Wednesday, May 29, 2013

Estimating Might Be Broken, But It’s Not Evil

Ron Jeffries's essay Estimation is Evil talks about how absurd estimating can be on a software project, and the nightmare scenarios that teams can end up in:
…Then we demand that the developers “estimate” when they’ll be done with all this stuff. They, too, know less about this product than they ever will again, and they don’t understand most of these requirements very well. But they do their best and they come up with a date. Does the business accept this date? Of course not! First of all, it’s only an estimate. Second, clearly the developers would leave themselves plenty of slack—they always do. Third, that’s not when we want it. We want it sooner.

So we push back on the developers’ estimate, leaning harder and harder until we’re sure we’ve squeezed out all the fat they left in there. Sometimes we even just tell them when they have to be done.

Either way, the developers leave the room, heads down, quite sure that they have again been asked to do the impossible. And the business people write down the date: “Development swears they’ll be done November 13th at 12:25PM.”

Software Estimation is Broken

Software Estimation – the way that most of us do it – is broken. As an industry we’re bad at estimating, we've been bad at it for a long time, and there’s no evidence that we’re getting much better at it.

Developers know this. The business knows this – so they don’t trust what the development team comes up with, and try to make their own plans. Management knows this too, so they work around estimates (I’ll take everything and double it), or worse they abuse estimates, cut them to the bone, and then use them as a lever to drive the team towards an unachievable goal.

Jeffries says that even teams who are trying to estimate properly are excessively concerned with predictability (and all of the overheads and navel gazing that come with trying to be predictable), when they really should be working on getting the right things done as soon as possible, which is all that the business actually cares about.

So because it’s hard, and because we’re not good at it, and because some people ignore estimates or abuse them, we should stop estimating at all.

As developers what we need to do is make sure that we understand what the most important thing is to the business, break the problem down into the smallest pieces possible and start iterating right away, deliver something and then go onto the next most important thing, and keep going until the business gets what they really need. If you can’t convince “them” (the sponsors) that this is the right way to work, then go through the theatre of estimating to get the project approved (knowing that whatever you come up with is going to be wrong and anyways management and the business are going to ignore it or use it against you), and then get to real work: understand what the most important thing is to the business, break the problem down into the smallest pieces possible and start iterating right away. In other words

“Stop estimating. Start Shipping”.

Martin Fowler wrote a recent post PurposeofEstimation where he says estimates are needed only if they help you make “significant decisions”. His examples are getting resources allocated (portfolio management go/no go – the game Jeffries describes above), and coordination, where your team's work needs to fit in with other teams (although he talks only about coordinating with other developers, ignoring the need to coordinate with customers, partners and other projects that have nothing to do with software development). There are many other times when estimates are needed: delivering to fixed-price contracts, budgeting for programs, when you need to hit a drop dead date (for example, when an industry-wide change is going to happen whether you are done or not).

The rest of the time, if your team is small enough and they know what they’re doing and they’re working closely with the business and delivering working software often, then nobody cares all that much about estimating – which to be honest is how my team does a lot of our work.

But this is a problem-solving approach, not a project management approach.

If you don’t know what you are building, why estimate?

It can work for online startups and other exploratory development: you have an idea that you think is good, but you’re not sure of the details, what people are going to like and what will catch on. If you don’t really know what you are building, then there’s no point trying to estimate how long it is going to take. Somebody will decide how much money you can spend, you start simple, deliver something useful and important (“minimum viable product”) as soon as you can so you can get feedback and keep iterating until hopefully enough people are using it and are telling you what you really need to build, or you run out of money.

We’re back to Evolutionary Prototyping, but with a strict focus on minimal features and prioritization (do only what’s important, don’t even try to consider the entire project because you may not have to deliver it all anyways), and fast feedback loops. Now it’s called “The Lean Startup” method.

If you are going to change it again tomorrow, why estimate?

