0% found this document useful (0 votes)
2K views33 pages

Civil Works Technical Specifications

The document provides specifications for earthworks on a civil works project. It outlines the scope of excavation work, which includes furnishing equipment and materials to excavate underground services and structural units. It describes general requirements such as constructing excavations and fills to the proper lines, levels and gradients. It also provides detailed requirements for various aspects of excavation work including site preparation, excavation procedures and tolerances, disposal of excavated materials, drainage of excavations, and excavation for foundations, pipelines and other structures. Safety measures for excavations like shoring and upholding excavation sides are also specified.

Uploaded by

Asim Khan
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views33 pages

Civil Works Technical Specifications

The document provides specifications for earthworks on a civil works project. It outlines the scope of excavation work, which includes furnishing equipment and materials to excavate underground services and structural units. It describes general requirements such as constructing excavations and fills to the proper lines, levels and gradients. It also provides detailed requirements for various aspects of excavation work including site preparation, excavation procedures and tolerances, disposal of excavated materials, drainage of excavations, and excavation for foundations, pipelines and other structures. Safety measures for excavations like shoring and upholding excavation sides are also specified.

Uploaded by

Asim Khan
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 33

CIVIL WORKS TECHNICAL SPECIFICATIONS

SECTION - 1

EARTHWORKS

1. SCOPE OF WORK

The work under this section of the specifications consists of furnishing


all plant, labour, equipment, appliances and materials and in performing all
operations in connection with earthworks of all underground services and
structural units, stock piling of suitable excavated material, disposal of
unsuitable and surplus excavated material in accordance with this section of
specifications, the applicable drawings and subject to terms and conditions of
the Contract.

2. GENERAL

2.1 The Contractor shall be deemed to have made local and independent inquires
as to, and shall take the whole risk of, the nature of the ground subsoil or
material to be excavated or penetrated and the Contractor shall not be entitled
to receive an extra or additional payment nor to be relieved from any of his
obligations by reasons of the nature of such ground subsoil or material.

2.2 All excavations, cut and fills shall be constructed to the lines, levels
and gradients specified with any necessary allowance for consolidation,
settlement and drainage so that at the end of the Period of Maintenance the
ground shall be at the required lines, levels and gradients. During the course
of the Contract and during the Period of Maintenance any damage or defects in
cuts and fills, in structures and other works, caused by slips, falls of wash-
ins or any other ground movement due to the Contractor's negligence shall be
made good by the contractor at his own cost.

3. SITE PREPARATION

3.1 The Contractor shall set out the works and shall be responsible for true
and perfect setting out of the same and for correctness of the positions,
levels, dimensions and alignments of all parts thereof. If at any time any error
in this respect shall appear during the progress of the works, the Contractor
shall at his own expense rectify such error, to the satisfaction of the
Engineer.

3.2 The Contractor shall construct and maintain accurate bench marks so that
the Lines and Levels can be easily checked by the Engineer.

3.3 The Contractor shall perform a joint survey with the Engineer's
Representative, of the area where earth work is required, plot the ground levels
on the drawings and obtain approval from the Engineer before starting the earth
work and shall supply a copy to the Employer duly checked, signed and
authenticated by the Engineer before start of work.
4. EXCAVATIONS

4.1 Excavation shall include the removal of all material of every name and
nature. It is expected that rock and other hard material will be encountered
during excavation. The rate of excavation shall include the removal of all sub-
surface material of every name and nature and no classification of sub-surface
material shall be made nor any additional payment shall be made.

4.2 The major portion of excavations shall be carried out by mechanical


excavators and excavated materials disposed off to stock on spoil as directed by
the Engineer. The excavation may be done by normal means. Unless otherwise
specified by the Engineer, levelling, trimming and finishing to the required
levels and dimensions shall be done manually. The material suitable for fill and
backfill, if approved by the Engineer shall be stockpiled within the limits of
whole of the Site as directed by the Engineer.
Excavated material unsuitable for use as fill and backfill shall be disposed off
by the Contractor at locations approved by the Engineer within specified free
haulage limit

4.3 The Contractor shall give reasonable notice that he intends to commence
any excavation and he shall submit to the Engineer full details of his
proposals. The Engineer's approval shall not relieve the Contractor of his
responsibility with respect to such work.

4.4 The Contractor shall preserve the completed excavation from damage due to
slips and earth movements, ingress of water from any source whatsoever and
deterioration by exposure to the sun and the effects of the weather.

All excavations shall be kept free of water and shall be maintained dry to
the satisfaction of the Engineer. Prevent surface water and sub-surface water
and sub surface ground water from flowing into the excavation and flooding the
project site and surroundings.

Do not allow water to accumulate in excavations, remove water from


excavations to prevent softening of foundation bottoms, under cutting footings
and soil changes determined to the stability of sub-grades and foundations.
Provide and discharge lines necessary to convey the water away from the
excavations convey water removed from excavation and rain water to outside the
limits in manner that no damages is caused to the surrounding services
properties.

4.5 Excavation for pits, cable trenches, equipment-foundations and other


structures shall be taken out to the levels and dimensions shown on Drawings or
such other levels and dimensions as the Engineer may direct.

4.6 Excavation shall extend to adequate distance from walls and footings to
allow for placing and removal of forms, installations of services and for
inspection, except where the concrete for walls and footings is authorized to be
deposited directly against excavated surfaces. Undercutting will not be
permitted. The additional excavation for placing and removal of forms,
installation of services, for inspection and generally for working area on
slopes for stability shall not be measured for payment and shall be deemed to be
included in the rates for excavation as measured net.

4.7 All excavations in foundations shall be taken to 6 inch above the final
excavation elevations shown on the drawings and the last 6 inch shall be trimmed
carefully to a smooth and level surface. Immediately after trimming to the final
elevation, a layer of blinding concrete shall be placed to the thickness shown
on the drawings. All excavations for foundations which have been trimmed and
disturbed shall be compacted and covered by lean concrete by the end of the day.

4.8 No excavation shall be refilled nor any permanent work commenced until the
foundation has been inspected by the Engineer and his permission to proceed is
given.

4.9 If excavations for sub-structures are carried below the required level, as
shown on the Drawings or as directed by the Engineer, the surplus depth shall be
filled in with concrete of the same grade as of blinding concrete at the sole
cost of the Contractor.

4.10 All excavations shall be performed in the dry. The placing of blinding
concrete, placing of reinforcement and casting of the permanent works in the
excavation shall be carried out in the dry.

4.11 Shoring, where required during excavation, shall be installed to protect


workmen and the bank, adjacent paving, structures and utilities. The term
shoring shall also be deemed to cover whatever methods the Contractor elects to
adopt, with prior approval of the Engineer, for upholding the sides of
excavation and also for planking and strutting to excavation against the side of
roadways and adjoining properties in existing hardcore of any other material.
The Contractor will be held responsible for upholding the sides of all
excavations and no claim for additional excavation, concrete or other material
will be considered in this respect.

4.12 Existing utility lines that are shown on the drawings or the locations of
which are made known to the Contractor prior to excavation and that are to be
retained, as well as utility lines constructed during excavation and
backfilling, and if damaged, shall be repaired by the Contractor at his own
expense. Any existing utility lines which are not known to the Contractor in
sufficient time to avoid damage, if inadvertently damaged during excavation,
shall be repaired by the Contractor and adjustment in payment will be made as
approved by the Engineer. When utility lines which are to be removed, are
encountered within the area of operations the Contractor shall notify the
Engineer in ample time for the necessary measures to be taken to prevent
interruption of the service.

4.13 Where applicable the excavation work shall include the excavation in above
water table and excavation below water table. The Contractor shall provide all
plant, equipment, pumps, sheeting, well points as required to keep the water
table 3.0 feet below the deepest foundation as shown on the drawings till the
completion of foundation works.

4.14 Before starting the excavation for pipelines, the Contractor shall ensure
the correct alignment of the pipeline on the ground the depth and width of
excavation of the trench, all in accordance with the Drawings and instructions
of the Engineer. The Contractor shall make profile with cement concrete pillars.

