This document provides a notice that various piping and equipment related to fuel gas and pilot gas systems for the Sleipner Boiler will be energized on April 2, 2009. It lists over 50 specific pieces of piping identified by tag numbers that will be part of the energization. It also provides descriptions of each piece of piping and notes when mechanical completion was completed for various parts of the system between August 2009 and May 2010.

Uploaded by

Aceel Fitch
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
345 views1 page

Livening Up Notes

This document provides a notice that various piping and equipment related to fuel gas and pilot gas systems for the Sleipner Boiler will be energized on April 2, 2009. It lists over 50 specific pieces of piping identified by tag numbers that will be part of the energization. It also provides descriptions of each piece of piping and notes when mechanical completion was completed for various parts of the system between August 2009 and May 2010.

Uploaded by

Aceel Fitch
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Livening-Up Notice

Omega Demo Domain

Filter: LUNNo = '0001-001'

LUN No: 0001-001 Sub System: 5710 Site: Notice:

Full System Statpipe Fuel Gas & Pilot Gas to Sleipner Boiler Prepared Date: 07-Jan-2009

Part System

Please be informed that the referenced equipments is planned to be energized :

Date: 02-Apr-2009 Description of plant/equipment proposed to energized :

ObjectID 0.5"-GF-57-041-AC40X-1 (Main) 0.5"-GF-57-042-AC40AX-4 (Vent) 0.5"-GF-57-045-AC40X-1 (Last Spool) 0.5"-GF-57-045-AC40X-1 (Main) 0.5"-GF-57-046-AC40X-4 (Branch) 0.5"-GF-57-046-AC40X-4 (Vent) 0.5"-GF-57-046-AC40X-4 (Vent) Part02 0.5"-GF-57-049-AC40X-1 (Last Spool) 0.5"-GF-57-049-AC40X-1 (Main) 0.5"-GF-57-050-AC40AX-4 (Branch) 0.5"-GF-57-050-AC40AX-4 (Vent) 1"-GF-57-040-AC40X-4 (Branch Section) 1"-GF-57-040-AC40X-4 (Vent) 1"-GF-57-044-AC40X-4 (Branch) 1"-GF-57-044-AC40X-4 (Vent) 1"-GF-57-048-AC40X-4 (Branch) 1"-GF-57-048-AC40X-4 (Vent) 1"-GF-57-051-AC40X-4 Part01 1"-GF-57-051-AC40X-4 Part02 1"-GF-57-080-AC30X-4 1.5"-GF-52-1414-AC10A-1 1.5"-GF-52-1416-AC10A-1 1.5"-GF-52-1418-AC10A-1 10"-GF-57-035-AC40X-1 3"-GF-57-038-AC40X-4 (Branch) 3"-GF-57-038-AC40X-4 (Vent) 52-F-0800 52-FA-0800 52-FAC-0800

Description Statpipe Fuel Gas to Pilot Burner 1 Vent to 1" Statpipe Fuel Gas to Pilot Burners 52-FB-122 Statpipe Fuel Gas to Pilot Burner 2 Statpipe Fuel Gas to Pilot Burner 2 Vent to 1" Statpipe Fuel Gas to Pilot Burners 52-FB-123 Vent to 1" Statpipe Fuel Gas to Pilot Burners 52-FB-123 Vent to 1" Statpipe Fuel Gas to Pilot Burners 52-FB-123 Statpipe Fuel Gas to Pilot Burner 2 Statpipe Fuel Gas to Pilot Burner 2 Vent to 1" Statpipe Fuel Gas to Pilot Burners 52-FB-124 Vent to 1" Statpipe Fuel Gas to Pilot Burners 52-FB-124 1" Statpipe Fuel Gas to Pilot Burners 1" Statpipe Fuel Gas to Pilot Burners 1" Statpipe Fuel Gas to Pilot Burners 52-FB-123 1" Statpipe Fuel Gas to Pilot Burners 52-FB-123 1" Vent Statpipe Fuel Gas to Pilot Burners 52-FB-124 1" Vent Statpipe Fuel Gas to Pilot Burners 52-FB-124 Statpipe Fuel Gas to Pilot Burners Statpipe Fuel Gas to Pilot Burners Statpipe Fuel Gas to Pilot Burners Statpipe Fuel Gas Mix Bypass Burner 1 Statpipe Fuel Gas Mix Bypass Burner 2 Statpipe Fuel Gas Mix Bypass Burner 3 Statpipe Fuel Gas to Burners 3" Vent Statpipe Fuel Gas to Pilot Burners 3" Vent Statpipe Fuel Gas to Pilot Burners SLEIPNER/STATPIPE FUEL GAS TO BURNERS, Loop ESD SYSTEM 15-ZC-100 FA101 PUSHBUTTONS REPEAT ESD SYSTEM 15-ZC-100 FA101 PUSHBUTTONS REPEAT

MC Complete 26-Aug-2009

01-Sep-2009 01-Sep-2009 01-Sep-2009 27-Aug-2009 01-Sep-2009 01-Sep-2009 01-Sep-2009 01-Sep-2009 01-Sep-2009 07-May-2010 01-Sep-2009 13-Aug-2009

Contractor Name: Company: Sign: Date: Printed by: Ramsvik, Nils Arne. 4 -Feb-2011 13:17, (ID=198).

Company

Commissioning

Page 1 of 1