Estimating Soil Hydrological Characteristics From Soil Texture and Structure
Estimating Soil Hydrological Characteristics From Soil Texture and Structure
Annex 1
where:
K = permeability (m/d).
m50 = median size of grains above 50 m. Half of the weight is above this size, half
below.
TABLE A1.1
Structure
K
(m/d)
C, heavy CL
C, CL, SC, sCL
0.010.02
0.100.20
0.010.05
> 10
0.010.03
0.010.1
0.030.08
0.10.4
0.060.12
0.31.0
0.120.18
1.03.0
Loamy sand
Medium crumb
0.150.22
1.66.0
Fine sand
Single grain
0.150.22
1.66.0
Medium sand
Single grain
0.220.26
>6
Single grain
0.260.35
>6
116
Guidelines and computer programs for the planning and design of land drainage systemss
The presence of silt (< 50 m) and especially clay (< 2 m) will lower this value
considerably. Therefore, this formula should not be used for such soils.
REFERENCES
FAO. 1980. Drainage design factors. FAO Irrigation and Drainage Paper No. 38. Rome. 52 pp.
USBR. 1984. Drainage manual. A Water Resources Tech. Publication. Second printing. Denver,
USA, US Dept. of Interior, Bureau of Reclamation. 286 pp.
117
Annex 2
GUMBELS METHOD
The Gumbel distribution can be used for extrapolating from a limited number of
extreme values (Gumbel, 1954 and 1958). The basic data appear in groups, such as
the daily rainfall in August (31 days per year), or the water levels in a river per year
(365/366 days). The highest value in such a group is the extreme. The groups should
contain at least ten elements, and the minimum number of extremes (often years) is at
least ten.
The method assumes that the underlying process remains constant. This supposition
is doubtful because of recent climate changes, which also influence data such as river
flows. These changes are especially noticeable in the extreme values. Therefore, the
method should be used with care.
Extreme values are obtained as follows:
Select the highest (sometimes lowest) value in a group, e.g. the highest autumn
rainfall or the highest river discharge in a year. Each group should contain at least
ten values.
These extremes are sorted according to their magnitude in order to prepare for
further analysis.
The probability that a certain value x does not exceed a limit x0 is:
with
(1)
where:
P = probability;
n = number of extremes;
u = constant (shift);
x = values of the extremes. The average is the standard deviation is sx;
x0 = limiting value;
y = reduced Gumbel variable, with average c and standard deviation sy. For y and
for a very large number of observations, c = 0.57722 = Eulers constant;
= constant (slope).
The probability that x exceeds x0 is:
(2)
The return period T is the number of groups in which the limit x0 is exceeded. If
there is one group per year, T is in years (as in the above examples). T is defined as:
(3)
For the x values, the procedure is:
118
Guidelines and computer programs for the planning and design of land drainage systems
standard deviation of y.
Table A2.1 shows the values derived by Kendall for a smaller number of
observations.
The line y = (x - u) has two parameters: the slope , and the shift u. They can be
found by plotting on Gumbel probability paper, usually with the return period T on
the horizontal axis, the value of the extremes on the vertical. The line may be drawn
visually through the points to allow extrapolation. In this way, the once-per-century
rainfall or the river discharge can be estimated. This is even possible for much longer
return periods.
The program GUMBEL calculates the parameters automatically and provides
estimates for the extremes to be expected with a certain return period.
For agricultural drainage design, a return period of 210 years is often taken, 2
5 years for field drainage and even 10 years for crop systems with high planting costs,
and 510 years for the main system where it does not affect inhabited places.
By extrapolation, a prediction can be given over much longer periods of time in order
to obtain estimates for values to be expected once in 100 years (the once-per-century
value) and even for much longer times. However, the uncertainty of the estimates
becomes very large for such longer return periods. Moreover, for such periods (and
even for a century), the basic data series cannot be considered as constant, owing to
human and geological influences.
Nevertheless, such a prediction is valuable for engineering purposes, e.g. the height
of a river embankment able to withstand a 100-year flood. This will almost certainly
not occur 100 years later, but it has a
TABLE A2.1
chance of 1 percent of occurring next
Values of c and sy as a function of n
year.
n
c
s
The influence of climate changes
10
0.495
0.950
can be analysed by comparing data
15
0.513
1.021
from the last 1020 years with earlier
20
0.524
1.063
ones (where available), and it is wise
25
0.531
1.092
to employ the worst prediction.
30
0.536
1.112
40
0.544
1.141
Where not different, the basic data
50
0.548
1.161
include recent changes already.
y
REFERENCES
Gumbel, E.J. 1954. Statistical theory of extreme values and some practical applications. Applied
mathematics series 33. U.S. Dept. of Commerce, National Bureau of Standards.
Gumbel, E. J. 1958. Statistics of extremes. New York, USA, Columbia Press.
119
Annex 3
FIGURE A3.1
Groundwater
Initial level y 1
Final level y 2
y
H
Final level y 2
Initial level y 1
h1 h2
120
Guidelines and computer programs for the planning and design of land drainage systems
3. Pump water out (e.g. with a bailer) several times and let that water flow back into
the hole.
4. Let the groundwater (where present) fill the hole until equilibrium. For
impermeable soils, return the next day; for permeable soils, a few hours are
sufficient (sometimes even a few minutes).
5. Measure the groundwater depth below soil surface.
6. Pump water out.
7. Measure the rise of the water level over time. Time intervals should be short
initially.
Example
The following data can be considered:
Depth of 8-cm diameter hole: 150 cm;
Groundwater at equilibrium: 50 cm;
Water level, first measurement: 8583 cm, t = 20 s;
Water level, second measurement: 8078 cm, t = 24 s;
Water level, third measurement: 7068 cm, t = 31s;
Impermeable base: deep (300 cm).
From these data (all distances below soil surface), the average permeability K
follows. This value is the mean value (mainly horizontal) between the groundwater
table and a few centimetres below the bottom of the hole.
It should be noted that:
The permeability of different layers can be found from measurements in holes of
different depths, but this is not very reliable; the piezometer method is better.
The first measurement may deviate because water is still running off the wall; in
this case, it should be discarded.
Measurements soon after lowering by pumping the water out are preferred.
The above methods cannot be used without an existing groundwater table at the time
of measurement. The following methods can be used in such cases. However, they are
less reliable.
The inverse method, also known as the Porchet method, may be also applied to
determine the saturated hydraulic conductivity above the groundwater level. In this case,
water is poured into an augered hole and the rate of lowering of the water level inside
the hole is measured (Figure A3.1). The measurements are taken after water has been
infiltrating for a long time until the surrounding soil is sufficiently saturated (in order
to diminish the effect of unsaturated soil on the rate of drawdown). The equation used
to calculate the K value has been derived from the balance between the water flowing
through the side walls and bottom of the hole, and the rate of lowering of the water
level in the hole. The basic assumption is that the flow gradients are unity. Although less
reliable than the measurements using an existing water table, it is often necessary where
measurements must be made outside a wet period in dry soils. However, many dry soils
swell so slowly that their permeability can only be reliably measured by the auger-hole
method during the wet season.
Van Hoorn (1979) made a comparison between normal and inverse methods and
found reasonably corresponding values for K, thus confirming the assumption about the
gradient.
Theory
According to Ernst and Westerhof (1950), Van Beers (1983) and Oosterbaan and
Nijland (1994), for the auger-hole method, the saturated soil permeability is calculated
using:
K =C
dy
(1)
dt
in which:
4000
C=
121
r
y
(2a)
y
H
+ 20 2
H
r
where the bottom of the hole is far above the impermeable base (D > H/2), or:
3600
C=
r
y
(2b)
y
H
+ 10 2
H
r
where the bottom of the hole reaches the impermeable base (D = 0). In these
formulae:
C
= constant, depending on hole geometry;
dy/dt
= rate of rise in water level (cm/s);
D
= depth of impermeable layer below bottom (cm);
h = H - y = height of water column (cm);
= initial and final water column in hole (cm);
h1,h2
H
= depth of borehole below groundwater (cm);
K
= average soil permeability (m/d);
r
= radius of borehole (cm);
t
= time (s);
y
= depth of water level below groundwater (cm);
= average value of y in the interval where y > 3/4y0 (cm);
dy y1 y2
dt
t2 t1
(3)
Where the impermeable base is close to the bottom of the hole, an interpolation
between Equations 2a and 2b is used.
For the inverse method, Oosterbaan and Nijland (1994) recommend:
r
r
2
ln
K=
r
2(t2 t1 )
h2 +
2
h1 +
(4)
(5)
Guidelines and computer programs for the planning and design of land drainage systems
122
FIGURE A3.2
y2
y1
PIEZOMETER METHOD
FOR DETERMINING SOIL
PERMEABILITY
D
The piezometer method is more
d
Impermeable layer
convenient than the auger-hole
method for measurements of the K
value in stratified soils and in layers
deeper than 3 m. In these cases, water is pumped out of a piezometer, of which only
the lowest part is open, while the upper part of the hole is protected by a pipe. The
rate of rise in the water level inside the tube is measured immediately after pumping.
Therefore, the K value of the small layer of soil near the open part is determined.
L
Method
The piezometer method (Luthin and Kirkham, 1949) differs from the auger-hole method
in that the upper part of the hole is covered by a non-perforated pipe (Figure A3.2).
The lower part of the borehole is open and collects the water from a specific layer. In
this way, the permeability of separate layers can be found easily.
The procedure is as follows:
1. Make an auger hole and cover the upper end with a tightly fitting pipe, while the
remaining open part acts as the water-collecting cavity, or cover the entire hole
and make a narrower cavity below the pipe with a smaller auger.
2. Measure the groundwater depth at equilibrium.
3. Pump some water out and measure the rise in water level at different times.
It is most convenient to take all measurements with reference to the top of the
protecting pipe. The computer program PIEZOM is based on Kirkhams formula.
It calculates the permeability K (in metres per day) from these observations and the
geometric factors.
Theory
The basic formula is:
(6)
where A is a factor depending on the geometry of the piezometer and the hole below
the end of the piezometer and 864 a constant for converting centimetres per second
(for K) to metres per day. Various authors (Luthin and Kirkham, 1949; Smiles and
Youngs, 1965; Al-Dhahir and Morgenstern, 1969; Youngs, 1968) have provided graphs
or tables for A. Except for very small distances between the top of the piezometer and
groundwater (and within certain limits), the tables for A/d given by Youngs (1968)
(with the necessary corrections for diameter rather than radius) may be approximated
by empirical formulae for the two limiting cases and for the standard value H = 8d:
L
= 4.40
d
d
A8
123
0.661
+ 2.6
(7a)
where the bottom of the cavity hole is at the impermeable base, and:
A
L
= 4.40
d
d
0.661
L
+ 0.2 0.06 1
d
(7b)
where the bottom of the cavity hole is far above the impermeable base (more than
four times the cavity diameter). For H/d less than eight, rather complicated corrections
are made to obtain A/d.
For H/d greater than ten, no values are tabulated. As an approximation, it is
supposed that for H/d > 8 the cylindrical cavity may be represented by a sphere and
that the remaining flow is radial. For this part of the flow, the inner radius is r8 = 8d
+ L/2, whereas the outer radius is taken as the depth of the cavity centre below the
groundwater level, H + L/2. These approximations are used in the program PIEZOM;
the corrections are small because most of the resistance to flow occurs immediately
around the cavity. They are:
A A8 (1 / ro 1 / r8 )
=
d d 1 / ro 1 / r *
(8)
where:
ro =
(9a)
4 / A8 + 1 / r8
r8 = 8d + L / 2
r* H + L / 2
(9b)
for H>8d
= 3.14
(9c)
124
Guidelines and computer programs for the planning and design of land drainage systems
REFERENCES
Al-Dhahir, Z.A. & Morgenstern, N.R. 1969. Intake factors for cylindrical piezometer tips. Soil
Sci., 107: 1721.
Amoozegar, A. & Wilson, G.V. 1999. Methods for measuring hydraulic conductivity and
drainable porosity. In R.W. Skaggs & J. Van Schilfgaarde, eds. Agricultural drainage, pp. 1149
1205. Agronomy Series 38. Madison, USA.
Ernst, L.F. & Westerhof, J.J. 1950. A new formula for the calculation of the permeability factor
with the auger hole method. Translated from the Dutch by H. Bouwer (1955). Ithaca, USA,
Cornell University.
Luthin, J.N. & Kirkham, D. 1949. A piezometer method for measuring permeability of soil in
situ below a water table. Soil Sci., 68: 349358.
Oosterbaan, R.J. & Nijland, H.J. 1994. Determining the saturated hydraulic conductivity.
In H.P. Ritzema, ed. Drainage principles and applications, pp. 435475. 2nd edition. ILRI
Publication 16. Wageningen, The Netherlands, ILRI.
Smiles, D.E. & Youngs, E.G. 1965. Hydraulic conductivity determinations by several field
methods in a sand tank. Soil Sci., 99: 8387.
USBR. 1984. Drainage manual. A Water Resources Tech. Publication. Second printing. Denver,
USA, US Dept. of Interior, Bureau of Reclamation. 286 pp.
Van Beers, W.F.J. 1983. The auger-hole method; a field measurement of the hydraulic
conductivity of soil below the watertable. 6th edition. ILRI Bulletin 1. Wageningen, The
Netherlands, ILRI.
