MDC BUILDPLUS, INC.
Project Name:
Amaia Scapes Trece Martires
Project Location: Trece Martires, Cavite
Civil Works: Detailed Breakdown
Fixed Lump Sum
Item
Description
Unit
DIVISION 01 - ENABLING WORKS
a.
b.
Mobilization/Demobilization
Community Taxes
lot
lot
Sub Total : DIVISION 01 - ENABLING WORKS
Total ENABLING WORKS
DIVISION 02 - SURVEY WORKS
a.
b.
Line & Grade
Lot Monumenting
mos
lots
Sub Total : DIVISION 02 - SURVEY WORKS
DIVISION 03 - EARTHWORKS FOR BLOCK DEVELOPMENT
a.
Clearing & Grubbing
b.
Soil Stripping
c.
Cut
d.
Engineered Fill
- Borrowed Fill
e.
Hauling & Disposals
- Excess Cut
- Topsoil (Soil Stripping)
f.
Material Testing
m2
m3
m3
m3
m3
m3
lot
Sub Total : DIVISION 03 - EARTHWORKS FOR BLOCK DEVELOPMENT
a.
c.
e.
2
4
g.
3
4
h.
j.
DIVISION 05 - ROAD RIGHT OF WAY
Sub Grade Preparation
Base Coarse
Portland Cement Concrete Pavement (PCCP)
- 3000 Psi (thk = 175 mm)
- 3000 Psi (thk = 150 mm)
Curb & Gutter
- S - Type Curb & Gutter
- Barrier
Concrete Sidewalk
- Concrete Sidewalk (thk = 100 mm)
- Base Coarse
Filling / Levelling of Sidewalk
m2
m3
m2
m2
l.m.
l.m.
m2
m3
m3
k.
m.
Filling / Levelling of Planting Strip
Material Testing
m3
lot
Sub Total : DIVISION 05 - ROAD RIGHT OF WAY
DIVISION 07 - RETAINING WALL/SLOPE PROTECTION
c.
RC Hybrid Retaining Wall
h = 0.50 m
h = 0.75 m
h = 1.00 m
h = 1.25 m
h = 1.50 m
h = 1.75 m
h = 2.00 m
h = 2.25 m
h = 2.50 m
h = 2.75 m
h = 3.00 m
h = 3.25 m
h = 3.50 m
Sub Total : DIVISION 07 - RETAINING WALL/SLOPE PROTECTION
Total CIVIL WORKS
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
SELLING PRICE
TOTAL
Qty
Rate
1.00
1.00
Amount
287,377.30
361,862.87
287,377.30
361,862.87
649,240.17
649,240.17
9.00
546.00
119,277.71
771.80
1,073,499.39
421,401.13
1,494,900.52
75,738.30
7,573.83
27,487.72
19.20
67.83
67.83
1,453,925.04
513,762.69
1,864,600.22
23,216.51
169.80
3,942,054.93
4,271.21
15,147.66
1.00
188.75
188.75
293,926.25
806,205.70
2,859,173.35
293,926.25
11,733,648.18
25,214.50
4,170.30
23.95
1,110.18
603,982.35
4,629,786.96
2,342.60
13,679.40
927.56
807.82
2,172,901.12
11,050,476.69
7,370.00
60.00
669.47
339.24
4,933,999.09
20,354.39
3,920.60
392.06
604.68
428.50
1,110.18
155.72
1,679,983.63
435,257.48
94,161.11
165.90
1.00
155.72
224,010.78
25,834.04
224,010.78
25,870,747.63
10.00
92.01
166.66
23.67
80.94
11.72
20.50
5.00
7.50
10.00
10.00
7.50
2.50
6,464.70
9,697.06
12,929.41
16,161.76
18,354.24
19,774.98
21,183.96
27,438.39
28,854.95
35,481.81
37,009.02
39,094.49
41,179.96
64,647.05
892,226.20
2,154,815.31
382,548.89
1,485,592.47
231,762.78
434,271.18
137,191.96
216,412.11
354,818.07
370,090.25
293,208.68
102,949.89
7,120,534.82
46,219,831.16
73,021,335.28
MDC BUILDPLUS, INC.
Project Name:
Amaia Scapes Trece Martires
Project Location: Trece Martires, Cavite
Wet Utilities: Detailed Breakdown
Fixed Lump Sum
Item
a.
c.
c.2
c.4
c.5
Description
DIVISION 08 - POTABLE WATER SYSTEM
uPVC Pipes Class 150 (Color Blue)
- 63 mm Pipes (2")
- 90 mm Pipes (3")
- 110 mm Pipes (4")
- 160 mm Pipes (6")
Unit
l.m.
l.m.
l.m.
l.m.
CI Fittings (Including Concrete Thrust Blocks)
For 63 mm Pipes
- Elbow 90 X 63 mm
- Elbow 45 X 63 mm
- Elbow 22.5 X 63 mm
- Elbow 11.25 X 63 mm
- Tee 63 mm
- Tee Reducer 90 x 63 mm
- Tee Reducer 110 x 63 mm
- Cross Tee 63 x 63 mm
- Cross Tee Reducer 90 x 63 mm
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
For 90 mm Pipes
- Elbow 90 X 90 mm
- Elbow 45 X 90 mm
- Elbow 22.5 X 90 mm
- Elbow 11.25 X 90 mm
- Tee 90 mm
- Tee Reducer 110 x 90 mm
- Tee Reducer 160 x 90 mm
- Cross Tee 90 x 90 mm
- Reducer 110 x 90 mm
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
For 110 mm Pipes
Elbow 90 X 110 mm
Elbow 45 X 110 mm
- Elbow 11.25 X 110 mm
- Tee 110 mm
- Tee Reducer 160 x 110 mm
- Reducer 160 x 110 mm
pcs
pcs
pcs
pcs
pcs
pcs
c.6
-
For 160 mm Pipes
Elbow 45 X 160 mm
Elbow 11.25 X 160 mm
pcs
pcs
Tee 160 mm
pcs
Gate Valve
160 mm
110 mm
90 mm
63 mm
pcs
pcs
pcs
pcs
Air Relief Valve
90 mm
pcs
Fire Hydrants
- 160 mm
- 110 mm
90 mm
pcs
pcs
pcs
d..2
d..3
d..4
e.
