0% found this document useful (0 votes)
74 views37 pages

Former Power Secretary Presentation

Stage) : 15.03.2012 Techno-Commercial Bid (2nd Stage) : 15.08.2012 Letter of Award : 28.01.2013 Financial Closure : 28.02.2013 Commissioning of 400 kV Lines : 30.08.2013 Commissioning of HVDC Station : 04.12.2013 Commercial Operation Date : 05.01.2014 This summary covers the key points from the presentation on power sector in Bangladesh: [1] The presentation discussed Bangladesh's current and future power

Uploaded by

Masuk Hasan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views37 pages

Former Power Secretary Presentation

Stage) : 15.03.2012 Techno-Commercial Bid (2nd Stage) : 15.08.2012 Letter of Award : 28.01.2013 Financial Closure : 28.02.2013 Commissioning of 400 kV Lines : 30.08.2013 Commissioning of HVDC Station : 04.12.2013 Commercial Operation Date : 05.01.2014 This summary covers the key points from the presentation on power sector in Bangladesh: [1] The presentation discussed Bangladesh's current and future power

Uploaded by

Masuk Hasan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 37

SEMINAR ON INVESTMENT IN BANGLADESH

Organised by
Indo-Bangladesh Chamber of Commerce and Industry (IBCCI)
&
High Commission of India

Presentation on Power Sector in Bangladesh


by

R.V. Shahi
Former Power Secretary, Govt. of India
Energy Advisor, World Bank
South Asia Regional Projects
(March 29, 2014)

COVERAGE OF PRESENTATION
The Presentation covers:

Bangladesh Power Sector at a Glance.

Generation Profile including Future Projection.

Transmission - Present and Future.

Distribution including Rural Electrification.

Role of World Bank in Power Sector

Bangladesh-India-Recent Initiatives on Power

January 2010 Agreement

Framework Agreement, September 2011

Bangladesh India-Cross Border Transmission.

BPDB-NTPC Joint Venture (1320 MW Khulna Project).

Bangladesh-India Friendship Power Company.


2

BANGLADESH POWER SECTOR AT A GLANCE


Installed Capacity

Transmission Line

10,200 MW (up from about 5,000 MW


in last 5 Years)

400 KV

55 KM

Transmission Line

230 KV

3040 KM

Transmission Line

132 KV

6150 KM
500 MW

HVDC

Grid Sub Station Capacity

230/132 KV

Grid Sub Station Capacity

132/33 KV

Distribution Line

33 KV & below

6975 MVA (13)

9705MVA (84)

34800 KM

Consumers

14.2 Millions

Per Capita Power


Consumption

321 Kwhr

HISTORICAL PERSPECTIVE

Power Division
(Ministry of Power, Energy & Mineral Resources)

Power Cell
Generation

EGCB

RPCL
(REB)

BPDB
NWPGCL

APSCL
PGCB

Transmission
Distribution

WZPDCL

IPP

BPDB

NWZPDCL

DPDC

SZPDCL

DESCO

REB

PBS
5

POWER SYSTEM MASTER PLAN (PSMP)


PSMP 2010 : Long term planning up to 2030
Study completion : February 2011
Findings generation capacity requirement :
- By 2021 : 24,000 MW (base); 26,000 MW (high)
- By 2030 : 39,000 MW (base) ; 47,000 MW (high)
- Coal based capacity by 2030 : 20,000 MW (base)
Other Key Findings :
- Coal and Nuclear for base load power requirement.
- Cross Border Trade with neighbouring countries.
6

UNDERLYING PRINCIPLES IN FORMULATING LONG TERM PLAN

Present highly skewed fuel mix needs to be changed.

Liquid fuel and later even Gas will be costly.

Coal needs to occupy a major space to balance the cost


structure of power.

Mix of Domestic and Imported Coal needs to be appropriately


fixed both for optimal cost and also for energy security.

Cross Border and Regional Trade possibility needs to be


factored.

Transmission capability enhancement and shift to higher


voltages will be needed.
7

CAPACITY TILL 2030


Sl. No.

Description

Capacity (MW)

1.

