CONDUIT, TRUNKING AND CABLE TRAY INSPECTION CHECKLIST
Project Title :
Type of Work :
Location :
No.
A
Date :
Main
Contractor
Items To Be Checked
Clients
Consultant
Remarks
Preparatory
1.
Material and product as per approved catalogue, sample and
specification
2.
Correct sizes, position and location as per approved drawing
3.
Approved Work Method Statement
B
4.
RFWI No :
Ref. Drawing No :
Installation
Conduit properly bend and connected without distortion
5.
Conduits, Trunking and Trays properly supported and brackets
rigidly fitted comply to the suggested maximum distances between
supports
6.
Flexible conduit installed with suitable fittings, adopters and
Securely griped to conduit.
7.
Conduits and accessories properly painted (if applicable)
8.
Trunking, Cable Tray and Ladder properly earthed
9.
Bends, elbows Ts, adaptor and jointing using standard
manufacturer fittings
10.
Screws, Bolts & nuts adequate provided and properly fastened
11.
Sufficient clearance in between others services
12.
Fire stops properly installed
Others (please state).
Status of Inspection
We have carried out all necessary inspections and verify that the above items/activities conform to the contract
specifications/document.
Checked By
Main-Contractor
Verified By
Clients Consultant
Signature
Name
Company
Date
* S t a t u s O f I n s p e c t i o n : = Acceptable, X = Not Acceptable, - = Not Applicable