0% found this document useful (0 votes)
281 views

Project Scheduling Unit III

The document discusses project scheduling and introduces two important project scheduling methods: the critical path method (CPM) and program evaluation and review technique (PERT). It explains that CPM and PERT use a network representation to help managers minimize project timelines, costs, and idle resources. The key aspects of networks like activities, events, precedence relationships, and calculations for earliest and latest start/finish times are also outlined.

Uploaded by

Ankur Goldar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
281 views

Project Scheduling Unit III

The document discusses project scheduling and introduces two important project scheduling methods: the critical path method (CPM) and program evaluation and review technique (PERT). It explains that CPM and PERT use a network representation to help managers minimize project timelines, costs, and idle resources. The key aspects of networks like activities, events, precedence relationships, and calculations for earliest and latest start/finish times are also outlined.

Uploaded by

Ankur Goldar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

PROJECT SCHEDULING UNIT III INTRODUCTION

Project scheduling is at the heart of many decision problems that are, in nature, nonrepetitive, unique, and clearly defined in terms of scope, objectives, and time frame. These decisions are referred to as a project; an interrelated set of activities directed towards the accomplishment of a unique, often major outcome and that have a definite starting and ending point. Every organization may be involved at any time in a project of any size, duration, and complexity level. All these projects consist of several activities that have to be completed and some of them are interdependent, that is, they cannot start before the completion of some other activities. In many situations, managers face the challenges of planning, coordinating, and monitoring these activities so that the project of interests is completed on time and within the allocated budget. Project management provides a number of approaches to cope with these challenges. Network is a graphical representation of all the Activities and Events arranged in a logical and sequential order. Network analysis plays an important role in project management. A project is a combination of interrelated activities all of which must be executed in a certain order for its completion.

Objectives
The critical path method (CPM) and the program evaluation review technique (PERT), two management science techniques developed in the late 1950s to plan, schedule, and control large, complex projects with many activities. These approaches differ primarily on how the duration and the cost of activities are processed. In the case of CPM, it is assumed that details about these inputs are known with certainty, whereas for PERT, these details are not known with certainty. Both approaches use a network representation (see Chapter 5) to display the relationships between project activities and to help managers to:

1. 2. 3. 4. 5. 6.

Minimization of total project completion time Minimization of total project completion cost Minimization of cost for a given total time Minimization of time for a given total cost Minimization of idle resources Minimization of conflicting production schedule scheduling is the method by which threads, processes or data flows are given access to system resources (e.g. processor time, communications bandwidth). This is usually done to load balance and share system resources effectively or achieve a target quality of service. The need for a scheduling algorithm arises from the requirement for most modern systems to perform multitasking (executing more than one process at a time)
METHODS OF SCHEDULING:-

Gantt or bar charts Milestone charts Line of balance Networks--------- Program Evaluation and Review Technique (PERT) Arrow Diagram Method (ADM) [Sometimes called the Critical Path Method (CPM)] Precedence Diagram Method (PDM) Graphical Evaluation and Review Technique (GERT) Two project scheduling methods: - Program Evaluation and Review Technique (PERT) - Critical Path Method (CPM)

BASIC CONCEPT OF NETWORK


ACTIVITY AN ACTIVITY IS A PHYSICALLY IDENTIFIABLE PART OF A PROJECT, WHICH CONSUMES BOTH TIME AND RESOURCES. ACTIVITY IS REPRESENTED BY AN ARROW IN A NETWORK DIAGRAM ( FIGURE 4 ). THE HEAD OF AN ARROW REPRESENTS THE START OF ACTIVITY AND THE TAIL OF ARROW REPRESENTS ITS END. ACTIVITY DESCRIPTION AND ITS ESTIMATED COMPLETION TIME ARE WRITTEN ALONG THE ARROW. AN ACTIVITY IN THE NETWORK CAN BE REPRESENTED BY A NUMBER OF WAYS: (I) BY NUMBERS OF ITS

HEAD AND TAIL EVENTS (I.E. 10-20 ETC.), AND (II) BY A LETTER CODE (I.E. A, B ETC.). ALL THOSE ACTIVITIES, WHICH MUST BE COMPLETED BEFORE THE START OF ACTIVITY UNDER CONSIDERATION, ARE CALLED ITS PREDECESSOR ACTIVITIES. ALL THOSE ACTIVITIES, WHICH HAVE TO FOLLOW THE ACTIVITY UNDER CONSIDERATION, ARE CALLED ITS SUCCESSOR ACTIVITIES ( FIGURE 5 ).

