SEMINAR ON INVESTMENT IN BANGLADESH
Organised by
Indo-Bangladesh Chamber of Commerce and Industry (IBCCI)
&
High Commission of India
Presentation on Power Sector in Bangladesh
by
R.V. Shahi
Former Power Secretary, Govt. of India
Energy Advisor, World Bank
South Asia Regional Projects
(March 29, 2014)
COVERAGE OF PRESENTATION
The Presentation covers:
Bangladesh Power Sector at a Glance.
Generation Profile including Future Projection.
Transmission - Present and Future.
Distribution including Rural Electrification.
Role of World Bank in Power Sector
Bangladesh-India-Recent Initiatives on Power
January 2010 Agreement
Framework Agreement, September 2011
Bangladesh India-Cross Border Transmission.
BPDB-NTPC Joint Venture (1320 MW Khulna Project).
Bangladesh-India Friendship Power Company.
2
BANGLADESH POWER SECTOR AT A GLANCE
Installed Capacity
Transmission Line
10,200 MW (up from about 5,000 MW
in last 5 Years)
400 KV
55 KM
Transmission Line
230 KV
3040 KM
Transmission Line
132 KV
6150 KM
500 MW
HVDC
Grid Sub Station Capacity
230/132 KV
Grid Sub Station Capacity
132/33 KV
Distribution Line
33 KV & below
6975 MVA (13)
9705MVA (84)
34800 KM
Consumers
14.2 Millions
Per Capita Power
Consumption
321 Kwhr
HISTORICAL PERSPECTIVE
Power Division
(Ministry of Power, Energy & Mineral Resources)
Power Cell
Generation
EGCB
RPCL
(REB)
BPDB
NWPGCL
APSCL
PGCB
Transmission
Distribution
WZPDCL
IPP
BPDB
NWZPDCL
DPDC
SZPDCL
DESCO
REB
PBS
5
POWER SYSTEM MASTER PLAN (PSMP)
PSMP 2010 : Long term planning up to 2030
Study completion : February 2011
Findings generation capacity requirement :
- By 2021 : 24,000 MW (base); 26,000 MW (high)
- By 2030 : 39,000 MW (base) ; 47,000 MW (high)
- Coal based capacity by 2030 : 20,000 MW (base)
Other Key Findings :
- Coal and Nuclear for base load power requirement.
- Cross Border Trade with neighbouring countries.
6
UNDERLYING PRINCIPLES IN FORMULATING LONG TERM PLAN
Present highly skewed fuel mix needs to be changed.
Liquid fuel and later even Gas will be costly.
Coal needs to occupy a major space to balance the cost
structure of power.
Mix of Domestic and Imported Coal needs to be appropriately
fixed both for optimal cost and also for energy security.
Cross Border and Regional Trade possibility needs to be
factored.
Transmission capability enhancement and shift to higher
voltages will be needed.
7
CAPACITY TILL 2030
Sl. No.
Description
Capacity (MW)
1.
Domestic Coal
11,250
2.
Imported Coal
8,400
3.
Domestic Gas/LNG
8,850
4.
Nuclear
4,000
5.
Regional Grid
3,500
6.
Others (Oil, Hydro, and
Renewable)
2,700
Total
38,700
8
REPOWERING OF GAS BASED POWER PLANTS
Gas Based Steam Turbine System is inefficient.
Even open cycle Gas Turbine has been phased out
in most of the countries (except for peaking
power).
Efficiency
Steam Turbine Less than 30% Efficiency.
Open Cycle About 40% Efficiency.
Combined Cycle About 60% Efficiency.
Ghorashal Repowering Study (World Bank Assistance).
9
Formation of PGCB
Under the Process of Power Sector Restructuring
As per recommendation of eight member
working group for Power Sector Restructuring,
Govt. decided to create Power Grid Company Of
Bangladesh Ltd. (PGCB) in the ECNEC meeting
held on 18 September, 1996.
Power Grid Company Of Bangladesh Ltd. (PGCB)
established on 21 November96 under the
Companies Act, 1994.
PGCB took over the responsibility for whole grid
network operation & maintenance from 31 st
Dec, 2002.
10
PGCB
A public limited company incorporated in 1996 through
sponsorship of BPDB.
At present 76.25% ownership with BPDB & 23.75%
with general public.
BPDB holding the ownership on behalf of Govt.
Present head office at Institution of Engineers ,
Bangladesh (IEB) Bhaban (new), 3 rd & 4th floor, Ramna,
Dhaka-1000.