Domestic Coal

11,250

2.

Imported Coal

8,400

3.

Domestic Gas/LNG

8,850

4.

Nuclear

4,000

5.

Regional Grid

3,500

6.

Others (Oil, Hydro, and


Renewable)

2,700

Total

38,700
8

REPOWERING OF GAS BASED POWER PLANTS


Gas Based Steam Turbine System is inefficient.
Even open cycle Gas Turbine has been phased out
in most of the countries (except for peaking
power).
Efficiency

Steam Turbine Less than 30% Efficiency.


Open Cycle About 40% Efficiency.
Combined Cycle About 60% Efficiency.

Ghorashal Repowering Study (World Bank Assistance).


9

Formation of PGCB
Under the Process of Power Sector Restructuring
As per recommendation of eight member
working group for Power Sector Restructuring,
Govt. decided to create Power Grid Company Of
Bangladesh Ltd. (PGCB) in the ECNEC meeting
held on 18 September, 1996.
Power Grid Company Of Bangladesh Ltd. (PGCB)
established on 21 November96 under the
Companies Act, 1994.
PGCB took over the responsibility for whole grid
network operation & maintenance from 31 st
Dec, 2002.
10

PGCB
A public limited company incorporated in 1996 through
sponsorship of BPDB.
At present 76.25% ownership with BPDB & 23.75%
with general public.
BPDB holding the ownership on behalf of Govt.
Present head office at Institution of Engineers ,
Bangladesh (IEB) Bhaban (new), 3 rd & 4th floor, Ramna,
Dhaka-1000.
PGCB is going
certification.

to

achieve

ISO

9001:2008

QMS
11

PGCB AT A GLANCE
Status
:
Public Limited Company
Business
:
Power Transmission
Year of Incorporation :
1996
Authorized Capital
:
Tk. 10 Billion
Present Paid-up Capital :
Tk. 4190.11 Million
Turnover (2012-13)
:
Tk. 8742.78 Million
Net profit after tax
:
Tk. 1010.18 Million
(2012-13)
Transmission Line as of March, 2014
400kV
230 kV
132 kV

: 54.7 Circuit km
: 3038 Circuit km
: 6147 Circuit km

Substations as of March, 2014


HVDC
230/132 kV
132/33 kV

: 01 (500MW)
: 13 (6975 MVA) + 2 No. Switching
: 84 (9705 MVA)

12

Voltage
(kV)

2010

2030

Additional (2010-2030)

Master Plan Summary


2010-2030

Length
(Km)

New Transmission Lines to be added from 2010-2030


Length
(Km)

Length
(Km)

230

2645

9360

400

4479

Source :

6715

4479

PSMP Study Team

13

Master Plan Summary


2010-2030

400 & 230kV substations required


from 2010 - 2030
Voltage

East or West

East
230/132kV
West

400/230kV

East
West

Region
Central
Dhaka
Southern
Northern
Western
Central
Dhaka
Southern
Western

Source: PSMP Study Team

Additional Number of
Substation
8
56
25
88
23
17
32
15
3
11
6
14
2
3
3

DISTRIBUTION INCLUDING RURAL ELECTRIFICATION


Town/City Distribution Public and Private
Sectors.
Distribution Lines About 35,000 Km (33 KV
and Below).
Rural Distribution through Palli Bidyut Samiti
(PBS).
JICA
and
World
Bank
funding
strengthening of Rural Network.

massive

World Bank has been assisting in a very large


Scheme - Solar Home System.
15

ROLE OF WORLD BANK

16

ROLE OF WORLD BANK


Partial Risk Guarantee (PRG) to Haripur Power PlantGuarantee amount US$ 60.9. The project contributes
through 360 MW gas-fired combined cycle power plants,
owned by Pendekar Energy, Malaysia to increased and
reliable power supply. The guarantee is effective since 2001.
Outstanding IDA Exposure: $9.3m (as of 30 June 2013).
Expiry: December 2015.
Power Sector Development Technical Assistance
Project (PSDTA) - US$ 15.5 million. Technical assistance to
build capacity in the sector and support new project
development. The project is closed in Dec 2012.
Rural Transmission & Distribution (T&D) - US$600
million. Rural distribution augmentation, transmission
enhancement and institution building. The project is
approved in February 2014.
17

ROLE OF WORLD BANK


Project under Preparation

Power Generation Efficiency Improvement


Project ($300 m). Upgrading the existing
Ghorashal Unit 4 Steam plant to energy efficient
combined
cycle
technology
and
associated
institution building.

