ABBF Analysis in P6
ABBF Analysis in P6
Disclaimer
Information contained within this presentation is for education purposes
only. How a programme or schedule is built, maintained and managed is
the responsibility of the owning organisation. Focus Planning Ltd
accepted no responsibility for changes made to programmes or
schedules which are altered as a result of reading slides contained within
this presentation. The configuration and settings of computer software
are the responsibility of the license holders and Focus Planning Ltd
accept no liability for the configuration used by the license holder.
What ABBF looks to answer is When would we have finished if the delay had not
occurred? And What was the impact on the actual critical path?
ABBF looks at the actual critical path rather than the planned, as the planned critical
path can change on various occasions throughout the life of the project. We will look
at how to complete this analysis in Primavera P6, this is a slight variation but to
software limitations.
Focus Planning Ltd
Take a copy of the schedule (including all baselines) and open the copy in the
Activities window. Identify the activities you need to calculate delay against
(known as the Window). Ensure all activities within the window are marked
with the Actual Start and Actual Finish dates. This is the As-Built schedule. Add
two milestones called Window Start and Window Finish ,logically link as
the first and last activities in the window and mark as complete. This helps to
define the Window Period.
As the As-Built logic was determined in Step 2, you can now remove the
constraints holding the activities in place and re-schedule to the window start
data date. Activities on the critical path should remain the same as the as-built
dates, other activities not on the critical path may differ because there actual
start date will not be directly dictated by the predecessor, this can be
corrected using lag on the relationship but is not required as we are only
concerned with activities along the critical path. You now have a clear As-Built
critical path.
10
Summary
So to summarise this variation on the As-Built But-For Analysis in P6
provides the project stakeholders with the following information;
The impact of implicit delays on the window finish
The impact of explicit delays on the window finish
The overall impact of all delays on the window finish
By comparing multiple baselines taken as the delay periods were
calculated we are able to see a timeline of the calculations used to
generate the claim for delays which can be issued to stakeholders as
required in a single Gantt chart, rather than separate pages of data.
Other Delay review methods including Time Impact Analysis will be
covered in future slides and a copy will be made available on the
Focus Planning Ltd website at http://www.focus-planning.com or by
contacting [email protected]
Focus Planning Ltd
11