Excavation shall be carried out true to lines, levels, grades and widths
as shown on the drawings or as directed by the Engineer ensuring proper laying
of the pipe line, the bedding fill, construction of chambers for appurtenances
and any other structures. The trench bottom shall be graded to provide even and
substantial bearing over the specified bedding and of the structure.
Without the written permission of the Engineer, not more than 600 feet of
the trench shall be opened in advance of the completed pipeline.

4.15 The Engineer may require the Contractor to excavate below the elevations
shown on the drawings or he may order him to stop above the elevations shown
depending upon the suitable foundation material encountered.

4.16 If for any reason, the levels, grades or profiles of the excavations are
changed adversely by the Contractor, the Contractor shall at his own cost, be
liable to bring the excavations to the required levels and profiles as shown on
the drawings or as directed by the Engineer.

5. EXCAVATION TOLERANCES

Excavation shall be performed within the tolerances for excavation limits


indicated on the drawings. Where no tolerance limits are indicated excavation
shall be performed to tolerances established by the Engineer, as acceptable for
the design and type of work involved.

6. FILL AND BACKFILL

6.1 The backfilling shall include filling under the floors, around the
foundation trenches, pipes, conduits, ducts and channels.

The backfilling shall include loading, unloading, transporting, placing,


stacking, spreading of earth, watering, rolling, ramming and compacting, etc.,
complete as specified herein.

6.2 The excavated material if found suitable shall be stockpiled within the
free haulage limit of the Project Boundary. This material shall be used for
filling/back-filling if approved by the Engineer and shall be transported by the
Contractor anywhere required for the purpose of filling/back-filling work in
this Contract.

6.3 The Contractor shall provide the approved quality of backfill and fill
material required to complete the fill and back- filling work from the places as
designated by the Engineer.

Deep filling shall be predominantly granular material and free from slurry
mud, organic or other unsuitable matter and capable of compaction by ordinary
means.

6.4 Material for backfilling shall be as approved by the Engineer and shall be
placed in layers not exceeding 6 inches measured as compacted material with
sufficient water and compacted to produce in-situ density not less than 95% of
the maximum dry density at optimum moisture content.

Depending on the depth of fill the Engineer may instruct increased


thickness of successive layers to be placed.

The filling shall be compacted by mechanical means as approved by the Engineer.

6.5 Filling around pipes and cables shall be carefully placed with fine
material to cover the pipe or cable completely before the normal fill is placed.
6.6 Backfilling of trenches/foundations shall be carried out only after the
pipe line/structural works within the excavations have been inspected, tested
and approved by the Engineer.

6.7 Fill shall not be placed against foundation walls prior to approval by the
Engineer. Fill shall be brought up evenly on each side of the walls as far as
practicable. Heavy equipment for spreading and compacting the fill shall not be
operated closer to the wall than a distance equal to the height of the fill
above the top of footing.

6.8 Before the start of fill and backfill, the Contractor shall satisfy
himself as to the levels and slopes of the fills and backfill shown on the
Drawings, the requirements of compaction, the possibility of settlement & all
other particulars whatsoever in connection with the filling works.

6.9 All filled areas shall be left neat, smooth and well compacted, the top
surface consisting of the normal site surface soil, unless otherwise directed.

7. TOLERANCES

The stabilization of compacted backfill/fill surface shall be smooth and


even and shall not vary more than 3/8 inch in 10 feet from true profile and
shall not be more than 1/2 inch from true elevation.

8. DISPOSAL OF SURPLUS EXCAVATED MATERIAL

8.1 The rejected unsuitable material and surplus excavated material shall be
disposed off anywhere within 10-kilometre lead measured along the most direct
route from the project boundary, as directed by the Engineer. No compensation of
any lead/lift is admissible and rates quoted shall be deemed to include the
same.

8.2 The disposal of surplus/unsuitable excavated material shall include


loading, unloading, transporting, stacking, spreading and levelling as directed
by the Engineer.

9. MEASUREMENT AND PAYMENT

9.1 General

Except otherwise specified herein or else where in the Contract Documents,


no measurement and payment will be made for the under mentioned works related to
the relevant BOQ items. The cost thereof shall be deemed to have been included
in the quoted unit rate of the respective items of the Bill of Quantities.

9.1.1 Timber shoring, planking, strutting and providing slope for upholding the
sides of excavations.

9.1.2 Any fill with approved material necessitated by over excavation due to
fault or convenience of the Contractor except under structural members.
9.1.3 Stockpiling the excavated material at approved location within free
haulage limit of the Project Boundary and transporting back suitable material to
places requiring fill or backfill.

9.1.4 Specified foundation bed preparation.

9.1.5 Excavation involved in providing adequate working space around sides of


foundation and service line trenches.

9.1.6 Providing approved quality fill/backfill material obtained from excavated


material as designated by the Engineer.

9.1.7 Rolling, levelling, watering & compacting the fill and backfill to
required density.

9.1.8 All laboratory and field tests stipulated in these specifications.

9.1.9 Disposal of rejected surplus and unsuitable excavated material anywhere


within 10-kilometre lead measured along the most direct route from the project
boundary, as directed by the Engineer. No compensation of any lead/lift is
admissible and rates quoted shall be deemed to include the same.

9.1.10 De-watering to keep the foundations dry during construction.

9.2 Excavation

9.2.1 Measurement

Quantities of excavation shall be calculated/measured from the pre-work


levels of levelled and graded ground taken jointly by the Contractor and the
Engineer before commencement of the work.

The quantities set out for excavation and its subsequent disposal shall be
deemed to be the bulk quantity before excavating and no allowance shall be made
for any subsequent variations in bulk or for any extra excavation.

Unless otherwise shown on the Drawings quantities of excavation shall be


measured of acceptably completed works on the basis of vertical excavations
required in accordance with lines of concrete.

Quantities of excavation for laying service line trenches shall be


measured for payment on the basis of vertical excavation faces for the specified
width for the trench as shown on the drawings.

Measurement for acceptably completed excavation works shall be made on the


basis of number of cubic feet of material excavated for foundation and service
trenches as shown on the Drawings or as directed by the Engineer.

9.2.2 Payment

Payment will be made for acceptably measured quantity of excavation on the


basis of unit rate per cubic feet quoted In the Bills of Quantities and shall
constitute full compensation for all the works related to the item, Including
but not limiting to back filling.
9.3 Backfill/Fills

9.3.1 Measurement

Measurement for acceptably completed backfill/fill works will be made on


the basis of number of cubic feet of compacted backfill/fill in position in
accordance with the lines, levels and grade as shown on Drawings or as directed
by the Engineer.

9.3.2 Payment

Payment will be made for acceptably measured quantity of backfill/fill on


the basis of unit rate per cubic feet quoted in the Bills of Quantities and
shall constitute full compensation for all the works related to the item.

SECTION-2

TERMITE PROOFING

This item of work shall consist of supplying and applying chemicals in the
soil to ensure protection from white ants and shall be carried out by specialist
in this field. The work shall also include the cost of all tools, transport,
labour and other costs necessary for the proper termite proofing of the Works.

At the time of Tendering the contractor shall, in his covering letter,


indicate the party he plans to engage for this work. He shall also attach with
his covering letter, the original copy of the Technical Proposal of the party,
on their letter head, he intends to awards this work to.

The chemical used shall be standard termite proofing chemical compounds


injected into the ground. The type proposed by the contractor shall be approved
by the ARCHITECT /ENGINEER.

Generally, the chemical shall be injected into the ground at various


intervals before concrete has been poured and as per the Instructions of the
manufacturers and shall ensure a proper seal around the structure. A minimum of
three applications shall be made 24 hours apart or the number of applications
recommended by the manufacturer, which ever is more.

The contractor shall take all necessary precautions to protect the


labourers from any harm or hazard from the chemical used.

Before fixing any wood, which is to be concealed or be in contact with


concrete, it shall be treated with anti-termite treatment.

The contractor shall give a guarantee/warrantee on judicial paper to the


effectiveness of the termite proofing for a period of ten years from the date of
application. If termite become visible in the aforementioned structure, the
contractor is liable to the cost of getting the structure termite proofed again,
at his own cost, and shall rectify the damage due to termites at his own
expense.

Payment shall be made after completion of this item and its approval by
the ENGINEER/ARCHITECT.