Working this way also makes sense for a lot of online businesses: Facebook, Twitter, Linkedin, Etsy Netflix all work this way today. They are constantly delivering small features, or maybe breaking bigger changes into small steps and pushing them out incomplete but “dark” as soon as they can (often several times a day), constantly fiddling with the UI, adding personalization features and new channels and integrating with new partners and continuously capturing behavioural data so that they can tell what changes users like or at least what they are willing to put up with, trying out new ideas and running A/B tests knowing that some or most of these ideas will fail.

This work can be done by small teams working independently, so the size and cost of each “project” is small. Marketing wants to add a new interface or run a small experiment of some kind (the details are fuzzy, we’re going to have to iterate through it), it will probably only take a few weeks or maybe a month or two, just get a few smart people together and you see how fast you can get something working. If it doesn't work, or it’s taking too long, cancel it and go on to the next idea. It’s an attention-deficit way of working, but if you are chasing after new customers or new revenue sources and your customers will put up with you experimenting with them, it can work.

Don’t bother estimating, just make it work

And routine maintenance (anything that doesn't have a fixed/drop-dead end date) can be done this way too. David Anderson’s most persuasive arguments in favor of Kanban (working without estimates and continuously pushing out individual pieces of work) are in streamlining maintenance and operations work.

The business doesn't care that much about how this kind of work is managed – they just want important things fixed ASAP, and at the least possible cost. Most of this work is done by individuals or small teams, so again the cost of any piece of work is small. Instead of wasting time trying to estimate each change or fix upfront, you assume everything takes 3 days or whatever to do, and if you aren't finished at 3 days, then stop and escalate it to management, let them review and decide whether the work needs more scoping or should be done at all. Focus on getting things done and everybody is happy.

Why bother estimating – it’s just another mobile app

And it works for mobile app development, again where most work is done by small teams and most of the focus is on the user experience, where the uncertainties are more around what customers are going to like (the product concept, the look-and-feel – which means lots of iterative design work, prototyping and usability testing... and this is going to take how long?) and not on technical risks or project risks.

But you can’t run a project without estimating

Yes a lot of work is done and can be done in small projects by small teams and if the project is small enough and short enough then you may not need to bother much or at all with estimating – because you’re not really running a project, you’re problem solving.

But this way of working doesn't scale up to large organizations running large projects and large programs with significant business and technical risks which need to be managed throughout, and work that needs to be coordinated between different teams doing lots of different things in different places at different times, with lots of handoffs and integration points and dependencies. This is where predictability – knowing where you are and seeing ahead to where you are going to be (and where everybody else is going to be) with confidence – is more important than minimizing cycle time and rapid feedback and improvisation.

It comes down to whether you need to deliver something as a big project or you can get away with solving many smaller problems instead. While there is evidence that software development projects are getting shorter on average (because people have learned that smaller projects fail less often or at least fail faster), some problems are too big to be solved piecemeal. So estimating isn’t going to go away – most of us have to understand estimating better and get better at doing it.

#NoEstimates – building software without estimating – is like Agile development in the early days. Then it was all about small teams of crackerjack programmers delivering small projects quickly (or not delivering them, but still doing it quickly) and going against the grain of accepted development methods. Agile didn’t scale, but it got a lot of buzz and achieved enough success that eventually many of the ideas crossed into the mainstream and we found ways to balance agility and discipline, so that now Agile development methods are being used successfully in even large scale programs. I don’t see how anyone can successfully manage a big project without estimating, but that doesn't mean that some people aren't going to try – I just wouldn't want to be around when they try it.

Thursday, September 13, 2012

Can you get by without estimating? Should you try?

Estimating remains one of the hardest problems in software development. So hard in fact that more people lately are advocating that we shouldn’t bother estimating at all.

David Anderson, the man behind Kanban, says that we should stop estimating, and that estimates are a waste of time. In his case study about introducing Kanban ideas at Microsoft, one of the first steps that they took to improve a team’s productivity was to get them to stop estimating and start focusing instead on prioritizing work and getting the important work done.