Lot Connections
For Single Service
Lot Non-Cross Connections (Single Connections)
20mm tapped to 160mm main
6.50M RROW
20mm tapped to 110mm main
8.00M RROW
6.50M RROW
20mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
20mm tapped to 63mm main
6.50M RROW
ea.
ea.
ea.
ea.
ea.
ea.
ea.
Lot Cross Connections (Single Connections)
20mm tapped to 160mm main
6.50M RROW
20mm tapped to 110mm main
8.00M RROW
6.50M RROW
20mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
20mm tapped to 63mm main
6.50M RROW
For Double Service
Lot Non-cross Connections (Double Connections)
25mm tapped to 160mm main
6.50M RROW
25mm tapped to 110mm main
8.00M RROW
6.50M RROW
25mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
25mm tapped to 63mm main
6.50M RROW
Lot Cross Connections (Double Connections)
25mm tapped to 160mm main
6.50M RROW
25mm tapped to 110mm main
8.00M RROW
6.50M RROW
25mm tapped to 90mm main
8.00M RROW
6.50M RROW
25mm tapped to 63mm main
6.50M RROW
f.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
Irrigation (150mm )
Lot Non-cross Connections
ea.
g.
Lot Connection Marker
ea.
Testing & Commissioning
lot
Sub Total : DIVISION 08 - POTABLE WATER SYSTEM
DIVISION 09 - DRAINAGE SYSTEM
Drainage Crossing 300mm
l.m.
a.1
REINFORCED CONCRETE PIPES (Class II Wall B) (Single Conduit)
- 300 mm Pipes
- d = 1.00 m
- d = 1.25 m
- d = 1.50 m
- d = 1.75 m
- d = 2.00 m
- 375 mm Pipes
- d = 1.25 m
- d = 1.50 m
- d = 1.75 m
- 450 mm Pipes
- d = 1.25 m
- d = 1.50 m
- 525 mm Pipes
- d = 1.50 m
- d = 1.75 m
- d = 2.75 m
- 600 mm Pipes
- d = 1.50 m
- d = 1.75 m
- 750 mm Pipes
- d = 1.75 m
- d = 4.00 m
- 900 mm Pipes
- d = 1.75 m
- 1050 mm Pipes
- d = 2.00 m
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
b.A
b.4
b.6
b.8
c.
DRAINAGE STRUCTURES (1 Conduit)
Terrain Inlet Manhole
- TIM 300 mm
- d = 1.25 m
- d = 1.50 m
- d = 2.25 m
- d = 2.50 m
- TIM 375 mm
- d = 1.50 m
- d = 1.75 m
- d = 2.00 m
- d = 2.25 m
- TIM 450 mm
- d = 1.50 m
- d = 1.75 m
- TIM 525 mm
- d = 1.75 m
- d = 2.00 m
- TIM 600 mm
- d = 1.75 m
- d = 2.00 m
- TIM 750 mm
- d = 1.75 m
- d = 2.00 m
- TIM 900 mm
- d = 2.00 m
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
- TIM 1050 mm
- d = 2.25 m
ea.
Terrain Inlet Box
- TIB 300 mm
- d = 1.50 m
ea.
Area Drain
- AD 300 mm
- d = 1.25 m
ea.
Drainage Outfall
- 750 mm (4.25m)
- 900 mm (2.00m)
- 1050 mm (2.25m)
ea.
ea.
ea.
Collector Pipe
200mm PVC Pipe
100mm End Plug
l.m.
ea.
Anaerobic Trench
750mm
900mm
1050mm
ea
ea
ea
c.
c.1
c.2
c.2
Lot Connections (150 mm PVC)
Stub Out Connected to Manhole
Stub Out Connected to Boxes
Stub Out Connected to PVC Collector Pipe
ea.
ea.
ea.
d.
d.1
Lot Connection Marker
L = 4.0 m
ea.
e.
Testing & Commissioning
lot
Sub Total : DIVISION 09 DRAINAGE SYSTEM
Total WET UTILITIES
SELLING PRICE
TOTAL
Rate
Qty
1,328.00
1,839.00
509.00
227.00
680.37
858.86
1,065.42
1,776.04
11.00
6.00
7.00
41.00
11.00
11.00
2.00
1.00
1.00
1,494.48
1,321.88
1,321.88
1,321.88
1,713.39
1,909.85
2,531.49
2,221.37
2,276.10
2.00
4.00
16.00
81.00
8.00
5.00
1.00
2.00
4.00
1,808.81
1,633.40
1,633.40
1,633.40
2,221.37
2,841.62
4,119.99
2,784.08
2,142.79
1.00
2.00
24.00
2.00
4.00
2.00
2,647.97
2,386.96
2,386.96
3,010.01
4,682.70
3,115.25
4.00
9.00
3,496.94
3,496.94
Amount
903,535.53
1,579,443.13
542,296.97
403,162.07
16,439.27
7,931.27
9,253.14
54,196.98
18,847.28
21,008.31
5,062.99
2,221.37
2,276.10
3,617.62
6,533.61
26,134.45
132,305.64
17,770.98
14,208.08
4,119.99
5,568.16
8,571.16
2,647.97
4,773.91
57,286.98
6,020.02
18,730.81
6,230.51
13,987.77
31,472.48
1.00
4,702.35
4.00
6.00
20.00
13.00
14,940.59
9,904.26
8,743.76
5,993.35
1.00
26,662.08
1.00
2.00
4.00
50,054.82
48,757.85
42,128.89
2.00
3,296.27
2.00
7.00
3,133.50
3,133.50
1.00
2.00
22.00
2,896.34
2,896.34
2,896.34
26.00
2,758.82
4,702.35
59,762.34
59,425.56
174,875.16
77,913.60
26,662.08
50,054.82
97,515.70
168,515.55
6,592.55
6,266.99
21,934.47
2,896.34
5,792.69
63,719.56
71,729.40
-
1.00
4,395.03
2.00
1.00
4,640.60
4,383.81
1.00
4.00
17.00
6,261.38
4,842.60
3,915.12
10.00
3,750.93
