Experienced staff, poor structure, high-level language, good tools

Worst Average Best
2100 2800 4500

Using good tools for code navigating and refactoring, reverse engineering, profiling and debugging can help to level the playing field between novice programmers and experts.

You’d have to be an idiot to ignore your tools (debuggers are for losers? Seriously?). But even with today’s good tools, an experienced programmer will still win out – 2x more efficient on average, 5x from best to worst case.

The difference can be effectively infinite in some cases. There are some bugs that an inexperienced programmer can’t solve at all – they have no idea where to look or what to do. They just don’t understand the language or the platform or the code or the problem well enough to be of any use. And they are more likely to make things worse by introducing new bugs trying to fix something than they are to fix the bug in the first place. There’s no point in even asking them to try.

You can learn a lot about debugging from a good book like Debug It! or Code Complete. But when it comes to fixing bugs, there’s no substitute for experience.

Tuesday, June 21, 2011

Estimation is not a Black Art

Construx Software is one of the few companies that take the problems of estimation in software development seriously. Earlier this year I attended Steve McConnell’s Software Estimation in Depth course based on his book Software Estimation: Demystifying the Black Art. Two days reviewing factors in estimation and the causes of errors in estimating, the differences between estimates and targets and commitments, how to present estimates to the customer and to management, the importance of feedback and data, estimating techniques that work and why they work, and when and how to apply these techniques to different estimating problems.

You can get a lot out of reading Steve’s book, but the course setting gives you a chance to work with other people and solve real problems in estimation and planning, dig deep into questions with the man himself, and it introduces new material and research not included in the book. The key takeways from this course for me were:

The Basics

Even simple techniques work much better than “expert judgment” (aka wild ass guesses). With training and using straightforward tools and simple mathematical models and following a bit of structure, you can get to 70-75% accuracy in estimating, which is good enough for most of us.

Never estimate on the spot – it is professionally irresponsible, and you’re setting yourself, your team, and your customer up to fail. Always give the person who is doing the estimate time to think. Everyone knows this, but it’s important to be reminded of it, especially under pressure.

People’s systemic error tendency is to underestimate. Many organizations underestimate by a factor of at least 2x. This also applies to comparing back to actual costs: a common mistake is to remember how much you estimated something would take, not how long it actually took.

Estimates are always better if you can use real data to calibrate them: to compare estimates against evidence of how your organization has performed in the past. I knew this. But what I didn’t know is that you don’t need a lot of data points: even a few weeks of data can be useful, especially if it contradicts with judgment and forces you to question your assumptions.

Use different techniques at different stages as you move along a project’s Cone of Uncertainty, depending on how much information you have available at the time, and how high the stakes are – what the cost of estimation errors could be to the business. If you need higher confidence or higher quality estimates, use multiple techniques and compare the results.

I like T-Shirt sizing to help in planning and making a business case. Developers come up with a rough order of magnitude estimate on cost or effort (small, medium, large, extra-large) while the Customer/Product Owner/Product Manager does the same for the expected business value of a feature or change request. Then you match them up: Extra-Large business value and Small development cost gets a big thumbs-up. Small business value and Extra-Large cost gets a big thumbs down.

Estimating by analogy – comparing the work that you need to estimate to something similar that you’ve done before – is a simple technique that we use a lot. It works well if you are adding “another screen”, writing “another report”, or building “another interface”. It’s a good fit for maintenance, if you’ve been working with the same code for a while and know most of the gotchas.

Intact teams (like mine) tend to view problems in a similar way – ideas and experience converge. This is good if you work on similar problems, in maintenance or a long-running project, because you can make decisions quickly and confidently. But this is bad if you are confronted with new problems – you need techniques like Wideband Delphi to challenge people’s thinking patterns and let new ideas in.

