Metro Rail Project
Phase I Review Phase I Review
-Line Opening Options (Full /Progressive Opening)
1
Major Milestones and their Status for EW
R2
Start of Trial Runs from Mysore Road in R2 to City Railway by Jan 2015
Full Track (with Cross Overs), Third rail, Power from Mys. Road GIS,
Power On for all R2 Stations ready by Oct. 14;
UG2 track ready with traction power at Majestic by Jan 2015
Follow up with Inclusion of Full Signaling System from Magadi Road to City
Railway Station Railway Station
- Signalling system Installation and T&C (Mar. 2015), I T &C Apr.2015,
ready for Operations May 2015
- City Rly station to be ready with TVM, ECS, Smoke extraction, fire
safety/ emergency evacuation by April 15
Major Milestones and their Status for EW
UG EW
Track Welding machine reaches site by end of week 250514
Track Welded panels shifting to plinth location by June
onwards; by which time transformer shifting will be done
Track Temporary track requirements being worked out for use
(630 m approx. for 3 UG stations) (630 m approx. for 3 UG stations)
Track WB track linking to take 3 4 months approx.
Track Survey/Design under progress, followed by drawings
preparation and interfaces
Major Milestones and their Status for EW
UG EW
E&M Procurement proposals for many items being processed
E&M Tunnel Support for 33 KV (WB by June and EB by July)
E&M ASSs at CRS and C College are in progress
E&M SER/SCR conduiting completed at BRCS and VSWA E&M SER/SCR conduiting completed at BRCS and VSWA
Target installation complete by Dec 2014
Major Milestones and their Status for EW
UG EW
ECS Procurement materials being delivered at site, BMS PLC
proposal modified and resubmitted
ECS AHU installations done at BRCS (both sides)
ECS Anciliary Bldg. at VSWA access by June 14 ECS Anciliary Bldg. at VSWA access by June 14
ECS ECS room at VDSA by June 14 (with pedestals, utility
galleries, delivery routes) installation in 3 months
Target installation complete by Dec 2014
Major Milestones and their Status for EW
UG EW
TVS Procurement materials being delivered at site, BMS PLC
proposal modified and resubmitted
TVS deliveries TVFs for 2 UG stations by Aug. 14; TV Dampers
for 2 UG stations by May 14, balance by Jul 14; Cables by Aug.
14; Sound Attenuators by June; Nozzles & MS Cones- July/Aug 14 14; Sound Attenuators by June; Nozzles & MS Cones- July/Aug 14
TVS All deliveries by Aug, by 2 openings of 5 x 5 m
TVS 6 out of 8 TVS rooms are provided access
Target installation complete by Dec 2014
Options under detailing for Majestic
Design/ Planning initiatives in progress for Full
condition with stop at Majestic
Shifting of SER from Majestic to Central College
Prioritised working for other rooms.
Options under detailing for Majestic
Design/ Planning initiatives in progress for Full
condition without stop at Majestic
Relocation of SER room within Majestic, for faster
access to Systems
Room requirements being worked out Room requirements being worked out
Minimum requirement of Entry/Exits and Podium
requirement at Majestic
Changes in interface triggered by relocation
DCs asked to provide schedule and cost for changes
Options under detailing for Majestic
Design/ Planning initiatives in progress for Empty
condition without stop at Majestic
Majestic may be treated as Tunnel section,
minimum safety aspects being worked out
Room requirements being worked out Room requirements being worked out
Minimum requirement of Entry/Exits
DCs asked to provide schedule and cost for changes