1.00
4,640.60
6.00
8.00
4,717.78
4,717.78
4.00
11.00
54.00
4,480.63
4,480.63
4,480.63
54.00
4,101.75
3.00
6,382.06
6.00
4.00
6,687.97
6,078.95
11.00
50.00
6,891.80
5,900.74
25.00
5,744.98
10.00
4,191.26
578.00
771.80
1.00
332,959.59
4,395.03
9,281.21
4,383.81
6,261.38
19,370.42
66,556.96
37,509.33
4,640.60
28,306.71
37,742.27
17,922.53
49,286.95
241,954.13
221,494.50
19,146.18
40,127.83
24,315.81
75,809.76
295,036.92
143,624.40
41,912.64
446,098.63
332,959.59
6,992,151.30
700.00
1,562.96
1,094,071.29
-
1,269.00
280.00
54.00
36.00
14.00
1,164.43
1,296.34
1,426.84
1,557.35
1,687.85
312.00
28.00
58.00
1,590.90
1,736.84
1,884.18
207.00
127.00
1,959.68
2,123.86
155.00
39.00
27.00
2,455.86
2,728.09
3,355.35
73.00
78.00
2,898.94
3,095.40
168.00
7.00
4,682.51
6,742.50
36.00
5,623.02
8.00
6,761.50
1,477,663.07
362,974.70
77,049.47
56,064.45
23,629.90
496,360.18
48,631.46
109,282.49
405,653.06
269,730.08
380,657.97
106,395.58
90,594.51
211,622.58
241,440.96
786,661.03
47,197.52
202,428.64
54,092.02
-
59.00
9.00
1.00
1.00
26,128.83
28,472.29
37,705.79
41,045.56
18.00
3.00
2.00
1.00
28,472.29
31,812.07
34,380.05
37,705.79
11.00
7.00
28,472.29
31,812.07
7.00
4.00
31,812.07
34,380.05
4.00
4.00
31,812.07
34,380.05
1.00
6.00
34,604.57
37,228.68
2.00
40,007.15
1.00
48,398.68
115.00
11,660.84
5.00
29,130.42
1.00
1.00
1.00
27,923.35
30,258.60
32,736.25
2,160.64
265.00
1,250.31
904.47
1.00
1.00
1.00
439,592.09
623,437.95
701,194.27
1,541,601.25
256,250.62
37,705.79
41,045.56
512,501.24
95,436.20
68,760.09
37,705.79
313,195.20
222,684.47
222,684.47
137,520.18
127,248.27
137,520.18
34,604.57
223,372.07
80,014.29
48,398.68
1,340,996.66
145,652.12
27,923.35
30,258.60
32,736.25
2,701,472.07
239,684.41
439,592.09
623,437.95
701,194.27
155.00
166.00
225.00
953.44
953.44
2,475.00
546.00
771.80
1.00
912,386.32
147,782.56
158,270.35
556,874.65
421,401.13
912,386.32
19,160,112.66
26,152,263.96
Summary of Proposal
Part 1.0 Project
Details
Project Name:
AMAIA SCAPES TRECE
Project Location:
TRECE MARTIRES, CAV
Part 2.0 Project Cost
Description
Preliminaries
Division 1 ENABLING WORKS
Fixed Lump Sum
CIVIL WORKS
Division 2
Division 3
Division 5
Division 7
SURVEY WORKS
EARTHWORKS
ROAD RIGHT OF WAY
RETAINING WALL/SLOPE PROTECTION
WET UTILITIES
Division 8 POTABLE WATER SYSTEM
Division 9 DRAINAGE SYSTEM
Overall Total
Qualifications
1
Exculsions
a
b
c
AMAIA SCAPES TRECE MARTIRES
SBU:
TRECE MARTIRES, CAVITE
AMAIA
Cost inclusive of VAT
Amount
PhP/m2
649,240.17
8.57
46,219,831.16
610.26
19.74
154.92
341.58
94.01
26,152,263.96
345.30
92.32
252.98
649,240.17
1,494,900.52
11,733,648.18
25,870,747.63
7,120,534.82
6,992,151.30
19,160,112.66
73,021,335.28
Deepwell
Water Tank
Tree Ball-out
964.13
GDA (m2)
Date:
75,738.30
Benchmark
PhP/m2
1/8/2014
MDC BUILDPLUS, INC.
Project Name:
Amaia Scapes Trece Martires
Project Location: Trece Martires, Cavite
Civil Works: Detailed Breakdown
Fixed Lump Sum
Item
Description
Unit
DIVISION 01 - ENABLING WORKS
a.
b.
Mobilization/Demobilization
Community Taxes
lot
lot
Sub Total : DIVISION 01 - ENABLING WORKS
Total ENABLING WORKS
DIVISION 02 - SURVEY WORKS
a.
b.
Line & Grade
Lot Monumenting
mos
lots
Sub Total : DIVISION 02 - SURVEY WORKS
NOTE!!
DIVISION 03 - EARTHWORKS FOR BLOCK DEVELOPMENT
a.
Clearing & Grubbing
b.
Soil Stripping
c.
Cut
d.
Engineered Fill
- Borrowed Fill
e.
Hauling & Disposals
- Excess Cut
- Topsoil (Soil Stripping)
f.
Material Testing
m2
m3
m3
m3
m3
m3
lot
Sub Total : DIVISION 03 - EARTHWORKS FOR BLOCK DEVELOPMENT
a.
c.
e.
2
4
g.
3
4
h.
j.
DIVISION 05 - ROAD RIGHT OF WAY
Sub Grade Preparation
Base Coarse
Portland Cement Concrete Pavement (PCCP)
- 3000 Psi (thk = 175 mm)
- 3000 Psi (thk = 150 mm)
Curb & Gutter
- S - Type Curb & Gutter
- Barrier
Concrete Sidewalk
- Concrete Sidewalk (thk = 100 mm)
- Base Coarse
Filling / Levelling of Sidewalk
m2
m3
m2
m2
l.m.
l.m.
m2
m3
m3
k.
m.
Filling / Levelling of Planting Strip
Material Testing
m3
lot
Sub Total : DIVISION 05 - ROAD RIGHT OF WAY
DIVISION 07 - RETAINING WALL/SLOPE PROTECTION
c.
