Planning & Design of WCS
Planning & Design of WCS
CONDUCTOR SYSTEM
RAJEEVA KUMAR
DEPUTY GENERAL MANAGER
(DESIGN & ENGINEERING)
GVK POWER & INFRASTRUCTURE LTD.
1
Water Conductor System
The water conductor system includes :- Pondage
arrangements including surplus arrangements,
diversion arrangements to divert the water from its
normal course into the power house, a fore bay
reservoir to cater to variations in load, on intake
structure for controlling the flow of water, surge tanks,
steel penstocks / penstock tunnels, draft tube
structure, tail race pool & channel to lead the water
back into the normal course and various gates, hoists
with controls.
The water conductor system should be such that it
conveys water with minimum loss of head and in a
reliable and safe manner under all conditions while
being economical for execution.
2
WATER CONDUCTOR SYSTEM
SIANG MIDDLE PROJECT
EL 430.25
TRANSFORMER
CAVERN
20000 APPROX 125000 APPROX 120000 20000 34400 11200 20000 23800 50600 17200
STEEL LINED
PRESSURE SHAFT
7000 Ø
EL 368.20
00
00
R2
3
EL 1376.5
ACCESS TO PRESSURE
SHAFT
NSL
EL 1282.0
RCC LINI NG
DRAINAGE
TEEL GALLARY
NING VENTILATION CUM CABLE
POWER HOUSE
TUNNEL RELAGAD
UCTION ADIT TRANSFORMER
NALLA
SURE SHAFT CAVERN ACCESS TUNNEL
EL 1059.0
INTAKE STRUCTURE
DESILTING SYSTEM
HEAD RACE TUNNEL
(HRT)
SURGE SHAFT
PRESSURE SHAFT
PENSTOCKS
DRAFT TUBES
TAIL RACE TUNNEL
5
INTAKE STRUCTURE
6
Intake Structure for hydro-electric schemes may be
broadly classified, depending upon their position in the
reservoir
1. Low Head Intake
2. High Head Intake
portals 7
Type 1 and 2 Intakes are dictated by project concept.Low
level,run-of-river developments dictate the need for an intake
built integrally with the powerhouse.In this case, the intake
also functions as the dam (in narrow valleys) or as a part of
the dam for developments built on streams those are wider
than the powerhouse.
Type 2 Intake is one of the most economical because it does
not require a special structure, perhaps, for the inlet portion,
which is built integrally with the dam (mostly arch dams).
Type 3 Intakes are used when the powerhouse is separate
from the dam and located along river bank and when type 4
intake is not feasible.
Type 4 Intake is preferable to the Type 3 Intake as the power
conduits are shorter and fewer problems in structural design
because the structure may, for substantial part of its height, be
constructed against rock,and,thus,gain lateral support.
8
Functions of Intake
Ensure required water intake
Reduce sediment entry to minimum
Design of Intake
1. Structural Stability
2. Limitations of entrance velocity
3. Hydraulic Efficiency
4. Practicability of operation
9
Losses in Intakes
Entrance Loss
Trash Rack Loss
Gate groove Loss
10
TYPICAL INTAKE SECTION
DHAULIGANGA H.E.PROJECT
1
16340
SPILLWAY AXIS 2.8
13165 11675
500
75
FOR PRECAST ELEMENTS
12000
(TYP.)
2000
C
L SPILLWAY
0
2 2
X Y INTAKE 1 INTAKE TUNNEL 1
+ =1
20000
( 6947 )2 ( 3800) 2
1500 1000
8000
3800
L POWER INTAKE-1
EL.1336.00
6807
3541
7°
C
EL.1333.50
A 1500
9769 200 Ø PIPE ROCK REINFORCEMENT
INSTALLED DURING EXCAVATION
1208 TO BE EXTENDED INTO CONCRETE
6300
1000 1500
7000 100
2 2
X Y
+ =1 EL.1328.00
( 6395 )2 ( 2000) 2 EL.1327.50 510
470
4130 2500 4500
3700
600
MIN. 36 Ø ROCK ANCHORS INSTALLED EL.1325.02 EL 1325.00
DURING EXCAVATION TO BE EL.1324.50
500
250
1750
2000
15340
900
CURVE CORRESPONDING
3700
7500 6807
TO EL. 1315.50 Y
600
907
L OF INTAKE
2 2
X Y
+ =1
10000
2 2
(7500) (3800)
EL.1320.00
5000
EL.1319.947
X
1200
TRANSITION DETAILS AS PER
C
Y Y
500
3800
2 2
DRAWING NO NHDG-1L03-41-DD-308 X Y
+ = 1 7807 FROM REFERENCE LINE 500
( 7500 )
2
( 2000) 2 EL.1317.50
L POWER INTAKE-2
6700
1250
1500
6300
1500
2000
1000
MIN.