Van Hoorn, J.W. 1979. Determining hydraulic conductivity with the inversed auger hole
and infiltrometer methods. In J. Wesseling, ed. Proceedings of the International Drainage
Workshop, pp. 150154. ILRI Publication 25. Wageningen, The Netherlands, ILRI.
Youngs, E.G. 1968. Shape factors for Kirkhams piezometer method for soils overlying an
impermeable bed or infinitely permeable stratum. Soil Sci., 106: 235237.
125
Annex 4
Figure A4.1
Relationships between the values of K and
0.3
O
-FA
BR
US
0.2
0.1
0.09
0.08
0.07
0.06
ers
n
Va
Be
1
2
3
0.05
0.04
1
ESTIMATIONS FROM
0.02
2
3
PERMEABILITY
Another option is to estimate the
0.5 0.7 0.9
0.04 0.06 0.08
0.3
K (m/d)
0.01
value from empirical relationships
2 3 4 5 6 7 8 9 10
0.05 0.07 0.1
0.2
0.4 0.6 0.8 1
between the macroporosity and the
Note: 1. all clay content; 2. less than 15% clay; 3. 15 < clay < 30%.
hydraulic conductivity. Figure A4.1
Source: Adapted from Chossat and Saugnac, 1985.
shows the relationships developed
by Van Beers (ILRI, 1972) and the
USBR (1984) and those obtained by Chossat and Saugnac (1985) for soils with different
clay contents.
However, as there are large variations, the field methods described below may be
preferable.
OBSERVATIONS OF GROUNDWATER-LEVEL VARIATIONS
A better method is to measure the rise in groundwater level at short intervals, for
example, before and soon after a heavy rain of short duration. The rainfall is divided
by the observed rise, both expressed in the same units. If a sudden rain of 20 mm and
no runoff causes a rise of 40 cm = 400 mm, = 20/400 = 0.05 (5 percent).
In drained lands, the fall in a rainless period can also be used, in combination with
drain outflow measurements, as described in Annex 8.
LARGE CYLINDER
A more laborious method uses a large cylinder of undisturbed soil, carefully dug out.
An oil drum (without its bottom) pushed tightly over the remaining column of soil
is suitable for the purpose. After taking out, a new bottom is made by sealing the
container to a plastic plate or welding it to a steel one. Water is added, and the water
table rise inside is measured.
REFERENCES
Chossat, J.C. & Saugnac, A.M. 1985. Relation entre conductivite hydraulique et porosite de
drainage mesurees par la methode du puits et des piezometres. Sci. du Sol, 1985/3.
126
Guidelines and computer programs for the planning and design of land drainage systems
ILRI. 1972. Fieldbook for land and water management experts. Wageningen, The Netherlands.
USBR. 1984. Drainage manual. A Water Resources Tech. Publication. Second printing. Denver,
USA, US Dept. of Interior, Bureau of Reclamation. 286 pp.
127
Annex 5
128
Guidelines and computer programs for the planning and design of land drainage systems
AQUIFER TRANSMISSIVITY
The transmissivity of an aquifer is the product of permeability and thickness (KD). In
regional groundwater flow, the distances are so large (mostly several kilometres) that
the entire thickness of the aquifer can be taken. In almost all cases, it will be thin in
comparison with one-third of this distance, so that the real thickness can be taken for
D.
Estimations of the average value of KD may be made by means of a regional
approach, by applying Darcys Law to the flow area:
(1)
The hydraulic gradient, s (dimensionless), is determined on the isohypses map.
The discharge Q (cubic metres per day) over a length L (perpendicular to the flow) is
measured or derived from a water balance.
Therefore, if Q is 2 m3/d over a length of 50 m, and s = 2/1 000, KD = 20 (square
metres per day). If the layer has a thickness of 5 m, K = 4 (metres per day).
For drained fields, the KD values can be determined by field observations if the
impervious layer is not deeper than 35 m from the rise in water level in between
existing open drains and the water level in the drains and the estimate of outflow to the
drainage system at the moment of measuring. Additional details on measurement of KD
can be consulted in Annex 8. From the KD value and the measured K, it is possible to
derive the D value. Where the thickness of the aquifer is greater, pumping tests in drilled
wells are required, or regional methods can be applied (described above).
VERTICAL RESISTANCE
Another parameter, useful for estimating regional flow, is the vertical resistance (c).
Many aquifers are covered by a less permeable (but not impermeable) layer. They
are semi-confined. In many river valleys, there is a clay layer on top of a thick
sandy aquifer, the top layer formed in the Holocene, the lower one in the Pleistocene.
Groundwater has to pass through the top layer twice: first, as downwards leakage; at
the end, as upward seepage.
Such resistive layers are characterized by their thickness (D) and their
vertical permeability (Kv), and c is their proportionality quotient for vertical flow
contribution:
(2)
For a clay with Kv = 0.001 m/d and D = 2 m, the vertical resistance is c = 2 000 days.
This value is expressed in days, as electrical resistance is in Ohms. A head difference
of 1 m between bottom and top will cause upward seepage of 1/2 000 m/d or about
180 mm/year. If this groundwater contains diluted seawater, with 11 kg/m3 of salts,
the annual salt load will be about 20 tonnes/ha. Even if the water seeping upward
through the clay cap is less salty, it will cause heavy topsoil salinization in the long
run, especially in arid and semi-arid regions.
CHARACTERISTIC LENGTH
The combination of transmissivity and resistance determines the properties of the
system. Thus, the characteristic length () is a measure for the extent of seepage zones
and is roughly equal to their width. It is found from:
(3)
where:
c = vertical resistance of covering layer (d);
d = equivalent thickness of aquifer (m);
K = permeability of the aquifer (m/d);
= characteristic length (m).
Values for c are found from pumping tests, estimated directly from experience or
derived form the thickness D and the (measured or estimated) vertical permeability
Kv of the upper layer. Pumping tests are the most reliable method (and supply values
for KD at the same time). Methods for pumping tests are described in the bibliographic
references (Boonstra and De Ridder, 1994; Kruseman and De Ridder, 1994).
Models for such regional flow, such as SAHYSMOD (ILRI, 2005), are also
available.
REFERENCES
Boonstra, J. & De Ridder, N.A. 1994. Single-well and aquifer tests. In H.P. Ritzema, ed. Drainage
principles and applications, pp. 341375. 2nd edition. ILRI Publication 16. Wageningen, The
Netherlands, ILRI.
Hooghoudt, S.B. 1940. Algemeene beschouwing van het probleem van de detailontwatering en
de infiltratie door middel van parallel loopende drains, greppels, slooten en kanalen. Versl.
Landbouwk. Onderz., 46(14).
ILRI. 2005. SAHYSMOD, spatial agro-hydro-salinity model. Version 1.7. Description of
principles, user manual and case studies. SAHYSMOD working group of ILRI. Wageningen,
The Netherlands. 134 pp.
Kruseman, G.P. & De Ridder, N.A. 1994. Analysis and evaluation of pumping tests data. ILRI
Publication 47, 2nd. Wageningen, The Netherlands, ILRI. 377 pp.
129
131
Annex 6
Guidelines and computer programs for the planning and design of land drainage systems
132
peak period is about 66 mm (ETc 5.5 mm/d). Therefore, deep percolation is about
21 mm and the average value in the period considered is 1.75 mm/d.
PREDICTING DEEP PERCOLATION IN NEW IRRIGATION PROJECTS
Where the irrigation and drainage systems are designed jointly in new developments,
the amount of expected percolation can be determined during the calculation of
irrigation requirements from water retention data:
(3)
being:
(4)
where:
ea = ETc/I = application efficiency (0.001.00), which represents the ratio between
the amount of water consumed by crops and the gross application
depth;
= average thickness of the rootzone (m);
Zr
fc
= soil water retained at field capacity (m3/m3);
i
= minimum soil water fraction that allows for non-stress of the crop
(m3/m3).
Where the i value is unknown, the amount of water readily available to the crops
can be estimated as approximately half the interval between field capacity and the
permanent wilting point:
(5)
where:
wp = soil water retained at wilting point (m3/m3).
For this calculation, an average value of ea must be assumed (see below).
ESTIMATIONS WHERE NO FIELD DATA ARE AVAILABLE
In the planning phase, field data for the project area are usually scarce or non-existent.
In these cases, tentative values for ea and R can be used from literature.
In 1980, FAO provided information on water management from irrigated lands
of arid zones (FAO, 1980). These guidelines considered only readily obtainable data,
such as soil texture and irrigation method and some qualitative information on water
management at the field level (Table A6.1).
TABLE A6.1
Application practices
Soil texture
Fine
Coarse
Fine
ea (%)
Sprinkler
Coarse
R (%I)
60
60
30
30
Night application
70
70
25
25
80
80
15
15
60
45
30
40
Trickle
Basin
75
60
20
30
55
40
30
40
65
50
25
35
133
TABLE A6.2
Distribution
uniformity
SJVDIP, 1999
Estimated deep
percolation
(%)
Sprinkler
Periodic move
7080
6580
7080
1525
Continuous move
7090
7585
8090
1015
Solid set
9095
8590
7080
510
Drip/trickle
8090
7590
8090
520
Furrow
8090
6090
7085
525
Border
7085
6580
7085
1020
Basin
9095
7590
Surface irrigation
520
Note: Estimates for deep percolation were made on the basis of the following assumptions: no surface runoff under drip and
sprinkler irrigation; daytime evaporation losses can be up to 10 percent sprinkling and 5 percent during night irrigation; tailwater
in furrow and border irrigation can be up to 10 percent and evaporation losses up to 5 percent; no runoff is expected in basin
irrigation and evaporation losses up to 5 percent (FAO, 2002).
Sources: Tanji and Hanson, 1990; SJVDIP, 1999.
In the past 20 years, considerable efforts have been made to improve irrigation
application efficiencies in order to save water. Table A6.2 shows data from well-designed
and well-managed irrigation systems in California, the United States of America, and
potential maximum values for application efficiencies determined in irrigation evaluations
in the San Joaqun Valley Drainage Implementation Program as mentioned in FAO
(2002).
Tables A6.1 and A6.2 contain data from different types of systems and management.
According to the expectations of a specific project area, the order of magnitude for
a first approach to deep percolation can be estimated with the help of these tables.
However, sensitivity analyses with various values should be performed in order to
see the consequences in case the estimates are not correct. In addition, after the first
parts of the irrigation system have been constructed, a direct verification in the field is
recommended.
REFERENCES
FAO. 1974. Effective rainfall, by N.G. Dastane. FAO Irrigation and Drainage Paper No. 25.
Rome. 68 pp.
FAO. 1977. Crop water requirements, by J. Doorenbos & W.O. Pruitt. FAO Irrigation and
Drainage Paper No. 24, revised edition (reprinted 1992). Rome. 144 pp.
FAO. 1980. Drainage design factors. FAO Irrigation and Drainage Paper No. 38. Rome. 52 pp.
FAO. 1998. Crop evapotranspiration guidelines for computing crop water requirements, by
R.G. Allen, L.S. Pereira, D. Raes & M. Smith. FAO Irrigation and Drainage Paper No. 56.
Rome. 300 pp.
FAO. 2002. Agricultural drainage water management in arid and semi-arid areas, by K.K. Tanji
& N.C. Kielen. FAO Irrigation and Drainage Paper No. 61. Rome. 188 pp.
San Joaquin Valley Drainage Implementation Program (SJVDIP). 1999. Source reduction
technical committee report. Sacramento, USA, Department of Water Resources 33 pp.
Tanji, K.K. & B.R. Hanson. 1990. Drainage and return flows in relation to irrigation management.
In B.A. Stewart & D.N. Nielsen, eds. Irrigation of agricultural crops. Agronomy Monograph
No. 30. Madison, USA, American Society of Agronomy.
135
Annex 7
136
Guidelines and computer programs for the planning and design of land drainage systems
(1)
However, to allow for flow through macropores it is better defined as:
(2)
This flow usually goes directly to the subsoil. In this case (Figure A7.1):
or
(3)
137
FIGURE A7.2
10
LF
=0
.05
Example
9
Following the example of the
8
previous section, it is possible to
7
10
calculate the minimum LF required
0.
F=
6
L
to control the salt buildup caused by
.15
=0
0
LF =0.2
5
the salts applied with the irrigation
LF
0
water, whose salinity content in
4
0.4
LF=
terms of ECi is 0.6 dS/m. If maize
3
40 %
is the most salt-sensitive crop of the
30
20
2
10
cropping pattern, and its tolerance
1
threshold in terms of ECe is 1.7 dS/
EC i (dS / m)
m, then a minimum LF of 0.05 is
1
2
3
4
5
required to control soil salinity
(Figure A7.2).
Assuming that the average LF during the irrigation season is 0.2 and the minimum
LF is 0.05, it can be concluded that no salt buildup should be expected in the rootzone,
and even the irrigation application efficiency might be increased while keeping soil
salinity under control.
In irrigated lands, it is possible to check whether the actual value of the LF satisfies the
minimum LF necessary to control soil salinity. Therefore, if the amount of percolation
water is enough to cover the leaching requirements, water might be saved by improving
the application efficiency. If not, the leaching requirements must be calculated.