RC Hybrid Retaining Wall
h = 0.50 m
h = 0.75 m
h = 1.00 m
h = 1.25 m
h = 1.50 m
h = 1.75 m
h = 2.00 m
h = 2.25 m
h = 2.50 m
h = 2.75 m
h = 3.00 m
h = 3.25 m
h = 3.50 m
Sub Total : DIVISION 07 - RETAINING WALL/SLOPE PROTECTION
Total CIVIL WORKS
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
SELLING PRICE
TOTAL
Qty
Rate
1.00
1.00
Amount
287,377.30
361,862.87
287,377.30
361,862.87
649,240.17
649,240.17
9.00
546.00
119,277.71
771.80
1,073,499.39
421,401.13
1,494,900.52
75,738.30
7,573.83
27,487.72
19.20
67.83
67.83
1,453,925.04
513,762.69
1,864,600.22
23,216.51
169.80
3,942,054.93
4,271.21
15,147.66
1.00
188.75
188.75
293,926.25
806,205.70
2,859,173.35
293,926.25
10,279,723.14
25,214.50
4,170.30
23.95
1,110.18
603,982.35
4,629,786.96
2,342.60
13,679.40
927.56
807.82
2,172,901.12
11,050,476.69
7,370.00
60.00
669.47
339.24
4,933,999.09
20,354.39
3,920.60
392.06
604.68
428.50
1,110.18
155.72
1,679,983.63
435,257.48
94,161.11
165.90
1.00
155.72
224,010.78
25,834.04
224,010.78
25,870,747.63
10.00
92.01
166.66
23.67
80.94
11.72
20.50
5.00
7.50
10.00
10.00
7.50
2.50
6,464.70
9,697.06
12,929.41
16,161.76
18,354.24
19,774.98
21,183.96
27,438.39
28,854.95
35,481.81
37,009.02
39,094.49
41,179.96
64,647.05
892,226.20
2,154,815.31
382,548.89
1,485,592.47
231,762.78
434,271.18
137,191.96
216,412.11
354,818.07
370,090.25
293,208.68
102,949.89
7,120,534.82
44,765,906.11
71,567,410.24
MDC BUILDPLUS, INC.
Project Name:
Amaia Scapes Trece Martires
Project Location: Trece Martires, Cavite
Wet Utilities: Detailed Breakdown
Fixed Lump Sum
Item
a.
c.
c.2
c.4
c.5
c.6
Description
Unit
DIVISION 08 - POTABLE WATER SYSTEM
uPVC Pipes Class 150 (Color Blue)
- 63 mm Pipes (2")
- 90 mm Pipes (3")
- 110 mm Pipes (4")
- 160 mm Pipes (6")
l.m.
l.m.
l.m.
l.m.
CI Fittings (Including Concrete Thrust Blocks)
For 63 mm Pipes
- Elbow 90 X 63 mm
- Elbow 45 X 63 mm
- Elbow 22.5 X 63 mm
- Elbow 11.25 X 63 mm
- Tee 63 mm
- Tee Reducer 90 x 63 mm
- Tee Reducer 110 x 63 mm
- Cross Tee 63 x 63 mm
- Cross Tee Reducer 90 x 63 mm
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
For 90 mm Pipes
- Elbow 90 X 90 mm
- Elbow 45 X 90 mm
- Elbow 22.5 X 90 mm
- Elbow 11.25 X 90 mm
- Tee 90 mm
- Tee Reducer 110 x 90 mm
- Tee Reducer 160 x 90 mm
- Cross Tee 90 x 90 mm
- Reducer 110 x 90 mm
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
For 110 mm Pipes
- Elbow 90 X 110 mm
- Elbow 45 X 110 mm
- Elbow 11.25 X 110 mm
- Tee 110 mm
- Tee Reducer 160 x 110 mm
- Reducer 160 x 110 mm
pcs
pcs
pcs
pcs
pcs
pcs
For 160 mm Pipes
- Elbow 45 X 160 mm
- Elbow 11.25 X 160 mm
pcs
pcs
d..2
d..3
d..4
e.
Tee 160 mm
Gate Valve
- 160 mm
- 110 mm
90 mm
63 mm
pcs
pcs
pcs
pcs
pcs
Air Relief Valve
90 mm
pcs
Fire Hydrants
- 160 mm
- 110 mm
90 mm
pcs
pcs
pcs
Lot Connections
For Single Service
Lot Non-Cross Connections (Single Connections)
20mm tapped to 160mm main
6.50M RROW
20mm tapped to 110mm main
8.00M RROW
6.50M RROW
20mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
20mm tapped to 63mm main
6.50M RROW
ea.
ea.
ea.
ea.
ea.
ea.
ea.
Lot Cross Connections (Single Connections)
20mm tapped to 160mm main
6.50M RROW
20mm tapped to 110mm main
8.00M RROW
6.50M RROW
20mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
20mm tapped to 63mm main
6.50M RROW
For Double Service
Lot Non-cross Connections (Double Connections)
25mm tapped to 160mm main
6.50M RROW
25mm tapped to 110mm main
8.00M RROW
6.50M RROW
25mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
25mm tapped to 63mm main
6.50M RROW
Lot Cross Connections (Double Connections)
25mm tapped to 160mm main
6.50M RROW
25mm tapped to 110mm main
8.00M RROW
6.50M RROW
25mm tapped to 90mm main
8.00M RROW
6.50M RROW
25mm tapped to 63mm main
6.50M RROW
f.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
Irrigation (150mm )
Lot Non-cross Connections
ea.
g.
Lot Connection Marker
ea.
Testing & Commissioning
lot
Sub Total : DIVISION 08 - POTABLE WATER SYSTEM
DIVISION 09 - DRAINAGE SYSTEM
Drainage Crossing 300mm
l.m.
a.1
REINFORCED CONCRETE PIPES (Class II Wall B) (Single Conduit)
- 300 mm Pipes
- d = 1.00 m
- d = 1.25 m
- d = 1.50 m
- d = 1.75 m
- d = 2.00 m
- 375 mm Pipes
- d = 1.25 m
- d = 1.50 m
- d = 1.75 m
- 450 mm Pipes
- d = 1.25 m
- d = 1.50 m
- 525 mm Pipes
- d = 1.50 m
- d = 1.75 m
- d = 2.75 m
- 600 mm Pipes
- d = 1.50 m
- d = 1.75 m
- 750 mm Pipes
- d = 1.75 m
- d = 4.00 m
- 900 mm Pipes
- d = 1.75 m
- 1050 mm Pipes
- d = 2.00 m
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
b.A
b.4
b.6
b.8
c.