SECTION -3

PLAIN AND REINFORCED CONCRETE

1. SCOPE

The work under this section of the specification consists of furnishing


all plant, labour, equipment, appliances and materials and in performing all
operations in connection with the providing and laying of plain and reinforced
concrete work complete in any floor and at any height as per drawings except
where specifically stated in the relevant item of Bill of Quantities, in strict
accordance with this section of the specifications and the applicable drawings,
and subject to the terms and conditions of the Contract. The scope of this
section of specification is covered with detailed specifications as laid down
herein.

2. APPLICABLE STANDARDS

Latest editions of the Pakistan, British and ASTM Standards are relevant
to these specifications wherever applicable.

3. MATERIALS

3.1 Aggregates

3.1.1 The sources of supply of all fine and coarse aggregates shall be subject
to the approval of the Engineer.

3.2 Cement

3.2.1 The cement shall be fresh and of approved origin and manufacture. It shall
be approved by the Engineer.

3.3 Water

Only clean water from the city supply, tube well installed at the site or
from other sources approved by the Engineer shall be used. The Contractor shall
supply sufficient water for all purposes.

4. NOMINAL CONCRETE MIXES

4.1 Proportions of Mix


4.1.1 Cement and aggregates:

Cement, fine aggregate and the coarse aggregate shall be weighed separately. The
proportions of cement to fine aggregate and coarse aggregate shall be adjusted
so as to provide the concrete of the required crushing strength when tested as
set out in Table 1.

Table 1: Strength requirements for Portland concrete with aggregates


complying with BS. 882.

Min Cube
Min Cement per Crushing Max. Water per
Class Cu.ft. of Strength at 28 110 lb. bag of
Concrete days Cement
(lb.) (psi) (gallon)
Class A
30.00 4,500 4.40
(1:1:2)
Class B
22.00 3,775 5.06
(1:1-1/2:3)
Class C
18.00 3,000 5.28
(1:2:4)
Class D
13.00 1,500 7.05
(1:3:6)
Class E
9.50 1,000 7.27
(1:4:8)

4.2 Placing

4.2.1 Before placing of concrete, formwork shall have been completed; water
shall have been removed; reinforcement shall have been secured in place;
expansion joint material, anchors and other embedded items shall have been kept
in position; and the entire preparation shall have been approved by the
Engineer.

4.3 Curing and Protection

4.3.1 Beginning immediately after placement, concrete shall be protected from


premature drying, excessively hot or cold temperatures and mechanical injury and
shall be maintained with minimum moisture loss at a relative constant
temperature for the period necessary for hydration of the cement and hardening
of the concrete. The materials and methods of curing shall be subject to
approval of the Engineer.

5. TEST OF CONCRETE QUALITY

5.1 The Contractor shall provide samples of concrete for testing at the
Engineer's direction. Proper facilities shall be provided for making and curing
the test specimens in accordance with PS 560 and PS 849. A competent person
shall be employed by the Contractor whose first duty shall be to supervise all
stages in the preparation and placing of the concrete. All test specimens shall
be made and site tests carried out under his direct supervision.

6. MEASUREMENT AND PAYMENT

6.1 General

Except otherwise specified herein or elsewhere in the Contract Documents,


no measurement and payment will be made for the under mentioned specified works
related to the relevant items of the Bills of Quantities. The cost thereof shall
be deemed to have been included in the quoted unit rate of the respective items
of the Bills of Quantities.

6.1.1 Providing, fixing, striking, etc. of formwork including fairface formwork.


6.1.2 Providing and installing types of joints in structure.
6.1.3 Testing of concrete cube specimens.
6.1.4 Curing, repair work, scaffolds and admixtures
6.1.5 Providing grooves on concrete surfaces.

6.2 Plain and Reinforced Concrete

6.2.1 Measurement

Concrete shall be measured as executed but no deduction shall be made for


the following:

• Volume of any steel embedded in the concrete.

Unless otherwise mentioned In the BOQ measurement of acceptably completed


works of plain and reinforced cement concrete will be made on the basis of
number of cubic feet concrete placed and compacted in position within the neat
lines of the structure as shown on the Drawings or as directed by the Engineer.

6.2.2 Payment

Payment will be made for the acceptable measured quantity of plain and
reinforced cement concrete on the basis of unit rate per cubic feet quoted In
the Bills of Quantities and shall constitute full compensation for all the works
related to the item.

SECTlON-4

FORM WORK
1. GENERAL

The form work shall be inclusive of all labour, material workmanship and
alike. All form work and supports thereto shall be designed by the Contractor
and relevant drawings shall be submitted to the Engineer for approval before the
work is put in hand. Such an approval shall not relieve the Contractor from all
the obligations of the Contract or give rise to any claims.

2. MAKING FORMS

The form work for columns, beams, slabs, lintels, fins, shells, blocks,
panels, purdees, surrounds for windows, and all other works, whether to be
precast or cast in situ, shall be made of sound and properly seasoned timber or
other approved material and shall be rigidly formed and designed by the
Contractor to the shapes and forms as per drawings in accordance with the best
of the existing practices so as to be able to withstand without displacement,
deflection or deformation movements of any kind, the pressure of the wet
concrete and all other loads.

3. RIGID WITH ALLOWANCE FOR CAMBER AND BULGES

It shall be fabricated and erected in position, perfect in alignment,


levels, and true to plumb and shape, and securely braced so as to enable it to
stand all weights, live and vibrating, to be endured during placing of concrete
and its subsequent hardening till the form work is struck. It shall be so
sufficiently rigid as not to loose its form and shall be so made for bulging and
deflection, as to give the finished concrete the required lines, plumb, size and
shape.

4. MATERIALS AND LABOUR

The Contractor shall supply all materials and labour, necessary for a good
and speedy erection of form work such as shuttering, planks, struts, bolts,
stays, gangways, boards, fillets etc., and shall do all that is essential in
executing the job in a workman like manner, to the satisfaction of the Engineer.

5. FORM WORK NO TO INTERFERE OR INJURE WORK

The formwork shall be so designed and arranged so as not to unduly


interfere with concrete, during its placing, and be easy to remove without
injuring the finished concrete. Wedges, clamps, bolts and the rods shall be
used, when permitted and where practicable, in making the form work rigid in
holding it to true position.

6. OPENING IN FORM WORK

Wherever the concreting is required to be carried out within forms of


considerable depths, temporary openings in the side of the form shall be
provided to facilitate the pouring and consolidation of the concrete. Small
temporary openings shall be provided at the bottom of all forms to permit the
removal of rubbish etc.

7. OPENINGS AND OTHER DETAILS


Provision shall be kept in the form work such as openings, recesses,
holes, pockets, fillets, etc. for housing services and other architectural
details in the finished concrete, or on its surface and edges, as shown on
drawings or as directed by the Engineer to fix all necessary inserts, dowels,
pipes, hold-fasts etc., as shown on drawings.

8. JOINTS IN FORM WORK

All joints in the form work shall be sufficiently closed to prevent undue
leakage of mortar for concrete surface not to be exposed in the finished work.
The joints in the form work for all concrete surfaces to be exposed in the
finished work shall be close jointed and perfectly smooth so as not to allow any
leakage of the mortar from the concrete and show any appearance of leaking
mortar on concrete surface.

9. TREATMENT AND INSPECTION OF FORMS

All rubbish particularly chipping, shavings and saw dust etc. shall be
removed from the interior of the forms, immediately before placing concrete.
Forms shall be coated with approved mould oil before reinforcement is placed.
Surplus oil on forms and any oil on reinforcing steel shall be removed. Forms
for surfaces not exposed to view or normal weathering may be thoroughly wetted
with soap and water, in place of oiling, before placing concrete. If the forms
are not used within 24 hours, a fresh coat of oil shall be given before placing
of concrete.

10. STRIKING SHUTTERING

No struts or timbering which serve the purpose of supporting the shuttering or


centering shall be struck and removed without direct permission from the
Engineer in writing, and the work of striking and removal after the receipt of
such permission shall be conducted under the personal supervision of the
competent foreman in the employment of the Contractor, and the Contractor shall
hold himself fully responsible for any consequences whatsoever. In all cases,
the Engineer will direct and control the minimum period of time for which the
forms, shuttering or centering shall remain in place before being struck; but,
for the general guidance of the Contractor, the following are to be considered
as the minimum periods for the main classes of work:

Portland Cement Portland Cement


Removal of Shuttering Cold Weather Normal Weather
Days Days
Beam sides, walls and
5 3
columns(Unloaded)

Slabs soffits (props left


10 7
under)
Beam soffits (props left
13 10
under)
Removal of props to slabs 18 14

The Engineer may require, however, that any walings, struts or other timbers or
supports, the removal of which may cause the transference of load to the
finished work, to be kept in place for three weeks after the placing of the
concrete.

