Toshiba Transformers History & Background
As power consumption in urban areas increases, a large number of substations have been constructed underground, beneath commercial buildings, parks and public spaces. Safety and the avoidance of fire incidents is the most important consideration for substations in urban areas. Compact and cost effective solutions are required for substations installed in areas where space is limited. Gas insulated transformers (GITs) instead of Oil immersed transformers (OITs) offer the best solution for overcoming the sharp increase in electric power demand in large cities.
History of Toshiba Power Transformers
85 93 39 94 52 03 18 67 19 96 19 18 19 19 19 19 20
330kV-400MVA GIT (Worlds largest)
50kV-4kVA TR
220kV-80MVA TR (Asias first) Almost same year as Europes first operation
66kV-3000kVA GIT (Japans first)
Start manufacturing in 1894 Worlds first by Ganz 275kV-99MVA TR (Japans first)
1050kV-3000/3MVA 525kV-1450MVA TR (Worlds largest) UHV TR
02
Fig.1
Only 9 years after the world s first transformer was manufactured, Toshiba started supplying transformers to the market in 1894. Since then, Toshiba has been one of the most innovative transformer manufacturers in the world. In 1967, Toshiba delivered the first GIT, 66kV, 3MVA transformer to the market, which features excellent characteristics for safety and environmental friendliness.
GIT World wide application
Underground Substation within a business complex
As of 2008
Supplied Under discussion
Fig.2
Fig.3
Toshiba has supplied a large number of GITs all over the world and there are many GIT projects planned for the future.
Application: GITs excel in explosion-proof safety and are widely used in underground and indoor substations in urban areas. GITs are also installed in environmentally critical areas where oil leakage is prohibited.
Advantages of GIT Technology
Excellent features of GIT
Features Advantages with GIT
GITs employ SF6 gas as the insulation & cooling medium, which avoids the need for fire fighting equipment, oil collection tanks and pits outside the transformer room. Since the rise in tank pressure for an internal fault is very small compared with the GIT tank withstand strength, the GIT tank will not explode on internal fault ensuring the safety of equipment within the substation. Since neither a conservator nor pressure relief arrangement is required, the height of the transformer room can be reduced. For the case of a 275kV 300MVA class application, approximately 2 to 2.5 meter reduction in height can be achieved. The application of GIT together with GIS offers a very compact substation design as the equipment is installed in the same room. A significant cost reduction for civil construction can thus be achieved.
Non-flammability
Non-explosive feature
Compactness Excellent interface with Gas Insulated Switchgear (GIS)
Pressure rise on internal fault
Significant tank pressure increases do not occur during internal failures due to the Gas characteristics. The risk of a tank explosion or fire incident can be completely eliminated.
SF6 Insulation Pressure rise during fault is small
100
Non-flammable Non-explosive
Pressure Rise(%)
Compact substation design through application of GIT
As oil is not used in a GIT, a fire wall between the GIT and GIS or separate rooms are not required. Therefore GIT and GIS can be installed in the same room. This arrangement enables a compact substation to be achieved.
150MVA-275kV Shunt Reactor
80 60 40 20 0 0 0.2 0.4
Tank Strength OIT Pressure rise of GIT is very small GIT
0.6 0.8 1 1.2
Fault Time(sec)
Fig.4
GIB GIT GIS ROOM PRESSURE RELIEF DEVICE
TRANSFORMER ROOM
OIL CABLE BOX
CONSERVATOR
300MVA-275kV GIT
GIS
> Close Arrangement of Transformers and GIS Without Partitions > Low Ceiling Substation Room * No Conservator and Pressure Relief Device
OIL TRANSFORMER
Fig.5
Construction
Features of GIT
Oil Immersed Transformer (OIT)
Insulation / Cooling
Insulating Oil Solid Insulation Material Oil Impregnated Paper, Pressboard Conservator Necessary On-Load Tap Changer Diverter Switch Arcing Switching in Oil Tap Selector Slide Contact
Gas Insulated Transformer (GIT)
SF6 Pressure 0.14 or 0.43MPa-g(20)
PET Film,PPS Film, Aramide Paper, Pressboard
Unnecessary
Vacuum Interrupter Roller Contact
The construction of a GIT is basically the same as an OIT, with the exception of insulating material and cooling medium. Therefore, broad experience of OIT technology can be applied to GIT design, manufacturing and maintenance.
Fig.6
Cooling system
Cooling design for GIT
The concept of the external cooling design for a GIT is nearly the same as that for an OIT; for this reason various types of cooling method can be applied.
Radiator
Gas Blower
Gas Blower
Gas - Water Heat-Exchanger
Radiator 1. GNAN Type 2. GDAN Type 3. GDAF Type
Cooler 4. GDWF Type
Fig.7
Flexibility in substation design
GDAN/GDAF-20/63MVA - 110kV GIT
Water cooling system for urban substations
Commercial building
Silencer Air Outlet Air Cooler Air Inlet
Water to Air
Cooling Fan
Water
Underground
P
Circulating water pump
Gas to Water
Gas to Water Gas Water cooler Gas Blower
Fig.8
Fig.9
Since the head pressure of SF6 gas is negligibly low, cooling equipment can be located above the GIT level as indicated in the figure. The GIT offers excellent flexibility when locating components such as radiators or coolers.
A water cooling system is widely used in large-capacity underground and/or indoor substations. The heat generated from a GIT is efficiently transferred to water-air heat exchangers by water flow. The cooling system is usually located on the top floor of the substation building.