LEACHING REQUIREMENTS
Once the minimum LF is known, the long-term leaching requirements, for example,
during the irrigation season, can be calculated by means of the salt equilibrium
equation developed by Dieleman (1963) and later modified by Van Hoorn and Van
Alphen (1994):
R * = (ETc Pe )
1 fi (1 LF )
fi (1 LF )
(4)
where:
ETc = actual crop evapotranspiration (mm);
Pe = effective precipitation (mm);
R* = long-term leaching requirement (mm).
Therefore, the net irrigation requirement (I) is:
I = (ETc Pe ) + R *
(5)
Example
This example uses the case of the irrigated lands mentioned in the previous example (in
which fi = 0.94) and assumes that farmers need to irrigate with groundwater with an ECi
of 1.5 dS/m. If they still wish to grow maize in the soil of the previous example, they
will need to irrigate with an LF of 0.3 (Figure A7.2). If the net irrigation requirement
(ETc - Pe) during the irrigation season is about 560 mm, at least 290 mm will be required
to leach the salts accumulated in the rootzone. The net irrigation requirement will be
Guidelines and computer programs for the planning and design of land drainage systems
138
850 mm. If the actual LF is 0.2, about 185 mm of leaching can be obtained during the
irrigation season (Equation 4). Therefore, the leaching deficit will be about 105 mm
(290 - 185).
Where slightly soluble salts (e.g. gypsum, and magnesium and calcium carbonates)
are present in the irrigation water, the leaching requirement is calculated first for the
soluble salts. Then, the small contribution of the slightly soluble salts to the total soil
salinity is added (Van der Molen, 1973). For average salt contents, the total solubility of
gypsum and carbonates is about 40 meq/litre, which is equivalent to an EC of 3.3 dS/m.
Where bicarbonates predominate in the irrigation water, it is advisable to decrease the
sodium adsorption ratio (SAR) by increasing the calcium content of the soil solution
by applying gypsum (520 tonnes/ha).
Once long-term soil salinity increases are no longer expected, a check should be
made on the short term in order to be certain that the salt content of the soil solution
does not exceed the threshold value of the crop salt tolerance. For this purpose, the
salt storage equation derived for predicting the buildup of soil salinity on a weekly or
monthly basis can be used (Van Hoorn and Van Alphen, 1994). The variation of salinity
in the short term (z) can be calculated thus:
z = z2 z1 =
fi In ECi fr REC1
f R
1+ r
2Wfc
(6)
where:
EC1 =
Wfc
z1
z2
z1
Wfc
(7)
The a coefficient may vary from 1.15 to 1.20 if irrigation uniformity is fairly
appropriate.
If, under the current irrigation management, the leaching requirements are not
satisfied (R aR*), there are two options: grow crops that are more tolerant of salinity
and in this way reduce the minimum LF; or find out how to cover the leaching deficit.
In the latter case there are two possibilities: remove the accumulated salts before
sowing the next crop by applying irrigation water; or split up the leaching requirement
during the irrigation period by increasing each irrigation application.
EFFECTS OF LEACHING FOR SALINITY CONTROL ON SUBSURFACE DRAINAGE
DESIGN
Where the leaching requirements are covered by the actual irrigation management
or after the cropping season by rainfall or out-of season leaching irrigation, salinity
control does not affect the drainage coefficient used for subsurface drainage design.
However, if more water has to be added with each application in order to increase the
LF, salinity control affects subsurface drainage design because the drainage coefficient
must also be increased.
The option of increasing the irrigation allocation depends on the availability of
water resources during or at the end of the growing season. It also depends on the
internal drainage capacity of the soils. Coarse-textured soils permit leaching fractions
of 0.150.25, while in fine-textured soils with low permeability the LF should be lower
than 0.10 because of their limited internal drainage (unless rice is grown). In addition,
the environmental effect of increasing the volume of drainage water on drainage
disposal should be considered. Thus, growing more salt-tolerant crops is frequently a
better option than using more water and increasing field and disposal drainage needs.
Controlling soil salinity caused by capillary rise generally does not increase the
drainage coefficient. This is because it is dependent on adopting a suitable depth of the
groundwater table and maintaining a downward flow of water during the irrigation
season. Where leaching is required in order to remove the accumulated salts in the
rootzone, water is generally applied before the start of the cropping season.
REFERENCES
Dieleman, P., ed. 1963. Reclamation of salt affected soils in Iraq. ILRI Publication 11.
Wageningen, The Netherlands. 174 pp.
FAO. 1985. Water quality for agriculture, by R.S. Ayers & D.W. Westcot. FAO Irrigation and
Drainage Paper No. 29 Rev. 1. Rome. 174 pp.
FAO. 2002. Agricultural drainage water management in arid and semi-arid areas, by K.K. Tanji
& N.C. Kielen. FAO Irrigation and Drainage Paper No. 61. Rome. 188 pp.
Maas, E.V. & Grattan, S.R. 1999. Crop yields as affected by salinity. In R.W. Skaggs & J. Van
Schilfgaarde, eds. Agricultural drainage. Agronomy Series 38. Madison, USA.
Van der Molen, W.H. 1973. Salt balance and leaching requirement. In: Drainage principles and
applications, pp. 59100. ILRI Publication 16, Vol. 2. Wageningen, The Netherlands, ILRI.
Van Hoorn, J.W. & Van Alphen, J.G. 1994. Salinity control. In H.P. Ritzema, ed. Drainage
principles and applications, pp. 533600. 2nd edition. ILRI Publication 16. Wageningen, The
Netherlands, ILRI.
139
141
Annex 8
hh=h1-h2
hap=h3-h4
hr=h2-h3
Guidelines and computer programs for the planning and design of land drainage systems
142
TABLE A8.1
Determination of KD values from groundwater-level observations in a drained soil with a sandy substratum
Drain
no.
Period of
observations (1984)
(m)
(m)
(m)
(m)
13
JanuaryMarch
0.95
0.97
1.07
0.85
AprilJune
1.03
1.04
1.14
0.77
JulyOctober
1.08
1.09
1.17
January March
0.86
0.89
0.97
AprilJune
0.95
0.97
January March
0.52
AprilMay
0.57
14
16
z25
z12.5
z6.5
h1 = 1.8-z25
hh
KD
(m)
(m)
(mm/d)
(m2/d)
0.73
0.12
22.3
58.1
0.66
0.11
19.5
55.4
0.72
0.63
0.09
17.0
59.0
0.94
0.83
0.11
22.6
64.2
1.05
0.85
0.75
0.10
18.0
56.3
0.56
0.62
1.28
1.18
0.10
21.1
65.9
0.60
0.66
1.23
1.14
0.09
18.0
62.5
FIGURE A8.2
July 1975
h2 = 1.8-z6.5
March 1975
5
February 1975
h (m)
0
0
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2
qt =
3.46 K
2
ht
Non-steady-state flow
In drained lands where laterals are laid
on the impervious layer, water flow
is generally non-steady, especially
after an irrigation application or
heavy rainfall. However, the average
value of the hydraulic conductivity
of the permeable layer can be
calculated from observations of the
drawdown of the water table, where
the phreatic level has an elliptic
shape. Under these conditions, the
Boussinesq equation for the specific
discharge reads:
(2)
where:
qt = specific discharge at time t (m/d);
ht = hydraulic head midway between drains at time t (m).
Therefore, if the function qt/ht = f(ht) is represented graphically, with data from
observations made during several drainage periods, straight lines can be obtained, as
those represented as an example in Figure A8.2.
The slope of the qt/ht = f(ht) function is equal to:
tg =
3.46 K
L2
(3)
143
TABLE A8.2
Correlation coefficient
qt/ht = f(ht)
tg 10-3
K
(m/d)
February 1976
0.301.10
0.96
4.05
0.47
JulyAugust 1976
0.101.10
0.91
8.67
1.00
JanuaryFebruary 1977
0.601.10
0.97
3.81
0.44
JuneJuly 1977
0.501.00
0.94
4.80
0.55
Period of observations
Results from Table A8.2 show K values of about 0.5 m/d where the groundwater level
is below the top layer (030 cm). A higher value of 1 m/d was obtained when the water
level was close to the ground surface. However, in this case, the correlation coefficient
was lower than in the previous cases (probably because of an almost flat shape of the
water table and because of the high hydraulic conductivity of the top layer).
DETERMINING RADIAL RESISTANCE
Resistance to steady-state radial flow towards drains installed above the impervious
layer can also be determined from observations in drained lands:
Wr =
hr
(4)
qL
where:
hr = hydraulic head for radial flow (m);
Wr = radial resistance (d/m).
In Equation 4, hr is measured by the difference in piezometer readings in tubes laid
at some distance from the drain (h2) and close to the drain trench (h3), as shown in
Figure A8.1.
Table A8.3 shows an example of calculation of Wr values from water-level
observations in piezometers laid in the vicinity of the drain (z6,5) and close to the drain
(z0), for drains laid at 50-m spacings and 1.8 m deep in a sand layer.
Results from three drains observed during different periods show an average radial
resistance of 0.24 d/m.
PROCEDURE FOR DETERMINING THE DRAINABLE PORE SPACE
For drained lands, the value of the layer above drain level can be measured from the
drawdown of the water table (determined by piezometer recording) and the amount
of water drained in the period considered (calculated from measurements of the drain
discharge). The restrictions are that evaporation and seepage to or from deeper layers
must be low and can be ignored relative to the drain discharge.
TABLE A8.3
z0
h2 = 1.8z6.5
hr
Wr
(m)
(m)
(mm/d)
(d/m)
0.42
0.31
22.3
0.28
0.42
0.24
19.5
0.25
0.63
0.47
0.16
17.0
0.19
Drain
no.
Period of observations
(1984)
(m)
(m)
(m)
13
JanuaryMarch
1.07
1.38
0.73
AprilJune
1.14
1.38
0.66
JulyOctober
1.17
1.33
14
16
h3 = 1.8-z0
January March
0.97
1.26
0.83
0.54
0.29
22.6
0.26
AprilJune
1.05
1.26
0.75
0.54
0.21
18.0
0.23
January March
0.62
0.87
1.18
0.93
0.25
21.1
0.24
AprilMay
0.66
0.87
1.14
0.93
0.21
18.0
0.23
144
Guidelines and computer programs for the planning and design of land drainage systems
TABLE A8.4
Drawdown of the
water level
Dr
(m)
(mm)
(mm)
(%)
(%)
January 1975
0.550.80
11.2
219
5.1
4.3
0.800.95
5.3
156
3.4
0.951.10
4.7
125
3.8
0.951.10
4.8
97
4.9
1.101.20
2.1
46
4.6
0.751.10
7.1
169
4.2
0.851.20
10.2
288
3.5
February 1976
January 1977
4.7
3.9
Therefore, if the recharge to the water table and natural drainage are negligible and
there is no depletion of the water table from plant roots in the time interval selected, the
drainable pore space can be found from:
(5)
where:
Dr = amount of drainage water converted to an equivalent surface depth (mm);
= drainable pore space;
h = average drawdown of the water table in the time considered (mm).
Dr and h must be expressed in the same units.
To determine the average value, it is only necessary to measure, during the interval of
time selected, the average drawdown of the water table from piezometer readings and the
amount of water drained in the same period. The drainable pore space is a dimensionless
fraction, often expressed as a percentage, as in Table A8.4. Table A8.4 shows an example
calculation of the average value of a silty-clay soil, with data from observations made
during three consecutive winters.
The results of this table show the tendency of to decrease with soil depth. For
example, the 1975 observations show a value of 5.1 percent for a soil layer with a
prismatic structure and about 3.9 for the deeper, less-structured soil layer. However,
for drain spacing calculations an average value of 4.3 percent can be considered.
The average value calculated with the results of the following years was of the same
magnitude.
REFERENCES
Martnez Beltrn, J. 1978. Drainage and reclamation of salt affected soils in the Bardenas area,
Spain. ILRI Publication 24. Wageningen, The Netherlands, ILRI. 321 pp.
145
Annex 9
FIGURE A9.1
q (mm/d)
34
32
30
0.4
0.5
0.6
28
26
24
0.7
0.8
0.9
22
20
1.0
1.1
1.2
1.3
1.4
1.5
18
16
14
12
10
8
6
1.6
1.7
1.8
4
2
0
J
Groundwater level
Discharge
FIGURE A9.2
Ground surface
q (mm/d)
1.2
12
1.0
10
0.8
0.6
0.4
4
2
0.2
0
Drain level
10 15 20
25
30
January 1975
10
15
20
25
February 1975
Groundwater level
Discharge
0
t (d)
Guidelines and computer programs for the planning and design of land drainage systems
146
FIGURE A9.3
09-03-03
10-03-03
11-03-03
12-03-03
13-03-03
14-03-03
FIGURE A9.4
0.8
0.6
0.4
0.2
TABLE A9.1
Maize and alfalfa yields compared with data of the groundwater table
Period (1977)
Consecutive days in which the groundwater level was above the depth indicated (cm)
25
50
75
100
25
50
75
100
25
50
75
100
25
50
75
100
June
20
10
30
22
30
20
30
30
July
10
10
31
10
25
31
19
31
31
August
16
10
31
14
28
31
24
30
31
September
23
17
30
14
30
16
19
41
71
12 195
7 600
5 780
5 415
1.00
0.62
0.47
0.44
5 800
4 000
1 730
1 180
1.00
0.69
0.30
0.20
SDW50
Annex 9 Procedure for deriving drainage design criteria from drained lands
Although under irrigation the water level varies with time, the average depth of
the water table is a good indicator concerning crop yields. Figure A9.4 shows the
relationship between the relative crop yield (Y) and the average depth of the water
table ( ) during the irrigation season, as per the data in Table A9.1.