Then you have experts like Ron Jeffries saying things like

I believe that most estimation is waste and that it is more common to use estimation as a replacement for proper steering, and to use it as a whip on the developers, than it is to use it for its only valid purpose in Release Planning, which is more like "decide whether to do this project" than "decide just how long this thing we just thought of is going to take, according to people who don't as yet understand it or know how they'll do it”

and

Estimation is clearly "waste". It's not software…If estimation IS doing you some good, maybe you should think about it as a kind of waste, and try to get rid of it.

And, from others on the “If you do bother estimating, there’s no point in putting a lot of effort into it” theme:

Spending effort beyond some minutes to make an estimate "less wrong" is wasted time. Spending effort calculating the delta between estimates and actuals is wasted time. Spending effort training, working and berating people to get "less wrong" estimates is wasted time and damaging to team performance.

In “Software estimation considered harmful?” Peter Seibel talks about a friend running a startup, who found that it was more important to keep people focused and motivated on delivering software as quickly as possible. He goes on to say

If the goal is simply to develop as much software as we can per unit time, estimates (and thus targets), may be a bad idea.

He bases this on a 1985 study in Peopleware which showed that programmers were more productive when working against their own estimates than estimates from somebody else, but that people were most productive on projects where no estimates were done at all.

Seibel then admits that maybe “estimates are needed to coordinate work with others” – so he looks at estimating as a “tool for communication”. But from this point of view, estimates are an expensive and inefficient way to communicate information that is of low-quality – because of the cone of uncertainty all estimates contain variability and error anyways.

What’s behind all of this?

Most of this thinking seems to come out of the current fashion of applying Lean to everything, treating anything that you do as potential waste and eliminating waste wherever you find it. It runs something like: Estimating takes time and slows you down. You can’t estimate perfectly anyways, so why bother trying?

A lot of this talk and examples focus on startups and other small-team environments where predictability isn’t as important as delivering. Where it’s more important to get something done than to know when everything will be done or how much it will cost.

Do you need to estimate or not?

I can accept that estimates aren’t always important in a startup – once you’ve convinced somebody to fund your work anyways.

If you’re firefighting, or in some kind of other emergency, there’s not much point in stopping and estimating either – when it doesn’t matter how much something costs, when all you care about is getting whatever it is that you have to do done as soon as possible.

Estimating isn’t always important in maintenance – the examples where Kanban is being followed without estimating are in maintenance teams. This is because most maintenance changes are small by definition - maintenance is usually considered to be fixing bugs and making changes that take less than 5 days to complete. In order to really know how long a change is going to take, you need to review the code to know what and where to make changes. This can take up to half of the total time of making the change – and if you’re already half way there, you might as well finish the job rather than stopping and estimating the rest of the work. Most of the time, a rule of thumb or placeholder is a good enough estimate.

In my job, we have an experienced development team that has been working on the same system for several years. Almost all of the people were involved in originally designing and coding the system and they all know it inside-out.

The development managers triage work as it comes in. They have a good enough feel for the system to recognize when something looks big or scary, when we need to get some people involved upfront and qualify what needs to get done, work up a design or a proof of concept before going further.

Most of the time, developers can look at what’s in front of them, and know what will fit in the time box and what won’t. That’s because they know the system and the domain and they usually understand what needs to be done right away – and if they don’t understand it, they know that right away too. The same goes for the testers – most of the time they have a good idea of how much work testing a change or fix will take, and whether they can take it on.

Sure sometimes people will make mistakes, and can’t get done what they thought they could and we have to delay something or back it out. But spending a little more time on analysis and estimating upfront probably wouldn't have changed this. It’s only when they get deep into a problem, when they’ve opened the patient up and there’s blood everywhere, it’s only then that they realize that the problem is a lot worse than they expected.