Agile Estimating and Story Points and Velocity

We spent more time than I expected exploring issues in estimating Agile development work. Incremental and iterative planning in Agile development poses problems for a lot of organizations. The business/customer needs to know when the system will be ready and how much it will cost so that they can make their own commitments, but the team ideally wants to work this out iteratively, as they go. This means instead that they have to define the scope and cost as much as they can upfront, and then work out the details in each sprint – more like staged or spiral development methods. Once they have the backlog sized, they can plan out sprints based on forecast velocity or historical velocity - if they can figure this out.

I’m still not convinced that Agile story point estimating is better than (or as good as) other techniques, or that programmers sitting around a table playing Planning Poker is really an effective alternative to thoughtful estimating. Story points create some problems in planning new project development, because they are purposefully abstract – too abstract to be useful in helping to make commitments to the business. You might have an idea of how many story points give or take you have to deliver, but what’s a story point in the real world? People who use story points can’t seem to agree on how to define a story point, what a story point means and how or when to use them in estimating.

More fundamentally, you can’t know what a story point costs until the team starts to deliver, by measuring the team’s velocity (the actual story points completed in an iteration).This leaves you with a bootstrapping problem: you can’t estimate how long it is going to take to do something until you do it. You can look at data from other projects (if you’ve tracked this data), but you’re not supposed to compare story points across projects because each project and each team is unique, and their idea of story points may be different. So you have to make an educated guess as to how long it is going to take you to deliver what’s in front of you, and now we’re back to the “expert judgement” problem.

The good news is that it won’t take long to calibrate Story Point estimates against evidence from the team’s actual velocity. Mike Cohn in Succeeding with Agile says that you need at least 5 iterations to establish confidence in a team’s velocity. But Construx has found that you can have a good understanding of a team’s velocity in as little as 2 iterations. That’s not a long time to wait for some kind of answer on how long it should take to get the work that you know that you have in front of you done.

There is more to estimating

There is a lot more to estimating, and to this estimation course: details on different techniques and rules of thumb, models and software tools, how to measure estimation error, how to turn estimates into schedules, how to handle schedule compression and how to stay out of the Impossible Zone. To get a taste of the course, check out this webinar on the 10 Deadly Sins of Software Estimation.

Software estimation, like other problems in managing software development, doesn’t require a lot of advanced technical knowledge. It comes down to relatively simple ideas and practices that need to be consistently applied; to fundamentals and discipline. That doesn’t mean that it is easy to do it right, but it’s not dark magic either.

Monday, November 15, 2010

Construx Software Executive Summit 2010

I spent a few days last week in Seattle at the Software Executive Summit hosted by Construx Software Builders. This is a small conference for senior software development managers: well organized, world class keynote speakers, and the opportunity to share ideas in supportive and open roundtables with smart and experienced people who are all focused on similar challenges, some (much) bigger, some smaller. It was good to reflect and reset, and a unique chance to spend time with some of the top thinkers in the field, swapping stories over lunch with Fred Brooks, chatting over drinks with Tim Lister and Tom DeMarco. This was my second time at this conference, and based on these experiences, I would highly recommend it to other managers looking for new ideas.

Key takeaways for me:
  • A lot of people are concerned that we (software developers in general) continue to do a poor job upfront, on requirements and architecture and design. And that the push to Agile methods, on collaborative and emergent design, isn’t helping: if anything, the problem is getting worse. We are getting better and faster at developing and delivering mediocre software.

  • The push for offshoring of programming and testing work continues to come mostly from the top. Even with the economic downturn, companies are having problems filling positions locally; and having problems keeping resources overseas, with turnover rates as high as 35% annually in India. The companies who are successful with offshoring make long-term commitments with outsourcing firms; invest in a lot of back-and-forth travel; rely on strong and hard-working onshore technical managers from their outsourcing partners to coordinate with their offshore teams; spend a lot of time on documentation and reviews; and spend more time and money on building and maintaining relationships. There can be real advantages at scale: for smaller companies I don’t see the return.