DRAINAGE STRUCTURES (1 Conduit)
Terrain Inlet Manhole
- TIM 300 mm
- d = 1.25 m
- d = 1.50 m
- d = 2.25 m
- d = 2.50 m
- TIM 375 mm
- d = 1.50 m
- d = 1.75 m
- d = 2.00 m
- d = 2.25 m
- TIM 450 mm
- d = 1.50 m
- d = 1.75 m
- TIM 525 mm
- d = 1.75 m
- d = 2.00 m
- TIM 600 mm
- d = 1.75 m
- d = 2.00 m
- TIM 750 mm
- d = 1.75 m
- d = 2.00 m
- TIM 900 mm
- d = 2.00 m
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
- TIM 1050 mm
- d = 2.25 m
ea.
Terrain Inlet Box
- TIB 300 mm
- d = 1.50 m
ea.
Area Drain
- AD 300 mm
- d = 1.25 m
ea.
Drainage Outfall
- 750 mm (4.25m)
- 900 mm (2.00m)
- 1050 mm (2.25m)
ea.
ea.
ea.
Collector Pipe
200mm PVC Pipe
100mm End Plug
l.m.
ea.
Anaerobic Trench
750mm
900mm
1050mm
ea
ea
ea
c.
c.1
c.2
c.2
Lot Connections (150 mm PVC)
Stub Out Connected to Manhole
Stub Out Connected to Boxes
Stub Out Connected to PVC Collector Pipe
ea.
ea.
ea.
d.
d.1
Lot Connection Marker
L = 4.0 m
ea.
e.
Testing & Commissioning
lot
Sub Total : DIVISION 09 DRAINAGE SYSTEM
Total WET UTILITIES
SELLING PRICE
TOTAL
Rate
Qty
Amount
1,328.00
1,839.00
509.00
227.00
680.37
858.86
1,065.42
1,776.04
11.00
6.00
7.00
41.00
11.00
11.00
2.00
1.00
1.00
1,494.48
1,321.88
1,321.88
1,321.88
1,713.39
1,909.85
2,531.49
2,221.37
2,276.10
2.00
4.00
16.00
81.00
8.00
5.00
1.00
2.00
4.00
1,808.81
1,633.40
1,633.40
1,633.40
2,221.37
2,841.62
4,119.99
2,784.08
2,142.79
1.00
2.00
24.00
2.00
4.00
2.00
2,647.97
2,386.96
2,386.96
3,010.01
4,682.70
3,115.25
4.00
9.00
3,496.94
3,496.94
903,535.53
1,579,443.13
542,296.97
403,162.07
16,439.27
7,931.27
9,253.14
54,196.98
18,847.28
21,008.31
5,062.99
2,221.37
2,276.10
3,617.62
6,533.61
26,134.45
132,305.64
17,770.98
14,208.08
4,119.99
5,568.16
8,571.16
2,647.97
4,773.91
57,286.98
6,020.02
18,730.81
6,230.51
13,987.77
31,472.48
1.00
4,702.35
4.00
6.00
20.00
13.00
14,940.59
9,904.26
8,743.76
5,993.35
1.00
26,662.08
1.00
2.00
4.00
50,054.82
48,757.85
42,128.89
2.00
3,296.27
2.00
7.00
3,133.50
3,133.50
1.00
2.00
22.00
2,896.34
2,896.34
2,896.34
26.00
2,758.82
4,702.35
59,762.34
59,425.56
174,875.16
77,913.60
26,662.08
50,054.82
97,515.70
168,515.55
6,592.55
6,266.99
21,934.47
2,896.34
5,792.69
63,719.56
71,729.40
-
1.00
4,395.03
2.00
1.00
4,640.60
4,383.81
1.00
4.00
17.00
6,261.38
4,842.60
3,915.12
10.00
3,750.93
1.00
4,640.60
6.00
8.00
4,717.78
4,717.78
4.00
11.00
54.00
4,480.63
4,480.63
4,480.63
54.00
4,101.75
3.00
6,382.06
6.00
4.00
6,687.97
6,078.95
11.00
50.00
6,891.80
5,900.74
25.00
5,744.98
10.00
4,191.26
578.00
771.80
1.00
332,959.59
4,395.03
9,281.21
4,383.81
6,261.38
19,370.42
66,556.96
37,509.33
4,640.60
28,306.71
37,742.27
17,922.53
49,286.95
241,954.13
221,494.50
19,146.18
40,127.83
24,315.81
75,809.76
295,036.92
143,624.40
41,912.64
446,098.63
332,959.59
6,992,151.30
700.00
1,562.96
1,094,071.29
-
1,269.00
280.00
54.00
36.00
14.00
1,164.43
1,296.34
1,426.84
1,557.35
1,687.85
312.00
28.00
58.00
1,590.90
1,736.84
1,884.18
207.00
127.00
1,959.68
2,123.86
155.00
39.00
27.00
2,455.86
2,728.09
3,355.35
73.00
78.00
2,898.94
3,095.40
168.00
7.00
4,682.51
6,742.50
36.00
5,623.02
8.00
6,761.50
1,477,663.07
362,974.70
77,049.47
56,064.45
23,629.90
496,360.18
48,631.46
109,282.49
405,653.06
269,730.08
380,657.97
106,395.58
90,594.51
211,622.58
241,440.96
786,661.03
47,197.52
202,428.64
54,092.02
-
59.00
9.00
1.00
1.00
26,128.83
28,472.29
37,705.79
41,045.56
18.00
3.00
2.00
1.00
28,472.29
31,812.07
34,380.05
37,705.79
11.00
7.00
28,472.29
31,812.07
7.00
4.00
31,812.07
34,380.05
4.00
4.00
31,812.07
34,380.05
1.00
6.00
34,604.57
37,228.68
2.00
40,007.15
1.00
48,398.68
115.00
11,660.84
5.00
29,130.42
1.00
1.00
1.00
27,923.35
30,258.60
32,736.25
2,160.64
265.00
1,250.31
904.47
1.00
1.00
1.00
439,592.09
623,437.95
701,194.27
1,541,601.25
256,250.62
37,705.79
41,045.56
512,501.24
95,436.20
68,760.09
37,705.79
313,195.20
222,684.47