We’re not getting away without estimates. What we’re doing is taking advantage of the team’s experience and knowledge to make decisions quickly and efficiently, without unnecessary formality.

This doesn't scale of course. It doesn’t work for large projects and programs with lots of inter-dependencies and interfaces, where a lot of people need to know when certain things will be ready. It doesn’t work for large teams where people don’t know the system, the platform, the domain or each other well enough to make good quick decisions. And it’s not good enough when something absolutely must be done by a drop dead date – hard industry deadlines and compliance mandates. In all these cases, you have to spend the time upfront to understand and estimate what needs to get done, and probably re-estimate again later as you understand the problem better. Sometimes you can get along without estimates. But don’t bet on it.

Wednesday, August 29, 2012

Contracting in Agile – You try it

One of the key principles in Agile development is

“Customer collaboration over contract negotiation”
Unfortunately, that means that if you’re trying to follow Agile methods, you’re left without useful guidelines to follow when it comes to contracting and coming up with contracts that fit the way that Agile teams work.

Time-and-materials of course is a no-brainer, regardless of how the team works – do the work, track the time and other costs, and charge the customer as you do it. But it’s especially challenging for people who have to work within contract structures such as fixed price / fixed scope, which is the way that many government contracts are awarded and the way that a number of large businesses still contract development work.

The advice for Agile teams usually runs something like: it’s up to you to convince the purchaser to change the rules and accept a fuzzier, more balanced way of contracting, with more give-and-take. Something that fits the basic assumptions of Agile development: that costs (mostly the people on the team) and schedule can be fixed, but the scope needs to be flexible and worked out as the project goes on.

But in many business situations the people paying for the work aren’t interested in changing how they think and plan – it’s their money and they want what they want when they want it. They are calling the shots. If you don’t comply with the terms of the bidding process, you don’t get the opportunity to work with the customer at all. And the people paying you (your management) also need to know how much it is going to cost and when it is going to be done and what the risks are so they know if they can afford to take the project on. This puts the developers in a difficult (maybe impossible) situation.

Money for Nothing and Change for Free

Jeff Sutherland, one of the creators of Scrum, proposes a contract structure called “Money for Nothing and your Change for Free”. The development team delivers software incrementally – if they are following Scrum properly, they should start with the work that is most important to the customer first, and deliver what the customer needs the most as early as possible. The customer can terminate the contract at any point (because they’ve already got what they really need), and pay some percentage of the remainder of the contract to compensate the developer for losing the revenue that they planned to get for completing the entire project. So obviously, the payment schedule for the contract can’t be weighted towards the end of the project (no large payments on “final acceptance” since it may never happen). That’s the “money for nothing” part.

“Change for free” means that the customer can’t add scope to the project, but can make changes as long as they substitute work still to be done in the backlog with work that is the same size or smaller. So new work can come up, the customer can change their mind, but the overall size of the project remains the same, which means that the team should still be able to deliver the project by the scheduled end date.

To do this you have to define, understand and size all of the work that needs to be done upfront – which doesn’t fit well with the iterative, incremental way that Agile teams work. And it ignores the fact that changes still carry a price: the developers have to throw away the time that they spent upfront understanding what needed to be done enough to estimate it and the work that they went in to planning it, and they have to do more work to review and understand the change, estimate it and replan. Change is cheap in Agile development, but it’s not free. If the customer needs to make a handful of changes, the cost isn’t great. But it can become a real drag to delivery and add significant cost if a customer does this dozens or hundreds of times over a project.

Fixed Price and Fixed Everything Contracts

Fixed Price contracts, and especially what Alistair Cockburn calls Fixed-Everything contracts (fixed-price, fixed-scope and fixed-time too) are a nasty fact of business. Cockburn says that these contracts are usually created out of lack of trust – the people paying for the system to be developed don’t trust the people building the software to do what they need, and try to push the risk onto the development team. Even if people started out trusting each other, these contracts often create an environment where trust breaks down – the customer doesn’t trust the developers, the developers hide things from the customer, and the people who are paying the developers don’t trust anybody.