Although data from only one irrigation season are not sufficient to obtain a
statistically sound relationship, these results are useful for providing practical guidance
to be confirmed later with further information. It seems that an average depth of
85 cm is critical for maize and alfalfa, which were the most relevant irrigated crops in
the study area. In this case, the groundwater depth criterion is dominant because no
long dry fallow periods or periods with frequent shortages of irrigation water occur.
Where this is not the case, especially where the groundwater is rather salty, deeper
groundwater levels during such extended dry periods are required in order to avert soil
salinization by capillary rise.
The data in Table A9.1 also show that short periods of high water tables are not
harmful for the above-mentioned crops.
In the Dutch polders, with a humid climate, no appreciable damage to crops
was found where during heavy rains in winter the groundwater did not rise above
0.30 m depth below the surface, provided that it receded within a few days. Higher
groundwater levels led to slaking of the ploughed layer, causing more permanent
anaerobic conditions and damage to field crops. These silty-clay soils needed a drainage
depth of 1.20 m in order to keep the average levels low enough.
REFERENCES
FAO/IMTA. 2004. Evaluacin de sistemas de drenaje en el Distrito de Riego 041, Ro Yaqui,
Son., y en el Distrito de Riego 076, Valle del Carrizo, Sin., Mxico.
Martnez Beltrn, J. 1978. Drainage and reclamation of salt affected soils in the Bardenas area,
Spain. ILRI Publication 24. Wageningen, The Netherlands, ILRI. 321 pp.
Sieben, W.H. 1964. De invloed vande ontwateringstoestand op stikstofhuishouding en
opbrengst. Landbouwkundig Tijds., 76: 784802.
147
149
Annex 10
Guidelines and computer programs for the planning and design of land drainage systems
150
TABLE A10.1
If y < 1 then
(2a)
else
(2b)
Water
depth y
(m)
< 0.75
Mannings
Km (m1/3s-1)
12
sandy
20
0.050
clayey
sandy
15
30
0.067
0.033
where:
B = length of waterway, in wind direction (km);
v = wind velocity (m/s);
(4)
151
where:
Fr = FroudeBoussinesq number;
g = 9.81 = acceleration gravity (m/s2);
y = water depth (m);
v = flow velocity (m/s).
For streaming water, it is required that Fr < 1; while for Fr > 1, shooting occurs.
Streaming water is supposed to obey Mannings formula (Equation 1).
If the water level downstream becomes higher than the land surface, overflow and
inundation occur.
Backwater effects
Backwater curves occur near the downstream end of a channel, where it joins other
watercourses with a higher water level or within the reach with a backwater curve effect
upstream of weirs. Upstream, the water will reach a constant equilibrium depth in
accordance with a given flow. However, near the downstream end, the water level will
come under the influence of the fixed downstream level and form a curve upwards
or downwards (Figure A10.2)
depending on whether this level is
higher or lower than the water level
FIGURE A10.2
Convex and concave backwater curves
corresponding with the upstream
equilibrium depth. Complications
Land surface
arise when the land is inundated or
when the channel overflows.
The program BACKWAT is
based on these considerations. This
Water level
program calculates the equilibrium
River
depth by iteration. The calculations
start at the downstream end, where
High
the water level is given. They are
Low
Channel bottom
numerical, with steps in water
depth of a given size. The water
depth diminishes inland if the curve
is convex, and increases inland if
Bottom
concave (Figure A10.2). In the latter
case, overflow may occur upstream.
Guidelines and computer programs for the planning and design of land drainage systems
152
FIGURE A10.3
Bridge (non-obstructing)
Bridge
Road
Water level
(6)
where:
A = area of the hydraulic section (m2);
g = 9.8 m/s2 is the gravity acceleration;
Q = design discharge (m3/s), preferably increased by a safety factor;
= coefficient that depends on the shape of the entrance and at the exit;
h = head loss along the culvert (m).
The design discharge is often taken some 2550 percent higher than for the upstream
drainage channel. This is because the flexibility of culverts to accommodate for higher
flows without causing structural damage is less than for open waterways. The values
of are about 0.7 for long culverts (2030 m) and 0.8 for short culverts (< 10 m) (ILRI,
1964). Head losses of 5 cm for small structures and 10 cm for large ones are generally
taken (Smedema, Vlotman and Rycroft, 2004). In order to calculate the cross-section of
the structure, in addition to the wet section A, a minimum of 10 cm of clearance should
be added.
The friction losses in culverts are of minor importance for the usual short passages
under rural roads. For longer culverts, the head losses for friction must be added.
Mannings formula is often used, with a Km of 6070 for smooth and 3040 for
corrugated walls.
Bridges are often constructed in such a way that the watercourse passes freely
underneath, in which case they have no influence (Figure A10.3). If the channel is
narrowed by the bridge, Equation 6 may be used, with = 0.80.9 (Smedema, Vlotman
and Rycroft, 2004). Friction losses can be ignored as the influence of the short length of
the narrow passage is small.
WEIRS AND DROP STRUCTURES
The width of freely discharging rectangular weirs and drop structures is calculated with
the formula:
(7)
where:
b = crest width (m);
g = 9.8 m/s2 is the gravity acceleration;
h = head above the crest level (m);
Q = discharge (m3/s);
= contraction coefficient.
153
FIGURE A10.4
(8)
where:
h1 = upstream water head (m);
h2 = downstream head (m);
h = h1 - h2 = available head (m).
Broad
The values of the coefficients
in Equation 7 and 8 are mostly
determined by the width/shape of
the weir crest (broad or sharp, as
Sharp
shown in Figure A10.4) and by the
nature of the approach flow (degree
of streamline contraction and entry
turbulence). For similar weirs, the
values are in principle the same
for both equations. Values for semi-sharp crested weirs commonly used in drainage
channels (e.g. stop-log weirs) are generally in the order of 1.01.1 (Smedema, Vlotman
and Rycroft, 2004). For sharp-crested weirs, the higher values of should be used.
OUTLET STRUCTURES
Sluices and flap gates
The discharge rate through a sluice or flap gate can be calculated with Equation 6,
being in this case b the width of the sluice and a coefficient from 0.9 to 1.1. The water
depth h2 should be increased by 3.5 percent if the sluice discharges directly into the
sea, because of the heavier saltwater outside (Smedema, Vlotman and Rycroft, 2004).
The outside water heights vary with tides or floods, so that at high levels discharge
is not possible and water must be stored inside. Therefore, the calculations must be
numerical, in time steps, for water level and storage conditions that are typical for the
location involved.
Pumping stations
The capacity of a pumping station is determined by the total discharge from all sources:
rainfall, irrigation excess, seepage, municipal and industrial wastewaters, etc. However,
it is not simple to estimate the simultaneous occurrence of all these events. In contrast
to open watercourses, pumps have a rather inflexible capacity, so that some reserve is
usually added.
A pumping station often has to run at full capacity for short periods only. Most of the
time it has to remove the base flow from more permanent sources, of which seepage and
tail-end losses from irrigation systems are the main ones. More than the strongly variable
inputs from rainfall, these flows determine the number of pumping hours per year and,
consequently, the costs of operation.
In order to cope with the variable capacity needed in different periods, more than one
pump is usually installed, of which one to remove the base flow and one or more to cope
with larger discharges and the design discharge at critical periods.
In order to select the most appropriate capacity arrangement and type of pump, some
design parameters should be calculated, namely: the base, usual and maximum discharge,
the lift and the dynamic head, and the power requirement.
The lift equals the static difference between inside and outside water. The dynamic
head may be calculated using:
Guidelines and computer programs for the planning and design of land drainage systems
154
h = hs + h +
vd 2
2g
(9)
where:
g 9.8 m/s2;
h = total head (m);
hs = lift or static head (m);
vd = flow velocity at the outlet of the delivery pipe (m/s);
h = total head loss in the suction and delivery pipes (m).
Consideration should be given to the head-increasing effect of choking of trashracks
that usually protect the inlet section of drainage pumping stations from the entrance of
floating debris such as mown aquatic weed, plastic, and branches, if timely cleaning of these
racks is not secured.
The power requirement may be calculated using:
P=
gQh
t p
(10)
where:
h = total head (m);
P = power required (kW);
Q = discharge rate (m3/s);
and p are the transmission (0.900.95) and pump efficiencies, respectively;
p = density of water 1 000 kg/m3.
The p values can vary for axial pumps from 0.65 for 1-m lift to 0.80 for 2.53.0m lift; for radial pumps from 0.6 for 1-m lift to 0.800.85 for lifts of more than 4.0 m
(Smedema, Vlotman and Rycroft, 2004); and Archimedes screws may have an efficiency
of 6575 percent (Wijdieks and Bos, 1994).
Some correction factors may be also considered in Equation 10 in order to take account
of the elevation of the site and safe load (Smedema, Vlotman and Rycroft, 2004).
REFERENCES
ILRI. 1964. Code of practice for the design of open watercourses and ancillary structures.
Bulletin 7. Wageningen, The Netherlands. 82 pp.
Smedema, L.K., Vlotman, W.F. & Rycroft, D.W. 2004. Modern land drainage. Planning, design
and management of agricultural drainage systems. Leiden, The Netherlands, A.A. Balkema
Publishers, Taylor&Francis. 446 pp.
Wijdieks, J. & Bos, M.G. 1994. Pumps and pumping stations. In H.P. Ritzema, ed. Drainage
principles and applications, pp. 965998. 2nd edition. ILRI Publication 16. Wageningen, The
Netherlands, ILRI.
155
Annex 11
Rainfall
Evaporation
Pumped
water
Excess
rainfall
Storage in:
Soil
Channels
Inundation
Total
(mm/d)
1
100
25
75
25
50
75
21
38
55
25
30
55
38
18
18
18
15
Guidelines and computer programs for the planning and design of land drainage systems
156
TABLE A11.2
Rainfall
Evaporation
Pumped
water
Excess
rainfall
Storage in:
Soil
Channels
Inundation
Total
(mm/d)
1
125
25
100
50
25
25
100
29
38
88
50
25
13
88
38
51
50
51
30
18
18
18
15
Excess
rainfall
Soil
TABLE A11.3
Rainfall
Evaporation
Pumped
water
Storage in:
Channels
Inundation
Total
(mm/h)
1
53
52.0
20
15
17.0
52.0
27
1.6
77.4
35
20
22.4
77.4
14
1.6
89.8
45
25
19.8
89.8
1.6
94.2
50
25
19.2
94.2
1.6
95.6
50
25
20.6
95.6
1.6
95.0
50
25
20.0
95.0
25 cm in one day. Inundation for two days could be tolerated by tomato and lettuce
in the Ebro Delta, providing that they are grown on beds between surface drainage
furrows. However, as the pumping requirements are higher than for standard rice field
needs, individual pumping stations may be needed in farms with surface and subsurface
drainage systems where vegetables are grown jointly with rice (as the actual shared
pumping facilities were designed mainly for covering rice field requirements).
The pumping capacity should also be increased if the critical period is less than
24 hours as it is frequently needed to cultivate more sensitive crops. If heavy rain falls
in the first three hours, soil storage may be limited by soil infiltration, which is usually
highest at the beginning. However, it soon decreases, becoming later almost constant
until the soil is saturated completely. In the example of Table A11.3, water distribution
is shown with pumping capacity and channel storage similar to the previous example.
In this example, inundation reaches its maximum value after about 2 hours. After
this time, it decreases slightly, but stagnation occurs in the following hours. If the
critical period is about 6 hours and the excess rainfall should be removed during this
time interval, the pumping capacity should be increased substantially or less sensitive
crops should be cultivated. Consequently, in certain areas of the Ebro Delta, where
horticultural crops are grown, in addition to the pumping stations for subsurface
drainage water, independent pumping stations with a higher capacity discharge surface
drainage water during the critical periods of heavy rainfall.
157
Annex 12
PRINCIPLES
The Soil Conservation Service
(now called the Natural Resource
Conservation Service) of the United
States Department of Agriculture
developed a simple formula called
the Cypress Creek equation (NRCS,
1998):
Q = qA5/6
(1)
TABLE A12.1
0.59
0.52
0.48
0.39
0.33
0.30
0.26
REFERENCES
ASAE-EP 407.1. 1994. Agricultural drainage outlets - open channels. In: American Society of
Agricultural Engineers book of standards, pp. 728733. St. Joseph, USA.
Natural Resource Conservation Service (NRCS). 1998. Water management (drainage).
Chapter 14 of Part 650 Engineering Field Handbook. Washington, DC. 160 pp.
Ochs, W.J. & Bishay, B.G. 1992. Drainage guidelines. World Bank Technical Paper No. 195.
Washington, DC. 186 pp.
159
Annex 13
PRINCIPLES
The maximum discharge at the outlet of the main drainage system can be determined
statistically where a data series of measured flows is available covering a period of at
least 1520 years. For example, the occurrence probability can be calculated with the
following formula:
(1)
where:
P = probability;
T = 1/P = return period (years);
m = order number in the data series;
N = number of total data available.
Example
Equation 1 has been applied in the example shown in Table A13.1.