307
250
EL.1316.00
2 2 EL.1315.50 X
X Y
250
+ =1 4500
( 900 ) 2 ( 300) 2
5000
C
EL.1313.00 1 4
600
6500
6300
1500
5000
ROCK REINFORCEMENT TO BE
3 C.J. (TYP.) INSTALLED DURING EXCAVATION
0
2000
907
(TYP.)
2000
EL.1301.50
EL.1301.00
VARIES
EL.1300.00
1000
11
DESILTING CHAMBERS / BASIN
SILTING TANKS
SETTLING BASIN
VORTEX TYPE SETTLING BASIN
12
DESILTING BASIN
For hydro-power schemes, the size of sediment
particle to be excluded depends on water head
available for power generation, petrographic nature
and concentration of sediment, metallurgy of
turbine blades etc.
The max. size of the particles that can be safely
permitted to enter the turbine is the basic
parameter which governs the design of desilting
chamber.
The desilting chambers are dimensioned on the
principle of fall velocity of sediment particles.
13
DESILTING BASIN – PLAN AND LONGITUDINAL SECTION
DHAULIGANGA H.E.PROJECT
NHDG-1LO5-41-DD-205
300
SEE TABLE FOR DETAIL OF OPENING
750 3750 3750 3750 3750 3750 3750 3750 3750 6500 6500 6500 6625 6625
13000
13000
2000
50
300
SECTION
300
C
PLAN 1L05
206
1. Ist OPENING
EL 1322.1
2.
EL 1322.10
3.
4.
EL 1308.9 4
7.
EL 1305.3 EL 1305.3
750 3750 3750 3750 3750 3750 3750 3750 3750 OPENING 300 Ø 8.
2500
6500 6500 6500 6625
1500 500
1020
1500
EL 1302.1
SLOPE 0.645 %
14
6625
1500
SLOPE 0.645 % MAN HOLE 600 (W) X 1000 (L)
500
9937
500
300 282000 300
DESILTING BASIN CROSS SECTIONS
DHAULIGANGA H.E.PROJECT
EL 1322.10 EL 1322.10
4402
EL 1317.698 EL 1317.698
8798
EL 1308.90 EL 1308.90
3600
2000
600
600
600 EL 1305.30 EL 1305.30
600
3200
1500
1500
500
500
EL 1302.10 EL 1302.10
500
500
670
3000
54000
EL 1322.10 EL 1322.10
4402
EL 1317.698 EL 1317.698
8798
EL 1308.90 EL 1308.90
36 00
2000 2000
1200 TO 2500
1200 TO 2500
EL 1305.30 EL 1305.30
V ARIES
VARIES
600
32 00 TO 5020
670 670
500 TO 1020
50 0 TO 1020
600
VARIES
V AR IES
V ARIES
1500
1500
EL VARIES EL VARIES
15
HEAD RACE TUNNEL
Headrace is that portion of the power canal which extends
from the intake works to the power house.