11. INJURY OR DAMAGE

The Contractor shall be responsible for any injury to the work and any
consequential damages caused by or arising from the removal and striking of
forms, centering and supports, due to striking too soon, and any advise,
permission or approval given by the Engineer, related to the removal and
striking of forms, centering and supports shall not relieve the Contractor from
the responsibilities herein defined.

12. TREATMENT AFTER REMOVAL OF FORMS

Any minor surface honey-combing or other irregularities are to be properly made


good immediately upon the removal of the form work, and the surface made good to
the satisfaction of the Engineer. Any small voids shall be neatly stopped with
cement mortar consisting of one part of cement to two parts of sand and the
whole surface rubbed over with carborundum stone and cement wash, and bring the
whole to a smooth and pleasing finish and uniform colour.

13. No form work shall be measured and paid for separately and shall be deemed
to be included in the unit price of concrete whether cast in-situ, or pre-cast
and subsequently fixed in position.

14. METHODS OF MEASUREMENT OF FORM WORK

14.1 Unless otherwise specifically stated in the bill of quantities, or herein,


all items for form work shall be deemed to be inclusive of, but not limited to,
the following

• Shop drawings of form work for special concrete finishes and all
pre-cast concrete members.

• All falsework, centering, fabricating, assembling, cutting, fitting


and fixing in position and taking all measures necessary to produce
the required shapes of concrete.

• Forming cambers and falls.

• Taking all measures necessary to produce the required finish to the


surface of the concrete.

• Cutting and fitting around projecting members, pipes reinforcement


and the like.
• Forming fillets, chamfers, splays, drips, rebates, recesses, grooves
and the like of 6 inches total width or less measured on the faces
in contact with the concrete.

• Maintaining in place until it is struck and allowing for any


variation from the minimum period for striking arising from
prevailing weather conditions.

• Striking, taking down and removing.

• Any additional concrete provided in lieu of form work to fill over-


break or working space.

14.2 Form work (if separate and/or extra payment is specifically stated in the
bill of quantities) shall be measured in square feet or linear feet as the
actual surfaces of the finished structure which require to be supported during
the deposition of the concrete. No deduction shall be made for voids not
exceeding 100 square feet.

Form work shall not be measured:

• For forming construction joints (whether shown or not on the Drawings),


skew backs, stunt ends, steppings, bonding chases and the like.

• For firming holes, pockets, sockets, mortises and the like.

• For chamfers not exceeding 6 inches in width and forming splays, internal
angles not exceeding 1 inch in width.

14.3 Classification of formwork, for separate and extra payment (if any), shall
be as follows:

• To horizontal or sloping soffits of suspended slabs, floors, roofs,


staircases, landings and the like.

• To sloping upper surfaces of suspended slab, floors rooms and the like
with more than 15 degree from horizontal.

• To vertical or battering sides of foundations, foundation beams and slabs,


ground beams, machine foundations and the like.

• To vertical or battering sides of walls, solid balustrades and the like.

• To vertical, battering or curved sides of stanchion casings, columns,


piers, pilasters and the like.

• To sides and sofits of openings in with, recesses in Walls, projecting


panels on walls and the like.

• To sides and soffits (including curved soffits) or horizontal or sloping


beam-casings, beams, brackets, lintels, staircase-strings and the like.
• To sloping upper surfaces of beam-casings, beams, brackets, lintel,
staircases-strings, and the like, where more than 15 degrees from
horizontal.

• To edges of beds, roads, footpaths, paving and the like.

• To edges of suspended slabs, floors, roofs, landing and the like.

• To sides of kerbs, upstands and the like.

14.4 Form work to throats, grooves, chases, rebates, chamfers over 4 inches
wide, splayed internal angels over 1 inch wide, mouldings and the like shall
each be measured separately in linear feet stating the size.

SECTlON-5

REINFORCEMENT

1. SCOPE

The work under this section of specifications consists of furnishing,


cutting, fabricating, bending and placing steel reinforcement in any floor and
at any height in concrete structures or elsewhere as shown on the drawings or as
directed by the Engineer. The scope of this section of specification is covered
with detailed specifications as laid down herein.

2. APPLICABLE STANDARDS

Latest editions of the following Pakistan, British and ASTM Standards are
relevant to these specifications wherever applicable.

Pakistan Standards

PS 231 Mild Steel Bars.


PS 241 Tensile Testing of Steel.
PS 244 Bend test for Steel
PS 580 Rolled deformed Steel bars (intermediate grade) for concrete
reinforcement.
PS 605 Rolled deformed steel bars (hard grade) for concrete reinforcement.
PS 606 Rolled deformed Steel bars (structural grade) for concrete
reinforcement.
PS 607 General technical delivery requirement for steel.
British Standards

BS 4449 Carbon steel bars for reinforcement of concrete.


BS 4466 Bending dimensions and scheduling of bars for the reinforcement of
concrete.

ASTM Standards

A 82 Cold- Drawn steel wire for concrete reinforcement.


A 305 Minimum requirement for the deformations of deformed steel bars for
concrete reinforcement.
A 615 Deformed billet steel bars for concrete reinforcement,Grade 60.

In addition to the above, the latest editions of other Pakistan Standards,


British standards, American Concrete Institute Standards, American Society for
Testing and Materials Standards and other standards as may be specified by the
Engineer for Special Material and construction are also relevant.

3. MATERIAL AND SIZE OF BARS

3.1 Reinforcement for concrete shall conform to the respective Pakistan,


British, ASTM, or other Standards as specified in the Drawings and in the
Contract Documents or as may be specified by the Engineer.

3.2 Unless otherwise specified all steel bars for reinforcements of concrete
shall conform to ASTM A615, Grade 60 deformed hot rolled billet steel bars with
a minimum yield strength of 60,000 psi.

3.3 Reinforcement shall be obtained only from manufacturers approved by the


Engineer. Each consignment of reinforcement steel shall be accompanied by the
manufacturer's certificate or shall refer to a previous certificate, if the
consignment is from the same batch, showing that the reinforcement steel
complies with the specified requirement. If such certificate is not made
available or if the Engineer considers that the manufacturer's tests are
inadequate, samples shall be taken for acceptance test from different
consignments as the Engineer may direct and shall be tested at the contractor's
cost. Should the result of such tests show that the sample does not meet with
the specifications the whole consignment shall be rejected and removed from the
site at the Contractor's cost.

3.4 Reinforcement shall be free from all loose or flaky rust and mill scale,
or coating, including ice, and any other substance that would reduce or destroy
the bond. Reduced section steel reinforcement shall not be used.

4. DELIVERY & STORAGE

4.1 Delivery

Steel reinforcement bars shall be kept in bundles firmly secured and


tagged. Each bar or bundle of bars shall be identified by marks stamped on hot
or cold or painted on or by any other means. The identifying marks shall contain
the following information:
• Name of the producer or his trade.
• Standard to which the bars have been manufactured.
• The class type and strength.
• The diameter.
• The number of the test certificate.

4.2 Storage

The method of storage shall be approved by the Engineer. Reinforcing bars


shall be stored in racks or platforms above the surface of ground and shall be
protected free from scaling, rusting, oiling, coatings, damage, contamination
and structural defects prior to placement in works. Bars of different diameters
and grades of steel reinforcement shall be kept separately.

5. BAR BENDING SCHEDULES

The Contractor shall prepare bar bending schedules of all the reinforcing steel
bars and these bar bending schedules shall be submitted to the Engineer for his
approval. All detailing shall be done as per AC, standards AC1-315 & 318. The
Contractor shall obtain approval of the bar bending schedules before starting
actual bar bending works.

6. FABRICATING, BENDING & PLACING

6.1 Bars used for concrete reinforcement shall be fabricated in accordance


with the dimensions shown in the bar-bending schedule approved by the Engineer.

