67% found this document useful (9 votes)
13K views2 pages

Build Up Rate Format - Precast Concrete

This document provides the material and labor costs to construct various precast concrete items for a construction project. It lists the unit costs for concrete, formwork, steel bars, and labor. It then calculates the costs per meter for 100mm and 50mm thick concrete cappings, and a 150mm thick concrete lintel, including costs for materials, wastage, and labor installation. The total costs per meter are Rs. 23.67 for the 100mm capping, Rs. 20.98 for the 50mm capping, and Rs. 20.82 for the 150mm lintel.

Uploaded by

Faiz Ahmad
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
67% found this document useful (9 votes)
13K views2 pages

Build Up Rate Format - Precast Concrete

This document provides the material and labor costs to construct various precast concrete items for a construction project. It lists the unit costs for concrete, formwork, steel bars, and labor. It then calculates the costs per meter for 100mm and 50mm thick concrete cappings, and a 150mm thick concrete lintel, including costs for materials, wastage, and labor installation. The total costs per meter are Rs. 23.67 for the 100mm capping, Rs. 20.98 for the 50mm capping, and Rs. 20.82 for the 150mm lintel.

Uploaded by

Faiz Ahmad
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

BUILT-UP RATE FOR PC ITEMS

TENDER FILE NO :

PROJECT :

LOCATION :

SUPPLIER :

SUB-CONTRACTOR :

QUOTATION DATE :

Material Cost :

Concrete G25 @ 135.00 per m3

Formwork @ 3.00 per m2 ( Allow for 6 usages )

Steel bar @ 2.20 per kg

7.00
Labour For Installing PC Capping/ per@m
Lintol

100mm x 253mm PC Capping Cost / m

Dimension
Concrete @ 0.10 x 0.25 3.42
Formwork @ 0.61 1.82
Steel bar :
Y12 1.00 x 4 x 0.89 7.81
R6 0.83 x 7 x 0.22 2.82
15.87
Wastage @ 5% 0.79
16.67
Labour cost / m 7.00
Total Cost / m 23.67

50mm x 253mm Copping Cost / m

Dimension
Concrete @ 0.05 x 0.253 1.71
Formwork @ 0.56 1.67
Steel bar :
Y12 1.00 x 4 x 0.89 7.81
R6 0.62 x 7 x 0.22 2.12
13.31
Wastage @ 5% 0.67
13.98
Labour cost / m 7.00
Total Cost / m 20.98

150mm x 100mm PC Lintol Cost / m

Dimension
Concrete @ 0.15 x 0.10 2.03
Formwork @ 0.40 1.20
Steel bar :
Y12 1.00 x 4 x 0.89 7.81
R6 0.62 x 7 x 0.22 2.12
13.16
Wastage @ 5% 0.66
13.82
Labour cost / m 7.00
Total Cost / m 20.82