But it’s still a common way to contract work because for many customers it is easier for them to plan around and it makes sense for organizations that think of software development projects as engineering projects and that want to treat software engineering projects the same way as they do building a road or a bridge. This is what we told you we want, this is when we need it, that’s how much you said it was going to cost (including your risk and profit margin), we agree that’s what we’re willing to pay, now go build it and we’ll pay you when you get it done.

Cockburn does talk about a case where a team was successful in changing a fixed-everything contract into a time-and-materials contract over time, by working closely with the customer and proving that they could give the customer what they needed. After each delivery, the team would meet with the customer and discuss whether to continue with the contract as written or work on something that customer really needed instead, renegotiating the contract as they went on. I’ve seen this happen, but it’s rare, unless both companies do a lot of work together and the stakes of failure on a project are low.

Ken Schwaber admits that fixed price contracting can’t be done with Scrum projects (read the book). Again, the solution is to convince the customer to accept and pay for work in an incremental, iterative way.

Martin Fowler says that you can’t deliver a fixed price, fixed time and fixed scope contract without detailed, stable and accurate requirements – which he believes can’t be done. His solution is to fix the price and time, and then work with the customer to deliver what you can by the agreed end date, and hope that this will be enough.

The most useful reference I’ve found on contracting in Agile projects is the freely-available Agile Contracts Primer from Practices for Scaling Lean and Agile Development, by Arbogast, Larman And Vodde.

Their advice: avoid fixed-priced, fixed-scope (FPFS) contracts, because they are a lose-lose for both customer and supplier. The customer is less likely to get what they need because the supplier will at some point panic over delivery and be forced to cut quality; and if the supplier is able to deliver, the customer has to pay more than they should because of the risk premium that the supplier has to add. And working this way leads to a lack of transparency and to game playing on both sides.

But, if you have to do it:

  • Obviously it’s going to require up-front planning and design work to understand and estimate everything that has to get done – which means you have to bend Agile methods a lot.
  • You don’t have to allow changes – you can just work incrementally from the backlog that is defined upfront. Or you can restrict the customer to only changing their mind on priority of work to be done (which gives them transparency and some control), or allow them to substitute a new requirement for an existing requirement of the same size (Sutherland’s “Change for Free”).

To succeed in this kind of contract you have to:

  • Invest a lot to do detailed, upfront requirements analysis, some design work, thorough acceptance test definition and estimation – by experienced people who are going to do the work
  • Don’t allow changes in requirements or scope – just replacement / substitution
  • Increase the margin of the contract price
  • Make sure that you understand the problem you are working on – the domain and technology
  • Deliver important things early and hope that the customer will be flexible with you towards the end if you still can’t deliver everything.

PMI-ACP on Agile Contracting?

For all of the projects that have been delivered using Agile methods, contracting seems to be still a work in progress. There are lots of good ideas and suggestions, but no solid answers.

I’ve gone through the study guide materials for the PMI-ACP certification to see what PMI has to say about contracting in Agile projects. There is the same stuff about Sutherland’s “Money for Nothing and your Change for Free” and a few other options. It’s clear that the PMI didn’t take contracting in Agile projects on as a serious problem. This means that they missed another opportunity to help large organizations and people working with large organizations (the kind of people who are going to care about the PMI-ACP certification) to understand how to work with Agile methods in real-life situations.

Thursday, August 2, 2012

Fixing Bugs – there’s no substitute for experience

We've all heard that the only way to get good at fixing bugs in through experience – the school of hard knocks. Experienced programmers aren’t afraid, because they’ve worked on hard problems before, and they know what to try when they run into another one – what’s worked for them in the past, what hasn’t, what they’ve seen other programmers try, what they learned from them.