  • Some companies have backed away from adopting Agile methods, or are running into problems with Agile projects, because the team is unwilling or unable to commit to a product roadmap or rough project definition. Customers and sponsors are frustrated, because they don’t understand what they can expect or when they can expect it. Executives don’t want to see demos: they want to know when the project will be delivered. Working in an Agile way can’t prevent you from giving the customer what they need to make business decisions and meet business commitments. This is another argument for adapting Agile methods, for doing at least some high-level design and roadmap planning upfront, agreeing on the shape of what needs to be done and on priorities before getting to work.

  • Productivity: there is no clear way to define productivity or compare it across teams doing different kinds of work. Data on velocity or earned value is useful of course on bigger projects to see trends or catch problems: you want to know if you are getting faster or slower over time. Tracking time on maintenance work (bug fixes, small changes) can help to hilight technical debt or other problems: but what if most of the work that you do is maintenance? We need better ways to answer simple management questions: Am I getting my money’s worth? Is this group well-managed?

  • Two of the keynote presentations looked at innovation, and two others explored related problems in design: design integrity, dealing with complexity in design. Better decisions are made by small teams, the smaller the better: the ideal team size may be just two people (Holmes and Watson). It's important to give people a safe place and time to think – uninterrupted, unstructured time, preferably time blocked off together so that people can collaborate and play off of each other's ideas. If people are always on the clock and always focused on delivery, always dealing with short-term issues, they won’t have the opportunity to come up with new ways of looking at things and better ways of working, and worse they may lose track of the bigger picture, forget to look up, forget what’s important.

  • Technical debt: it’s our fault, not the business’s fault. It’s our house, so keep it clean. We have to find time to do the job right. One company uses the idea of a “tech tax”, a small (10%) overhead amount that’s included in all work for upgrades and refactoring and re-engineering.

  • The importance of building business cases for technical changes like re-architecture. Remember that business cases don’t have to be solid; they just need to be reasonable. Make sure that you have some data on cost and risk, and tie your case into the larger business strategy.

  • As a leader, you need to take responsibility. You have to deal with ambiguity: that's your job. Don't be a victim. Make a decision and execute.

Wednesday, October 20, 2010

Adopting and Adapting Agile Practices: It's more than just Cherry-Picking

I'm deeply interested in anything that will help me and help my team do a better job of building good software. But I’ve been around long enough to learn that there isn’t one way to build good software – that XP, or Scrum, or XBreed, or RUP, or Crystal, or CMMI, or TSP/PSP, or Scrumban, or any of yesterday’s or today's or tomorrow’s new better ways of making software, that none of these methods will give me all of the answers, solve all of my problems: or yours either. I’m a pragmatist. I’ve learned from experience and from thoughtful people like Steve McConnell a simple truth: that there are smart ideas and smart ways of doing things; and there are stupid ideas and stupid ways of doing things. That if you do more smart things and less stupid things, you will have a better chance of success. And that the hard part is recognizing that you are doing stupid things, and then having the discipline to stop doing these stupid things and do smart things instead.

I like to work with other pragmatists, people who are open-minded, who want to understand, who keep looking for what works. I long ago ran out of patience for orthodoxy and for people without the experience, creativity, patience and courage to question and learn, to find their own answers, and who believe that all you need to do is follow the One Right Way. And that if you do anything less, you will fail: that any house you build will be a house of straw (…that article still burns me up).

The people who put together Scrum, or XP, RUP, TSP/PSP, Software Kanban or these other ways to manage software development are smart, and they spent a lot of time thinking through the problems of how to build software, experimenting and learning. I look closely into how other people build software, I try to understand the decisions that they made and why they made them. But that doesn’t mean that what worked for them will be a perfect fit for my organization or your organization, my circumstances or yours.