With the data of Table A13.1, the maximum discharge for a return period of up to
20 years can be determined (98.3 m3/s in this case), which is sufficient to design the
main drainage system. Where a higher return period is required in order to design
special structures, the design discharge can be estimated by extrapolation, once the
TABLE A13.1
QM
(m3/s)
QM
(m3/s)
P=
m
N +1
T = 1/P years
1967
85.1
98.3
0.05
20
1968
50.1
17
90.2
0.10
10
1969
48.2
18
85.3
0.15
1970
68.3
10
85.1
0.20
1971
60.4
13
80.7
0.25
1972
55.2
14
80.6
0.30
1973
80.7
78.4
0.35
1974
90.2
78.3
0.40
1975
85.3
76.7
0.45
1976
61.3
12
68.3
10
0.50
1977
98.3
61.5
11
0.55
1978
78.4
61.3
12
0.60
1979
80.6
60.4
13
0.65
1980
36.7
19
55.2
14
0.70
1981
50.2
15
50.2
15
0.75
1982
61.5
11
50.2
16
0.80
1983
50.2
16
50.1
17
0.85
1984
78.3
48.2
18
0.90
1985
76.7
36.7
19
0.95
160
Guidelines and computer programs for the planning and design of land drainage systems
available data are plotted on a probability paper, for example by using the normal
distribution. However, this type of calculation is based on historical data, and runoff
may change with changes in land use.
REFERENCES
Smedema, L.K., Vlotman, W.F. & Rycroft, D.W. 2004. Modern land drainage. Planning, design
and management of agricultural drainage systems. Leiden, The Netherlands, A.A. Balkema
Publishers, Taylor&Francis. 446 pp.
161
Annex 14
Unit hydrograph
PRINCIPLES
This method, developed by Sherman (1932), is based on the proportionality principle:
the surface runoff hydrograph produced by certain amount of rainfall (P) can be
obtained from the hydrograph of other storm of equal duration (P) by multiplying
the ordinates of the latter hydrograph by the following conversion factor:
(1)
Example
In Figure A14.2, the hydrograph
for the surface runoff produced by
a rainfall of 40 mm accumulated
in 6 hours, of which 25 mm was
accumulated in the first 3 hours, has
q (mm/h)
ym
ay
ay m
td
t (h)
t
td Lag time
t
Time base
FIGURE A14.2
P (mm)
25
15
q (mm/h)
where:
a = conversion factor;
Sr = amount of surface runoff
produced by precipitation
P (mm);
Sr = amount of surface runoff
produced by precipitation
P (mm).
This method is also based on the
concept that the base length (t) of a
hydrograph depends on the duration
of the storm, but is independent of
the amount of rainfall and surface
runoff, as shown in Figure A14.1.
The recession time (t - td) is
almost constant. This is because
it only depends on the physical
characteristics of the basin.
For practical applications, it is
advisable to convert the available
hydrographs to unit hydrographs,
namely, hydrographs for precipitations of 1 or 10 mm. Thus, for
the project basin, a series of unit
hydrographs can be obtained for
different rainfall durations. In order
to determine the hydrograph for the
design rainfall, the unit hydrograph
with a time basis similar to the
design rainfall is selected.
FIGURE A14.1
10
0
12
t (h)
162
Guidelines and computer programs for the planning and design of land drainage systems
been determined from the unit hydrograph available for a rainfall of 10 mm in 3 hours.
It is assumed that all rain becomes surface runoff.
The hydrograph for the first 3 hours is obtained from the 10-mm unit hydrograph
by applying a conversion factor (a = 2.5). For the following 3-hour period, a conversion
factor (a = 1.5) is used. The final hydrograph is obtained by superimposing both
hydrographs. It can be observed that the peak discharge will be produced 5 hours after
the beginning of the storm.
REFERENCES
Sherman, L.K. 1932. Streamflow from rainfall by the unit-graph method. Eng. News Rec., 108:
501505.
163
Annex 15
Rational formula
PRINCIPLES
The rational method assumes that, in small agricultural basins, the maximum flow of
surface water in the outlet is for a rainfall with a duration equal to the concentration
time. Then, the maximum discharge depends on the rainfall intensity, the surface area
and the hydrological conditions of the basin:
(1)
where:
QM = maximum discharge for a return period equivalent to the design rainfall
(m3/s);
C = coefficient for surface runoff;
I = rainfall intensity during the concentration time (mm/h);
A = area of the basin (ha).
For the return period selected, rainfall intensity is assumed: (i) constant during the
time interval considered; and (ii) equal to the ratio between the accumulated rainfall
and the concentration time. Where only the amount of rainfall in 24 hours is known,
the value of the precipitation accumulated in the concentration factor can be estimated,
first by using an appropriate coefficient for the 6-hour rainfall (P6/P24 = 0.50.7), and
then with the coefficients of the rainfall distribution model described in Chapter 6 of
the main text.
SURFACE RUNOFF COEFFICIENT
The runoff coefficient can be estimated directly through the indicative values of the Soil
Conservation Service (SCS, 1972) shown in Table A15.1.
250 m
Example
The rational method has been applied to estimate the maximum discharge of surface
water at the outlet (point D) of a farm of 85 ha shown in Figure A15.1.
In order to estimate the concentration time at point D, three sections
FIGURE A15.1
have been considered from the most
Example of drained farm with a system of furrows and open
distant point from the outlet (point
ditches
A): section AB (furrows), section BC
1 700 m
(open collector drain), and section
B
C
CD (the main drain).
Assuming values of the water
velocity of 0.15 and 0.35 m/s along
the furrows and the open ditches,
A
respectively, Table A15.2 shows the
concentration time tc for each section
as calculated using:
D
(2)
where:
Furrows
Collector
Guidelines and computer programs for the planning and design of land drainage systems
164
TABLE A15.1
Pasture
Forest
Slope
(%)
High
Soil infiltrability
Medium
<5
0.30
0.50
0.60
510
0.40
0.60
0.70
1030
0.50
0.70
0.80
<5
0.10
0.30
0.40
510
0.15
0.35
0.55
1030
0.20
0.40
0.60
<5
0.10
0.30
0.40
510
0.25
0.35
0.50
1030
0.30
0.50
0.60
Low
TABLE A15.2
Length
Slope
Difference of
elevation
Water velocity
tc
(m)
(%)
(m)
(m/s)
(h)
AB
250
0.10
0.25
0.15
0.46
BC
1 700
0.15
2.55
0.35
1.35
CD
500
0.35
0.40
AD
2 450
2.80
2.21
165
Annex 16
PRINCIPLES
The Curve Number (CN) method
is based on the conceptual
interpretation of the hydrological
process during a rainfall period.
Initially, no surface runoff (Sr) is
produced while rainfall is intercepted
by vegetation and water infiltrates
into the soil (Ia). When rainfall
exceeds this initial interception,
overland flow begins while soil
infiltration continues (Inf). Once
the soil is saturated, any amount of
excess rainfall (P) produces surface
runoff (Figure A16.1).
Figure A16.2 shows the relationship between the precipitation
accumulated and surface runoff
during a rainfall period.
The amount of Sr is zero if the
accumulated rainfall is lower than
the Ia value. Once this threshold
value has been exceeded, the Sr
function takes a curve shape up
to the saturation point where Sr is
equal to P. From this point, the Sr
function becomes a straight line
with unit slope (a = 45 ). If this
line is extended to cut the x-axis, a
point is achieved that represents the
maximum retention potential (S).
The S value depends on the physical
characteristics of the basin and on
the soil moisture content before the
rainfall period.
Once overland flow starts, the
water balance on the soil surface is:
(1)
where:
Inf = actual infiltration while
surface runoff is produced
(mm);
FIGURE A16.1
Sr
I nf
t
Ia
Source: Adapted from Boonstra, 1994.
FIGURE A16.2
Sr = P
Sr = f(P)
la
P(mm)
S
S
Guidelines and computer programs for the planning and design of land drainage systems
166
Ia
= amount of water intercepted and infiltrated into the soil before overland
flow occurs (mm);
P
= amount of accumulated rainfall (mm);
P - Ia = maximum potential of surface runoff (mm);
= accumulated surface runoff (mm).
Sr
This method, developed by the Soil Conservation Service (SCS), assumes that the
relationship between the actual surface runoff and its maximum potential value is equal
to the rate between the actual infiltration and the maximum potential retention. The
latter is approximately equal to the accumulated infiltration after runoff has started
(Figure A16.2):
Sr
P Ia
(P I ) S
a
(2)
where:
S = maximum potential retention (mm).
Surface runoff can be then expressed as:
(P I )
(P I ) + S
2
Sr =
(3)
Equation 3 has been simplified by assuming that the value of the potential retention is
constant during a storm and the initial interception is about 20 percent of the maximum
potential retention (Ia = 0.2S). Thus, surface runoff depends only on precipitation and
the maximum potential retention:
Sr =
(P 0.2 S)
for
P + 0 .8 S
(4)
The SCS formulated a new undimensional parameter, named the Curve Number
(CN), to assess the capacity of a basin to produce surface runoff after certain
precipitation. This parameter is a hydrological characteristic of the basin, which
depends on the maximum potential retention:
CN =
25400
(5)
254 + S
FIGURE A16.3
150
80
75
125
70
100
65
60
55
50
75
45
40
50
35
30
25
20
25
0
25
50
75
100
125
150
175
200
225
250
275
300
P (mm)
Source: Adapted from Boonstra, 1994.
167
This method does not consider land slope because lands with gradients of more
than 5 percent are not cultivated in the United States of America. However, classes for
different slopes can be considered in a specific project (Boonstra, 1994).
The CN value increases progressively as retention decreases, the maximum value
being 100 where retention in negligible. Table A16.1 shows the CN values established
by the SCS (1972) for average soil moisture conditions before the design storm,
considered as Class II.
In Table A16.1, the term straight rows means rows along the land slope. The
hydrological condition essentially depends on the vegetation density. Condition is
poor where meadows are intensively used or the grass quality is low, or where field
crops are in the initial stage of growing. Otherwise, condition is good for densely
vegetated meadows and for field crops covering the soil surface well.
In addition to the average soil moisture conditions considered in Table A16.1 for
Class II, the SCS defined two additional classes (I and III), taking into account the
amount of precipitation in the five-day period before the design storm (Table A16.2).
If the antecedent soil moisture condition differs from Class II, the equivalent
CN values for Class I or Class III can be estimated by using the conversion factors
developed by the SCS (1972) and shown in Table A16.3, once the CN value has been
determined for Class II.
TABLE A16.1
CN values Class II
Land use
Practice
Hydrological
condition
Soil infiltrability
Low
Very low
Fallow
Straight row
Poor
77
86
91
94
Row crops
Straight row
Poor
72
81
88
91
Good
67
78
85
89
Contoured
Poor
70
79
81
88
Good
65
75
82
86
Contoured/terraced
Poor
66
74
80
82
Good
62
71
78
81
Poor
65
76
84
88
Good
63
75
83
87
Contoured
Poor
63
74
82
85
Good
61
73
81
84
Contoured/terraced
Poor
61
72
79
82
Good
59
70
78
81
Poor
66
77
85
89
Good
58
72
81
85
Contoured
Poor
64
75
83
85
Good
55
69
78
83
Contoured/terraced
Poor
63
73
80
83
Good
51
67
76
80
Poor
68
79
86
89
Fair
49
69
79
84
Small grain
Close-seeded legumes
or rotational meadow
Straight row
Straight row
Pasture range
High
Medium
Good
39
61
74
80
Poor
47
67
81
88
Fair
25
59
75
83
Good
35
70
79
Meadow (permanent)
Good
30
58
71
78
Woodland
Poor
45
66
77
83
Fair
36
60
73
79
Good
25
55
70
77
Contoured
Guidelines and computer programs for the planning and design of land drainage systems
168
TABLE A16.2
Growing season
(mm)
< 13
< 36
II
1328
3653
III
> 28
> 53
TABLE A16.3
CN
100
78
63
51
40
31
22
15
II
100
90
80
70
60
50
40
30
20
10
III
100
96
91
85
78
70
60
50
37
22
In order to estimate the average CN value of a basin, all the sections with different
hydrological conditions, land use and agricultural practices should first be mapped.
Then, the respective CN is assigned to each independent section. Last, the weighted
average is calculated according to the surface area of each section.
Example
In this example, the CN method has been applied to estimate the amount of surface
runoff produced by an extreme rainfall of 125 mm in 24 hours, determined for a
return period of 10 years, in a basin of 4 740 ha, where the current land use is rainfed
agriculture and forest. This was the previous stage to calculate later the maximum water
flow at the outlet of the main watercourse draining the basin.
The first step for this calculation was to estimate the concentration time of the basin
with the Kirpich formula (although this formula was developed for small agricultural
basins). For a watercourse with a length of 15.5 km and a difference in elevation
between the most distant point from the outlet and the outlet itself of 299.4 m, the tc
value is 2.5 hours.
The second step was to assess the rainfall distribution during the first 6 hours of
the storm. This period of 6 hours was selected, because the concentration time is less
than 6 hours. It was assumed that during the first 6 hours, 60 percent of the one-day
precipitation occurred, i.e. 75 mm. The rainfall distribution during this period can be
estimated by the WMO model for time intervals of 0.5 hours, as shown in Table A16.4.
