This document outlines 12 hydro power projects ready for implementation in Gilgit-Baltistan with a total capacity of 65 MW and estimated cost of Rs. 35098.579 million. It also lists 14 additional potential hydro power projects currently undergoing feasibility studies with the goal of completing them by 2020, which would provide 100 MW of additional capacity. In total, the document discusses 26 hydro power projects that could generate 165 MW of power for Gilgit-Baltistan.

Uploaded by

shamoojee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views2 pages

Ready For Implementation

This document outlines 12 hydro power projects ready for implementation in Gilgit-Baltistan with a total capacity of 65 MW and estimated cost of Rs. 35098.579 million. It also lists 14 additional potential hydro power projects currently undergoing feasibility studies with the goal of completing them by 2020, which would provide 100 MW of additional capacity. In total, the document discusses 26 hydro power projects that could generate 165 MW of power for Gilgit-Baltistan.

Uploaded by

shamoojee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

HYDRO POWER PROJECTS READY FOR IMPLEMENTATION

S
#

Name Of Project

1 Hanzel, Gilgit

Tormik Ph-II
Skardu

Total
Capacity
(MW)

Estimated Cost
(Rs. in Million)

20

7145.687

PC-1 recommended by CDWP on 15-08-2012. Updated PC-1 Submitted


to Planning Commission, Islamabad.

10

3021.852

PC-1 recommended by CDWP on 15-08-2012. Updated PC-1 Submitted


to Planning Commission, Islamabad.

Ghowari,
Ghanche

30

10752.387

Hassanabad,
Hunza

05

1678.653

Establishment
Of Regional
5 Grids In Gilgit132/66kv
Baltistan (PhaseII)
Total

65.00

REMARKS

PC-1 recommended by CDWP on 15-08-2012. Included in the PSDP


2013-14 with allocation of Rs. 30.000 million and also included in the
PSDP of M.O. Water & Power. Updated PC-1 Submitted to Planning
Commission, Islamabad.
PC-1 recommended by CDWP on 15-08-2012. Updated PC-1 Submitted
to Planning Commission, Islamabad.
Feasibility Study completed through independent consultant.

12500.000

PC-1 for Ph-I submitted for Rs.5000.000 million for 132 KV line 190
Km, 66 KV line 54 Km and Grid Stations 06 Nos.
132 KV line 232 Km, 66Kv line 53 Km & Grid Stations 07 Nos
amounting to Rs.6850.000 million will be implemented by WAPDA
from 34.5 MW Harpo and 80 MW Phandar hydro power projects.

35098.579

PC-1 of Ph-II for the remaining scope i.e. 132 KV line 121.606 Km, Grid
Stations 06 Nos 66 KV line 457 Km and Grid Stations 14 Nos is under
preparation for Rs.12500.000 million .

PROJECTS UNDER FEASIBILITY STUDY THROUGH GB ADP AND TO BE


COMPLETED BY 2020 (MEDIUM TERM PLAN)
S. #

Name of Project

Total Capacity (MW)

Hydro Power Project in upper Sai Nullah Gilgit

06

Hydro Power Project at Silpi Ghizar on Ishkoman River

10

Hydro Power Project at Pasu Gojal on Hunza River

10

Hydro Power Project on Bar nullah Nagar

05

Hydro Power Project in upper Chaprote nullah Nagar

02

Hydro Power Project on Stak nullah Skardu

15

Hydro Power Project at Damel Shiger on Basha River

10

Hydro Power Project at Ghursay Ghanche on Saltro River

10

Hydro Power Project on Shayoke River in Chorbat valley,


Ghanche

12

10

Hydro Power Project at Darel Ph-VI Diamer

11

Hydro Power Project at Thore Chilas

03

12

Hydro Power Project Rattu on Rattu River Astore

10

14

Hydro Power Project Yashlitu Phase-II Astore

02

Total

100

G. Total

165