PGCB is going
certification.
to
achieve
ISO
9001:2008
QMS
11
PGCB AT A GLANCE
Status
:
Public Limited Company
Business
:
Power Transmission
Year of Incorporation :
1996
Authorized Capital
:
Tk. 10 Billion
Present Paid-up Capital :
Tk. 4190.11 Million
Turnover (2012-13)
:
Tk. 8742.78 Million
Net profit after tax
:
Tk. 1010.18 Million
(2012-13)
Transmission Line as of March, 2014
400kV
230 kV
132 kV
: 54.7 Circuit km
: 3038 Circuit km
: 6147 Circuit km
Substations as of March, 2014
HVDC
230/132 kV
132/33 kV
: 01 (500MW)
: 13 (6975 MVA) + 2 No. Switching
: 84 (9705 MVA)
12
Voltage
(kV)
2010
2030
Additional (2010-2030)
Master Plan Summary
2010-2030
Length
(Km)
New Transmission Lines to be added from 2010-2030
Length
(Km)
Length
(Km)
230
2645
9360
400
4479
Source :
6715
4479
PSMP Study Team
13
Master Plan Summary
2010-2030
400 & 230kV substations required
from 2010 - 2030
Voltage
East or West
East
230/132kV
West
400/230kV
East
West
Region
Central
Dhaka
Southern
Northern
Western
Central
Dhaka
Southern
Western
Source: PSMP Study Team
Additional Number of
Substation
8
56
25
88
23
17
32
15
3
11
6
14
2
3
3
DISTRIBUTION INCLUDING RURAL ELECTRIFICATION
Town/City Distribution Public and Private
Sectors.
Distribution Lines About 35,000 Km (33 KV
and Below).
Rural Distribution through Palli Bidyut Samiti
(PBS).
JICA
and
World
Bank
funding
strengthening of Rural Network.
massive
World Bank has been assisting in a very large
Scheme - Solar Home System.
15
ROLE OF WORLD BANK
16
ROLE OF WORLD BANK
Partial Risk Guarantee (PRG) to Haripur Power PlantGuarantee amount US$ 60.9. The project contributes
through 360 MW gas-fired combined cycle power plants,
owned by Pendekar Energy, Malaysia to increased and
reliable power supply. The guarantee is effective since 2001.
Outstanding IDA Exposure: $9.3m (as of 30 June 2013).
Expiry: December 2015.
Power Sector Development Technical Assistance
Project (PSDTA) - US$ 15.5 million. Technical assistance to
build capacity in the sector and support new project
development. The project is closed in Dec 2012.
Rural Transmission & Distribution (T&D) - US$600
million. Rural distribution augmentation, transmission
enhancement and institution building. The project is
approved in February 2014.
17
ROLE OF WORLD BANK
Project under Preparation
Power Generation Efficiency Improvement
Project ($300 m). Upgrading the existing
Ghorashal Unit 4 Steam plant to energy efficient
combined
cycle
technology
and
associated
institution building.
18
OTHER ASSISTANCE TO POWER DIVISION
19
INDIA-BANGLADESH RECENT BILATERAL
INITIATIVES
January 1910 Agreement On Power
Supply of 500 MW.
Cross Border Transmission.
Cooperation in Power Generation, Training.
Joint Steering Committee, Joint Working Group, Joint
Technical Team.
September 2011 Framework Agreement
Sub Regional Cooperation.
Developing and Financing Projects jointly.
Cooperation in Generation, Transmission and
Distribution.
Power Grid connectivity and Power Exchanges.
20
Overview
Overviewof
ofIndo
IndoBangladesh
Bangladesh1X500
1X500MW
MW
HVDC
HVDCBTB
BTBInterconnector
Interconnector
INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS
MALDA
BARAPUKURIA
JAYPURHAT
KHEJURIA
KAHALGAON
BOGRA
FARRAKA
NAOGAON
CH. NAWABGANJ
BOGRA
SOUTH
NIAMATPUR
BANGLADESH
DHULIAN
RAJSHAHI
NATORE
SIRAJGANJ
SAGARDIGHI
BAHARAMPUR
DURGAPUR
GOKARNA
BAHARAMPUR
(400 KV)
PABNA
SHAHJAD
PUR
BAGHABARI
GHORASAL
BHERAMARA
INDIA
BOTTAIL
KATWA BAKRESHWAR
KOLAGHAT
SUBHASGRAM
ISHURDI
MADHOPUR
RAGHUNATHGANJ
JEERAT
KHULNA
(SOUTH)
FARIDPUR
LEGEND
THE PROJECT
400 kV
230 kV
132 kV
Existing
Under Constr. / Future
Overview of Indo Bangladesh 1X500 MW
Outline.
HVDC BTB Interconnector
India Bangladesh Interconnector
Scope of Works
1x 500 MW HVDCBTB Station, Bheramara
Bangladesh Side T/L
India Side T/L
India Side Sub Station at Behrampur
Overview
of Indo
Bangladesh
1X500 MW
Scope
of Work
for the
interconnector
HVDC BTB Interconnector
project
Indian Portion
Transmission Line
Baharampur(India)
Double Circuit line.
Bheramara(Bangladesh)
400kV
(Indian Portion) : App 71 Kms (Twin ACSR Moose
Conductor).
