Building House-Critical Path Method
Building House-Critical Path Method
http://www.home-building-answers.com/critical-path-method.html
First let's review why you would even want to do this! Because it's going to reveal to you the sequence of home building events - which activities follow which other activities - and which activities can be going on at the same time. Then you put some time durations on each home building activity and you'll have a timeline for your project and a scheduling tool par excellence! Follow along. You're going to enjoy this. And you're going to be really surprised at what a valuable tool it will be when construction begins and you are managing the construction on a day-to-day basis.
A CPM EXAMPLE
In a CPM diagram, each activity is represented by an arrow. Each activity must have a beginning (either at the beginning of the project or at the end of some preceding activity) and an end (either just before the beginning of some succeeding activity, or at the end of the project). The following figure illustrates this principal. Note: It's just an example! We know it's not all the activities you'll need to build your new home.
CLEAR LOT POUR FOOTINGS FRAME HOUSE INSULATE DRYWALL PAINT EXTERIOR SIDING/ROOFING
1z7
10/6/2013 4:24 PM
http://www.home-building-answers.com/critical-path-method.html
The activities are represented by the arrows which begin and end with the circles 0, 10, 20,30, 40, 50, and 60. The circles are called events, and simply designate the point in time at which one activity has ended and another is about to begin. The numbers in the event circles are arbitrarily assigned and have no meaning other than their use to name the arrows (activities). For example, the Clear Lot activity is called Activity 0-10. The project starts at the circle labeled 0 and proceeds to the right.
ACTIVITY DURATION
Notice the number under each arrow. This represents the number of days it will take to complete each activity. You will see that insulating, hanging the drywall, and painting will take a total of 5 days, while exterior siding and roofing will only take 2 days. It would be possible to wait three days after the framing is completed before starting on the siding and roofing and still complete the project on time.
FLOAT TIME
There is said to be three days of Float Time in activity 30-60. That is because while activity 30-60 will only take two days to complete, it is scheduled to be done sometime during the five day period when insulation, drywall, and painting are being completed. Activity 30-60 doesnt have to be started immediately after the framing is completed. You could wait until after the first day of drywall work before starting 30-60 without holding up the job.
CRITICAL ACTIVITIES
Any activity which has float time is not on the critical path. All other activities in our example are critical. A delay in completing any of them will delay the completion of the job. Notice that if the float time in activity 30-60 is used up, then that activity also becomes critical. The Critical Path is that path through the Critical Path Diagram which links critical activities sequentially. A delay in any activity on the Critical Path will delay completion of the job.
PURCHASE LOT PLANS AND SPECIFICATIONS ESTIMATE SECURE CONSTRUCTION LOAN SECURE BUILDING PERMIT(S) LINE UP SUBS AND SUPPLIERS
The time required to accomplish these things could vary considerably from situation to
2z7
10/6/2013 4:24 PM
http://www.home-building-answers.com/critical-path-method.html
situation, so we have shown their relationship to the process in their own diagram below. No time frame has been assigned to these activities. You may take six days or six months to find a lot. It really doesnt matter. But once you start construction, it should proceed in a consistent, well organized manner.
Note that activities 0-10 and 10-15 could be reversed. In other words, you could start with a lot and design a home to fit it, or you could design your home and then find a lot that will accommodate it
ACTIVITIES
LOT PREPARATION (CLEARING AND ROUGH GRADING) FOOTINGS FOUNDATION SOIL TREATMENT (SPRAYING TO PREVENT TERMITES) FRAMING (WOOD STRUCTURE OF THE HOME PLUS SHEATHING) ROOFING SET WINDOWS AND EXTERIOR DOORS CORNICE, VENEER, AND EXTERIOR TRIM EXTERIOR PAINTING GUTTERS AND DOWNSPOUTS SET FIREPLACE ROUGH PLUMBING (PIPES IN SLAB, PIPES IN WALLS) ROUGH ELECTRICAL (WIRING IN WALLS, SWITCH AND OUTLET BOXES INSTALLED) ROUGH HVAC (DUCTS IN WALLS) TELEPHONE PRE-WIRE (TELEPHONE WIRE IN WALLS) FRAMING INSPECTION INSULATION DRYWALL INTERIOR DOORS AND TRIM
3z7
10/6/2013 4:24 PM
http://www.home-building-answers.com/critical-path-method.html
APPLIANCES CABINETS CERAMIC TILE PAINTING HANG WALL PAPER FINISH PLUMBING (WATER HEATER, SHOWERS, TUBS, SINKS, FAUCETS) FINISH ELECTRICAL (LIGHT FIXTURES, SWITCHES, OUTLETS, FANS, SMOKE DETECTOR) FINISH HVAC (FURNACE, A.C., AIR HANDLER, REGISTERS, THERMOSTAT) GLASS AND HARDWARE FLOOR COVERINGS WALKS, DRIVES, AND PATIOS DECK FINISH GRADING (FINAL ELEVATIONS SET, TRASH REMOVED) LANDSCAPING FINAL INSPECTION PUNCH OUT (ALL REMAINING UNCOMPLETED AND DEFECTIVE WORK FINISHED) TURN UTILITIES ON
The list itself more or less shows the order in which activities occur. But it falls short of showing which activities are dependent on each other and which activities can occur simultaneously. To discover these relationships, we can put them into a CPM diagram.
2. Notice that the construction diagram shows the home being built in a total of 59 working days (about twelve weeks). There are no idle days shown - that is, days when the home sits with no work being done on it. Youll probably have some of these days! You may also experience some delays because of materials shipments, inspectors, subcontractors that don't show up, and bad weather. So dont be surprised if you take longer than 59 working days. This is an ideal. If you take twice as long, its OK. Obviously this is a small house. Probably one this builder and his regular subs have built before. Your house will probably take six months to a year to
4z7
10/6/2013 4:24 PM
http://www.home-building-answers.com/critical-path-method.html
complete. We just chose an example that would fit in the illustration! Take a look at this builder. He built homes on a 12-Day schedule!
3. The gray arrows (40-45) are called dummy arrows. They do not represent any activity or any passage of time. They either show dependence or are used to prevent two activities from having the same number. Arrow 50-55 is a dependency arrow. It shows that the exterior doors and windows should be set before you insulate (so insulation can be stuffed into those narrow spaces between the door and window frames and the 2x4 studs). Therefore it is said that activity 55-60 (insulation) is dependent on activity 25-50 (Exterior Doors and Windows). It would be more accurate to say that the starting of activity 55-60 is dependent on the completion of activity 25-50. Arrow 40-45 is an example of the other type of dummy. Without 40-45, Rough Elec and Telephone Pre-wire would have the same number (40-55).
4. The usual schedule for inspections and surveys is indicated. The footing inspection is usually performed after the trench has been excavated and any form materials and steel are in place, but prior to pouring the concrete.
5z7
10/6/2013 4:24 PM
http://www.home-building-answers.com/critical-path-method.html
Good luck!
Whew! Some of that was kind of complicated, wasnt it? Well, the good news is that you dont really have to understand it all or use it to build your home. The Bar Chart is an easier concept to understand and use, although it doesnt give you as much information as the CPM.
6z7
10/6/2013 4:24 PM
http://www.home-building-answers.com/critical-path-method.html
For the first time, you were able to see all of the tasks involved in building your home, and how they all fit together. By plugging this information into a chart, we were able to develop a workable schedule that let us put some dates to the project.
For additional information on the Critical Path Method, see Lesson Nine of our online course
Click here to go back to Bar Charts Click here to go back to Construction Scheduling
Return to the Home Building Answers' Home Page from Critical Path Method
7z7
10/6/2013 4:24 PM