6.2 The cutting tolerance for all bars shall be +/- 1 inch.

6.3 Where an overall or an internal dimension of a bent bar is specified in


the schedule, the bending tolerance, unless otherwise stated, shall be as in
Table 1.

Table 1: Bending Tolerances

Dimensions of bent bars Tolerance


Over Upto & including plus Minus
Feet Feet inch inch
-- 3 1/5 1/5
3 6 1/5 1/5
6 -- 1/5 1

6.4 Reinforcement shall not be bent or straightened in a manner that will


injure the material.
No bars shall be bent twice in the same place, nor shall they be straightened
after bending.
Unless permitted by the Engineer, reinforcement shall not be bent after being
partially embedded in hardened concrete.
Bars which depend for their strength on cold working shall not be heated for any
reason.
6.5 Welding shall be permitted for bars only under suitable conditions and
with suitable safeguards in accordance with BS 693, BS 1856, or AWS D12.1,
provided the type of reinforcing bar has the required welding properties. Tack
welding may be used to fix in position bars that cross each other, only with
prior approval of the Engineer. Welding shall be done as in lectum structural
steel & metal works.

6.6 No splice of reinforcement shall be made except as shown on the working


drawings.

6.7 Reinforcement is to be accurately placed as shown in the drawings, and


secured against displacement by using 18-20 gauge black annealed wire ties or
suitable slips at intersections and supported from the formwork by using
concrete, metal or plastic chairs and spacers or hangers of an approved pattern.
Where concrete blocks are used for ensuring the cover, they shall be made of
mortar not leaner than 1 part of cement to 2 parts of sand.

Where the concrete surface will be exposed to the weather in the finished
structure, the portions of all accessories in contact with the formwork shall be
galvanized or shall be made of plastic.

6.8 Concrete clear cover for reinforcing steel shall be as follows:

Structural Members Minimum Cover


(inches)
a. Concrete cast against and permanently exposed 3
to earth
b. Concrete exposed to earth or weather
For reinforcing bars #6 or larger 2
For reinforcing bars less than #6 1-1/2
c. Concrete not exposed to weather or in contact
with ground
Slabs, Walls ¾
Beams, Columns (Primary Reinforcement 1-1/2

6.9 Bars shall be placed to the following tolerances:

1. Concrete cover to formed surfaces +/- 1/4”


2. Minimum spacing between bars - 1/4”
3. Top bars in slabs and beams
a. Members 8 inch deep or less +/- 1/4"
b. Members more than 8 inch but not over 2 +/- 1/2”
feet deep
c. Members more than 2 feet deep +/- 1”
4. Crosswise of members spaced evenly
within 2 inch
5. Lengthwise of members +/- 2”

6.10 Bars may be moved as necessary to avoid interference with other


reinforcing steel, conduits, or embedded items. If bars are moved more than one
bar diameter or enough to exceed the above tolerances, the resulting arrangement
of bars shall be subject to approval of Engineer.
6.11 Vertical bars in columns shall be offset at least one bar diameter at
lapped splices. To ensure proper placement, templates shall be furnished for all
column dowels.

6.12 Exposed reinforcement intended for bonding with future extensions is to be


effectively protected from corrosion. Protection is also to be provided to
reinforcement partly built into concrete where the exposed part is to be built
into later concrete.

6.13 All reinforcement, at the time concrete is placed, shall be free of loose
mill scale, loose rust, mud, oil & grease, or other materials that may adversely
affect or reduce the bond.

6.14 No concreting is to be carried out until the reinforcement has been


checked and approved by the Engineer.

7. MEASUREMENT & PAYMENT

7.1 General
Except otherwise specified herein or elsewhere in the Contract Documents,
no measurement and payment will be made for the under mentioned specified works
related to the relevant items of the Bills of Quantities. The cost thereof shall
be deemed to have been included in the quoted unit rate of the respective items
of the Bills of Quantities.

The rates quoted by the Contractor in the Bill of Quantities shall


include work to be executed under these specification in any floor and at any
height except where otherwise specifically stated in the relevant item of Bill
of Quantities and the Contractor shall not be entitled to any claim or claim any
compensation on this account.

Providing and installing cover blocks, chairs, supports, hooks, spacers,


binding wires, and laps not shown on drawings including wastage and rolling
margin. Laps shown on drawings shall be payable.

7.2 Mild Steel and Deformed/Tor Steel

7.2.1 Measurement~

Measurement for acceptably completed works of reinforcement according to


bar bending schedules approved by the Engineer shall be made by weight.

Computed on the bases of Table 2, the Contractor shall not claim for the
difference in the actual weights of bars and their standard weights given in
Table-2.

Table-2: Standard Weights of Bars

Nominal Bar Diameter, inches* Bar No. Weight, Lbs/ft


1/4” #2 ?? 0.167
3/8” #3 0.376
1/2” #4 0.668
5/8” #5 1.043
3/4" #6 1.502
7/8” #7 2.044
1” #8 2.670
1-1/8” #9 3.400
1-1/4” #10 4.303
1-3/8” #11 5.313

2204.60 Lbs = 1.00 tonne


*to the nearest 1/7"

7.2.2 Payment:

Payment will be made for acceptable measured quantity of reinforcement on the


basis of unit rate per tonne quoted in the Bill of Quantities and shall
constitute full compensation for all the works related to the item.

The rate quoted include all lead/lift required for steel fabrication & placement
at/in any floor and at any height as per drawings.

SECTlON-6
CEMENT CONCRETE BLOCK MASONRY

1. GENERAL REQUIREMENTS

The Contractor shall examine all other Sections of the Specifications for
requirements which affect work of this Section, whether or not such work is
specifically mentioned in this Section.
The Contractor shall coordinate work with that of all other trades
affecting/affected by work of this section.

2. SCOPE

The scope of work consists of the installation of all materials to be


furnished under this section, and without limiting the generality thereof,
includes all equipment, labour and services required for all masonry work,
including all items incidental thereto, as specified herein and as shown on the
Drawings.

3. MATERIALS

The sources of supply of all materials, to be provided by the Contractor


for the manufacture of blocks, shall be approved by the Engineer before these
materials are delivered to the site. All materials shall comply with the
requirements of these specifications except where otherwise agreed to, or
required by the Engineer whose approval shall be obtained in writing.

3.1 Portland Cement shall conform to B.S. 12

3.2 Sand shall be clean, hard sharp and free from adherent coatings and shall
be washed if so directed by the Engineer. Sand shall be free from clay lumps and
pellet, laminated materials, salts, alkali and other impurities likely to affect
adversely the strength of the mortar. The grading of the sand shall conform to
B.S.S. 1200 reproduced here.

B.S. Sieve % Passing by Weight


3/16 100
No.7 90-100
No.14 70-100
No.25 40-100
No.52 15-70
No.100 0-15

3.3 Coarse aggregate shall comply with requirements of B.S. 812 in respect of
their petrological, physical and chemical properties. Aggregates which do not
satisfy the specified requirements in the aforementioned standard shall be
rejected by the Engineer. The maximum size of aggregate as defined herein shall
be 3/4". The grading of the fine and coarse aggregates to be used in manufacture
of blocks shall conform to the requirements given for this purpose in B.S. 882.
The samples of aggregate to be used shall be submitted to the Engineer for
approval and the aggregate actually used for the works shall be similar in all
respects to the approved samples. All aggregate shall be stored in such a manner
as to avoid contamination of the aggregate by matter harmful to the quality of
concrete for blocks, to be manufactured from it. The Engineer reserves the right
to require the Contractor to wash and/or screen all aggregate if the method of
storage or the nature of the aggregate is such that the aggregate contain matter
harmful to the concrete. Alternatively, the Engineer may reject any aggregate
which has been contaminated in such a manner that screening and/or washing will
not remove the impurities.

3.4 All water used for block work shall comply with B.S. 3418 "Tests for water
for making concrete".

4. CONCRETE BLOCK MANUFACTURING

4.1 The Solid or Hollow blocks shall be machine molded. The block making
machines shall be of the standard approved by the Engineer. They shall be
operated according to the instructions laid down by the manufacturers.