They’ve built up their own list of bug patterns and debugging patterns, and checklists and tools and techniques to follow. They know when to try a quick-and-dirty approach, use their gut, and when to be methodical and patient and scientific.They understand how to do binary slicing to reduce the size of the problem set. They know how to read traces and dump files. And they know the language and tools that they are working with.

It takes time and experience to know where to start looking, how to narrow in on a problem; what information is useful, what isn’t and how to tell the difference. And how to do all of this fast. We’re back to knowing where to tap the hammer again.

But how much of a difference does experience really make?

Steve McConnell’s Code Complete is about programmer productivity: what makes some programmers better than others, and what all programmers can do to get better. His research shows that there can be as much as a 10x productivity difference in the quality, amount and speed of work that top programmers can do compared to programmers who don't know what they are doing.

Debugging is one of the areas that really show this difference, that separates the men from the boys and the women from the girls. Studies have found a 20-to-1 or even 25-to-1 difference in the time it takes experienced programmers to find the same set of defects found by inexperienced programmers. That’s not all. The best programmers also find significantly more defects and make far fewer mistakes when putting in fixes.

What’s more important: experience or good tools?

In Applied Software Measurement, Capers Jones looks at 4 different factors that affect the productivity of programmers finding and fixing bugs:

  1. Experience in debugging and maintenance
  2. How good – or bad – the code structure is
  3. The language and platform
  4. Whether the programmers have good code management and debugging tools – and know how to use them.

Jones measures the debugging and bug fixing ability of a programmer by measuring assignment scope - the average amount of code that one programmer can maintain in a year. He says that the average programmer can maintain somewhere around 1,000 function points per year – about 50,000 lines of Java code.

Let’s look at some of this data to understand how much of a difference experience makes in fixing bugs.

Inexperienced staff, poor structure, high-level-language, no maintenance tools

Worst Average Best
150 300 500

Experienced staff, poor structure, high-level language, no maintenance tools

Worst Average Best
1150 1850 2800

This data shows a roughly 20:1 difference between experienced programmers and inexperienced programmers, on teams working with badly structured code and without good maintenance tools. Now let’s look at the difference good tools can make:

Inexperienced staff, poor structure, high-level language, good tools

Worst Average Best
900 1400 2100

Experienced staff, poor structure, high-level language, good tools

Worst Average Best
2100 2800 4500

Using good tools for code navigating and refactoring, reverse engineering, profiling and debugging can help to level the playing field between novice programmers and experts.

You’d have to be an idiot to ignore your tools (debuggers are for losers? Seriously?). But even with today’s good tools, an experienced programmer will still win out – 2x more efficient on average, 5x from best to worst case.

The difference can be effectively infinite in some cases. There are some bugs that an inexperienced programmer can’t solve at all – they have no idea where to look or what to do. They just don’t understand the language or the platform or the code or the problem well enough to be of any use. And they are more likely to make things worse by introducing new bugs trying to fix something than they are to fix the bug in the first place. There’s no point in even asking them to try.

You can learn a lot about debugging from a good book like Debug It! or Code Complete. But when it comes to fixing bugs, there’s no substitute for experience.

Tuesday, June 5, 2012

Agile Estimating: Story Points and Decay

I’m re-reading Mike Cohn’s Agile Estimating and Planning. It's the best book I've found on this and worth reading, even if he gets too Scrummy at times, and even if you don’t agree with everything he says. Which I don’t.

For example, I don’t agree with him that Story Points are better for estimation than Ideal Days. When we do estimates, we use Ideal Days, because thinking this way is more natural and more useful, and because these estimates are more meaningful to people inside and outside of the team.

Estimates in Ideal Days Decay

One of the reasons that Cohn recommends Story Points is that, unlike estimates in Ideal Days, Story Point estimates “have a longer shelf life” because they don’t decay – the meanings of the estimates don’t change over time as the team gets more information.