In order to estimate the weighted average CN for the whole basin, the area was
split into six sections with homogeneous land use and hydrological conditions by
superimposing the land-use map and the soil map. The physical characteristics of these
sections are described in Table A16.5, where the individual CN, estimated for Class II,
were assigned to each section.
The weighted average CN for the basin as a whole is 69 for Class II (Table A16.5).
However, the previous soil moisture conditions are more similar to those of Class III
as in the area studied extreme rainfalls are frequent in autumn. Therefore, it is more
adequate to use the equivalent CN for Class III, i.e. 85 according to Table A16.3.
TABLE A16.4
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
15
22
60
70
78
84
88
92
96
100
1.5
6.0
11.3
16.5
45.0
52.5
58.5
63.0
66.0
69.0
72.0
75.0
169
TABLE 16.5
Surface area
Soil type
Land use
Agricultural practice
Infiltrability
CN
Pasture
Low
79
Medium
69
Medium
71
High
59
(ha)
1
762
1 566
1 161
Vineyard
990
Field crops
30
231
Basin
Straight rows
Terraced soils
Low
76
Pasture
Low
74
4 740
69
TABLE A16.6
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
1.5
6.0
11.3
16.5
45.0
52.5
58.5
63.0
66.0
69.0
72.0
75.0
39.3
0.1
1.1
16.1
21.5
26.0
29.5
31.9
34.4
36.8
Sr (mm)
1.0
15.0
5.4
4.5
3.5
2.4
2.5
2.4
2.5
FIGURE A16.4
q/q M
t/t e
1.0
0.8
0.6
0.4
0.2
t/t e
q/q M
0
0.25
0
0.12
0.50
0.43
0.75
0.83
1.00
1.00
1.25
0.88
1.50
0.66
1.75
0.45
2.00
0.32
2.25
0.22
2.50
0.15
2.75
0.105
3.00
0.075
3.25
0.053
3.50
0.036
3.75
0.026
4.00
0.018
4.25
0.012
4.50
0.009
4.75
0.006
5.00
0.004
(6)
where:
qM = maximum specific discharge (litres per second per hectare);
Sr = amount of surface runoff (mm);
te = elevation time (h).
Guidelines and computer programs for the planning and design of land drainage systems
170
FIGURE A16.5
Example
The elevation time (te) in the basin
of the previous example is about
1.75 hours. With this value, in
Table A16.7 the maximum specific
discharge (qM) for each increment
of surface runoff (Sr) has been
calculated with Equation 6. In
Table A16.7, the distribution of
the specific discharge has also been
determined by applying the tabulated
t (h)
values of the undimensional hydro2
3
4
5
6
7
8
9
10 11 12
graph represented in Figure A16.4 to
the qM values.
The hydrograph for the total specific discharge (Figure A16.5) was obtained by
superimposing the partial hydrographs obtained with the results of Table A16.7.
TABLE A16.7
t (h)
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
7.0
7.5
8.0
8.5
9.0
9.5
10.0
10.5
11.0
11.5
12.0
12.5
13.0
13.5
14.0
Undimensional
hydrograph
t/te
q/qM
0.00
0.00
0.29
0.17
0.57
0.54
0.86
0.91
1.14
0.93
1.43
0.72
1.71
0.48
2.00
0.32
2.29
0.21
2.57
0.14
2.86
0.09
3.14
0.06
3.43
0.04
3.71
0.03
4.00
0.02
4.29
0.01
4.57
.008
4.86
.005
5.14
.003
5.43
5.71
6.00
6.29
6.57
6.86
7.14
7.43
7.71
8.00
1.5
2.0
2.5
1.0
15.0
5.4
1.2
17.9
6.4
0.20
0.65
1.09
1.12
0.86
0.58
0.38
0.25
0.17
0.11
0.07
0.05
0.04
0.02
0.01
0.01
0.01
3.04
9.67
16.29
16.65
12.89
8.59
5.73
3.76
2.51
1.61
1.07
0.72
0.54
0.36
0.18
0.14
0.09
0.05
1.09
3.46
5.82
5.95
4.61
3.07
2.05
1.34
0.90
0.58
0.38
0.26
0.19
0.13
0.06
0.05
0.03
0.02
t (h)
3.0
3.5
4.0
Sr (mm) (see Table A16.6)
4.5
3.5
2.4
qM = 2.08 Sr/te = 1.19Sr
5.4
0.92
2.92
4.91
5.02
3.89
2.59
1.73
1.13
0.76
0.49
0.32
0.22
0.16
0.11
0.05
0.04
0.03
0.02
4.2
0.71
2.27
3.82
3.91
3.02
2.02
1.34
0.88
0.59
0.38
0.25
0.17
0.13
0.08
0.04
0.03
0.02
0.01
2.9
0.49
1.57
2.64
2.70
2.09
1.39
0.93
0.61
0.41
0.26
0.17
0.12
0.09
0.06
0.03
0.02
0.01
0.01
qt (l s-1 ha-1)
4.5
5.0
5.5
2.5
2.4
2.5
3.0
2.9
3.0
0.51
1.62
2.73
2.79
2.16
1.44
0.96
0.63
0.42
0.27
0.18
0.12
0.09
0.06
0.03
0.02
0.02
0.01
0.49
1.57
2.64
2.70
2.09
1.39
0.93
0.61
0.41
0.26
0.17
0.12
0.09
0.06
0.03
0.02
0.01
0.01
0.51
1.62
2.73
2.79
2.16
1.44
0.96
0.63
0.42
0.27
0.18
0.12
0.09
0.06
0.03
0.02
0.02
0.20
3.69
11.85
21.79
26.96
27.09
24.50
21.60
19.10
16.85
14.03
10.59
7.34
4.93
3.28
2.13
1.43
0.92
0.61
0.38
0.24
0.13
0.08
0.04
0.03
Figure A16.5 shows that about 4 hours after of the beginning of the design storm
the maximum specific discharge is expected, its value then being about 27 l s-1 ha-1.
With this surface drainage coefficient, each section of the main drainage system can be
dimensioned. At the outlet of this basin of 4 740 ha, the maximum estimated flow will
be about 128 m3/s.
REFERENCES
Boonstra, J. 1994. Estimating peak runoff rates. In H.P. Ritzema, ed. Drainage principles and
applications, pp. 111143. 2nd edition. ILRI Publication 16. Wageningen, The Netherlands,
ILRI.
Soil Conservation Service (SCS). 1972. Hydrology. National Engineering Handbook Section 4.
Washington, DC, USDA.
171
173
Annex 17
FIGURE A17.1
Recharge q
x=0
Impermeable base
x=L
FIGURE A17.2
Discharge q1
above drains
Recharge q
K1
Drain level
Discharge q2
below drains
D1
K2 D
Equivalent layer d
K2
x=0
Impermeable base
x=L
Guidelines and computer programs for the planning and design of land drainage systems
174
D2 = real thickness of the layer below drain level, down to the impermeable subsoil
(m);
K1 = permeability above drain level (m/d);
K2 = permeability below drain level (m/d);
r = effective drain radius (m).
Inputs for Equation 2 are D2, h, K1, K2, q and r, of which D2 may be infinite. Because
d depends on the required distance L, iteration is necessary.
Hooghoudts method for calculating drain spacings is valid for a two-layered soil
profile: one layer above and one below drain level. The latter not only offers resistance
to horizontal flow, but also radial resistance that occurs near the drain, where the
streamlines are converging.
In this approach, the flow pattern is replaced by horizontal flow through a thinner
layer; the actual thickness D2 of the layer below the drains is replaced by the equivalent
layer d without radial resistance (Figure A17.2). For steady-state flow, this is allowed,
but errors may occur in non-steady cases.
The equivalent layer d, which is a complicated function, is used as a substitute
correction for the radial resistance caused by the convergence of streamlines near the
drain. It is smaller than the real thickness D2 of the lower layer and was tabulated by
Hooghoudt. Subsequently, nomographs were based on these tables (Van Beers, 1979).
However, for computer applications a series solution is more effective. The following
series solution may be used to find d:
d=
L / 8
L
ln + G(x)
r
x=
2D2
L
(3)
(4)
(6)
175
THE TOKSZKIRKHAM
Figure A17.3
ALGORITHM
Drainage of a multilayered anisotropic soil profile the
Toksz and Kirkham (1971a
TokszKirkham and Ernst methods
and 1971b) devised a general
(for Ernst, K1 = K2 and D4 = 0)
theory for determining drain
spacings in multilayered soils with
Recharge q
arbitrary horizontal boundaries
D1
(Figure A17.3). It consists of a set
of complicated hyperbolic functions Discharge q
h
K v1
1
that depend on the number and above drains
K h1
thickness of layers considered.
x=L
The method calculates the flow Discharge q x = 0
2
D2
K h2
through 13 different layers below below drains
drain level (Figure A17.3). It uses
K h3
D3
the following definitions:
The layer above drain level
K h4
D4
Impermeable base
has permeability K1. It is not
considered in the theory, but the
resulting flow can be calculated
by Equation 1.
The first layer below drain level has permeability K2 and thickness D2.
The second layer below drain level has permeability K3 and thickness D3.
The third layer below drain level has permeability K4 and thickness D4.
The drain spacing is L, the drain radius r, the recharge intensity q, and the head
midway h.
Distances a, b, c and s are defined as:
a = D2
c = D2 + D3 + D4
b = D2 + D3
s=
(7)
m =
K3
m (b a)
cosh
s
m (b a)
m = tanh
s
cosh
m =
m a
s
m b
sinh
s
m =
K4
K3
coth
sinh
m =
m b
s
m a
s
m b
sinh
s
m =
K3
1
m a
K2
sinh
s
m = tanh
m =
K3
K2
m (c b)
s
coth
m a
s
(8.a)
(8.b)
(8.c)
Furthermore:
Sm = me
Tm =
m a
s
m
1
m (1 + m m ) (1 + m m ) + m m ( m m m )
Um = 1 Sm Tm m Sm Tm m ( m m + m m )
(9)
(10)
(11)
Guidelines and computer programs for the planning and design of land drainage systems
176
Combination with the ellipse equation for flow above drains requires an iterative
solution.
These formulae are suited for computer applications.
INFLUENCE OF ANISOTROPY
In many soils, permeability depends on the direction of flow. Considerations here are
confined to horizontal layering and vertical cracks. The former results in a permeability
that is larger in the horizontal than in the vertical direction, the latter in the reverse.
In such cases, where the axes of the anisotropy coincide with the horizontal and
vertical x and z axes, the following rules may be used (Boumans, 1963):
An anisotropy factor ani is defined for each layer i as:
ani =
Khi
(13)
Kvi
i = zi ani
(14)
i =
Khi
(15)
ani
In this transformed isotropic system (Figure A17.4), all formulae for steady-state
flow are valid. The resulting spacing L is horizontal and, consequently, it remains
unchanged.
For flow above drains, a different
approach
is used. Here, the vertical
FIGURE A17.4
permeability
Kv1 of the first layer is
Anisotropic and transformed isotropic system
used to find the head loss between
ANISOTROPIC CASE
TRANSFORMED ISOTROPIC CASE
maximum head h and drain level
Recharge q
Recharge q
and, consequently, the corrected
head hc (the head at drain level) as:
K h1 K v1
x=0
K h2
an2
K h3
an3
K h4
an4
Impermeable base
x=L
D2
(16)
1
x=0
D3
D4
Recharge q 2
2
3
4
Impermeable base
x=L
REFERENCES
Boumans, J.H. 1963. Een algemene nomografische oplossing voor het stationaire
ontwateringsvraagstuk met toepassingen voor isotroop en anisotroop doorlatende gronden.
Polytechn. Tijdschr., 18(14B): 545551.
Ernst, L.F. 1956. Calculation of the steady flow of groundwater in vertical cross-sections. Neth.
J. of Agr. Sci., 4: 126131.
Hooghoudt, S.B. 1940. Algemeene beschouwing van het probleem van de detailontwatering en
de infiltratie door middel van parallel loopende drains, greppels, slooten en kanalen. Versl.
Landbouwk. Onderz., 46(14).
Toksz, S. & Kirkham, D. 1971a. Steady drainage of layered soils: I, Theory. J. Irr. Dr. Div.
ASCE, 97, IR1, 118. Erratum in J. Irr. Dr. Div. ASCE, 104, IR3, 333.
Toksz, S. & Kirkham, D. 1971b. Steady drainage of layered soils: II, Nomographs. J. Irr. Dr.
Div. ASCE, 97, IR1, 1937.
Van Beers, W.F.J. 1979. Some nomographs for the calculation of drain spacings. ILRI Bulletin 8.
Wageningen, The Netherlands.
Van der Ploeg, R.P., Marquardt, M. & Kirkham, D. 1997. On the history of the ellipse
equation for soil drainage. Soil Sci. Soc. Am. J., 61: 16041606.