222,684.47
137,520.18
127,248.27
137,520.18
34,604.57
223,372.07
80,014.29
48,398.68
1,340,996.66
145,652.12
27,923.35
30,258.60
32,736.25
2,701,472.07
239,684.41
439,592.09
623,437.95
701,194.27
155.00
166.00
225.00
953.44
953.44
2,475.00
546.00
771.80
1.00
912,386.32
147,782.56
158,270.35
556,874.65
421,401.13
912,386.32
19,160,112.66
26,152,263.96
Summary of Proposal
Part 1.0 Project
Details
Project Name:
AMAIA SCAPES TRECE MARTIRES
Project Location:
TRECE MARTIRES, CAVITE
Co
Part 2.0 Project Cost
Description
Preliminaries
Division 1 ENABLING WORKS
649,240.17
Fixed Lump Sum
CIVIL WORKS
Division 2
Division 3
Division 5
Division 7
SURVEY WORKS
EARTHWORKS
ROAD RIGHT OF WAY
RETAINING WALL/SLOPE PROTECTION
1,494,900.52
10,279,723.14
25,870,747.63
7,120,534.82
WET UTILITIES
Division 8 POTABLE WATER SYSTEM
Division 9 DRAINAGE SYSTEM
6,992,151.30
19,160,112.66
Overall Total
Qualifications
1
Exculsions
a
b
c
Deepwell
Water Tank
Tree Ball-out
RTIRES
SBU:
GDA (m2)
AMAIA
75,738.30
Cost inclusive of VAT
Amount
Benchmark
PhP/m2
PhP/m2
649,240.17
8.57
44,765,906.11
591.06
19.74
135.73
341.58
94.01
26,152,263.96
345.30
92.32
252.98
71,567,410.24
Date:
944.93
1/8/2014
MDC BUILDPLUS, INC.
Project Name:
Amaia Scapes Trece Martires
Project Location: Trece Martires, Cavite
Civil Works: Detailed Breakdown
Fixed Lump Sum
Item
Description
Unit
DIVISION 01 - ENABLING WORKS
a.
b.
Mobilization/Demobilization
Community Taxes
lot
lot
Sub Total : DIVISION 01 - ENABLING WORKS
Total ENABLING WORKS
DIVISION 02 - SURVEY WORKS
a.
b.
Line & Grade
Lot Monumenting
mos
lots
Sub Total : DIVISION 02 - SURVEY WORKS
DIVISION 03 - EARTHWORKS FOR BLOCK DEVELOPMENT
a.
Clearing & Grubbing
b.
Soil Stripping
c.
Cut
d.
Engineered Fill
- Borrowed Fill
e.
Hauling & Disposals
- Excess Cut
- Topsoil (Soil Stripping)
f.
Material Testing
m3
m3
m3
m3
m3
lot
Sub Total : DIVISION 03 - EARTHWORKS FOR BLOCK DEVELOPMENT
a.
c.
e.
2
4
g.
3
4
h.
j.
DIVISION 05 - ROAD RIGHT OF WAY
Sub Grade Preparation
Base Coarse
Portland Cement Concrete Pavement (PCCP)
- 3000 Psi (thk = 175 mm)
- 3000 Psi (thk = 150 mm)
Curb & Gutter
- S - Type Curb & Gutter
- Barrier
Concrete Sidewalk
- Concrete Sidewalk (thk = 100 mm)
- Base Coarse
Filling / Levelling of Sidewalk
m2
m3
m2
m2
l.m.
l.m.
m2
m3
m3
k.
m.
Filling / Levelling of Planting Strip
Material Testing
m3
lot
Sub Total : DIVISION 05 - ROAD RIGHT OF WAY
DIVISION 07 - RETAINING WALL/SLOPE PROTECTION
c.
RC Hybrid Retaining Wall
h = 0.50 m
h = 0.75 m
h = 1.00 m
h = 1.25 m
h = 1.50 m
h = 1.75 m
h = 2.00 m
h = 2.25 m
h = 2.50 m
h = 2.75 m
h = 3.00 m
h = 3.25 m
h = 3.50 m
Sub Total : DIVISION 07 - RETAINING WALL/SLOPE PROTECTION
Total CIVIL WORKS
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
lm
SELLING PRICE
TOTAL
Qty
Rate
1.00
1.00
Amount
187,761.25
236,427.25
187,761.25
236,427.25
424,188.50
424,188.50
9.00
546.00
77,931.46
504.26
701,383.11
275,327.25
976,710.37
75,738.30
7,573.83
27,487.72
44.32
44.32
335,672.74
1,218,257.90
23,216.51
110.94
2,575,586.72
4,271.21
15,147.66
1.00
123.32
123.32
192,040.08
526,743.72
1,868,073.64
192,040.08
6,716,374.79
25,214.50
3,450.56
15.65
725.35
394,618.78
2,502,858.17
2,342.60
13,679.40
606.03
527.80
1,419,689.82
7,219,955.44
7,370.00
60.00
437.41
221.65
3,223,684.78
13,298.77
3,920.60
392.06
604.68
279.97
725.35
101.74
1,097,636.53
284,380.46
61,521.24
165.90
1.00
101.74
146,360.01
16,878.97
146,360.01
16,380,882.98
11.00
112.07
161.64
73.68
36.40
18.39
22.55
5.50
8.25
11.00
11.00
8.25
2.75
4,223.79
6,335.68
8,447.58
10,559.47
11,991.96
12,920.21
13,840.78
17,927.19
18,852.71
23,182.44
24,180.27
25,542.83
26,905.40
46,461.68
710,062.18
1,365,425.02
777,989.15
436,547.94
237,656.93
312,109.65
98,599.53
155,534.86
255,006.89
265,982.97
210,728.37
73,989.84
4,946,095.00
29,020,063.13
46,759,386.72
MDC BUILDPLUS, INC.