And it’s clear that I’m not alone in thinking this way. A study published earlier this year by Forrester Research on Agile Development: Mainstream Adoption Has Changed Agility reported some interesting statistics on the state of the practice for software development methods, what development methods companies are following and how they are doing adopting new ideas:
  • Roughly 1/3 of developers and development managers are following Waterfall or Iterative methods such as RUP or Spiral
  • Another 1/3 are following Agile methods (Scrum, XP, Lean, FDD, …)
  • And 1/3 aren’t following any method at all, or if they are, they don’t know what it is.
Of the organizations adopting Agile methods, less than 1/3 stick to a particular Agile methodology as closely as possible. More than 2/3 deliberately mix different Agile practices; or incorporate Agile practices and ideas into “non-Agile” approaches. The report explains that:
“Perhaps the clearest sign of the mainstreaming of Agile is the abandonment of orthodoxy: Teams are puzzling out the mix of methodologies and combining them to fit within their organizational realities…”
The reasons for this are clear: most organizations find that it is better to learn from these methods and adapt them to their specific circumstances, their culture, their needs, their constraints. The report calls this “cherry-picking”, a “mix-and-match” approach to take the best bits from different methods and create a customized solution.

But I think that “cherry picking” is the wrong metaphor here. It’s more than just taking the “best bits”: it’s understanding why these practices work, and how they work together, how they support each other. Then focusing in on where you are experiencing problems, where you need to save costs, where you need to be faster or where you need to create some other advantage: where you will get the highest return. It’s taking what makes the most sense to you, what fits the best for your organization, what’s important. Understanding what you need and which practices (alone or together) can be applied to your needs; seeing what works, and then building on this to improve.

Some practices make plain good sense no matter where you work and how you work. Frequent builds, or better continuous build and continuous integration, is a no-brainer. Shortening development and delivery cycles, with more frequent checkpoints. Automated developer testing. But it doesn’t matter if you don’t do pair programming, if the developers in your organization don’t like it, won’t do it – as long as you understand why mainline XPers think that pair programming is useful and important, and that you find your own way to write good code, maybe through peer code reviews and static analysis (note I said “and”, not “or”: static analysis is not a substitute for code reviews). It doesn’t matter if what you are doing is XP or Scrum or Scrumban or that you can find a label for it at all. What matters is that it works, and that you are committed to making it work, and to learning, and to making it better.

Sunday, November 22, 2009

Small Teams, Big Results

How big a team do you need to deliver big results?

When my partners and I created this startup a few years ago, we made the decision to staff the development team with people that we knew, strong developers and test engineers who we had worked with before, people who we trusted and who trusted us. There were a lot of unknowns in what we were trying to achieve, could we secure enough funding, would our business model succeed, did we choose the right technologies, did we have the right design, could we handle all of the details and problems in launching a new market, could we deal with all of the integration and service needs, the regulatory and compliance requirements, …. and all of the other challenges that startups with aggressive goals face. So we wanted to take the risks out of development as much as possible, to assure stakeholders that we could deliver what we needed to, when we needed it.

We were lucky to put together a strong team of senior people: many of them we had worked with for several years, and some of them on only one project. But they were known quantities: we knew what to expect, and so did they. They understood the problem domain well and came up to speed on our design, and they came together as a team quickly of course, re-establishing relationships and norms – so we could hit the ground running. And we’re even more fortunate in that the core of the team has stayed in place from the start, and that we have been able to carefully add a few more senior people to the team, so that we continue leverage the experience and knowledge that everyone has built up.

There are tremendous advantages in working with a small group of experienced people who know what they are doing and care about doing a good job, people who enjoy challenges and who work well together.

In 10x Software Engineering, Construx Software examines the key factors that contribute to exceptional performance in software development: the factors and good engineering practices that drive some individuals and teams to outperform others by up to 10x. Some of these key success factors are keeping teams small, keeping teams together, and leveraging experience: that small teams of senior people, with a strong sense of identity and high levels of trust, staying together through projects, can significantly outperform the norm.