4.2 The blocks shall be continuously water cured by sprinkling for a minimum
of 10 days and covered between sprinkling operations with polyethylene sheeting.
After the 10 days water curing period the blocks shall be air dried. Under no
circumstances will blocks be used in the construction work until they are
completely dry. During curing period no surfaces of the block will be allowed to
dry.

4.3 Cured concrete blocks shall be stored off the ground, stacked on levelled
platforms to allow for air circulation under stacked units. Units shall be
covered and protected against getting wet.

4.4. Care shall be exercised in the handling of all concrete blocks. No damaged
blocks shall be used in the work.

4.5 The Hollow blocks shall be manufactured as shown on the drawing. These
blocks units shall be provided by the Contractor for use where required in
building structures from approved type of materials. Units shall have uniformly
fine smooth surfaces of uniform colour. These shall be free of any honey-combing
or other imperfections or deformations, all edges should be true and straight,
and at right angles with each other and without any chipped or otherwise broken
edges.

4.6 The blocks cast on different dates shall be stacked separately and must be
labelled showing the date on which they were cast.

5. STORAGE

All blocks shall be stacked in a quantity not exceeding 3,000 blocks in


each stack, height of stack, being limited to 5.0 ft. The stacking shall be done
in such a manner as to avoid smearing of the blocks in the lowest part of the
stacks with soil.

6. SAMPLING AND TESTING

6.1 Samples of blocks properly cured and dried shall be tested before
installation at least one month before they are to be used. The concrete blocks
shall meet the following requirements. Besides the following tests the samples
of block shall have to be approved by the Engineer before use in the building.

6.2 Concrete blocks shall have a minimum compressive strength of 1300 psi at
28 days.

6.3 Water absorption - 1.5 Ibs per ft3 for masonry.

6.4 Moisture content - 40% of total absorption value of the blocks at the time
of installation.

6.5 Field tests of moisture content of concrete masonry blocks will be made as
follows:

• Test samples shall be taken from on site stock piles and shall be
representative of the blocks being currently used in the work.

• At least one check will be made per 3,000 blocks or equivalent.

• Each field check test will be made on 3 specimen of each size of blocks.
The entire stock of blocks out of which the samples have failed to meet
the specifications in the tests shall be rejected.
6.6 Stock of blocks which fail to comply with the specifications will be
rejected except that in the case of rejections based on field check moisture
content the contractor has option of further drying the units until they are
retested and comply with the moisture content requirements.

6.7 Sampling and testing as specified above and required by the Engineer will
be at the expense of the Contractor.

7. MORTAR PROPORTIONS AND MIXING~

7.1 Cement and sand shall be mixed together and thoroughly incorporated with a
proper quantity of water according to the proportion of mix as indicated in the
Drawings or the Bill of Quantities. The mortar shall be used within 30 minutes
of mixing and no mortar that has become partially set shall be re-used.

7.2 All mortar shall be mixed in a manner approved by the engineer. The mix
shall be thoroughly mixed together.

7.3 The amount of water shall be the minimum required to ensure sufficient
workability and shall be varied to suit the moisture content in the sand.

8. REINFORCING AND ANCHORS

Unless otherwise stated reinforcing and anchors shall conform to under mentioned
sizes:

8.1 Reinforcing bar anchors shall be 3/8" dia. deformed bar minimum 10" long.

8.2 Tie bars shall be provided at the rate of 3.0 ft c/c horizontal, and 1'-6"
vertical, of the size and shape as shown in the drawings in cavity block masonry
with insulation.

9. REINFORCED BLOCK MASONRY

Where specified, reinforced Block Masonry shall be installed by


incorporating two Mild Steel reinforcing bars of 1/4" dia. laid horizontally in
the mortar bed in alternate courses of Block Masonry in the entire length of the
wall. The cost of reinforcing rods shall be included in the unit rate of the
reinforced Block Masonry item.

10. DOVE TAIL ANCHORS

Dove tail anchors made of G.I. steel flats 4" x l' x 1/2" size shall be anchored
to all ACC columns by embedding a female receptacle to snugly fit the dove tail
anchor. The female receptacle shall be embedded in the concrete columns and the
dove tail anchors shall be inserted in the column, receptacle along with the
masonry courses and embedded in the mortar bed. Dove tail anchors shall be
installed on masonry horizontal joints on ever third course.

11. ERECTION
11.1 Blocks shall be laid true to line, level and laid in accurately spaced
courses in stretching bond with vertical joints of each course located at centre
of units in alternate courses below. Vertical joints shall be buttered the
entire height of blocks. Each course shall be bonded at corners and
intersections of walls and shall be properly bonded. Courses of block shall be
kept in plumb throughout and corners, reveals shall be true and in plumb.

11.2 Standard width of mortar joints for both horizontal and vertical joints
shall be 3/8" (maximum). Mortar joints in walls shall have full mortar coverage
on vertical and horizontal faces between the blocks. Mortar joints on wall
including astruck joints, shall be thoroughly compacted and pressed tight
against the edges of the blocks with proper tools. Blocks terminating against
soffits of beam or slab construction shall be wedged tight with wedges and the
joints shall be packed solidly with mortar between the top of the block and the
bottom of beam or slab.

11.3 Control expansion joints shall be kept free from mortar or other debris.

11.4 Unless otherwise shown on the drawings, or specified by the Engineer, the
spaces around door frames and other material or built in items shall be solidly
filled with mortar. Spaces around the door holdfasts shall be filled in with
class 'C' concrete. Work required to be built in with masonry including door
frame anchors, wall plugs, dovetail anchors and accessories shall be built in as
the erection progresses.

11.5 The block work shall be carried up in uniform manner and no portion shall
be carried more than 3 ft above the adjoining one at any time. All masonry shall
be kept strictly true and square and the whole properly bonded together and
levelled round each floor.

11.6 Sleeves, Chases and holes shall be built in as construction proceeds,


chiselling of completed walls or the formation of holes shall only be carried
out with the approval of the Engineer.

11.7 Lintels where required in concrete masonry unit partitions, unless


otherwise shown on drawings, shall be constructed using R.C.C. lintels as
specified under section of R.C.C. of the specifications and as shown on the
structural drawings. All lintels shall extend at least 9" on each side of the
opening for bearing.

12. SCAFFOLDING

12.1 Contractor shall provide safe scaffolding of adequate strength for use of
workmen at all levels and heights at his own expense. Scaffolding which is
unsafe in the opinion of the Engineer shall not be used until it has been
strengthened and made safe for use of workmen. Cost of scaffolding etc., shall
be included by the Contractor in the unit rate for masonry items.

12.2 Damage to masonry from scaffolding or from any other object shall be
repaired by the Contractor at his own cost.

13. TOLERANCES

All block work shall be erected plumb and true to line and level with the
maximum variation in any story height of any length of wall being 1/25 of an
inch in 3 ft. The maximum tolerance in the length, height or width of any single
masonry unit shall be +/- 1/8 inch.

14. DAMP PROOF COURSE

All damp proof course unless otherwise specified, shall consist of class
'C' cement concrete 2 inches thick, mixed with 5 Ibs of pudlo per bag of cement,
or other approved quality water proofing compound as per manufacturer's
specifications, shall be laid at required levels as per drawings and
instructions of the Engineer. The D.P.C. shall be tamped, consolidated, levelled
and edges and comers made to the requirements of concerned drawings including
finishing and curing complete.

14. MEASUREMENT AND PAYMENTS

Masonry work will be paid for according to the actual area of masonry for the
required thickness of Masonry Work. All the openings left in the masonry walls
will be deducted.

The rate for this item shall cover:

14.1 The cost of material, labour, curing, scaffolding and appliances at site
and all operations, in connection with the installation of masonry in accordance
with the instructions of the engineer, Schedule of Quantities and as specified
above.

14.2 Cutting and patching work required for the installation of pipes.

14.3 The cost of all the works involved within the scope of this specifications
as per all the drawings and conditions of contract are covered only within the
quoted rate of items of the B.O.Q.

14.4 Unless due to change of Technical Specifications or change in the


Drawings, no payment for separate items shall be made.

14.5 Works shall be measured not done as fixed in position, acceptably


completed as drawings and instructions of the Engineer. Each measurement shall
be taken to the nearest 1/2", this rule shall not apply to any dimensions stated
in descriptions.