Loop-in and loop-out of Farakka-Jeerat 400kV Single
Circuit
line at Baharampur (India) : 3 Kms
Overview
of Indo
1X500
MW
Scope of Work
for Bangladesh
the interconnector
project
HVDC BTB Interconnector
Indian Portion
Sub-station
Establishment of 400kV switching-station at
Baharampur(India)
2 Nos of 400 kV line bays for loop-in and loop-out of
Farakka-Jeerat 400kV Single circuit line
1 No. of 80 MVAR Bus Reactor
Space provision for at least 2 no. of 400kV bays
Overview of Indo Bangladesh 1X500 MW
ScopeBTB
of Work
for the interconnector project
HVDC
Interconnector
Bangladesh Portion
Transmission Line
Baharampur(India)
Bheramara(Bangladesh)
400kV
Double Circuit line (Bangladesh Portion) : App 27 Kms
(Twin ACSR FINCH Conductor)
Loop-in and loop-out of Ishurdi - Khulna South 230kV
Double Circuit line at Bheramara(Bangladesh) : App 5 Kms
Overview of Indo Bangladesh 1X500 MW
Scope of Work for the interconnector project
HVDC BTB Interconnector
Bangladesh Portion
Sub-station
Establishment of 500 MW HVDC back-to-back station
Installation of 500 MW HVDC back-to-back terminal.
4 nos of 230 kV line bays for LILO of Ishurdi -Khulna
South 230kV Double Circuit line.
2 No of 400 KV Line bays (for Bheramara Bherampur
D/c line).
Space provision for at least 2 no. of 230kV bays.
Details
of Various
Packages under
the India
Overview
of Indo
Bangladesh
1X500
MW
Bangladesh
Interconnector Project
HVDCBTB
Interconnector
Note: Consultancy Assignment for No. 1 & 2.
Overview of Indo Bangladesh 1X500 MW
Commissioning of the interconnector project
HVDC BTB Interconnector
1
400 kV and 230 kV Charged
Transmission Lines Successfully on
30.08.2013
Regular Power Flow 05.10.2013
Started
Full Load Power
Flow Started
04.12.2013
CROSS BORDER TRANSMISSION PROJECT
(HVDC)
Important Dates
Tender Process (Two Stage Bid)
OBD (1st Stage) May,2010
Loan Agreement with ADB
February, 2011
Zero date of Project Contract
with M/s. Siemens
1st June, 2011
Commissioning Target
July, 2013
Commissioning
October, 2013
29
SAVING OUT OF 500 MW POWER IMPORT
500 MW means about 4,000 Million Units of
Power.
Average price per year 6 Tk/Kwhr.
Average price of Liquid Fuel Power 16 Tk/Kwhr.
Per Unit Saving 10 Tk.
Annual Saving -
Tk 40,000 Million.
= Tk 4,000 Crores.
30
31
Maitree Super Thermal Power Project
Mode of Generation Ratio Worldwide
32
Maitree Super Thermal Power Project
Project Overview
Project Implementation : Bangladesh India
Friendship Power Co.
(Pvt.) Ltd.
Project Cost : 1.68 Billion USD (BDT 14510 Crs.)
Equity
Funding
Beneficiary
: 50:50 (BPDB:NTPC)
: Debt: 70%, Equity : 30%
: 100% Power to Bangladesh
(PPA : 25 yrs)
Mode of Operation : Base load
Year of completion : 2018
33
Maitree Super Thermal Power Project
Capacity
1320 MW
( 2 X 660 )
Basic Plant
Information
Technology
Primary Fuel
Quality
Source
Requirement
Stack height
Emission SOx max
Emission NOx max
Particulate matter
Supercritical Technology
Sub-Bituminous/Bituminous Coal
(GCV 5,500 6,000 kcal/Kg, Sulfurmax. 0.6%, Ash Max. 15%)
Imported
1,2000 Ton/Day (85% plant factor)
275 m
819 g/s (WB standard 1597 g/s)
Less than 500 g/m3 (WB Standard:
max conc. 500 g/m3)
100 mg/Nm3 (DoE standard 150
mg/Nm3)
34
Maitree Super Thermal Power Project
Water
Source
Requirement
Cooling System
Basic Plant Information
Possur River
Plant make up : 2.5 m3 per sec
(apprx. 0.04% of the lowest flow of the
Possur River)
Flow of the Possur river: 6000 m3/s during
dry season)
Closed Cycle
Water is cooled in Cooling Towers and recirculated.
At the rate of 1.4 m3 /sec to Possur River
Discharge of treated waste
satisfying DoEs standard (Ambient
water
Temperature)
35
Bangladesh-India Friendship Power Company (Pvt.) Limited
Maitree Super Thermal Power Project at Rampal , Bagherhat
Calendar of Events
03.03.2014
Inter Govt. MOU
11.01.10
MOU Bet. NTPC & BPDB
30.08.10
JV Agreement Between NTPC
& BPDB
29.01.12
JV Company Incorporated
31.10.12
BOI Approval
27.11.12
PPA/IA Signed
20.04.13
Cos Cor. Office Started
05.05.13
Cos Bank A/C Opened
20.05.13
Cos Site Office Started
29.05.13
Promoters Contribution
11.07.13
Apvl. of EIA Report by DOE
05.08.13
EOI for Coal Consultant
31.10.13
1st AGM of Company
31.12.13
OE Bid opened on
13.03.14
36
THANK YOU
37