The value of small, experience-heavy teams, and especially of senior people who are deeply committed to doing a good job, committed to their craft, is explored in Pete McBreen’s excellent book Software Craftsmanship: the New Imperative. Pete shows that developers who have worked together in the past are more productive than teams created from scratch: that it is an important success factor for teams to be able to choose who to work with, to choose people who they know they can depend on, and who they feel comfortable working with. He especially emphasizes the importance of experience: that a jelled team of experienced people, working in an open and trusting way, can amplify each other’s strengths and work at hyper-productive levels, and that in a hyper-productive team of experienced developers who are playing at the top of their game, there is little space for beginners or “warm bodies”.

Pete also looks at the issue of team size in Questioning Extreme Programming, a skeptical but balanced review of XP practices which deserves more attention. Pete suggested at the time that
"XP is best suited to projects with a narrow range of team sizes, probably 4 to 12 programmers. Outside that range, other processes are probably more appropriate. The good news, however, is that a great many projects fall into the range of applicability. Indeed, there is some evidence that XP-size projects are predominant in the industry.”
Although my focus here is not on XP practices, the idea that most problems that the industry faces can be managed by small teams, following lightweight but disciplined practices, is an important one.

Back in March 2008, Steve McConnell asked a question on the Construx Forum about how to scale up a development team quickly. My answer would be to keep the core team as small as possible, add people that other people have worked with before and know and trust, and add fewer, more senior, experienced, technically strong staff.

I have worked a lot with large technology companies like IBM and HP, and I was surprised to find out how small the core engineering teams are in those big companies. Where a company like IBM might have a big distributed first-level and second-level support organization, trainers, offshore testing labs, product managers, marketing teams, technical writers, pre-sales support engineers, sales teams, vertical industry specialists, integration specialists, project managers and other consultants: all of these people leverage the IP created by small, senior teams of engineers and researchers. These engineering teams, even at a company like IBM, have a different culture than the customer-facing parts of the organization – less formal and more inward-focused on technical excellence, on “alpha geekdom” – and were more free to come up with new ideas. Google, of course, is an extreme example of this: a large company where lots of software is created by very small, very senior teams driven to technical excellence.

It makes sense to follow the same model in scaling out a team: start with a small, senior core, be careful to add a few senior people, space out your hires, and scale out primarily in supporting roles, allowing the small core engineering team to continue to focus on results, on excellence.

One of the many advantages of small teams is that they spend less time and make fewer mistakes communicating with each other, you can use less formal (and less expensive) and more efficient communication methods. This lets you move faster, and adapt faster to change. If the team is made up of mostly of experienced, senior staff, they can get maximum value out of lightweight “small a” agile methods, take on less unintentional technical debt, again reducing cost and time, and by making fewer mistakes and writing better code in the first place, create a higher quality product, further accelerating results in a virtuous circle.

The key here is to have enough discipline, to follow enough good engineering practices, without weighing the team down too much.

In Nailing the Nominals, Eric Brechner, in charge of engineering excellence at Microsoft, sets the limit at 100,000 lines of code and 15 people. Below this line,
"you can…use emergent design, have a loose upfront design bar, rewrite and refactor the code endlessly while the customer looks over your shoulder. When your code base and your project is bigger, it's solid design and disciplined execution or it's broken code, broken teams, and broken schedules."
In another related post, Green Fields are Full of Maggots, I.M. Wright, er, I mean Eric, goes on to say that
"the regular refactoring and rework needed for emergent design isn't a problem for small code bases. However, when you get above 100,000 lines of code serious rework becomes extraordinarily expensive. That's why customer-focused, up-front architecture is essential for large projects.

This was researched by Dr. Barry Boehm, et al, in May 2004. They found that rework costs more than up-front design on projects larger than 100 KLOC. The larger the project, the more up-front design saves you."
What’s of particular interest to me is that we work right on the edge of these limits, in terms of size of code base (although we also have a lot of test code and other supporting code) and total team size. Our extra focus on discipline and controls is necessary because of the high standards of reliability that we need to stand up to, and the complexity of the problems that we solve. While we could move even faster, the risk and cost of making mistakes is too high. So the challenge is to achieve the right balance, between speed and efficiency and discipline.