16
HRT - SETTING OUT PLAN
DHAULIGANGA H.E.PROJECT
TO DHARCHULA
CONTRACTS
LIMIT OF
LOT 1 LOT 2
IT1
1839 TRANSFORMER HALL
742 103000X12000/10000X10000
IT2 HEADRACE TUNNEL
6500 Ø HORSE-SHOE POWER HOUSE TR
INTAKE TUNNELS 103000X16500X39000
TAILRACE TUNNEL
P2 6500 Ø H.S.SHAPED
1750
6500 Ø D-SHAPED
1700
1100
1700
1500
1600
1800
1900
2000
2200
2500
2600
2700
2700
2600
2500
2300
2200
2100
2000
1400
1700
2100
2300
2400
2400
13°
1900
1800
1700
1600
1200
1400
1300
1500
1650
1600
11500
12000
11000
10500
16000
13000
15500
13500
12500
16500
15000
14500
14000
13000
17
HRT- LONGITUDINAL SECTION
DHAULIGANGA H.E.PROJECT
NSL
CONTRACT
LIMITS OF
LOT-1 LOT-2
SURGE SH
0
CONSTRUCTION ADIT NO 2
HR1 HR2
HR3 HR5 SS
HR6
HR4
HR7 HR8
DESILTING BASIN
PRESSURE SHAFT
1839742 14850
PARTIAL LENGTHS 1000000 2344358 43830
50296
5278226
CUMULATIVE LENGTH
0 1000000 5234396
3344358 3394654 5293076
SLOPE 0.833% 0.496%
CURVE DATA
R=200000 R=200000
ANTICIPATED GEOLOGY WIDELY TO MODERATELY JOINTED BIOTITE GNEISS WITH SMALL BENDS OF MICASCHIST
PROJECTED ROCK CLASSIFICATION CLASS I 5% ; CLASS II 55% ; CLASS III 20% ; CLASS IV 15% ; CLASS V 5%
LONGITUDINAL SECTION
18
Geometric Design
Egg.Shaped section
19
HRT CROSS SECTIONS
SIANG MIDDLE PROJECT
81000
'B' LINE C
L HEAD RACE TUNNEL - 1 C
L HEAD RACE TUNNEL - 2 C
L HEAD RACE TUNNEL - 3 C
L HEAD RACE TUNNEL - 4
'A' LINE
600 TH. CONCRETE LINING
( TYP.)
0
R3
R3
R3
75
R7500
75
75
75
R3
0
WITH WIREMESH
0 R750
R750 0
17900
100
100
0
0
10
10
200
200
R=4350
R=4350
R=4350
R=4350
100
100
WELDED WIREMESH
50
0
10
DETAIL 3
1 DETAIL 4
DETAIL 2 25 Ø 4000 LONG ROCK 25 Ø 4000 LONG ROCK
DETAIL
ANCHORS @ 1500 C/C ANCHORS @ 1500 C/C
25 Ø 4000 LONG ROCK 25 Ø 4000 LONG ROCK 'B' LINE BOTHWAYS 'B' LINE BOTHWAYS
'B' LINE 'B' LINE
ANCHORS @ 1500 C/C ANCHORS @ 1500 C/C
'A' LINE 'A' LINE
'A' LINE BOTHWAYS 'A' LINE BOTHWAYS
3 4
1 2 ISHB 200 @ 1000 C/C ISHB 200 @ 750 C/C
0
435
435
100 TH. SHOTCRETE 100 TH. SHOTCRETE
50 TH. SHOTCRETE 100 TH. SHOTCRETE
WITH WIREMESH WITH WIREMESH
350 350 WITH WIREMESH
R4 R4
RIBS IF
REQUIRED
ROCK SUPPORT ROCK SUPPORT
( CLASS - II ) ( CLASS - III ) ROCK SUPPORT ROCK SUPPORT
( CLASS - IV ) ( CLASS - V )
20
Hydraulic Design
For Hydraulic Design the following factors are taken
into consideration:-
General
Hydraulic gradient
Transient conditions like water hammer,surges
Maximum & Minimum levels at the head & tail end.
Pulsating conditions are to be avoided
Negative pressure should be avoided
21
Pressure Flow Losses
Friction Losses
Trash Rack Losses
Entrance Losses
Bend Losses
Exit Losses
22
Reasons For Concrete Lining in HRT
The tunnel alignment if passes through zones of weak
rock or fault zones the reinforced concrete lining in
addition to rockbolts or steel supports may be required for
long term stability.
Where external groundwater pressure exceeds internal
water pressure, external pressure washes joint fill
material and fault gouge into the tunnel creating instability
of jointed rock around tunnel periphery- a concrete liner
should be considered.
