Pitfalls of Fusing Power Transformers
Pitfalls of Fusing Power Transformers
Background
PG&E is one of the largest combination electric and gas utilities in the United States. It serves
about 15 million customers in the northern and central California. Approximately 20,000
employees serve its 70,000 square mile territory. It is a vertically integrated utility with
Generation, Transmission and Distribution assets. Its transmission system is made up of
approximately 18,610 miles of 500, 230, 115, 70 and 60kV lines.
Introduction
Power transformers are one of the most expensive and difficult to replace components in a power
system. Transformers can be protected by various methods, using circuit breakers, circuit
switchers, Transruptors and fuses. However, there are instances where the infrastructure for
providing full transformer protection cannot be used. The use of circuit breakers requires the
installation of protective relays, a DC system, battery and charger and other associated equipment
such as a control building and, additionally, there may not be room for the installation. In these
cases fuses may be the protection of choice.
1/16
LV
HV Before Fuse
Operates
DLG AB flt
IA = 877 @-84
IB = 439@96
IC = 439 @96
DLG AB flt
IA = 877 @-84
IB = 528@131
IC = 519 @62
DLG AB flt
IA = 439 @-23
IB = 877 @ 157
IC = 439 @ -23
DLG AB flt
IA = 439 @-23
IB = 877 @ 157
IC = 439 @ -23
SLG A phase
IA = 800 @ -86
IB = 300 @ 94
IC = 300 @ 94
IA = 465 @ -86
IB = 233 @ 94
IC = 233 @ 94
DLG AB flt
IA = 0
IB = 0
IC = 0
DLG AB flt
IA = 386 @157
IB = 0
IC = 386 @157
SLG A phase
IA = 0
IB = 233 @ -86
IC = 233 @ -86
IA = 0
IB = 0
IC = 0
LV After Fuse
Operates
DLG AB flt
Ia = 0
Ib = 0
Ic = 0
DLG AB flt
Ia = 2780 @ 6
Ib = 2780 @ 6
Ic = 0
3Io = 5561 @ 6
Ia = 0
Ib = 0
Ic = 0
DLG AB flt
Ia = 1251 @157
Ib = 1251 @ -23
Ic = 0
SLG A phase
Ia = 1350 @94
Ib = 0
Ic = 0
Ia = 0
Ib = 0
Ic = 0
Table 1
2/16
As shown in Table 1 for Double Line to Ground (DLG) faults, the two winding configurations
have current in the intact phases after the first fuse operates, however there is enough fault current
to allow the remaining fuses to operate thereby clearing the fault. The same cannot be said for the
three winding transformers for a sustained SLG fault.
The sequence network for a DLG fault for this winding configuration is illustrated below:
Z1
V1
Z2
Z0
_
+
Z0 h-l
Zsys2
Zsys1
Z2 h-l
Z1 h-l
Figure 1
Delta Wye DLG fault
Shown below is an AB phase DLG fault simulation with the resulting fault current distribution
before and after the fuse operates.
Ia = 5046 amps
IA = 877 amps
Ib = 5136 amps
IB = 528 amps
Ic = 0 amps
IC = 519 amps
Figure 2
Ia = 2780 amps
IA = 0 amps
Ib = 2780 amps
IB = 289 amps
Ic = 0 amps
IC = 286
Figure 3
70/12.47kV XFMR Grounded HV Wye w/ 125E Fuse
DLG fault after fuse operates
3/16
As can be seen in Figures 2 and 3, for the Delta Wye gnd connection for an A-B phase DLG
fault causes one of the 70kV phase fuses to operate after which the current in remaining two
phases increases, causing those fuses to operate. The fuse should be sized adequately to operate
for the resulting fault currents.
Wye Grounded Delta Wye Grounded.
This is one of the most common transformer winding configurations on the PG&E system. The
three winding configurations with the delta tertiary are the configurations in which fault clearing
after the faulted phase fuse operates can be a potential problem. This issue is identified in the
following sections.
A phase SLG Fault
The sequence network for this winding configuration during an A phase SLG fault is illustrated in
Figure 4 below:
Z1
V1
_
+
I1
Zsys1
Z1 h-l
Io
Z2
3Z f
I2
Zsys2
Z2 h-l
Z0
Itr
Zsys0
Z0 t-l
Z0 h-t
Itert
Z0 l-t
Figure 4
A phase SLG Fault
4/16
After the faulted phase fuse operates, the delta tertiary will continue to feed the fault, and the
resulting High Voltage (HV) fault current is not high enough to operate the fuses in the two
remaining phases. The resulting tertiary current can be over five times the rated current resulting in
eventual failure of the transformer if no further mitigating actions are taken The sequence network
model with load impedance neglected, and the solution with matrix equations are shown below as
well. Current values are shown below for a typical fused transformer 10 MVA. The current
values were derived using the Aspen Oneliner Simultaneous faults feature.