Sunday, September 27, 2009

Risk Management - You Don't Have to Waltz with Bears

I recently finished reading Waltzing with Bears: Managing Risk on Software Projects by Tom DeMarco and Tim Lister, both recognized experts in software development and risk management. The material in this book covers much of the same territory as courses that I attended several years ago in software project management and risk management presented by these authors through The Atlantic Systems Guild.

This work is based on their experience as consultants and as expert witnesses in contract disputes and litigation over software project failures. The authors make a strong case that effective risk management is essential to the success of any software project worth doing; that you must be prepared to face failure and deal with uncertainty; that you must actively manage risks, by containing risks through schedule and budget buffers, or proactively mitigating risks by taking steps to reduce the probability and/or impact of a problem; that you must consider alternatives for any critical activities or work items; and that managing for success, attempting to evade risks, is the path to failure.

Waltzing with Bears focuses on the kinds of problems faced by (and effectively created by) large waterfall projects: trying to commit to scope and schedule and cost up front when there isn’t enough information to do so; and trying to account for and manage the unknown and unaccountable. It’s an almost hopeless situation, but the authors provide ideas and disciplines and tools that at least offer a better chance at success.

What’s necessary is to change the rules of the game, to consider other ways of building software.

In an earlier post, I explored how risk management can and should be burned into the way that you develop software; how schedule and scope and quality risks and other risks can be managed through the development lifecycle you choose and the engineering practices that your team follows. Johanna Rothman, in a paper titled “What Lifecycle: Selecting the Right Model for your Project” explores some of the same ideas, how to manage schedule risks and other risks through lifecycle models, in particular incremental and iterative development approaches.

It is clear to me that following incremental, iterative, timeboxed development, as in Extreme Programming and Scrum, will effectively mitigate many of the common risks and issues that concern the authors of Waltzing with Bears. To some extent, the authors agree, when they conclude that

“The best bang-per-buck risk mitigation strategy we know is incremental delivery” (by which they mean Staged Delivery), “development of a full or nearly full design, and then the implementation of that design in subsets, where each successive subset incorporates the ones that preceded it”.

While Scrum (interestingly) does not explicitly address risk management; it does mitigate scope, schedule, quality, customer and personnel risks through its driving principles and management practices: incremental timeboxed delivery (sprints), close collaboration within a self-managing team and with the customer, managing the backlog (scope) together with the customer (Product Owner), and daily standup meetings and retrospectives which allow the team to continuously adjust to issues and changes.

Extreme Programming (XP) recognizes and confronts risk directly and fundamentally – chapter 1 of Extreme Programming Explained: Embrace Change begins:

“The basic problem of software development is risk”.

In The Case for XP Chris Morris explains that XP is resilient to risk, that it inherently accepts change and uncertainty, rather than attempting to anticipate risk, to predict and manage dangers up front; building on a risk management model developed by political scientist Aaron Wildavsky.

XP addresses risk through:

- short iterations with fine-grained feedback

- keeping the customer close

- test-driven development to maintain a quality baseline

- refactoring and pair programming to ensure code quality

- continuous integration

- simple design

While you can manage most types of risks effectively through your SDLC especially by following incremental, iterative techniques and disciplined engineering practices, there are two general classes of risk that require active and continuous risk discovery and explicit risk management, using tools and ideas such as the ones detailed in Waltzing with Bears, Steve McConnell’s Top 10 Risk List, and the formal methods and techniques taught by the Project Management Institute (this is where my PMP comes in handy):

1. Project risks outside of your team’s work in software development, but which directly impact your success. These include: sponsor and stakeholder issues and other political risks, larger business issues outside of your control, regulatory changes, reliance on delivery from partners and sub-contractors, implementation and integration with partners and customers.

