Profit & Loss Report - Structures & Bridge No. 2
Profit & Loss Report - Structures & Bridge No. 2
9.0 EARTHWORKS
PILECAP
(a) 0 to 3 depth 320 Cu.m - 17.25 - 17.25 5,520.00 - - 6.50 6.50 2,080.00 3,440.00
9.1.5 Granular backfill between wingwalls. 10 Cu.m - 45.00 - 45.00 450.00 - 43.00 - 43.00 430.00 20.00
Or As An Alternative
RATES TO INCLUDE
iv) Standing time for all equipment and labour due to all
foregoing circumtances
9.3.2 Ditto 1st. extension in length exceeding 12.0m 504 Lin.m - 74.00 - 74.00 37,296.00 - 71.00 - 71.00 35,784.00 1,512.00
9.3.3 Ditto 2nd. extension in length exceeding 12.0m 504 Lin.m - 74.00 - 74.00 37,296.00 - 71.00 - 71.00 35,784.00 1,512.00
9.3.4 Ditto 3rd. extension in length exceeding 6.0m Rate only Lin.m - 80.00 - 80.00 - - 78.00 - 78.00 - -
9.3.5 Handle, transport, pitch and drive vertical pile 1,512 Lin.m - 34.50 - 34.50 52,164.00 - 30.00 - 30.00 45,360.00 6,804.00
9.3.6 Fillet weld to vertical pile. 84 Nos - 50.00 - 50.00 4,200.00 - 40.00 - 40.00 3,360.00 840.00
9.3.8 Ditto 1st. extension in length exceeding 12.0m 504 Lin.m - 74.00 - 74.00 37,296.00 - 71.00 - 71.00 35,784.00 1,512.00
9.3.9 Ditto 2nd. extension in length exc. 12.0m 504 Lin.m - 74.00 - 74.00 37,296.00 - 71.00 - 71.00 35,784.00 1,512.00
9.3.10 Ditto 3rd. extension in length exc. 6.0m Rate only Lin.m - 80.00 - 80.00 - - 78.00 - 78.00 - -
9.3.11 Handle, transport, pitch and drive raked pile 1,512 Lin.m - 34.50 - 34.50 52,164.00 - 30.00 - 30.00 45,360.00 6,804.00
9.3.12 Fillet weld to raked pile. 84 Nos. - 50.00 - 50.00 4,200.00 - 40.00 - 40.00 3,360.00 840.00
9.5.1 Allow for test piles as per clause and/or as directed by the S.O.
directed by the S.O. inclusive of supply,handle,
transport,pitch,drive,load test,remove all debris,
etc.
9.7.2 Concrete Grade 40/20 for piers 35 cu.m - 230.00 - 230.00 8,050.00 - 220.00 - 220.00 7,700.00 350.00
9.7.3 Concrete Grade 40/20 for abutments 65 cu.m - 230.00 - 230.00 14,950.00 - 220.00 - 220.00 14,300.00 650.00
9.7.4 Concrete Grade 40/20 for pile caps. 128 cu.m - 235.75 - 235.75 30,176.00 - 220.00 - 220.00 28,160.00 2,016.00
9.8.2 25mm diameter high tensile steel reinforcement bars 14,040 kg 0.40 1.50 - 1.90 26,676.00 0.40 1.40 - 1.80 25,272.00 1,404.00
9.8.3 20mm diameter high tensile steel reinforcement 6,022 kg 0.40 1.50 - 1.90 11,441.80 0.40 1.40 - 1.80 10,839.60 602.20
9.8.4 16mm diameter high tensile steel reinforcement bars 14,309 kg 0.40 1.50 - 1.90 27,187.10 0.40 1.40 - 1.80 25,756.20 1,430.90
9.8.5 12mm diameter high tensile steel reinforcement bars 12,435 kg 0.40 1.50 - 1.90 23,626.50 0.40 1.40 - 1.80 22,383.00 1,243.50
9.8.6 12mm diameter mild steel reinforcement bars 1,925 kg 0.40 1.50 - 1.90 3,657.50 0.40 1.40 - 1.80 3,465.00 192.50
9.8.7 10mm diameter mild steel reinforcement bars 904 kg 0.40 1.50 - 1.90 1,717.60 0.40 1.40 - 1.80 1,627.20 90.40
9.90 FORMWORK
9.9.1 To vertical of abutment and wingwalls 290 sq.m - 35.00 - 35.00 10,150.00 - 34.00 - 34.00 9,860.00 290.00
9.9.2 To vertical sides of diaphragms 279 sq.m - 35.00 - 35.00 9,765.00 - 34.00 - 34.00 9,486.00 279.00
9.9.3 To soffit of deck slab 545 sq.m - 35.00 - 35.00 19,075.00 - 34.00 - 34.00 18,530.00 545.00
9.9.4 To vertical sides of parapet 212 sq.m - 35.00 - 35.00 7,420.00 - 34.00 - 34.00 7,208.00 212.00
9.9.5 To vertical sides of pilecaps 98 sq.m - 35.00 - 35.00 3,430.00 - 34.00 - 34.00 3,332.00 98.00
9.10 SUNDRIES
9.10.1 Supply, fix, paint, testing as specified Galvanised iron post and
railing including holding down bolts embedded in concrete
parapet all as shown in drawings. (Measurement is based on per
meter length on each side of the bridge) 94 Lin.m - 227.70 - 227.70 21,403.80 - 198.00 - 198.00 18,612.00 2,791.80
9.10.3 Supply and fix diameter 30mm x 645mm long galvanised dowels
conform to ms 146 and MS 443 in abutment and casting rubber
dowel caps as specified in the drawings. galvanised dowels
conform to ms 146 and ms 443 in abutment and casting rubber
dowel caps as sp 40 No - 43.70 - 43.70 1,748.00 - 32.00 - 32.00 1,280.00 468.00
9.12.1 Supply and lay 1000 x 1000 x 2000mm rock filled gabion as
shown in the drawings inclusive of cages, ties, wires, rock, etc. 272 cu.m - 180.00 - 180.00 48,960.00 - 120.00 - 120.00 32,640.00 16,320.00
9.12.6 Drive single vertical r.c. pile to set, including all 6,120 lin.m - 10.00 - 10.00 61,200.00 - 6.00 - 6.00 36,720.00 24,480.00
handling,positioning extension,etc.
9.12.6 Cut pile to the required level for gabion base. 340 no. - 18.40 - 18.40 6,256.00 - 8.00 - 8.00 2,720.00 3,536.00
9.13.1 Supply and lay 200mm well compacted hardcore under approach 15 cu.m 4.30 44.00 - 48.30 724.50 - 48.00 - 48.00 720.00 4.50
9.15 MISCELLANOUS
9.15.1 Supply and install brass plagues for bridge 1 no - 877.50 - 877.50 877.50 - 650.00 - 650.00 650.00 227.50