To ensure long term stability of the tunnel and prevent
rock erosion and washing out of joint fillings.
To prevent or reduce seepage flow
23
SURGE TANK / CHAMBER / BASIN
24
Surge Shaft – General Arrangement
Chemara-III H.E. Project
N.S.L
2000 THK. AIR VENT PIPE 300Ø
SLAB
Ø18
1
00
4
0
2000
EL 1435.00
18000 A
6000
EL 1430.00 EL
1327.00
3000
COMPACTED
BACK FILL
D
EL 1416.50
6500 D-SHAPED
UPPER EXPANSION 750 THICK R.C.C
GALLERY LINING (M-25)
EL 1408.290
B B
SECTION
( SCALE - 1:100 )
EL 1342.50
7500 D-SHAPED
LOWER EXPANSION
GALLERY
GATE GROOVE
EL 1333.089
AIR VENT PIPE 300Ø
2000
EL 1327.00
1000
500
500
C SLOPE 1 IN
6500
6500
10
EL 1318.50
SS
6500
6000
500
SECTION
A
500
Ø18
1000
0 00
6500 Ø HEAD RACE TUNNEL
6500 Ø PRESSURE SHAFT
C
SECTION
( SCALE - 1:100 )
25
Functions Of Surge Tank
Provides a free reservoir close to the discharge
regulation mechanism.
Supplies additional water required by the turbine
during load demand until the conduit velocity
accelerates to a new steady state value.
Stores water during load rejection until the
conduit velocity decelerates to a new steady
state value.
26
Types Of Surge Tanks
27
PRESSURE SHAFT
It is a vertical or inclined pressure conduit excavated in the rock,
in most cases having a steel lining , may or may not supported
by the surrounding rock , to convey water in high head
developments from the head pond or the surge tank to the
power house.
28
PRESSURE SHAFT - PLAN & SECTION
DHAULIGANGA H.E.PROJECT
AIRVENT PIPE 300Ø
L4
STEEL LINER
L4
AIRVENT PIPE 300Ø
STEEL LINER
L4
L4
M20/A40 BACKFILL CONC.
R4
9
73
M20/A40 BACKFILL CONC.
73
R4
9
VARIES FROM 7300 TO 5000
R
VA O
0
0 IE
RIE 20 0
75
T
00 TO S
S 0
20
0 0
VA 0 T
TR
21 ANS 400 0
R
RI O
R
ES 20
9
VA O
ITIO
0
RIE 20 0
N
T
11
S 0
(ST 3 42
00
SS EE
C LL
INE
L4 R)
SS'
41
18
(ST 80
7500
L4 R)
0
VARIES 6741 TO 5600 VARIES VARIES 6741 TO 5600
80
D
00
40
1841 1300 28
00
3600
00
C
40
50
00 C
219
TRANSITION
SECTION 2L10
202
(STEEL LINER)
PS1
0
80
5000
4000
6000
4000 L4
8860
PS3
4000
AIRVENT PIPE 300Ø
801 658 M20/A40 BACKFILL CONC.
00
L4
B
56
2L10
202
PS 2 STEEL LINER
4000
500 500
0
5 00 M20/A40 BACKFILL CONC.
R2
202
M25/A40 REINFORCED CONC LINING M25/A40 REINFORCED CONC LINING
800
500
E
M25/A40 REINFORCED CONC LINING
2000
2000
00
0
22
R2
99
9
0
50
2000
2000
(S 10
TE 0 00
EL
LIN
L4 ER
500
)
00
800
40
PS4
1°
.7 1
0
52 500
80
500
0
50
PS6
M20/A40 BACKFILL CONC. 800 2000 2000 800 2000 2000
00
40
D
D 2L10
SECTION E
0
80
E 2L10
36
50
SECTION
202
80
M20/A40 BACKFILL CONC. 00
00
56
A
2L10
202
28
00
STEEL LINER 4000Ø PRESSURE SHAFT
29
PRESSURE SHAFT - UPPER HORIZONTAL PORTION
DHAULIGANGA H.E.PROJECT
300 THK. CONC. LINING
6000 X
(STEEL LINER)
L4 AIRVENT PIPE 300 Ø 10000
(STEEL LINER)
L4
EL. 1282.10 M25/A40 REINFORCED CONC LINING M20/A40 BACKFILL CONC. L4 EL 1282.00 EL 1281.70
M20/A40 BACKFILL CONC.