177
179
Annex 18
Guidelines and computer programs for the planning and design of land drainage systems
180
D2
u
1 u 1 (P q1 )+ h
c +
K2v
L
Q2 =
D
c + 2
K2v
cb
+
+ 1
u
L
1 =
aB L2
u K2v
3
F (n,z) =
n =1
1
n u
sin 2
F (n,0)
3
n
L
(n + 1) e + (n
(n + 1) e (n
n
aB =
K2v
1 =
K2h
(1)
1
1
1) e -n
1) e -n
2 K2v c
(3)
3
2 =
aB L
(2)
2 (D2 y )
aB L
3 =
2 D2
aB L
(4)
(n
(n
1
1
+ 1)+ (n 1 1) e -2n
+ 1) (n 1 1) e -2n
(5)
3
Q2
L u
where:
c = resistance of semi-confining layer (d);
cb = entry resistance of drain (cb = 0) (d);
D2 = thickness of layer below drain level (m);
h = head midway, at drain level (m);
ha = head in artesian aquifer, above drain level (m) (in Figure A18.1);
K2h = horizontal permeability below drains (m/d);
K2v = vertical permeability below drains (m/d);
L = drain spacing (m);
q2 = flux density below drain level (m/d);
Q2 = flux below drain level, per metre of drain (m2/d);
R = recharge by precipitation or irrigation excess (m/d) (in Figure A18.1);
u = wet circumference of drain (m);
y = vertical coordinate, positive downward (m).
(6)
For artesian conditions and a two-layer profile (one of which is below drain level),
the design program ARTES was developed. It is based on Bruggemans algorithm, in
combination with flow above drain level according to the ellipse equation.
It also requires general design criteria. These are followed by the soil properties,
which now include the hydraulic head in the underlying artesian aquifer and the
vertical resistance of a semi-confining layer between the aquifer and the two top layers
mentioned.
An approximation is to use Hooghoudts formula with the expected seepage from
below added to the recharge from above. In most cases, the difference in spacing is
negligible in practice (less than 510 percent). However, there are exceptions, especially
where the resistance of the semi-confining layer is low and part of the drainage water
passes through the aquifer.
ARTES uses the Bruggemans method except in the rare cases where this procedure
is not convergent or is otherwise doubtful. Then, the Hooghoudt approximation is
given, together with a warning.
REFERENCES
Bruggeman, G.A. 1999. Analytical solutions of geohydrological problems. Dev. Wat. Sci., 46:
331.
ILRI. 2005. SAHYSMOD, spatial agro-hydro-salinity model. Version 1.7. Description of
principles, user manual and case studies. SAHYSMOD working group of ILRI. Wageningen,
The Netherlands. 134 pp.
Van Drecht, G. 1983. Calculation of steady groundwater flow to ditches. RID-Mededelingen 833. In Dutch with English abstract. The Netherlands, National Institute for Water Supply.
181
183
Annex 19
184
Guidelines and computer programs for the planning and design of land drainage systems
Based on this solution, Guyon proposed the following formula for calculating drain
spacing (with = 0), valid for Boussinesqs pseudo-ellipse:
(3)
where:
h = hydraulic head midway, at time t (m);
h0 = initial head midway between drains (at time t = 0) (m);
K = soil permeability (m/d);
L = drain spacing (m);
t = time (d);
= lag time (d);
= storage coefficient.
The factor 4.5 is an approximation of an expression that yields 4.46208
If the lag time has to be considered, the L value may be calculated with the
following formula, obtained by combining Equations 1 and 3:
(4)
185
twice the design discharge. It is further supposed that, at design discharge, no water is
standing above the drain (hp = 0).
The outflow is further restricted by the radial and entrance resistance near the drain.
This quantity is given as Wr in the program SPACING and here denoted as resistance
W. It causes a head loss proportional to the flow.
Evaporation aids in lowering the groundwater, but it decreases rapidly with
increasing groundwater depth. For this relationship, there are two options:
linear reduction to zero at a given groundwater depth;
exponential reduction with a given characteristic groundwater depth where E =
0.4343Eo.
These principles form the framework of the programs NSDEPTH and NSHEAD
to check calculated drain spacings under non-steady-state flow.
Principle for numerical solution
The principle for numerical solutions is that both time and (horizontal) space are
divided into discrete elements and steps. In each element, the water balance during one
time-step is:
(5)
where:
Qin = flux entering an element, per metre of length (m2/d);
Qout = flux leaving an element, per metre of length (m2/d);
x
= distance (m);
h = fall of groundwater table (m);
t = time-step (d);
x = distance step (m);
= storage coefficient.
To develop this principle into a calculation program, both explicit and implicit
methods are possible. The programs use the first approach although the risk of
instability requires small time-steps t.
Differential equation
For flow below the drain level in the area D2 (Figure A19.2) and a permeability K being
the same above and below drain level (K1 = K2 = K), Equation 2 becomes:
(6)
where:
D2 = thickness of layer below drains (m).
The explicit finite difference expression for Equation 6 is:
(7)
where:
h = hydraulic head (m);
i = index for distance step;
j = index for time step;
x = distance (m);
t = time-step (d);
x = distance step (m).
In the model based on this equation, the drain spacing L has been divided into
20 equal parts. Index i = 0 represents the left-hand boundary; and i = 10 is a plane of
Guidelines and computer programs for the planning and design of land drainage systems
186
symmetry that forms the right-hand boundary (midway between drains). Therefore,
index i = 11 is the highest used. In the drainpipe, the head is hp, near the drain it is ho.
Boundary conditions
The initial condition (j = 0) is a constant head everywhere between the drains (i.e.
groundwater at the soil surface):
hi,0 = hinit
i = 1,11
(8)
(9)
The left-hand boundary is more complicated. Here, two types of resistance against
flow are present:
a linear resistance W (d/m) against total flow (from both sides), being the sum of
the radial resistance (caused by convergence of streamlines near the drain) and
entry resistance for flow into the drain;
a non-linear resistance, caused by the limited capacity of the outflow system
(usually the drainpipes). Here, flow is turbulent and proportional to the square
root of the available head.
For the one-sided flow q0 (in cubic metres per day per metre of drain) converging
towards and entering into the drain:
q0 =
h0 hp
(10)
2W
q0 =
qL hp + hdes
hdes
2
if
hp > 0
(11)
where:
hdes = design head for outflow system (m).
Finally, for horizontal flow in the first compartment:
h1 + h0
h1 h0
q0 = K
+ D2
2
x
where:
h1 = head in first compartment (m).
Equalizing Equations 1012 yields two equations in the unknown h0 and hp.
(12)
187
The upper boundary receives a sudden large input at t = 0, that saturates the entire
soil profile. For t > 0, evaporation may help in lowering the water table, but it is
dependent on the groundwater depth. Two options are available in the model:
linear decrease with groundwater depth z;
exponential decrease.
The linear case is characterized by the critical depth zc:
E = E0 1
z
c
E=0
for
else
(13a)
(13b)
where:
E = actual evaporation from groundwater (m/d);
E0 = potential evaporation from groundwater (m/d);
hinit = initial head = drain depth (m);
zc = critical depth where E = 0 (linear model) (m);
z = groundwater depth (hinit - h) (m).
The exponential case is characterized by the characteristic depth zh:
E = E0 e
z
zh
(14)
where:
= depth where E = 0.4343E0 (exponential model) (m).
zh
h1 + h0
h1 h0
= K
+ D2
2W
2
x
leads to the quadratic equation:
x
2
x
2
h0 +
+ 2 D2 h0 h1 + 2D2 h1 +
hp = 0
KW
KW
(15)
(16)
h0 = U + U + V
(17a)
where:
U=
x
+ D2
2KW
(17b)
V = h1 + 2 D2 h1 +
2
xhp
KW
(17c)
The relation for the head near the drain is found as follows:
h0 hp
2W
qL
2
hp
hdes
+1
(18)
Guidelines and computer programs for the planning and design of land drainage systems
188
2 2
2
q L W
2 2
2
2
hp 2 h0 +
hp + h0 q L W = 0
hdes
(19)
with solution:
2
h0
q L W
q L W
hp = h0 +
qLW
+
+1
2
hdes
2hdes
4hdes
(20a)
( )
hp = max hp ,0
(20b)
Iteration starts with Equation 17, with hp = 0 in (17c). The value of h0 obtained
from Equation 17 is used in Equation 20 to find a new hp value, which is inserted in
Equation 17, etc., until convergence is sufficient.
The process is repeated before each time-step. With h1,j = h0 and h2,j = h1 Equation 7
is used to find the new values for the next time-step.
The index F is used as a criterion for stability of explicit numerical calculations:
F =
KDt
(x)
where:
(21)
FIGURE A19.3
% of drain spacing
50 %
30 %
20 %
10 %
5%
FIGURE A19.4
Instability at F = 0.6
% of drain spacing
50 %
30 %
20 %
10 %
5%
F =
K t
(D2 + hinit )
(x) 2
(22)
REFERENCES
Boussinesq, M.J. 1904. Recherches thoriques sur lcoulement des nappes deau infiltres dans
le sol et sur le dbit des sources. J. Math. Pures Appl., 10 : 178.
Guyon, G. 1966. Considrations sur le drainage des nappes. Thorie et Experimentation. Bull.
Tech. Gn. Rur., 79.
Moody, W.T. 1967. Nonlinear differential equation of drain spacing. J. Irrig. Drain. Div. ASCE,
92(IR2): 19.
189
191
Annex 20
Diameters of drainpipes
Elevation, m
PRINCIPLES
Drains are collecting systems. Along their length, the discharge and the flow velocity
increase gradually. Therefore, the gradient of the hydraulic head is zero at the beginning,
and will increase downstream.
Most drains are laid with a certain slope, and this slope is usually taken as a basis
for calculating the required diameter. However, not the drain slope, but the total head
loss is the basic design parameter.
At the upstream end, the hydraulic
head should remain at a certain
FIGURE A20.1
Sloping drain
depth below the soil surface, and
this depth determines the available
1
head with respect to the drain outlet,
irrespective of the pipe length. The
0.8
slope is not important, as illustrated
in the following example. A drain
0.6
200 m long with an outlet 1.50 m
below surface and a slope of
0.2 percent, without water standing
0.4
above the upper end, loses 0.40 m in
height along its length. Thus, it will
Hydraulic head
0.2
control the upstream water table at a
Drain
depth of 1.10 m. However, the same
will be the case for a horizontal drain
0
(slope zero) of the same length and
0
20
40
60
80
100
Distance, m
outlet depth if it loses 0.4 m in head
over its length owing to friction.
As an example, at the design
discharge intensity q (metres per
day for pipe flow, q is recalculated
FIGURE A20.2
and expressed in metres per second),
Horizontal drain
the drain is running full at the outlet
1
and the head at the beginning has
a design value H (m) above the
0.8
outlet. The drain itself has a slope,
and the slope is such that no water
is standing above the drain at its
0.6
beginning (Figure A20.1). If the
slope is less and also when the
0.4
drain is horizontal (Figure A20.2)
there is water above the drain at
Hydraulic head
the upper end.
0.2 H
From a hydraulic point of view,
B
the drain is functioning equally
Drain
0
well in both cases. Sometimes self0
20
40
60
80
100
Distance, m
cleaning is used as an argument for
having the drain slope. However, in
Elevation, m
120
120
Guidelines and computer programs for the planning and design of land drainage systems
192
flat lands, drain slopes are seldom more than 0.5 percent and often far less. At such low
slopes, the flow velocity is not enough to move sediments.
However, in practice, a slope for the pipe is usually prescribed. Horizontal drains
are seldom encountered, except in subirrigation projects where drains are used for
discharge in wet seasons and for recharge during droughts.
In the following, the system of Figure A20.1 is considered exclusively. Calculation
of the diameter of horizontal drains (Figure A20.2) with formulae for sloping ones
(Figure A20.1) sometimes shows small differences, but they are always on the safe
side.
The available head loss at design discharge and the amounts of water to be drained
under that condition form the basis for calculations concerning required drain
diameters. These calculations are based on the laws for pipe flow, which differ for
smooth and corrugated pipes.
Both smooth and corrugated pipe drains collect water along their length. As a
consequence, the flow is not constant, but it increases gradually from zero at the
upstream end to a maximum at the outflow. Introducing this variable Q corresponds
with integration of the expressions for laterals and collectors. In laterals, Q increases
continuously; in collectors, flow occurs stepwise, namely where the collector is joined
by another lateral. However, provisional calculations show that in practice this makes
almost no difference, provided that the laterals are of equal length.
SMOOTH PIPES
Non-perforated pipes made of glass, metals, PVC, PE and similar materials may be
considered as hydraulically smooth. Pipes that are perforated or made of ceramics
or cement are technically smooth, in which case they obey the same laws, but
with a slightly different roughness coefficient. Corrugated pipes are hydraulically
rough.
Basic equations
For smooth pipes, the DarcyWeissbach equation is valid:
(1)
where:
or
(Blasius)
(2a)
(Nikuradse)
(2b)
with:
a = coefficient;
d = pipe diameter (m);
g = acceleration of gravity = 9.81 m/s2;
h = hydraulic head (m);
Re = Reynolds number for pipes;
v = flow velocity (m/s);
x = distance along pipe (m);
= coefficient;
= kinematic viscosity ( 10-6 m2/s).
Both expressions for give comparable results (Table A20.1, for a = 0.3164). Because
Equation 2b requires iteration, Equation 2a is normally used.
193
TABLE A20.1
Reynolds number
2 000
5 000
10 000
20 000
50 000
100 000
-Nikuradse
0.0495
0.0374
0.0309
0.0259
0.0209
0.0180
% difference
4.6
-0.6
-2.4
-2.7
-1.2
1.1
TABLE A20.2
a coefficient
Remarks
0.3164
Technically smooth
0.40
0.77
Theoretically not allowed for hydraulically rough pipes, but in accordance with field data for small-diameter corrugated drains.
