0% found this document useful (0 votes)
46 views1 page

M04B Pump Positive Displacement

The document is a function test report for a positive displacement pump located in South Acis. It summarizes 21 test items to check the pump's performance, safety features, installation, and operation. Key checks include verifying the pump can achieve specified capacity and head at rated pressure, checking motor starting and running amps, and performing an initial 4 hour run test to log operating data. The report documents the results of testing to ensure the pump was installed correctly and functions as intended.

Uploaded by

zacktee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views1 page

M04B Pump Positive Displacement

The document is a function test report for a positive displacement pump located in South Acis. It summarizes 21 test items to check the pump's performance, safety features, installation, and operation. Key checks include verifying the pump can achieve specified capacity and head at rated pressure, checking motor starting and running amps, and performing an initial 4 hour run test to log operating data. The report documents the results of testing to ensure the pump was installed correctly and functions as intended.

Uploaded by

zacktee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Drawing Ref No:

Location: Area:
Package: SubSubSystem:
Sub System: System:
Description: TagNo:
21-Feb-2013 Date: Murphy Sarawak Oil Ltd. Client:
Function Test Report
M04B Pump Positive Displacement
SOUTH ACIS
Perform 4 hours initial run test and log operating data every hour intervals. 23
Check that motor starting & running ampere are within the specification 22
Check the pump will be able to achieve the specified capacity/head @rated pressure 21
Ensure that the pump is primed, start up & test manual and remote shutdown function. 20
Check that pressure gauge provided has the correct range with Over Pressure potection. 19
Check discharge check valve direction is correct 18
Check Pump discharge relief Valve & validity 17
Check Pump suction strainer 16
Pre charge Suction & Discharge Dampner(Record Precharge Pressure) 15
Check that pump Lubricator is provided & filled with oil 14
Confirm Leak detection system installed 13
Check alignment of pulley & belt tension.(Record Result) 12
Check alignment of coupling.(Record Result) 11
Check alignment of suction & discharge piping.To ensure no stress & spring back force. 10
Perform Uncouple run test /function logic/ for the Motor Driver 09
Check that Air Supply Pressure is correct and lubrication provided and filled for
Pneumatic Driver/Diapraghm
08
Earth Contuinity Test (Record Value) 07
Verify that Electric check on Motor, cabling and MCC are complete in accordance to
specification & control philosophy.
06
Turn pump shaft/Gear box input shaft /motor shaft to ensure free rotation 05
Correct lubricant filled (Record Lube type & volume) 04
Ensure gearbox cleanliness prior to lube oil flush and filling 03
Anchor Bolt attachment SKID/PUMP/GEARBOX/DRIVER 02
Check vendors instruction, ensure that manual and part list are available 01
Output /Remarks PL OK NA Description Item
Remarks:
Date of Signing:
Print Name:
Signature:
Company:
Accepted By Verified By Performed By