14.6 Masonry work will be paid for according to the actual costs mentioned in
the B.O.Q. All the openings left in the masonry walls will be deducted.

14.7 Providing and fixing all joint reinforcing bars, reinforcing bar anchors
and dovetail anchors shall not be measured or paid for and deemed to be included
in the unit rate of masonry work.

14.8 No payment for damp proof course shall be made unless otherwise stated in
the Bill of Quantities.

14.9 In case of different thicknesses of slab in different areas or rooms or


for any other reason whatsoever, if chiselling of masonry is required, the
contractor shall do so at his own cost. Where for any reason whatsoever, the
height of the wall is short of ceiling height, the actual height shall be made
good with 1:2:4 nominal mix concrete. This concrete shall neither be measured
nor be paid under item of concrete but will be paid for under the item of wall
masonry. Similarly, where the lintel heights are such that the Contractor has to
chisel the masonry or provide cast-in-place concrete to make up the height of
the course, no payment will be made for chiselling, but where such cast-in-place
concrete is provided, payment for the same will be made at the unit rate of
masonry.

SECTION - 7
CEMENT PLASTER AND SCREED

1. SCOPE

The work under this section of the Specifications consists of furnishing all
plant, labour, equipment, appliances, and materials and in performing all
operations in any floor and at any height connection with providing and applying
of cement plaster complete in strict accordance with this section of the
Specifications and the applicable drawings and subject to the terms and
conditions of the Contract.

2. MATERIAL

2.1 Cement, aggregates and water shall conform to requirements specified in


the section "Plain and Reinforced Concrete" and as approved by the Engineer.

3. PREPARATION OF SURFACE TO BE PLASTERED

3.1 Concrete surface to be plastered shall be cleaned to remove all grease,


form oil and other surface impurities, which will otherwise adversely affect the
adhesion of plaster to the surface concerned. The surface of all-concrete
ceilings, beams and columns shall be lightly hacked by approved means to give
the required key for plastering.

4. APPLICATION OF PLASTER AND LAYING OF SCREED

4.1 The plaster of thickness less than the specified thickness shall be
rejected. If the plaster is to be more than 1/2" thick, it shall be done in two
coats. The surface of first coat shall be made rough before the second coat is
applied.

4.2 The plaster shall not have wavy surface and shall be perfectly in plumb.

4.3 Water proof screed on inside tank floor shall be 3/4" thick, 1:2:4 cement
concrete mixed with approved water proofing agent.

5. METAL LATH
Metal lathing shall be fabricated from sheet steel and shall be of uniform
quality and free from flaws broken strands, cracks and corrosive pitting, shall
be rectangular and true to shape and shall comply with BS-1369.

6. INTERNAL / EXTERNAL PLASTER

6.1 Where specified in the Drawings external surface shall have an average
1/2" thick plaster finish, consisting of a base coat of 1:4 cement sand mortar
in Grey cement and the finish coat of smooth plaster as shown on the Drawings
and as directed by the Engineer.

6.2 Where specified in the Drawings all internal plaster shall have an average
1/2" thick consisting of base coat of 1:3 / 1:4 cement sand mortar in grey
cement and finish coat of smooth plaster as shown on the Drawings and as
directed by the Engineer.

7. MEASUREMENT AND PAYMENT

7.1 General

Except otherwise specified herein or elsewhere in the Contract Documents,


no measurement and payment will be made for the under mentioned specified works
related to the relevant items of the Bill of Quantities. The cost thereof shall
be deemed to have been included in the quoted unit rate of the respective item
of the Bill of Quantities.

The rates quoted by the Contractor in the Bill of Quantities shall include
work to be executed under these specification in any floor and at any height
except where otherwise specifically stated in the relevant item of Bill of
Quantities and the Contractor shall not be entitled to any claim or claim any
compensation on this account.

7.1.1 Metal lath over reinforced concrete and masonry joint.

7.1.2 Joints, junctions, corners, beads, drip course edge, roundings, and
aluminium U/Y channels in groves etc.

7.1.3 More than one layer due to any unevenness in the finished works and base
coat plaster in stucco plaster including marble chips/colour pigments.

7.1.4 Cutting & patching of all defective works.

7.1.5 Surface preparation, cleaning and protection as specified.

7.1.6 Marble chips & pigments in stucco plaster.

7.1.7 Water proof admixture as approved by the Engineer.

7.1.8 Scaffolding and curing etc.

7.2 MEASUREMENT
Measurement of acceptably completed works of plaster and screed will be
made on the basis of number of square feet of the surface area of the plaster as
shown on the Drawings, or as directed by the Engineer.

7.3 PAYMENT

Payment will be made for acceptable measured quantity of plaster and screed on
the basis of unit rate per square feet quoted in the Bill of Quantities and
shall constitute full compensation for all the works related to the item.

SECTION-8
PAINTING

1. SCOPE

The work under this section of the Specifications consists of furnishing all
materials, plant, labour, equipment, appliances and performing all operations in
any floor and at any height in connection with surface preparation, mixing,
painting concrete works, gates, frames, walls, ceilings and all such surfaces as
shown on the Drawings and/or as directed by the Engineer. The scope of this
section of specification is covered with detailed specifications as laid down
herein.

2. APPLICABLE STANDARDS

Latest editions of following British Standards are relevant to these


specifications wherever applicable.

BSI # (British Standards Institution)

245 Specification for mineral solvents (white spirits and related hydrocarbon
solvents) for paints and other purposes.
2521 Lead-based priming paint for wood work.
2523 Lead based priming paint for iron and steel.
2569 Sprayed metal coatings.
4800 Paint colours for building purposes.
CP.231 Painting of building.
CP.3012 Cleaning and preparation of metal surfaces.

3. GENERAL

3.1 Except as otherwise specified, all painting shall be applied in conformity


with BS CP 231 "Painting of Building" as applicable to the work.

3.2 The Contractor shall repair at his own expense all damaged or defective
areas of shop-painted metal work and structural steel work. Metal surfaces
against which concrete is to be placed will be furnished shop-painted and shall
be cleaned prior to being embedded in concrete.

3.3 Except as otherwise specified all concrete and plastered surfaces are to
be painted.

3.4 The Engineer will furnish a schedule of colours for each area and surface.
All colours shall be mixed in accordance with the manufacturer's instructions.

3.5 Colours of priming coat (and body coat) where specified, shall be lighter
than those of finish coat. The Engineer shall have unlimited choice of colours.

3.6 Samples of all colours and finishes shall be prepared in advance of


requirement so as not to delay work and shall be submitted to the Engineer for
approval before any work is commenced. Any work done without such approval shall
be redone to the Engineer's satisfaction, without additional expense to the
Employer. Samples of each type of paint shall be on separate 12" x 12" x 1/8"
tempered hard board panels. Manufacturer's colour chart shall be submitted for
colour specifications and selection.

4. MATERIALS

4.1 All materials shall be acceptable, proven, first grade products and shall
meet or exceed the minimum standards of reputable manufacturers as approved by
the Engineer.

4.2 Colours shall be pure, non-fading pigments, mildew-proof sun-proof, finely


ground in approved medium. Colours used on-plaster and concrete surfaces shall
be lime-proof. All materials shall be subject to the Engineer's approval.

4.3 All synthetic enamel paints and primers for structural steel works, metal
work and wood works will be the best available of its type and shall be approved
by the Engineer prior to its procurement.

4.4 Approved quality Weather Shield / Weather Coat paint shall be used for
painting the exteriors of the structures or other surfaces where specified on
the drawings as directed by the Engineer.

4.5 The plastic emulsion paint, vinyl emulsion paint or similar as approved by
the Engineer shall be used for interior surfaces.

4.6 All material for Bitumen painting shall consist of Bitumen grade 10/20. It
shall be used for foundations or wherever recommended by the Engineer. The rate
of application in foundations shall not be less than 5.0 Ib/10 sft each coat.

4.7 Only paints manufactured by ICI or Berger shall be used in this Project.
All material shall be delivered to site in their original unbroken containers or
packages & bear the manufacturer's name, label, brand & formula & will be mixed
and applied in accordance with their directions.