If you’re estimating using Ideal Days, as you learn more about the tools and language and platform, as you have more code to build on and work with, your understanding of how much work you can do in an Ideal Day will change. You may be able to get more work done – or less, because it turns out that you need to spend more time testing or whatever. As you learn and get better at how you work and understand it better, the definition of an “Ideal Day” will change. You’re learning and getting more information, so why not use this information and make better-quality decisions as you go forward?

But this means the estimates that you did earlier aren’t as useful any more – they’ve decayed. You’ll have to re-estimate this work at some point, because you’re mixing before-the-fact and after-the-fact information.

At some point you may have to do this anyways, whether you use Ideal Days or Story Points. Because relative-size estimates in Story Points also decay over time.

Story Points Decay too

Estimates in Ideal Days change as you learn more about the solution space: about how much work it actually takes to build some thing. Story Point estimates change as you learn more about the problem space: as you learn more about the domain and the problems that you need to solve, as you learn more about how big something really is in comparison to other things.

Take Cohn’s “Zoo Points” exercise, where people attempt to estimate the relative size of different wild animals. Everyone knows that a blue whale is much bigger than a rabbit or a fox. But if you’ve never seen a blue whale in real life, you have no real idea just how much bigger it is. 10x? 100x? 500x? 1000x? What about a tarsier or an okapi – some of the rarest animals in the world. You’re unlikely to ever see one. How the heck could you know how big they are relative to a rabbit, or to each other? You don’t know, so you’ll need to make a reasonable guess and use that for the time being.

Later, as you learn more about the problem space, especially if it’s a deeply technical domain, your understanding of size and complexity and risk will improve, and could change a lot.

So your idea of whether a thing is twice as big as something else, or about 1/5 as big as another thing, whether it's worth 5 points or 15 points, will change as you understand more about what these things actually are. As you continue to estimate the changes and new requirements that come in, your new estimates won’t align with earlier ones. The kind of work that you thought to be 5 points earlier you now know is 15 points. Unlike an Ideal Day, you haven’t changed what “5 points” means, but you have changed your understanding of what work is actually “5 points” worth.

On a project that’s run for a long time, people will join the team bringing new knowledge and experience, and people will leave taking knowledge and experience with them. Which means that estimates that you made earlier, before you learned something, or when you knew something that you’ve now lost, can't be the same as the estimates that you're making now, regardless of whether you’re sizing work in days or points. It’s unavoidable – you can’t not use what you have learned, and you can’t keep using what you’ve lost.

There may be reasons that Story Points are a better choice for estimating, for some teams at least, but “decay” isn’t one of them.

Tuesday, June 21, 2011

Estimation is not a Black Art

Construx Software is one of the few companies that take the problems of estimation in software development seriously. Earlier this year I attended Steve McConnell’s Software Estimation in Depth course based on his book Software Estimation: Demystifying the Black Art. Two days reviewing factors in estimation and the causes of errors in estimating, the differences between estimates and targets and commitments, how to present estimates to the customer and to management, the importance of feedback and data, estimating techniques that work and why they work, and when and how to apply these techniques to different estimating problems.

You can get a lot out of reading Steve’s book, but the course setting gives you a chance to work with other people and solve real problems in estimation and planning, dig deep into questions with the man himself, and it introduces new material and research not included in the book. The key takeways from this course for me were:

The Basics

Even simple techniques work much better than “expert judgment” (aka wild ass guesses). With training and using straightforward tools and simple mathematical models and following a bit of structure, you can get to 70-75% accuracy in estimating, which is good enough for most of us.

Never estimate on the spot – it is professionally irresponsible, and you’re setting yourself, your team, and your customer up to fail. Always give the person who is doing the estimate time to think. Everyone knows this, but it’s important to be reminded of it, especially under pressure.

People’s systemic error tendency is to underestimate. Many organizations underestimate by a factor of at least 2x. This also applies to comparing back to actual costs: a common mistake is to remember how much you estimated something would take, not how long it actually took.