DUMMY ACTIVITY AN ACTIVITY, WHICH IS USED TO MAINTAIN THE PRE-DEFINED PRECEDENCE RELATIONSHIP ONLY DURING THE CONSTRUCTION OF THE PROJECT NETWORK, IS CALLED A DUMMY ACTIVITY. DUMMY ACTIVITY IS REPRESENTED BY A DOTTED ARROW AND DOES NOT CONSUME ANY TIME AND RESOURCE (FIGURE 6 ). AN UNBROKEN CHAIN OF ACTIVITIES BETWEEN ANY TWO EVENTS IS CALLED A PATH. EVENT AN EVENT REPRESENTS THE ACCOMPLISHMENT OF SOME TASK. IN A NETWORK DIAGRAM, BEGINNING AND ENDING OF AN ACTIVITY ARE REPRESENTED AS EVENTS. EACH EVENT IS REPRESENTED AS A NODE IN A NETWORK DIAGRAM. AN EVENT DOES NOT CONSUME ANY TIME OR RESOURCE. EACH NETWORK DIAGRAM STARTS WITH AN INITIAL EVENT AND ENDS AT A TERMINAL EVENT. EACH NODE IS REPRESENTED BY A CIRCLE ( FIGURE 7) AND NUMBERED BY USING THE FULKERSON'S RULE. FOLLOWING STEPS ARE INVOLVED IN THE NUMBERING OF THE NODES:

THE INITIAL EVENT, WHICH HAS ALL OUTGOING ARROWS AND NO INCOMING ARROW, IS NUMBERED AS 1. DELETE ALL THE ARROWS COMING OUT FROM THE NODE JUST NUMBERED (I.E. 1). THIS STEP WILL CREATE SOME MORE NODES (AT LEAST ONE) INTO INITIAL EVENTS. NUMBER THESE EVENTS IN ASCENDING ORDER (I.E. 2, 3 ETC.). CONTINUE THE PROCESS UNTIL THE FINAL OR TERMINAL NODE WHICH HAS ALL ARROWS COMING IN, WITH NO ARROW GOING OUT, IS NUMBERED. RULES FOR DRAWING NETWORK DIAGRAM

RULE 1: EACH ACTIVITY IS REPRESENTED BY ONE AND ONLY ONE ARROW IN THE NETWORK. RULE 2: NO TWO ACTIVITIES CAN BE IDENTIFIED BY THE SAME END EVENTS ( FIGURE 9 ).

RULE 3: PRECEDENCE RELATIONSHIPS AMONG ALL ACTIVITIES MUST ALWAYS BE MAINTAINED. RULE 4: DUMMY ACTIVITIES CAN BE USED TO MAINTAIN PRECEDENCE RELATIONSHIPS ONLY WHEN ACTUALLY REQUIRED. THEIR USE SHOULD BE MINIMIZED IN THE NETWORK DIAGRAM ( FIGURE 10). RULE 5: LOOPING AMONG THE ACTIVITIES MUST BE AVOIDED( FIGURE11 ).

CALCULATIONS IN NETWORK ANALYSIS THE FOLLOWING CALCULATIONS ARE REQUIRED IN NETWORK ANALYSIS IN ORDER TO PREPARE A SCHEDULE OF THE PROJECT.

TOTAL COMPLETION TIME OF THE PROJECT EARLIEST TIME WHEN EACH ACTIVITY CAN START (I.E. EARLIST START TIME) EARLIEST TIME WHEN EACH ACTIVITY CAN FINISH (I.E. EARLIST FINISHED TIME) LATEST TIME WHEN EACH ACTIVITY CAN BE STARTED WITHOUT DELAYING THE PROJECT (I.E. LATEST START TIME) e. LATEST TIME WHEN EACH ACTIVITY CAN BE FINISHED WITHOUT DELAYING THE PROJECT (I.E. LATEST FINISH TIME) f. FLOAT ON EACH ACTIVITY (I.E. TIME BY WHICH THE COMPLETION OF AN ACTIVITY CAN BE DELAYED WITHOUT DELAYING THE PROJECT) g. CRITICAL ACTIVITY AND CRITICAL PATH a. b. c. d.

.....................................................................................................CPM AND PERT.................................................................................................

PERT and CPM have been used for a variety of projects, including the following types. 1. Construction of a new plant 2. Research and development of a new product 3. NASA space exploration projects 4. Movie productions 5. Building a ship 6. Government-sponsored projects for developing a new weapons system 7. Relocation of a major facility 8. Maintenance of a nuclear reactor 9. Installation of a management information system 10. Conducting an advertising campaign

You might also like