18

OTHER ASSISTANCE TO POWER DIVISION

19

INDIA-BANGLADESH RECENT BILATERAL


INITIATIVES
January 1910 Agreement On Power

Supply of 500 MW.


Cross Border Transmission.
Cooperation in Power Generation, Training.

Joint Steering Committee, Joint Working Group, Joint


Technical Team.

September 2011 Framework Agreement

Sub Regional Cooperation.


Developing and Financing Projects jointly.
Cooperation in Generation, Transmission and
Distribution.
Power Grid connectivity and Power Exchanges.

20

Overview
Overviewof
ofIndo
IndoBangladesh
Bangladesh1X500
1X500MW
MW
HVDC
HVDCBTB
BTBInterconnector
Interconnector
INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS
MALDA

BARAPUKURIA

JAYPURHAT
KHEJURIA

KAHALGAON

BOGRA

FARRAKA

NAOGAON
CH. NAWABGANJ

BOGRA
SOUTH

NIAMATPUR

BANGLADESH

DHULIAN

RAJSHAHI

NATORE
SIRAJGANJ

SAGARDIGHI
BAHARAMPUR
DURGAPUR

GOKARNA

BAHARAMPUR
(400 KV)

PABNA

SHAHJAD
PUR

BAGHABARI
GHORASAL

BHERAMARA

INDIA

BOTTAIL

KATWA BAKRESHWAR

KOLAGHAT
SUBHASGRAM

ISHURDI

MADHOPUR

RAGHUNATHGANJ

JEERAT

KHULNA
(SOUTH)

FARIDPUR
LEGEND
THE PROJECT
400 kV
230 kV
132 kV
Existing
Under Constr. / Future

Overview of Indo Bangladesh 1X500 MW


Outline.
HVDC BTB Interconnector
India Bangladesh Interconnector
Scope of Works
1x 500 MW HVDCBTB Station, Bheramara
Bangladesh Side T/L
India Side T/L
India Side Sub Station at Behrampur

Overview
of Indo
Bangladesh
1X500 MW
Scope
of Work
for the
interconnector
HVDC BTB Interconnector
project
Indian Portion
Transmission Line

Baharampur(India)
Double Circuit line.

Bheramara(Bangladesh)

400kV

(Indian Portion) : App 71 Kms (Twin ACSR Moose


Conductor).
Loop-in and loop-out of Farakka-Jeerat 400kV Single
Circuit
line at Baharampur (India) : 3 Kms

Overview
of Indo
1X500
MW
Scope of Work
for Bangladesh
the interconnector
project
HVDC BTB Interconnector
Indian Portion
Sub-station
Establishment of 400kV switching-station at
Baharampur(India)
2 Nos of 400 kV line bays for loop-in and loop-out of
Farakka-Jeerat 400kV Single circuit line
1 No. of 80 MVAR Bus Reactor
Space provision for at least 2 no. of 400kV bays

Overview of Indo Bangladesh 1X500 MW


ScopeBTB
of Work
for the interconnector project
HVDC
Interconnector
Bangladesh Portion
Transmission Line
Baharampur(India)

Bheramara(Bangladesh)
400kV
Double Circuit line (Bangladesh Portion) : App 27 Kms
(Twin ACSR FINCH Conductor)
Loop-in and loop-out of Ishurdi - Khulna South 230kV
Double Circuit line at Bheramara(Bangladesh) : App 5 Kms

Overview of Indo Bangladesh 1X500 MW


Scope of Work for the interconnector project
HVDC BTB Interconnector
Bangladesh Portion
Sub-station

Establishment of 500 MW HVDC back-to-back station

Installation of 500 MW HVDC back-to-back terminal.