EL. 1280.75
500
800
2000
CL OF HEADRACE TUNNEL TIGHT STEEL COVER
L4
PS 2 PS 4 PS 6 EL 1277.90
4000
4000
3600
3600
EL. 1275.90
1200
SS SS' EL 1275.90
800
MAN HOLE
EL 1274.80
500
5000 2500 M25/A40 REINFORCED CONC LINING
M20/A40 BACKFILL CONC.
STEEL LINER
M20/A40 BACKFILL CONC.
L4
7500 5000 3149 22999 3650
711 00
C E 80 M20/A40 BACKFILL CONC.
R=
2L10 2L10 EL 1269.90
201 201 800
PS 8
800
4000
D
EL 1268.00
2L10
201
A
SECTION 2L10
201
8000 2000
800
X
DETAIL
SCALE (1 : 5)
SURGE SHAFT
300 THK. CONC. LINING
REFER SEPARATE DRG.
(STEEL LINER)
L4
EL. 1282.10 AIRVENT PIPE 300 Ø EL 1282.00
M20/A40 BACKFILL CONC. EL 1281.70
L4
EL. 1280.75
800
2000
CL OF HEADRACE TUNNEL TIGHT STEEL COVER
L4
PS1 EL 1277.90
4000
3600
EL. 1275.90
1200
SS SS' EL 1275.90
MAN HOLE
EL 1274.80
800
3166
5000 2500
M20/A40 BACKFILL CONC. STEEL LINER
7500 5000 1800 4542 L4
30
4000
EL 1268.00
B
SECTION 2L10
201
PRESSURE SHAFT - VERTICAL PORTION
DHAULIGANGA H.E.PROJECT
M25/A40 REINFORCED CONC LINING
500
L4 L4
PS 3 EL 1269.90 PS 8 EL 1269.90
800 800 800 800
4000 4000
4000
0
00
EL 1268.00 EL 1268.00 Ø4
500
M20/A40 BACKFILL CONC. M20/A40 BACKFILL CONC.
C C
_ _ 4000
500 500
4000 4000
C
500 500 500 500 SECTION _
118000
118000
STEEL LINER
L4
M20/A40 BACKFILL CONC.
800
4000 4000
4000
0
00
Ø4
800
EL 1150.00 EL 1150.00
114000
STEEL LINER
L4
M20/A40 BACKFILL CONC.
800
4000
D D
_ _
800 800 800 800
4000
0
4000 4000 00
Ø4
800
E 00
E
CONSTRUCTION ADIT
_
CONSTRUCTION ADIT
45° 80 _
45°
00
800 800
8000
8000
1150
1150
800
E
R
30
00
R
30
00
SECTION _
PS 7 PS12
EL 1028.00 EL 1028.00
4000
4000
4000
PS 5 PS 10
300
1150
1150
31
PENSTOCK
Penstock is a pressure pipe line conveying the water in
high-head developments from the reservoir/ head pond or
the surge tank to the power house.
32
TYPES OF PENSTOCK
coupling
Semi rigid pipe lines – with expansion joint between
33
DRAFT TUBE
Draft tube may be defined as a diverging passage
connecting the runner to the tail race.
Draft tubes are either straight conical draft tubes with a
circular section or they are elbow-shaped tubes with
gradually increasing area, the shape changing from
circular at the runner section to rectangular at the outlet
section.
Draft tubes are needed for Francis & Kaplan turbines.
The provision of draft tube increases the efficiency of
the plant.
It enables the utilisation of static head between the
bottom of the runner and the tail race when runner is
placed above the tail water, and the dynamic head in
the water at the turbine exit due to high velocity of flow.