Computer Aided Engineering (CAE)
Temperature analysis for GIT design and GIT room considerations
In the cooling design for the GIT winding or substation buildings, Computer Aided Engineering (CAE) methods can be applied. The calculation using CAE for the airflow inside the building and/or outside is very useful during the planning stage of the substation building.
Winding cooling
Coil Horizontal Cooling Duct Gas Stopper
Radiator cooling
Gas Stopper
Transformer room cooling
Exhaust Flow Late = 760m3/min, No-Duct
Fig.10
Air Temperature distribution
Air velocity vector and distribution
Fig.11
The calculation result used in the figure shows that the top cooler arrangement is suitable in terms of efficient substation cooling for this case. Positions of coolers can be decided by carrying out the CAE analysis taking into consideration the arrangement of the substation.
Interface with other substation equipment
There are various types of terminal construction for GIT applications. In order to reduce the space required for the terminal construction, cable connection or GIB direct connection is widely applied instead of air bushing connection especially for underground or indoor substations.
Cable connection
The cable interface construction is well defined and termination work can be done in a secure manner in accordance with the international standard (IEC or others).
Plug-in connector interface
Gas treatment work at the cable compartment is not required during installation work in the case of the plug-in connector. A plug-in connector is usually only applied for small capacity, low voltage GITs due to availability of the connector.
Gas Insulated Busbar (GIB) direct connection
GITs can be installed together with GIB or GIS in the same room by applying either GIB or GIS direct connection as shown in Fig. 5 on Page 2.
Fig.12
On-Load Tap Changers (OLTC) & Accessories
Line-up of OLTC for GIT
Type GVT-D100AL GVT-M100CL GVT-100DH
Photo
Step Voltage Rated Current
1200V 380A
1500V 600A
2500V 870A
Fig.13
Sudden gas pressure relay
Temperature indication
RESISTANCE BULB
SENSING UNIT
GAS
WTI
Fig.14
DIAL TYPE THERMOMETER
Fig.15
Comparison between accessories for GIT and OIT
Item
Temperature Protective Device & Accessory Leak Protection Others Air ventilation Ventilation to outdoors
GIT
Gas Temperature Indicator Winding Temperature Indicator Gas density relay Compound gauge Sudden gas pressure relay (OLTC)
OIT
Oil Temperature Indicator Winding Temperature Indicator Oil Level gauge Buchholtz relay, Gas detection relay, Pressure relief device, Oil Preservation System Dehydrating Breather Ventilation with fireproof dampers to outdoors
Table.1
Diagnostics & Maintenance
GIT Diagnostics
The integrity of GITs can be checked and a failure cause analysis can be made using gas chromatography. Using a simple gas detective tube device, GIT integrity can be confirmed at site.
Gas sampling bag Gas detective tube
Fig.16
GIT Maintenance Program (Example)
Required maintenance period
NO. 1 2 3 4 5 6 7 8 9 10 11 12
Maintenance Item
Every 2 years
Every 3 years
Every 5 years
Every 10 years
Every 15 years
30 years
when failure occur
Gas analysis Replenish the bearing grease of gas blower Gas blower bearings Exchange Gas blower Indication and protection devices Exchange Gas pressure sensor Exchange Bushing Exchange control cable Wiring Inspection of OLTC Exchange a Cooler Exchange O-ring, Gasket Running repairs of small gas leakage
Table.2
Maintenance cycle & items for GITs
Typical application
OIT and GIS application GIT and GIS application
GIT substation is simple & small
Fire extinguisher Lower ceiling High ceiling Long GIS interface
Gravel filling oil catch pit
Substation size is half
Fire wall
Fig.17
Fig.18
OIT and GIS must be separated by a fire wall or installed in separate rooms dependent upon the fire risk.
As oil is not used in both GIT and GIS equipment, neither a fire wall nor separate rooms are required. By installing both GIT and GIS in the same room, a compact substation can be realized.
Applied Voltage, Capacity & Gas pressure
500 275
0.43Mpa-g
154
High Pressure Large Capacity
Toshiba supplies a wide range of GITs with low pressure gas and high pressure gas technology.
15/50MVA - 110kV GIT in underground substation
Low pressure design: 0.14MPa-g
Voltage (kV)
0.14Mpa-g
66 22 10
Low Pressure Small Capacity
Fig.19
68
100
200
300
Capacity (MVA)
400MVA GIT in underground substation
High pressure design:0.43MPa-g
Fig.20
Water cooling system is applied
Fig.21
Environmentally friendly feature
39MVA-132kV GIT near Australian national park
Fig.22
The Hydro Power station shown in this photograph is located in the wet tropical area within a world heritage site. A GIT was provided at the power station to remove the risk of oil leakage.
Control for SF6 gas emission SF6 gas emission from gas-insulated equipment in Japan
700 600
With Action Without Action
Gas leak test at the factory
SF6 Emissions(t)
500 400 300 200 100 0
491 449 378
Fig.24
209 117 86 65
92 94 96 98 00 02
50 40
29 28.7
20 10
Fig.23
20
19
19
Electric power companies and Electric equipment manufacturers in Japan have made tremendous efforts to reduce SF6 gas emissions based on an agreed voluntary target. With careful gas treatment and complete SF6 gas recovery systems, the amount of SF6 gas emission from gas insulated equipment has been dramatically reduced as indicated by the green bars. If no action had been taken, the amount of SF6 gas emissions would still be increasing as indicated by the orange bars.
19
19
19
20
20
20
In order to confirm no gas leakage from the GIT tank, gas leak tests are performed at the factory for all GIT tanks. At site the gas leak test is performed on re-assembled parts to ensure no leakage.
04
90
06
10