Project Name:
Amaia Scapes Trece Martires
Project Location: Trece Martires, Cavite
Wet Utilities: Detailed Breakdown
Fixed Lump Sum
Item
a.
c.
c.2
c.4
c.5
Description
DIVISION 08 - POTABLE WATER SYSTEM
uPVC Pipes Class 150 (Color Blue)
- 63 mm Pipes (2")
- 90 mm Pipes (3")
- 110 mm Pipes (4")
- 160 mm Pipes (6")
Unit
l.m.
l.m.
l.m.
l.m.
CI Fittings (Including Concrete Thrust Blocks)
For 63 mm Pipes
- Elbow 90 X 63 mm
- Elbow 45 X 63 mm
- Elbow 22.5 X 63 mm
- Elbow 11.25 X 63 mm
- Tee 63 mm
- Tee Reducer 90 x 63 mm
- Tee Reducer 110 x 63 mm
- Cross Tee 63 x 63 mm
- Cross Tee Reducer 90 x 63 mm
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
For 90 mm Pipes
- Elbow 90 X 90 mm
- Elbow 45 X 90 mm
- Elbow 22.5 X 90 mm
- Elbow 11.25 X 90 mm
- Tee 90 mm
- Tee Reducer 110 x 90 mm
- Tee Reducer 160 x 90 mm
- Cross Tee 90 x 90 mm
- Reducer 110 x 90 mm
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
For 110 mm Pipes
Elbow 90 X 110 mm
Elbow 45 X 110 mm
- Elbow 11.25 X 110 mm
- Tee 110 mm
- Tee Reducer 160 x 110 mm
- Reducer 160 x 110 mm
pcs
pcs
pcs
pcs
pcs
pcs
c.6
-
For 160 mm Pipes
Elbow 45 X 160 mm
Elbow 11.25 X 160 mm
pcs
pcs
Tee 160 mm
pcs
Gate Valve
160 mm
110 mm
90 mm
63 mm
pcs
pcs
pcs
pcs
Air Relief Valve
90 mm
pcs
Fire Hydrants
- 160 mm
- 110 mm
90 mm
pcs
pcs
pcs
d..2
d..3
d..4
e.
Lot Connections
For Single Service
Lot Non-Cross Connections (Single Connections)
20mm tapped to 160mm main
6.50M RROW
20mm tapped to 110mm main
8.00M RROW
6.50M RROW
20mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
20mm tapped to 63mm main
6.50M RROW
ea.
ea.
ea.
ea.
ea.
ea.
ea.
Lot Cross Connections (Single Connections)
20mm tapped to 160mm main
6.50M RROW
20mm tapped to 110mm main
8.00M RROW
6.50M RROW
20mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
20mm tapped to 63mm main
6.50M RROW
For Double Service
Lot Non-cross Connections (Double Connections)
25mm tapped to 160mm main
6.50M RROW
25mm tapped to 110mm main
8.00M RROW
6.50M RROW
25mm tapped to 90mm main
12.00M RROW
8.00M RROW
6.50M RROW
25mm tapped to 63mm main
6.50M RROW
Lot Cross Connections (Double Connections)
25mm tapped to 160mm main
6.50M RROW
25mm tapped to 110mm main
8.00M RROW
6.50M RROW
25mm tapped to 90mm main
8.00M RROW
6.50M RROW
25mm tapped to 63mm main
6.50M RROW
f.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
Irrigation (150mm )
Lot Non-cross Connections
ea.
g.
Lot Connection Marker
ea.
Testing & Commissioning
lot
Sub Total : DIVISION 08 - POTABLE WATER SYSTEM
DIVISION 09 - DRAINAGE SYSTEM
Drainage Crossing 300mm
l.m.
a.1
REINFORCED CONCRETE PIPES (Class II Wall B) (Single Conduit)
- 300 mm Pipes
- d = 1.00 m
- d = 1.25 m
- d = 1.50 m
- d = 1.75 m
- d = 2.00 m
- 375 mm Pipes
- d = 1.25 m
- d = 1.50 m
- d = 1.75 m
- 450 mm Pipes
- d = 1.25 m
- d = 1.50 m
- 525 mm Pipes
- d = 1.50 m
- d = 1.75 m
- d = 2.75 m
- 600 mm Pipes
- d = 1.50 m
- d = 1.75 m
- 750 mm Pipes
- d = 1.75 m
- d = 4.00 m
- 900 mm Pipes
- d = 1.75 m
- 1050 mm Pipes
- d = 2.00 m
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
l.m.
b.A
b.4
b.6
b.8
c.
DRAINAGE STRUCTURES (1 Conduit)
Terrain Inlet Manhole
- TIM 300 mm
- d = 1.25 m
- d = 1.50 m
- d = 2.25 m
- d = 2.50 m
- TIM 375 mm
- d = 1.50 m
- d = 1.75 m
- d = 2.00 m
- d = 2.25 m
- TIM 450 mm
- d = 1.50 m
- d = 1.75 m
- TIM 525 mm
- d = 1.75 m
- d = 2.00 m
- TIM 600 mm
- d = 1.75 m
- d = 2.00 m
- TIM 750 mm
- d = 1.75 m
- d = 2.00 m
- TIM 900 mm
- d = 2.00 m
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
ea.
- TIM 1050 mm
- d = 2.25 m
ea.
Terrain Inlet Box
- TIB 300 mm
- d = 1.50 m
ea.
Area Drain
- AD 300 mm
- d = 1.25 m
ea.
Drainage Outfall
- 750 mm (4.25m)
- 900 mm (2.00m)
- 1050 mm (2.25m)
ea.
ea.
ea.
Collector Pipe
200mm PVC Pipe
100mm End Plug
l.m.
ea.
Anaerobic Trench
750mm
900mm
ea
ea
1050mm
ea
c.
c.1
c.2
c.2
Lot Connections (150 mm PVC)
Stub Out Connected to Manhole
Stub Out Connected to Boxes
Stub Out Connected to PVC Collector Pipe
ea.
ea.
ea.
d.
d.1
Lot Connection Marker
L = 4.0 m
ea.
e.