34
DRAFT TUBE – LONG. SECTION
Dhauliganga H.E. Project
3800 4500
EL. 1029.50
EL. 1028.00
1027.25
1800
500
1375.3
3000
EL. VARIES
500
EL 1019.50
EL. VARIES
35
DRAFT TUBE MANIFOLD – PLAN
Dhauliganga H.E. Project
POWER HOUSE AXIS TRANSFORMER CAVARN AXIS
A B C D
TURBINE AXIS H 2L13 2L13 2L13 2L13
2L13 01 202 202 202 202
202
750 7900 46284
9729
5000 1000 131
SEWERAGE 85
OUTLET PIPE 500 THK. LINING
01
300 THK. LINING
SEWERAGE
U1 OUTLET PIPE
EL
3622
3800
3500
1021.00
D1 1 DG 1 D1 01
2
200 Ø POTABLE
INLET PIPE
01
28000 5000 2000 5000 6284
0
50
D13
15000
50.3
61
R13250
°
19
4
78
0
50
44
0
500 THK. LINING
8
R2
00 0 E
U2 EL 2L13
1021.00 202
3622
3500
SEE DRAWING NO. NHDG-2L11-41-DD-228
D2 DG D2 2
1 2
500 THK. LINING
300 THK. LINING
0
28000 5000 2000 5000 17636
50
10
86
1021 6
15000
D23
R12000
51.8
79°
19
47
8
46
P3
69
500 THK. LINING
300
R2 F
00
3770
0
2L13
U3
202
3622
3500
EL
D3 DG 1021.00 D3
1 3 2
0
108
50
66
1021
D33
15000
R12000
1 51.8
19
79°
475
46
96
R20
00 EL
1021.00
U4 3500
3622
EL
1021.00
D41 DG 4 D4
2 G
2L13
9729 500 THK. LINING 202 TAIL RACE
500
300 THK. LINING
750 7900 28000 5000 2000 5000 41177 SURGE GALLERY
105
48
1026
TR1
R12000
50.3
61°
18
03
TO TAILRACE OUTLET
3. FOR SETTING OUT REFER DRAWING NO. NHDG-2L13-41-DD-002 & 003. SCALE :-
4. FOR REINFORCEMENT REFER SEPARATE DRAWING. 0 1.5 3.0 4.5 6.0 7.5 METERS
36
DRAFT TUBE - SECTIONS
Dhauliganga H.E. Project
500 TO 1000
500 TO 1000
VARIES
VARIES
500
0 TO 1375
VARIES
VARIES VARIES
18 VA 17 VA
1375
0 TO 3800 0 TO 3800
80 RIE 50 RIE
TO S TO S
0
0 TO 3000
0 TO 3000
0 TO 3000
88 0
VARIES
0
VARIES
VARIES
R1
S
RIE
VA TO 0
350
VA T O
0
350
RIE 0
1625
1625
0
200 Ø POTABLE 200 Ø POTABLE 200 Ø POTABLE
S
WATER INLET PIPE WATER INLET PIPE VARIES WATER INLET PIPE
0 TO 3800
01 01
01
500
500 TO 1000
500 TO 1000
VARIES
VARIES
SEWERAGE SEWERAGE SEWERAGE
OUTLET PIPE OUTLET PIPE OUTLET PIPE
500 3622 01 500 01 VARIES 01 VARIES
VARIES VARIES
3622 TO 3800 500 TO 1200 0 TO 3800 500 TO 1200
VARIES VARIES
500 TO 1200 500 TO 1200
A B C
SECTION 2L13 SECTION 2L13 SECTION 2L13
201 201 201
300
500
0
0 25
00