Estimates are always better if you can use real data to calibrate them: to compare estimates against evidence of how your organization has performed in the past. I knew this. But what I didn’t know is that you don’t need a lot of data points: even a few weeks of data can be useful, especially if it contradicts with judgment and forces you to question your assumptions.

Use different techniques at different stages as you move along a project’s Cone of Uncertainty, depending on how much information you have available at the time, and how high the stakes are – what the cost of estimation errors could be to the business. If you need higher confidence or higher quality estimates, use multiple techniques and compare the results.

I like T-Shirt sizing to help in planning and making a business case. Developers come up with a rough order of magnitude estimate on cost or effort (small, medium, large, extra-large) while the Customer/Product Owner/Product Manager does the same for the expected business value of a feature or change request. Then you match them up: Extra-Large business value and Small development cost gets a big thumbs-up. Small business value and Extra-Large cost gets a big thumbs down.

Estimating by analogy – comparing the work that you need to estimate to something similar that you’ve done before – is a simple technique that we use a lot. It works well if you are adding “another screen”, writing “another report”, or building “another interface”. It’s a good fit for maintenance, if you’ve been working with the same code for a while and know most of the gotchas.

Intact teams (like mine) tend to view problems in a similar way – ideas and experience converge. This is good if you work on similar problems, in maintenance or a long-running project, because you can make decisions quickly and confidently. But this is bad if you are confronted with new problems – you need techniques like Wideband Delphi to challenge people’s thinking patterns and let new ideas in.

Agile Estimating and Story Points and Velocity

We spent more time than I expected exploring issues in estimating Agile development work. Incremental and iterative planning in Agile development poses problems for a lot of organizations. The business/customer needs to know when the system will be ready and how much it will cost so that they can make their own commitments, but the team ideally wants to work this out iteratively, as they go. This means instead that they have to define the scope and cost as much as they can upfront, and then work out the details in each sprint – more like staged or spiral development methods. Once they have the backlog sized, they can plan out sprints based on forecast velocity or historical velocity - if they can figure this out.

I’m still not convinced that Agile story point estimating is better than (or as good as) other techniques, or that programmers sitting around a table playing Planning Poker is really an effective alternative to thoughtful estimating. Story points create some problems in planning new project development, because they are purposefully abstract – too abstract to be useful in helping to make commitments to the business. You might have an idea of how many story points give or take you have to deliver, but what’s a story point in the real world? People who use story points can’t seem to agree on how to define a story point, what a story point means and how or when to use them in estimating.

More fundamentally, you can’t know what a story point costs until the team starts to deliver, by measuring the team’s velocity (the actual story points completed in an iteration).This leaves you with a bootstrapping problem: you can’t estimate how long it is going to take to do something until you do it. You can look at data from other projects (if you’ve tracked this data), but you’re not supposed to compare story points across projects because each project and each team is unique, and their idea of story points may be different. So you have to make an educated guess as to how long it is going to take you to deliver what’s in front of you, and now we’re back to the “expert judgement” problem.

The good news is that it won’t take long to calibrate Story Point estimates against evidence from the team’s actual velocity. Mike Cohn in Succeeding with Agile says that you need at least 5 iterations to establish confidence in a team’s velocity. But Construx has found that you can have a good understanding of a team’s velocity in as little as 2 iterations. That’s not a long time to wait for some kind of answer on how long it should take to get the work that you know that you have in front of you done.

There is more to estimating

There is a lot more to estimating, and to this estimation course: details on different techniques and rules of thumb, models and software tools, how to measure estimation error, how to turn estimates into schedules, how to handle schedule compression and how to stay out of the Impossible Zone. To get a taste of the course, check out this webinar on the 10 Deadly Sins of Software Estimation.

Software estimation, like other problems in managing software development, doesn’t require a lot of advanced technical knowledge. It comes down to relatively simple ideas and practices that need to be consistently applied; to fundamentals and discipline. That doesn’t mean that it is easy to do it right, but it’s not dark magic either.