Testing & Commissioning
lot
Sub Total : DIVISION 09 DRAINAGE SYSTEM
Total WET UTILITIES
SELLING PRICE
TOTAL
Rate
Qty
1,328.00
1,839.00
509.00
298.00
11.00
6.00
7.00
41.00
11.00
11.00
2.00
1.00
1.00
2.00
4.00
16.00
81.00
8.00
5.00
1.00
2.00
4.00
1.00
2.00
24.00
2.00
4.00
2.00
4.00
9.00
444.53
561.15
696.10
1,160.40
976.44
863.66
863.66
863.66
1,119.46
1,247.82
1,653.98
1,451.36
1,487.12
1,181.81
1,067.20
1,067.20
1,067.20
1,451.36
1,856.60
2,691.84
1,819.01
1,400.02
1,730.08
1,559.55
1,559.55
1,966.62
3,059.50
2,035.39
2,284.77
2,284.77
Amount
590,335.28
1,031,947.25
354,315.93
345,798.88
10,740.79
5,181.98
6,045.65
35,410.22
12,314.09
13,726.02
3,307.96
1,451.36
1,487.12
2,363.62
4,268.81
17,075.24
86,443.41
11,610.87
9,283.01
2,691.84
3,638.02
5,600.06
1,730.08
3,119.09
37,429.10
3,933.25
12,237.99
4,070.77
9,139.07
20,562.90
1.00
4.00
6.00
20.00
13.00
1.00
1.00
2.00
4.00
2.00
2.00
7.00
1.00
2.00
22.00
26.00
3,072.33
9,761.60
6,471.06
5,712.83
3,915.83
17,419.97
32,703.89
31,856.50
27,525.39
2,153.66
2,047.31
2,047.31
1,892.36
1,892.36
1,892.36
1,802.51
3,072.33
39,046.41
38,826.37
114,256.68
50,905.74
17,419.97
32,703.89
63,713.00
110,101.56
4,307.32
4,094.61
14,331.14
1,892.36
3,784.72
41,631.90
46,865.23
1.00
3.00
1.00
1.00
4.00
17.00
10.00
1.00
6.00
8.00
4.00
11.00
54.00
54.00
3.00
6.00
4.00
12.00
51.00
26.00
10.00
579.00
1.00
700.00
2,871.54
3,031.99
2,864.21
4,090.94
3,163.97
2,557.99
2,450.72
3,031.99
3,082.42
3,082.42
2,927.47
2,927.47
2,927.47
2,679.93
4,169.79
4,369.66
3,971.75
4,502.83
3,855.32
3,753.55
2,738.41
504.26
217,542.96
1,021.18
2,871.54
9,095.98
2,864.21
4,090.94
12,655.89
43,485.75
24,507.15
3,031.99
18,494.51
24,659.35
11,709.89
32,202.19
158,083.50
144,715.97
12,509.37
26,217.98
15,887.02
54,034.00
196,621.07
97,592.19
27,384.11
291,967.91
217,542.96
4,666,438.36
714,824.00
1,269.00
280.00
54.00
36.00
14.00
312.00
28.00
58.00
207.00
127.00
155.00
39.00
27.00
73.00
78.00
168.00
7.00
36.00
8.00
760.79
846.98
932.24
1,017.51
1,102.78
1,039.43
1,134.78
1,231.05
1,280.38
1,387.65
1,604.56
1,782.43
2,192.26
1,894.06
2,022.41
3,059.37
4,405.29
3,673.86
4,417.71
965,448.08
237,153.68
50,341.15
36,630.35
15,438.86
324,302.61
31,773.92
71,400.97
265,038.07
176,231.24
248,707.24
69,514.77
59,190.96
138,266.04
157,748.21
513,973.99
30,837.04
132,259.07
35,341.64
59.00
9.00
1.00
1.00
18.00
3.00
2.00
1.00
11.00
7.00
7.00
4.00
4.00
4.00
1.00
7.00
3.00
2.00
115.00
5.00
1.00
1.00
1.00
2,160.64
265.00
1.00
1.00
17,071.57
18,602.70
24,635.51
26,817.59
18,602.70
20,784.78
22,462.60
24,635.51
18,602.70
20,784.78
20,784.78
22,462.60
20,784.78
22,462.60
22,609.29
24,323.78
26,139.13
31,621.83
7,618.74
19,032.70
18,244.04
19,769.80
21,388.60
816.91
590.95
287,212.52
407,330.32
1,007,222.83
167,424.28
24,635.51
26,817.59
334,848.55
62,354.33
44,925.19
24,635.51
204,629.67
145,493.45
145,493.45
89,850.39
83,139.11
89,850.39
22,609.29
170,266.48
78,417.38
63,243.67
876,155.52
95,163.48
18,244.04
19,769.80
21,388.60
1,765,037.70
156,600.55
287,212.52
407,330.32
1.00
166.00
177.00
236.00
579.00
1.00
458,133.30
622.94
622.94
1,617.07
504.26
596,118.04
458,133.30
103,407.75
110,260.07
381,628.18
291,967.91
596,118.04
12,648,696.73
17,315,135.09
Summary of Proposal
Part 1.0 Project
Details
Project Name:
AMAIA SCAPES TRECE MARTIRES
Project Location:
TRECE MARTIRES, CAVITE
Co
Part 2.0 Project Cost
Description
Preliminaries
Division 1 ENABLING WORKS
424,188.50
Fixed Lump Sum
CIVIL WORKS
Division 2
Division 3
Division 5
Division 7
SURVEY WORKS
EARTHWORKS
ROAD RIGHT OF WAY
RETAINING WALL/SLOPE PROTECTION
976,710.37
6,716,374.79
16,380,882.98
4,946,095.00
WET UTILITIES
Division 8 POTABLE WATER SYSTEM
Division 9 DRAINAGE SYSTEM
4,666,438.36
12,648,696.73
Overall Total
Qualifications
1
Exculsions
a
b
c
Deepwell
Water Tank
Tree Ball-out
RTIRES
SBU:
GDA (m2)
AMAIA
75,738.30
Cost inclusive of VAT
Amount
Benchmark
PhP/m2
PhP/m2
424,188.50
5.60
29,020,063.13
383.16
12.90
88.68
216.28
65.31
17,315,135.09
228.62
61.61
167.01
46,759,386.72
Date:
617.38
1/8/2014