Z1
_
+
V1
I1
Zsy
1:1
I1
Z1 h-l
Z2
I1
Z0
Zsy
1:1
I1
Z2 h-l
2I1
Zsy
Z0 t-l
Z0 h-t
3I1 1:1
I1
I1
Z0 l-t
Figure 5
Sequence network for open HV A phase fuse and sustained LV SLG fault
Figure 6 shows a simplification of the above network where the system impedance has been
removed and only reactance is shown:
5/16
j1.0 pu
+-
I1
I1
L4
j0.8345
+
V2
-
I1
V2
L2
+
j0.8345
V1
L1
+
- V1
-j0.0983
j0.9333
V0
I1
j0.5738
L3
2I1
+
V0
-
3I1 (I tertiary)
Figure 6
Simplified sequence network
0 = -V0+j1.62*(2I1)
L4
0 = V1 +V2+V0
Solving the above equations for v1,v2, v0, and I1 on a per
unit basis
v1
v2
v0
I1
:=
1
0
0
1
1
1 1 2.79
0
0
0 1 1.62
0
1 1
0
v1
v2
v0
I1
0.578
0.422
0.155
0.096
6/16
I1 = 0.096
IC
:=
1 1 1 I1
1 a2 a I1
1 a a2 2I1
IA
IB
IC
a2 := .5 .866i
a := .5 + .866i
0.144 0.249i
0.144 + 0.249i
= 825.764
1.73 70000
HV phase currents
IB 825 = 237
amps
IC 825 = 237
amps
100000000
1.73 7200
ITERTpu = 8028
amps
2940000
1.73 7200
Itertrated = 236
amps
7/16
= 565%
Figures 7 and 8 below show the resulting fault currents before and after the fuse operates.
Ia = 6000 amps
IA = 800 amps
Ib = 0 amps
IB = 300 amps
Ic = 0 amps
IC = 300 amps
1485 amps
Figure 7
70/7.2/12.47kV XFMR Grounded HV Wye w/ 125E Fuse
SLG fault before fuse operates
Ia = 1350
IA = 0 amps
Ib = 0 amps
12kV bus SLG
fault
1350 amps
IB = 233 amps
Ic = 0 amps
1334 amps
IC = 233 amps
Figure 8
70/7.2/12.47kV XFMR Grounded HV Wye w/ 125E Fuse
SLG fault after fuse operates
IC = 155A @ 94 deg
Station B Voltages
VAN = 42.1kV @ 0 deg
VBN = 42.1kV @ - 120 deg
VCN = 42.1kV @ 120 deg
IB = 155 A @ 94 deg
IA = 155 A @ 94 deg
If = 155 A
Figure-9
IB = 155 A @
94 deg
IA = 155 A @
94 deg
Station A
70kVbreaker is open
after tripping on SLG
fault
IC = 155 A @
94 deg
3I0 = 465 A
Ia = 0 A
Ic = 0 A
8/16
Ib = 0 A
The example in Figure -9 is the same transformer as used in Figure -7 and 8, tapped on a 70kV
transmission line. The current values were obtained using the Aspen Oneliner Simultaneous
Fault feature. As can be seen in Figure-9 the resulting SLG fault trips the 70kV circuit breaker at
Station A, since the conductor on the other side of the opened phase is still suspended on the tower
the relays on the Station B side of the line do not detect the fault. The fault continues to be back
fed from the HV ground and tertiary winding of the transformer. The resulting fault current is not
high enough to operate the transformer fuses, but the resulting tertiary current can be many times
the rated value resulting in eventual transformer failure. The mitigation features listed below can
Mitigation Methods:
Unground the HV winding this will remove the zero sequence path from the HV
winding thereby removing the fault.
o If this method is used ensure the HV winding, H0 bushing, and lightning
arrestors are rated for L-L voltage (For transformers 69KV and above
graded insulation toward the neutral, therefore this is not an option).
Trip station HV circuit breaker (if available).
o A tertiary relay can be installed to trip the station breakers (this may not be
an option if the bank was fused in the first place).
Fuse the tertiary winding This will also open the zero sequence path thereby
removing the fault after the faulted phase fuse operates.
o Ensure the fuse coordinates with transmission and distribution ground
relays. Due to the size of the fuse and the magnitude of the resulting tertiary
fault current there may be a problem coordinating with downstream and up
stream ground protective devices. Subsequent operation of this fuse may
not be detected resulting in an open tertiary winding resulting in power
quality problems, notably triple harmonic distortion on the loads served by
this transformer.
Open the tertiary winding.
o Discuss with the transformer manufacturer whether the transformer can be
operated with the tertiary winding open.
o Since this winding is used to suppress third harmonic currents from the
transmission system operation of this winding open should be discussed
with the distribution engineer to determine if there have been power quality
issues or complaints related to electrical noise on the feeders served by this
transformer.
