400 KV MSDS-1 , JSPL Angul
TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL &INSTRUMENTATION
MONTHLY MAINTENANCE OF TRANSFORMER
Switchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.
ACTIVITY
Check Colour of Silica Gel in Breather ,If crystals are Pink,Replace
with Reactivated Crystals.Check Oil Level in Oil cup,Top-up if
required
Checking of Oil Leakage ,rectify wherever found.
Oil pumps and cooling fans to be cleaned and lubricated and
trailrun of each fans and pumps .
Checking of insulation & bushing and inspection for any crack/
chipping &oil level
BDV &DGA test to be made
YES/NO
Signature of
Maintenance Engg.
400 KV MSDS-1 , JSPL Angul
Doc. No.:- E&I/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000
MONTHLY MAINTENANCE OF TRANSFORMER
REMARKS
Signature of
Substation Incharge
400 KV MSDS-1 , JSPL Angul
TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL (O&M)
QUARTERLY MAINTENANCE OF TRANSFORMER
Switchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.
ACTIVITY
YES/NO
Whether permit on the transformar taken.
Whether the bay and the transformer in which maintenance is to done is
identified correctly and the primary part discharged with the help of
portable earth rod.
Whether isolation of deluge (Fire fighting) system is done.
Whether oil BDV, DGA,Oil PPM taken and recorded.
Whether Ground level earth connection on transformer & Transformer LA.
Clean Corrosion as Required
Electrical Checking of Bucholz relay, Oil Surge Relay & Pressure Relieve
Devices
Whether permit cancelled after completing the job.
Permit No.:
Observation
Date:
Signature of
Maintenance Engg.
400 KV MSDS-1 , JSPL Angul
Doc. No.:- ELE (O&M)/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000
LY MAINTENANCE OF TRANSFORMER
REMARKS
PTW No.
Signature of
Substation Incharge
400 KV MSDS-1 , JSPL Angul
TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL &INSTRUMENTATION
MAINTENANCE OF TRANSFORM
Switchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.
1
2
3
6
12
ACTIVITY
Whether permit on the transformar taken.
Whether the bay and the transformer in which maintenance is to done is
identified correctly and the primary part discharged with the help of portable
earth rod.
Whether isolation of deluge (Fire fighting) system is done.
Inspection of main and OLTC MB's /contactors/ switches etc. to be carried
out.for mark of overheating in the TB/power & control cable.
Take Main Tank & OLTC Tank oil samples. Carry out DGA ,BDV &Oil PPM Tests &
Record Results
14
Calbration of OTI and WTI to be carried out and Oil level in thermometre oil
pockets checking and charging.
Cooling system , buchholz relay ,oil surge relay &PRV, interlock etc. to be
checked .
15
Whether permit cancelled after completing the job.
16
Manual/ Auto starting of oil pumps & fans checked.
17
Permit No.:
13
18
Observation
Signature of
Maintenance Engg.
Date:
SDS-1 , JSPL Angul
Doc. No.:- E&I/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000
CE OF TRANSFORMER
YES/NO
REMARKS
PTW No.
Signature of
Substation Incharge
400 KV MSDS-1 , JSPL Angul
TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL &INSTRUMENTATION
YEARLY MAINTENANCE OF TRANSFO
Switchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.
1
2
3
4
ACTIVITY
Whether permit on the transformar taken.
Whether the bay and the transformer in which maintenance is to done is
identified correctly and the primary part discharged with the help of portable
earth rod.
Whether isolation of deluge (Fire fighting) system is done.
The radiators clened externally.
The insulation & bushing are cleaned and inspection for any crack/ chipping
carried out.
Inspection of main and OLTC MB's /contactors/ switches etc. carried out.for
mark of overheating in the TB/power & control cable.
Inspection of OLTC operation .
Neutral Earth Pit Resistance
Cleaning of oil pumps and cooling fans and lubrication and trailrun of each
fans and pumps .
9
10
Oil level of conservator tank, HV bushing checking and topping.
Insepection of Oil leakage and gasket damages and rectified wherever found.
11
Insepection of LV bushing chamber for any oil seepages.
12
Carry out IR Measurment & PI of wdgs
Tan delta,oil BDV, DGA,Oil PPM,winding resistance,IR value test to be taken
and recorded.
13
14
15
Calbration of OTI and WTI to be carried out and Oil level in thermometre oil
pockets checking and charging.
Checking of cooling system , buchholz relay , interlock etc.
16
17
18
19
Whether permit cancelled after completing the job.
Manual/ Auto starting of oil pumps & fans checked.
Permit No.:
Observation
Signature of
Maintenance Engg.
Date:
SDS-1 , JSPL Angul
Doc. No.:- E&I/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000
NANCE OF TRANSFORMER
YES/NO
REMARKS
PTW No.
Signature of
Substation Incharge
400 KV MSDS-1 , JSPL Angul
TITLE
DEPARTMENT MAINTENANCE FORMAT FOR TRANSFORMER
DEPARTMENT : ELECTRICAL 7INSTRUMENTATION
MAINTENANCE OF TRANSFORMERSwitchyard Name :
Equipment Name :
DATE :
MAKE :
RATING :
S. No.
1
2
3
4
5
6
ACTIVITY
Whether permit on the transformar taken.
Whether the bay and the transformer in which maintenance is to done is
identified correctly and the primary part discharged with the help of portable
earth rod.
Whether isolation of deluge (Fire fighting) system is done.
Inspect Selector & Diverter Switch and Maintain in accordance with
Manafacturer's specification
Measurment of Winding resistance at all tap position
Measurment of winding Turns Ratio
Whether permit cancelled after completing the job.
Permit No.:
Observation
Signature of
Maintenance Engg.
Date:
SDS-1 , JSPL Angul
Doc. No.:- E&I/SW/01/001
Issue No. / Date:- 001/01-12-2012
Rev. No / Date:000/00-00-000
OF TRANSFORMER-5 YEAR
YES/NO
REMARKS
PTW No.
Signature of
Substation Incharge