5. DELIVERY STORAGE AND CONTAINER SIZES

Paints shall be delivered to the site in sealed containers, which plainly


show the type of paint, colour (formula or specifications number) batch number,
quantity, date of manufacture, name of manufacturer and instructions for use.
Pigmented paints shall be supplied in containers not larger than 20 litres. All
materials shall be stored under cover in a clean storage space, which should be
accessible at all times to the Engineer. If storage is allowed inside the
building, floors shall be kept clean and free from paint spillage.

6. SURFACE PREPARATION

6.1 All oil, grease, dirt, dust, loose mill scale and any other foreign
substance shall be removed from the surface to be painted, polished and white
washed by the use of a solvent and clean wiping material. Following the solvent
cleaning, the surfaces shall be cleaned by scrapping, chipping, blasting, wire
brushing or other effective means as approved by the Engineer.

6.2 In the event the surfaces become otherwise contaminated in the interval
between cleaning and painting, re-cleaning will be done by the Contractor at no
additional cost.

6.3 Surfaces of stainless steel, aluminium, bronze, and machined surfaces


adjacent to metal work being cleaned or painted shall be protected by effective
masking or other suitable means, during the cleaning and painting operations.

6.4 All the surfaces to be painted with approved quality paint shall be free
from dust, dirt, fungus, lichen, algae etc. Oil paint, varnish and lime wash
should always be removed by scraping and washing.

6.5 All surfaces to be bitumen painted shall be thoroughly cleaned of any


accretion, dust, dirt etc. by scraping, wire-brushing or as directed by the
Engineer. The surface shall be primed with a coat of asphalt oil used at the
rate of not less than 0.50 pound per square foot.

6.6 No work in this section shall be allowed until all surfaces or conditions
have been inspected and approved by the Engineer.

7. APPLICATION

7.1 All paint and coating materials shall be in a thoroughly mixed condition
at the time of application. All work shall be done in a workman like manner,
leaving the finished surface free from drips, ridges, waves, laps, and brush
marks. All paints shall be applied under dry and dust free conditions. Unless
approved by the Engineer paint shall not be applied when the temperature of the
metal or of the surrounding air is below 7 degrees centigrade. Surfaces shall be
free from moisture at the time of painting.

7.2 All primary paint shall be applied by brushing. The first coat of paint
shall be applied immediately after cleaning. When paint is applied by spraying,
suitable measures shall be taken to prevent segregation of the paint in the
container during painting operation.

7.3 Effective means shall be adopted for removing all free oil and moisture
from the air supply lines of the spraying equipment. Each coat of paint shall be
allowed to dry or harden thoroughly before the succeeding coat is applied.
Surfaces to be painted that will be inaccessible after installation shall be
completely painted prior to installation.
7.4 Coats of Weather Shield / Weather Coat paint shall be applied in
accordance with the manufacturer’s instructions or as directed by the Engineer.
Only as much material should be mixed, as can be used up in one hour. Over-
thinning will not be permitted. Second coat shall be applied after leaving for
at least overnight.

7.5 Where shown on Drawings all exterior finishes shall be painted with
Weather Shield / weather coat paint in approved colours as per manufacturer’s
specifications. The number of coats shall be as shown on the drawings or as
directed by the Engineer.

7.6 All wooden doors shall be painted with approved synthetic enamel paint as
per manufacturer’s recommendation and instructions and after approval of the
Engineer.

7.7 Plastic emulsion paint, vinyl emulsion paint or matt enamel paint of the
approved make and shade shall be applied to surfaces as shown on Drawings as per
manufacturer’s instructions. The number of coat shall be as indicated on the
Drawings or as directed by the Engineer.

7.8 Two coats of hot bitumen paint shall be applied to exposed concrete
surfaces in contact with earth. The first coat shall be allowed to dry for about
six hours before applying the second coat. During the operation of painting
great care should be taken to avoid air bubbles. The manufacturer’s instructions
and Engineers directions shall be complied with.

8. JOB CONDITIONS

8.1 Observe manufacturers recommended minimum and maximum temperature but do


not apply paint or finish to any surface unless ambient temperature is 10 degree
C or above and less than 43 degree C. No painting shall be done above 90%
relative humidity.

8.2 Place drop cloths to adequately protect all finished work.

8.3 Remove and replace all items of finish hardware, device plates,
accessories, lighting fixtures or other removable items.

8.4 In no case shall any finish hardware or other finished item that is
already fitted into place be painted, unless otherwise specified.

9. QUALITY ASSURANCE

All paint for anyone surface shall be top quality, of one manufacturer and
approved by the Engineer. Deep tone accent colours shall be used and the
unavailability of final coat colours may be the basis for rejecting materials
for anyone surface.

10. SCHEDULE OF MEASUREMENT OF PAINT AREA:

10.1 Irrespective of prime coats and number of paint coats applied to exposed
painting surface area of column, walls, projections, ceilings, false ceilings
and other surfaces (Except gates, doors, windows and ventilators) shall be
measured as per actual paint surface area for single time only and paid in
accordance with quoted rate of Bill of Quantities.

11. MEASUREMENT AND PAYMENT

11.1 General

Except otherwise specified herein or elsewhere in Contract Documents, no


measurement and payment will be made for the under mentioned specified works
related to the relevant items of the Bill of Quantities. The cost thereof shall
be deemed to have been included in the quoted unit rate of the respective items
of Bill of Quantities.

The rates quoted by the Contractor in the Bill of Quantities shall include
work to be executed under these specification in any floor and at any height
except where otherwise specifically stated in the relevant item of Bill of
Quantities and the Contractor shall not be entitled to any claim or claim any
compensation on this account.

11.1.1 Preparatory works, including preparatory materials, scraping, scratching,


sand blasting, cleaning, prime coating, priming, protection of finished works
etc.

11.1.2 Polishing works, including preparatory materials, scraping, cleaning,


sanding etc.

11.1.3 Painting work on steel & wooden surfaces.

11.1.4 Before application of paint on existing surface the old paint surface
shall be removed existing paint, filling of cracks, surface preparation and
application of primer coat, if any.

11.2 Measurement

Measurement of acceptably completed respective type of painting works will


be made on the basis of net actual areas in square feet of the surface painted
as shown on the Drawings or as directed by the Engineer.

11.3 Payment

Payment will be made for acceptable measured quantity of respective type


of painting on the basis of unit rate per square feet quoted in the Bill of
Quantities and shall constitute full compensation for all the works related to
the item.
Further Technical Specs. (Draft)

Granolithic Finish

Granolithic finish is used to provide a hard wearing, abrasion resistant


and dustless surface to concrete floors, stair treads, etc. and also where
smooth polished and rich surface is wanted. Granolithic concrete is composed of
cement and specially selected aggregate of hard rock (gravel) and graded from 10
mm down to 150 micron (No.100 BS) sieve. Mix proportions are normally 1:2 or 1:3
by volume (all-in grit aggregate); or may consist of 2 parts cement, 1 part of
fine aggregate and, 4 parts of coarse aggregate. Coarse aggregate is graded from
10 mm or 6 mm down to 2.36 mm (No.7 BS) sieve and fine aggregate from 4.75 mm
down.
The all-in aggregate specified above may consist of 3 parts of 10 mm
screenings and 1 part of 2.36 mm screenings, with sufficient sand added to make
a workable mix. Particular care should be taken to sift out all dust or fine
material and to use minimum amount of mixing water which will give adequate
workability and will permit of satisfactory finishing.

Best results are obtained where granolithic is laid before the base
concrete has set. Many specifications require this to be done within 30 minutes
after placing of base concrete, and in any case it should be done within two
hours. The granolithic layer should be of 12 mm minimum thickness. The base
concrete need not be smooth finished. The granolithic should be well tamped into
place, screeded and lightly floated to required levels. Finishing, as described
later, should be left for at least an hour after laying. Where the base concrete
has hardened, its surface should be roughened by hacking, laitance removed and
well saturated with water and cleaned. Immediately before laying granolithic,
any excess water should be removed and the surface of the concrete covered with
a thin layer of neat cement grout well brushed in. The granolithic should then
be laid as described above but in this case minimum thickness must be increased
to at least 25 mm and preferably 40 mm. An adequate key between the base
concrete and the top finish is essential where the base concrete has set.

You might also like