75 R2
0
R1
R45
R350
0
88
3500
4500
R1
500
00
R35
R450
0 PVC WATER STOP
3622
SEWERAGE
300
500
SEWERAGE
300 3500 300 OUTLET PIPE
D H
SECTION 2L13 E SECTION 2L13
201 201
SECTION 2L13 01
201
500
500
R3
NHDG-2L13-41-DD-101
25
0
0
75
R2
0
R550
5500
6500
6000
R550
0 00
R65
200
500
SEWERAGE
500
OUTLET PIPE
SEWERAGE
500 01 500
5500 OUTLET PIPE
500 6500 01 500
G
F
SECTION 2L13
SECTION 2L13
201
201
37
TAIL RACE
38
POWERHOUSE COMPLEX - LAYOUT PLAN
DHAULIGANGA H.E.PROJECT
12
00
EL
1055.00
10800
12
25
EL
AT1 1060.60
10800 10800
TAIL RACE SURGE 1050
GALLERY 6000 Ø
D-SHAPED SWITCH YARD
63000 X 20500
VT1
ACCESS TUNNEL
8000X6500 E
D-SHAPED 106 L
4.00
CONSTRUCTION ADIT
PRESSURE SHAFT RO
AD
6000 Ø D-SHAPED TO
A CC
ESS
TUN
NE
L
12 VENTILATION CUM CABLE
75 TUNNEL 6000 Ø D-SHAPED TR
10700 10700
TRANSFORMER HALL
103000X12000/10000X10000
13
00
POWER HOUSE
13 103000X16500X39000
25 TAILRACE TUNNEL
6500 Ø H.S.SHAPED
BUS DUCT
4000 X 5000
11 4 NOS.PENSTOCKS
35 2400 Ø
0
P2
CABLE TUNNEL
13 DRAINAGE GALLERY
75 3000 Ø D SHAPED
10600 3000 D - SHAPED
14 P3
00
DRAFT TUBE
SURGE SHAFT
3800X3000 VENTILATION EQUIPMENT
PS
1
P1 NITCH 6000X6000
1100
14
25
SS
PS
6 2 NOS PRESSURE
SHAFTS 4000 Ø
10500
LA
D NA
GA
10500
EL
14 A
75
ADIT TO SURGE SHAFT
1275.00
REL SCALE:-
AS
6500 Ø D-SHAPED 1
0 10 20 30 40 50m
15
00
10600
39
GATES ALONG THE WATER CONDUCTOR SYSTEM
INTAKE GATES
SILT FLUSHING TUNNEL GATE
DESILTING BASIN GATE
SURGE SHAFT GATE
MAIN INLET VALVE
DRAFT TUBE GATE
40
Head loss calculations
Shape Dia Area Q n L V R Head loss
m sq.m cumecs m m/sec m m
A RIVER
DHAULIGANG
TAWAGHAT KA
LI
RI
V ER
A
N AL
D
L AGA
RE
RI DT OUTLET
VE
R
D/S COFFERDAM
EL
13
01
.0
DT INLET
E
HUT
YC
P I LL WA
S
POWER INTAKE
DIVERSION TUNNEL
TRANSFORMER HALL
ACCESS TUNNEL
TAILRACE TUNNEL
POWER HOUSE
DRAFT
TUBES VENTILATION TUNNEL
SURGESHAFT
HRT
PRESSURE SHAFTS
CYLINDER HOIST
INTAKE GATE
(TYPICAL)
A
7500
_
EL 426.50
EL 426.50
600
KEY PLAN
EL
426.50
A
SECTION _
46
DIVERSION TUNNEL PLAN
SIANG MIDDLE PROJECT
47
POWER INTAKE - PLAN & SECTION
SIANG MIDDLE PROJECT
4000 10000
7500
EL
423.25
7500
27000
2000
(TYP.)