Transformers with a virtual tertiary winding configuration where the tertiary
is not accessible. For transformers with a virtual tertiary opening the tertiary
winding is not an option. The following alternatives are available:
o Do not fuse the bank, install circuit interrupting device.
o Install CT and relay on HV neutral and trip station HV breakers, if available
or trip LV feeder breakers.
It should be noted with the tertiary winding open either intentionally or when the tertiary
fuse operates the tertiary winding will no longer feed the fault, however load will continue
to be supplied from the remaining two phases resulting in single phasing the load.
9/16
The Wye Ungrounded Delta Wye grounded configuration is another one of the more common
configurations on the PG&E system. Operating with the HV winding ungrounded is limited to
70kV and below, where the HV winding and Ho bushing is fully insulated for the LineLine
voltage. At 70kV and above windings generally cannot operate with the neutral lifted since the
windings consist of graded insulation, where the H0 portion of the winding is rated at 12kV.
For a single line to ground fault on this type of winding configuration when the fuse operates the
lifted HV ground opens the zero sequence path thereby extinguishing the fault. It should be noted
the loads supplied by this transformer will be single phased. The sequence network for this
winding configuration for an A phase SLG fault is shown in Figure 10.
Z1
V1
_
+
Zsys1
Z1 h-l
Z2
3Z f
Zsys2
Z2 h-l
Z0
Z0 t-l
Zsys0
Z0 h-t
Z0 l-t
Figure 10
A phase SLG with HV winding H0 lifted, before the fuse operates
10/16
Z1
V1
_
+
1:1
I1
Zsy
I1
Z1 h-l
Z2
I1
Z0
Zsy
I1
1:1
Z2 h-l
1:1
Z0 t-l
Zsy
I1
I1
Z0 h-t
Z0 l-t
Figure 11
SLG after A phase HV fuse Operates
Figure 11 shows the sequence network after the fuse operates, in which I1 will go to zero. Figures
12 and 13 show the fault current simulation associated with the fault for an A phase single line to
ground fault, before and after the fuse operates.
Ia = 5800 amps
IA = 600 amps
Ib = 0 amps
IB = 300
Ic = 0 amps
IC = 300 amps
1941
Figure 12
70/7.2/12.47kV XFMR Ungrounded HV Wye w/ 125E Fuse
SLG fault before fuse blows
IA = 0 amps
Ia = 0 amps
Ib = 0 amps
IB = 0 amps
Ic = 0 amps
IC = 0 amps
0 amps
Figure 13
70/7.2/12.47kV XFMR Ungrounded HV Wye
SLG fault after fuse blows, fault is cleared.
11/16
Open phase
VA
VB
3VBN
2
3VBN
2
0 volts
VC
Vb
Va
o
Vc
Figure 14
Effects of open phase on LV winding voltage
Primary Winding
voltages
VBC = 3VBN
Secondary Winding
voltages
Vbc = 3VBN
VBN = 3VBN
2
VCN = 3VBN
2
VAO = 0 volts
VbN = 3VBN
2
VcN = 3VBN
2
Vao = 0 volts
3 + 0i
VC:=
VB:=
VA := 0
( 0) i
a := .5 + .866
a2 := .5 .866
arg ( a) = 120.001deg
arg ( a2) = 120.001deg
VB = 0.866
arg ( VB) = 180deg
12/16
va2
1 a a2 VC
va0 0
va1 = 0.5i
va2
0.5i
va1 = 0.5
Resulting phase and sequence vectors for an open HV winding A phase fuse.
Vc 6.6kV @ 0 deg
Va2 3.8kV @ -90
13/16
Feeder
Breakers
12MVA
70/12.47kV
HV Wdg
Ungrounded
52-1
52-2
52-3
47
Figure 15
Example of Phase Voltage Negative Sequence Tripping for fuse
protected XFMR
14/16
12MVA
70/12.47kV
HV Winding
Grounded
52-1
52-2
52-3
51TT
Figure 16
Tertiary over current relay installed to trip and lock out feeder breakers
15/16
Summary
Fusing transformers is not as straight foreword as it seems, certain winding configurations can lead
to sustained faults that cannot be cleared even after the faulted phase fuse operates. Care should be
taken to ensure fault simulations take into account the unique winding configurations to ensure the
transformer is fully protected with the designated fuses, both before and after the fuse operates.
For those transformer configurations where fusing may not adequately clear a sustained fault there
are mitigation measures that can be taken to eliminate the issue. If these methods cannot be
applied fuses should not be used and a three phase interrupting device should be applied.
References:
IEEE Std C37.91 2008 IEEE Guide for Protecting Power Transformers
Biography:
Mike Jensen is a Supervising Protection Engineer with Pacific Gas and Electric, with 17 years of
transmission protection, substation design, nuclear power plant maintenance and design
experience. Served 6 years in the U.S. Navy on board nuclear submarines. Received a BS in
Electrical Engineering from California Polytechnic University, San Luis Obispo in 1992 and is a
16/16