4 nos of 230 kV line bays for LILO of Ishurdi -Khulna
South 230kV Double Circuit line.
2 No of 400 KV Line bays (for Bheramara Bherampur
D/c line).
Space provision for at least 2 no. of 230kV bays.

Details
of Various
Packages under
the India
Overview
of Indo
Bangladesh
1X500
MW
Bangladesh
Interconnector Project
HVDCBTB
Interconnector

Note: Consultancy Assignment for No. 1 & 2.

Overview of Indo Bangladesh 1X500 MW


Commissioning of the interconnector project
HVDC BTB Interconnector
1

400 kV and 230 kV Charged


Transmission Lines Successfully on
30.08.2013

Regular Power Flow 05.10.2013


Started

Full Load Power


Flow Started

04.12.2013

CROSS BORDER TRANSMISSION PROJECT


(HVDC)
Important Dates
Tender Process (Two Stage Bid)

OBD (1st Stage) May,2010

Loan Agreement with ADB

February, 2011

Zero date of Project Contract


with M/s. Siemens

1st June, 2011

Commissioning Target

July, 2013

Commissioning

October, 2013
29

SAVING OUT OF 500 MW POWER IMPORT


500 MW means about 4,000 Million Units of
Power.
Average price per year 6 Tk/Kwhr.
Average price of Liquid Fuel Power 16 Tk/Kwhr.
Per Unit Saving 10 Tk.
Annual Saving -

Tk 40,000 Million.

= Tk 4,000 Crores.

30

31

Maitree Super Thermal Power Project


Mode of Generation Ratio Worldwide

32

Maitree Super Thermal Power Project

Project Overview
Project Implementation : Bangladesh India
Friendship Power Co.
(Pvt.) Ltd.

Project Cost : 1.68 Billion USD (BDT 14510 Crs.)

Equity
Funding
Beneficiary

: 50:50 (BPDB:NTPC)
: Debt: 70%, Equity : 30%
: 100% Power to Bangladesh
(PPA : 25 yrs)

Mode of Operation : Base load


Year of completion : 2018

33

Maitree Super Thermal Power Project


Capacity
1320 MW
( 2 X 660 )
Basic Plant
Information
Technology

Primary Fuel
Quality
Source
Requirement
Stack height
Emission SOx max
Emission NOx max
Particulate matter

Supercritical Technology
Sub-Bituminous/Bituminous Coal

(GCV 5,500 6,000 kcal/Kg, Sulfurmax. 0.6%, Ash Max. 15%)


Imported
1,2000 Ton/Day (85% plant factor)
275 m
819 g/s (WB standard 1597 g/s)
Less than 500 g/m3 (WB Standard:
max conc. 500 g/m3)
100 mg/Nm3 (DoE standard 150
mg/Nm3)
34

Maitree Super Thermal Power Project


Water
Source
Requirement

Cooling System

Basic Plant Information

Possur River
Plant make up : 2.5 m3 per sec
(apprx. 0.04% of the lowest flow of the
Possur River)
Flow of the Possur river: 6000 m3/s during
dry season)

Closed Cycle
Water is cooled in Cooling Towers and recirculated.

At the rate of 1.4 m3 /sec to Possur River


Discharge of treated waste
satisfying DoEs standard (Ambient
water
Temperature)
35

Bangladesh-India Friendship Power Company (Pvt.) Limited


Maitree Super Thermal Power Project at Rampal , Bagherhat
Calendar of Events
03.03.2014
Inter Govt. MOU
11.01.10
MOU Bet. NTPC & BPDB
30.08.10

JV Agreement Between NTPC

& BPDB

29.01.12

JV Company Incorporated

31.10.12

BOI Approval

27.11.12

PPA/IA Signed

20.04.13

Cos Cor. Office Started

05.05.13

Cos Bank A/C Opened

20.05.13

Cos Site Office Started

29.05.13

Promoters Contribution

11.07.13

Apvl. of EIA Report by DOE

05.08.13

EOI for Coal Consultant

31.10.13

1st AGM of Company

31.12.13

OE Bid opened on

13.03.14

36

THANK YOU

37

You might also like