7500
2000
7500
KEY PLAN
7500
2000
NSL
7500
BACKFILL
CONCRETE
M10/A80
6000
27000
2000
1000
500
EL 430.25 A
7500
7500
500
1000
2000
3000
5000
8000
20000
4000 10000 20000
2000
B
A SECTION
SECTION
48
PRESSURE SHAFT - GENERAL ARRANGEMENT
SIANG MIDDLE PROJECT LONG @ 1500 C/C BOTH WAYS
STEEL LINER
BACK FILL
CONCRETE
5000 20000
0
100 THK. SHOTCRETE
50
'B'- LINE
R3
WITH WIRE MESH
A 'A'- LINE
BACK FILL CONCRETE
HEADRACE TUNNEL
EL 430.25
7500
7000
SCALE 1: 200
SCALE 1: 200
CONSTRUCTION ADIT
1
B BACK FILL
CONCRETE
'B'- LINE
50
'A'- LINE 100 THICK SHOTCRETE
6000 LONG 25 Ø ROCK 6000 LONG 25 Ø ROCK
32
ANCHORS @ 1500 C/C ANCHORS @ 1500 C/C WITH WIRE MESH
STEEL LINER
40000 25600
800 THK. BACK FILL
CONCRETE
C 10000
00
00
R2
POWER HOUSE
CAVERN U/S WALL
6500
49
HEAD RACE TUNNELS
SIANG MIDDLE PROJECT
10
00
00
6
97
83
LIMIT OF H.R.T
PRESSURE SHAFT
8
66
47
50
TAIL RACE TUNNEL PLAN
SIANG MIDDLE PROJECT
51
TAIL RACE TUNNEL – SECTION
SIANG MIDDLE PROJECT
0
75
R3
10000
0
R750
10000
B
A B
7500 7500
EL 351.00
52
WATER CONDUCTOR SYSTEM
DESIGN DISCHARGE GROSS HEAD CAPACITY DESIGN ENERGY
S.NO. PROJECT DIAMETER LENGTH
(Cumecs) (m) MW (MU) (m) (km)
54
LIST OF INDIAN STANDARDS
IS 4880 (PT 7):1971 – Code of practice for design of tunnels
conveying water:Part 7 Structural design of
steel lining
IS 5330:1984 – Criteria for Design of anchor blocks for
penstocks with expansion joints
IS 5878 (PT 1):1971 – Code of practice for construction of tunnels conveying
water: Part 1 Precision survey & setting out
IS 5878 (PT 2/ – Code of practice for construction of tunnels conveying
SEC 1):1970 water: Part 2 Underground excavation in rock section 1
Drilling & Blasting
IS 5878 (PT 2/ – Code of practice for construction of tunnels conveying
SEC 2):1971 water: Part 2 Underground excavation in rock section 2
Ventilating,Lighting,Mucking and Dewatering
IS 5878 (PT 2/ – Code of practice for construction of tunnels conveying
SEC 3):1971 water: Part 3 Tunneling method for steeply inclined
tunnels, shafts and underground power houses
IS 5878 (PT 3):1972 – Code of practice for construction of tunnels conveying
water: Part 3 Underground excavation in soft strata
55
LIST OF INDIAN STANDARDS
IS 5878 (PT 4):1971 – Code of practice for construction of tunnels conveying
water: Part 4 Tunnel supports
IS 5878 (PT 5):1976 – Code of practice for construction of tunnels conveying
water: Part 5 Concrete lining
IS 5878 (PT 6):1975 – Code of practice for construction of tunnels conveying
water: Part 6 Steel lining
IS 5878 (PT 7):1972 – Code of practice for construction of tunnels conveying
water: Part 7 Grouting
IS 7357:1974 – Code of practice for structural design of surge tanks
IS 7396 (PT 1):1985 – Criteria for hydraulic design of surge tanks:Part 1
Simple,restricted orifice and differential surge tanks
IS 7396 (PT 2):1985 – Criteria for hydraulic design of surge tanks:Part 2
Tailrace surge tanks
IS 7396 (PT 3):1990 – Criteria for hydraulic design of surge tanks:Part 3
Special surge tanks
IS 7396 (PT 4):1983 – Criteria for hydraulic design of surge tanks:Part 4
Multiple surge tanks
IS 7563:1985 – Code of practice for structural design of cut and cover
concrete conduits
56
LIST OF INDIAN STANDARDS
IS 7916:1992 – Code of practice for open power channels
IS 11105:1984 – Code of practice for design aspect of of tunnel plugs
IS 11625:1986 – Criteria for hydraulic design of Penstocks
IS 11639 (PT 1):1986 – Criteria for structural design of Penstocks: Part 1
Surface Penstocks
IS 11639 (PT 2):1995 – Criteria for structural design of Penstocks: Part 2
Buried/embedded Penstocks
IS 11639 (PT 3):1996 – Criteria for structural design of Penstocks: Part 3
Specials for Penstocks
IS 12633:1989 – Guidelines for first filling and emptying of pressure
tunnels
IS 12967 (PT 1):1990 – Code of practice for analysis of hydraulic transients
in hydro-electric and pumping plants:Part 1 Criteria
for analysis
57
THANK YOU
58