2. Technical risks in the platform, architecture or design. This is especially important if you are building enterprise, high reliability systems such as a telco, banking systems, large e-commerce sites, or financial trading. Some lifecycle and SDLC factors help to mitigate technical risks, such as prioritizing work that is technically difficult in XP, or using exploratory prototyping not only for customer feedback but for technical proof of concept work. But to ensure that your product works in the real world, the team constantly needs to consider technical risk: difficult problems to solve; fragile or complex parts of the system; areas where you are pushing beyond your technical knowledge and experience. Using this information you can determine where to focus your attention in technical reviews and testing; what to try early and prove out; what to let soak; what you should have your best people work on.

If you are building software incrementally and carefully, you won’t have to “waltz with bears”, but you still need to continuously look for, and actively manage, risks inside and outside of the work that your team is doing.

Thursday, November 13, 2008

Construx SW Development Executive Summit

I have started working again with Construx Software, helping us improve our software engineering practices. I was of course familiar with Steve McConnell, Construx's CEO and his books on software engineering, and I had worked with Construx at a previous company on training and mentoring our development team and development managers.

Earlier this year I attended their 10x Software Engineering course, an excellent software development management course which focuses on understanding and implementing good practices in software development, how to improve quality and team productivity. We enlisted their help on a project assessment with a partner, and Construx is scheduled to come in later this year to teach a Developer Testing Bootcamp course to the development team.
In October I also attended Construx's Software Development Executive Summit: an intimate, intense and highly-focused series of roundtable sessions and high-quality keynotes with the heads of software development and software engineering at large and small companies across North America, Europe and Asia. Like other Construx offerings, the summit was pragmatic, selective, carefully organized and very professionally run. The keynote speakers included Martin Fowler of ThoughtWorks and Ken Schwaber, the creator of Scrum, as well as Construx's CEO Steve McConnell, author of Code Complete and Rapid Development, and Matt Peloquin of Construx; and interesting case studies presented by IT executives at MSNBC and RIM.

It was a unique forum: a chance to meet and share ideas in an open, constructive and respectful environment with serious people who all had extensive experience leading software development and who were all looking for ways to improve. There were so many different stories: companies who had great success (or disappointing failures) at outsourcing (onshore and offshore); companies who were successful delivering using small, agile, results-oriented collocated teams; other companies who followed highly structured, metrics-driven SDLCs and were equally successful. The development organizations ranged in size from a handful of developers to hundreds or thousands of engineers in multiple countries. The roundtable sessions provided me the opportunity to explore problems and share ideas with experienced development managers, product managers and project managers, and thinkers like Martin Fowler. The social engagements provided excellent networking opportunities and were generally good fun, and there was no pressure from vendors or sponsors.

What key ideas did I take back from the summit?

  1. The first key to success is talent. Get the best people you can. Treat them well and support them, give them what they need. Be careful when hiring, and spend time with new hires, help them to be successful. Keep teams together as long as you can: continuity and cohesion of a team pays dividends.
  2. There is no “one way to skin a cat”: software development poses different problems to different organizations, and there are different answers to these problems. What is important is to execute, and to constantly review and improve.
  3. If you want to show value to your customers, deliver value often, deliver what is important first. It’s all about incremental delivery.
  4. In globally distributed teams, follow-the-sun works for operations, but doesn’t for development. Co-locate teams whenever possible.
  5. Develop technical leadership within your organization. Create a path for talented and ambitious technical people who do not fit or do not want to pursue the management track. Follow the lead of IBM, Microsoft and Google and offer a “distinguished engineer” career path where senior technical people are given respect, latitude and a voice in product direction.
  6. Don’t expect to save costs through outsourcing. Outsource for flexibility, to flex your organization’s delivery capability; and to gain access to talent. To outsource successfully takes a lot of discipline and management attention and supporting costs.
  7. Constantly be aware of, and beware of, technical debt. Don’t bet on “throwing one away” when you build a system. Agile methods without discipline (comprehensive reviews or pair programming, developer testing, …) gets fast results at first, but builds up a lot of technical debt that has to be addressed eventually. If you start with disciplined, good practices from the beginning you won't dig yourself as deep a hole.

This is an event I look forward to attending again in the future and will defintely recommend to my colleagues.