Completely smooth laterals and collectors do not exist. Smooth plastic pipes contain
perforations; ceramic and baked clay ones have joints and are not always aligned. For
such technically smooth drains and collectors, the a coefficient in Equation 2a was
taken as 0.40 instead of 0.3164. Table A20.2 shows values used for the a coefficient, as
found in the literature.
Smooth laterals
Drain laterals collect additional water all along their length. At any point x, measured
from their upstream end, the discharge Q and the velocity v are:
and
(3)
where:
L
= drain spacing (m);
q
= design discharge (m/s);
Q = drain discharge (m3/s).
Accordingly, the flow velocity v varies along the length and so does the Reynolds
number.
Inserting v in the basic equations (Equations 1 and 2a) leads to:
(4)
and integrating between x = Bi-1 and x = Bi:
(5)
with:
Bi-1, Bi = begin, end of a drain section (m);
Fs
= calculation coefficient for smooth pipes;
n
= 11/4;
H
= head loss in the drain (m).
In drains consisting of one pipe size only, Bi-1 = 0. However, the full expression will
be needed later for drains with increasing pipe diameters downstream (multiple drains).
The head loss H in the drain must be less than or at most equal to the design head loss
over the entire drain length, H.
Guidelines and computer programs for the planning and design of land drainage systems
194
If Bi-1 = 0, the permissible drain length B for this design head equals:
11 7/4
B=
16 2
gHd 19/4
av1/4 q 7/4 L7/4
4/11
(6)
and the minimum diameter required for a given drain length B is:
16 2
d=
11 7/4
gH
4/19
(7)
7/4
gHd 19/4
11
L=
16 2 av1/4 q 7/4 B 11/4
4/7
(8)
For hydraulically smooth, new, collecting pipes the required head can be calculated
with:
H=
(qL)
59 .77
7/4
7/4
19/4
4 11/4
B
11
(9)
195
CORRUGATED PIPES
Basic equations
Most authors calculate flow through corrugated pipes with Mannings equation:
Q = Km AR 2/3 s 1/2
(10)
where:
d
A =
2
Km
R=
A d r
= hydraulic radius (m);
= =
u 4 2
= slope of H;
d
= wet circumference (m).
u = 2
2
The formula for smooth pipes is sometimes used for corrugated pipes, but with a
much larger constant a (Zuidema and Scholten, 1972), whereas other authors (e.g. Van
der Beken, 1969, Van der Beken et al., 1972) introduce an equivalent sand roughness
to account for the influence of the corrugations.
Mannings Km for corrugated pipes
In Mannings equation, the constant Km depends mostly on the spacing, depth and
shape of the corrugations S and also on the diameter d. The Km values for corrugated
pipes are compiled in Table A20.3. The narrower the corrugation spacing S, the larger
Km. According to Irwin (1984) and Boumans (1986):
Km = 70
Km = 18 .7 d 0.21 S 0.38
(10 mm)
(11a)
(10 mm)
(11b)
where:
d
= inner pipe diameter (m);
S
= spacing of individual corrugations (m).
Equations 11a and 11b for Km are used in the programs for corrugated pipes. For
safety reasons, the maximum value is taken as 65 instead of 70.
Corrugated laterals
If for full flowing pipes, Equations 3 and 10 are solved for Q:
qLx = Km
d
d2
4
2
2/3
s 1/2 = Km
d 8/3 dh
4 5/3 dx
1/2
(12)
The head loss H between points B1 and Bi-1 can be obtained by integrating
Equation 12 between these points:
dh =
4 10/3 (qL)
K d
2
2
m
16/3
x 2 dx
(13)
Guidelines and computer programs for the planning and design of land drainage systems
196
TABLE A20.3
Material
Netherlands
PVC
Germany
PVC
PE
United Kingdom
PP
Drain diameter d
Outer
Inner
(mm)
65
57
80
72
100
91
160
148
60
52
100
91
125
115
380
307
129
100
196
171
265
225
350
305
with n=3
Rib spacing S
Km value
(mm)
6.25
6.25
6.25
7.50
6.30
8.30
8.30
50.00
18.00
20.00
33.00
50.00
70
74
78
80
69
70
73
46
53
57
50
45
(14)
with:
Fc = calculation coefficient for corrugated pipes.
As mentioned above, in drains consisting of one pipe size only Bi-1 = 0. For
corrugated pipes, integration of Mannings equation results in:
(15)
(16)
Corrugated collectors
If the collectors have the same spacing Lc, the same formulae may be used for their
calculation, substituting their spacing Lc and length Bc for L and B. If they do not
have the same spacing, calculations have to be made separately for each section of the
collector. The spacing of laterals, and, thus, the distances of inflow points along the
collector, has only little effect, provided that more than five laterals are involved.
MAINTENANCE STATUS AND REDUCTION FACTORS
The problem of clogging of drainpipes
In practice, drains are seldom completely clean. This is because some siltation always
occurs, notably during and shortly after construction owing to the entrance of soil
particles from the yet unsettled soil and/or envelope around the pipe when relatively
large amounts of water enter. A layer of sediment usually forms over time. This
197
198
Guidelines and computer programs for the planning and design of land drainage systems
(18)
is:
(19)
(20)
The hydraulic radius was R = r/2 and becomes:
(21)
(24)
Table A20.4 shows the f values calculated for different fractions of sediment height
and area. These values are represented in Figure A20.4.
Categories according to maintenance status
For the reasons discussed above, maintenance can only be specified in a global way. From
the data in Table A20.4, the following choices were made with respect to maintenance
status by distinguishing five categories. These categories have been defined in terms of
the relative height of sediments in the drainpipes (Table A20.5). Table A20.5 shows the
influence of maintenance status on the flow in partially clogged drains.
199
FIGURE A20.4
1.2
1
0.8
0.6
0.8
0.6
0.4
0.4
0.2
0.2
0
0
0.2
0.4
0.6
0.8
1
Height and area of sediment fraction
0
1.2
TABLE A20.4
(25)
Fraction of
sediment
area
Factors
l/2r
1 - A/A
f1
f2
.050
.019
.981
.986
.972
.100
.052
.948
.961
.923
.150
.094
.906
.930
.863
.200
.142
.858
.894
.796
.250
.196
.804
.854
.724
.300
.252
.748
.810
.650
.350
.312
.688
.764
.575
.400
.374
.626
.715
.501
.450
.436
.564
.664
.429
.500
.500
.500
.611
.360
.550
.564
.436
.556
.295
.600
.626
.374
.500
.235
.650
.688
.312
.441
.181
.700
.748
.252
.382
.133
.800
.858
.142
.259
.058
.850
.906
.094
.196
.032
.900
.948
.052
.131
.013
.950
.981
.019
.066
.003
.990
.998
.002
.013
.000
TABLE A20.5
Cross-section clogged
(%)
New pipe
1.000
Excellent
0.972
Good
10
0.923
Fair
20
0.796
Poor
40
0.501
Guidelines and computer programs for the planning and design of land drainage systems
200
FIGURE A20.5
0.4
Elevation, m
Elevation, m
0.3
Given slope
It is supposed that the drain slope equals s = Ht/Bt so that at design discharge there
is no water above the upper end of the drain (Figure A20.5).
The first section AB has a length B1, governed on the one hand by Equation 5 or 14;
on the other, by the given slope. From the latter, it follows that the head loss in this
section equals:
(26)
where H is the design head.
201
Inserting H1 in Equation 5 or
14, with B0 = 0 (first section), and
rearranging, leads to:
FIGURE A20.7
(27)
0.25
0.2
For smooth pipes, F1 = Fs with d =
Head in pipe 0.08
d1 and m = 4/7; for corrugated pipes,
F1 = Fc with d = d1 and m = 1/2
0.15
If B1 exceeds the total length B,
the first section is already sufficient
0.1
Head in pipe 0.12
to meet the requirements. In this
case, a combination with narrower
0.05
pipes might be used.
The second section, with diaDiameter 0.12 mm
Diameter 0.08 mm
0
meter d2, causes a head loss H2,
0
100
200
300
for smooth drains according to
Equation 5, for corrugated pipes to
Equation 14. The factors Fs or Fc are
now calculated with d = d2 .
The total head loss Ht = H1 + H2 must be smaller than or at most equal to the
required H. If greater, a second section with larger diameter must be chosen or another
combination be tried.
(28)
400
202
Guidelines and computer programs for the planning and design of land drainage systems
REFERENCES
Boumans, J.H. 1986. Stromingsformules voor drainage ribbelbuis. Cultuurtech. Tijdschr., 26:
4146.
FAO. 2005. Materials for subsurface land drainage systems, by L.C.P.M. Stuyt, W. Diericks & J.
Martnez Beltrn. FAO Irrigation and Drainage Paper No. 60 Rev. 1. Rome. 183 pp.
Irwin, R.W. 1984. Corrugated pipe flow rate from pipe geometry. J. Irr. Dr. Eng., 237241.
Van der Beken, A. 1969. Bijdrage tot de hydraulica van draineerbuizen. Meded. Rijk. Landbouw.
Publ., 35/WB-5. 87 pp.
Van der Beken, A, De Troch, F., De Somer, M. & Zuidema, F.C. 1972. The lateral inflow into
submerged drains. Bull. Int. Ass. Hydrol. Sci., 17: 273289.
Zuidema, F.C. & Scholten J. 1972. De afvoercapaciteit van geribbelde plastieken draineerbuizen.
Van Zee tot Land, 49: 73102.
203
Annex 21
Interceptor drains
FIGURE A21.1
Surface
D1
K
Phreatic
level
Drain
Base
(impermeable)
D0
HILLSIDES
An analysis of the interception of flow from hillsides of uniform slope was given by
Donnan (1959), as represented in Figure A21.1.
The flow from upstream, per metre of length, is:
(1)
and downstream:
(2)
The drain discharges, per metre of length, is:
(3)
where:
q1 = upstream flow per metre of length (m2/d);
q0 = downstream flow per metre of length (m2/d);
K = permeability (m/d);
D1 = upstream thickness of flow (m);
D0 = downstream thickness (m);
= angle of slope (rad).
In this analysis, the downstream flow has a thickness D0, which is entirely governed
by the distance of the drain above the impermeable base (which is governed by the
drain depth).
The upstream thickness varies from D0 near the drain to D1 far upstream. A given
thickness y appears at a distance x from the drain:
(4)
Guidelines and computer programs for the planning and design of land drainage systems
204
where:
x = distance from drain (upstream) (m).
On hill slopes, hydrological conditions are often much more complicated. Wet or
saline spots caused by seepage may sometimes be protected by an interception drain
laid at the upper end of the affected field.
This formula ignores the radial resistance encountered in the convergence of the
stream lines onto the drain. Because of this resistance, D0 has to be increased, with the
resulting head h.
In a homogeneous soil, this radial resistance can be estimated by Ernsts formula:
(5)
and
(6)
D0
where:
d = effective diameter of drain (m);
Wr = radial resistance (d/m);
hr = extra head from radial resistance (m).
In the described case of a homogeneous soil and a constant angle , this increase in
D0 will usually be slight. However in the cases described below, the consequences can
be considerable.
In most cases, an interceptor drain will be laid if: the slope decreases, the depth
of the impermeable base becomes less, or the permeability decreases. At places
where these occur, hillside flows tends to come too close to the surface and cause
waterlogging, eventually followed by soil salinization. Based on the above theory,
the program INCEP gives the required effective diameter of the drain, necessary to
diminish the radial resistance to a sufficiently low level. It is valid for a non-layered
soil (Figure A21.2), and allows jumps in thickness and permeability at the drain. The
arithmetic averages of thickness and permeability are used in order to calculate the
radial resistance.
The capacity of pipes for interceptor drains must be calculated separately from
the discharge per metre, their length and their longitudinal slope. The programs
DRSINGLE and DRMULTI can
be used for this purpose. The largest
FIGURE A21.2
value from both calculations (for
Definition sketch for program INCEP
effective diameter and for capacity)
must be taken.
Conditions become far worse
Surface
where the drain cannot reach wellpermeable subsoil and remains
D1
K1
within a less permeable top layer, a
Phreatic level
case covered by program INCEP2.
near drain: head at base
Then hr soon reaches such high
values that a single interceptor drain
h
is not sufficient, and a wide ditch or
y
Drain
even regular drainage is needed.
Base
(impermeable)
The program INCEP2 supposes
that the drain trench or open ditch
K0
has a flat bottom that is located in the
topsoil and receives the flow from the
x
permeable subsoil (Figure A21.3). In
205
this case, the exact solution can be found by complex transformation. An excellent
approximation for this case is obtained by calculating the parallel lines flow between
the border with the permeable subsoil and the ditch bottom with Equation 7, using a
correction factor of 0.88.
for
(7)
where:
a = distance to more permeable subsoil (K1 < 0.1K2) (m);
b = width of drain trench or ditch bottom (m);
K1 = permeability of topsoil (m/d);
K2 = permeability of subsoil (K2 > 10 K1) (m/d);
q = upward flow (m2/d);
h = difference in piezometric head above the trench bottom (m).
INCEP2 provides both solutions for b.
LEAKY CANALS AND UPSTREAM FIELDS
The same principles apply for interceptor drains catching leakage from irrigation canals
of losses from upstream fields.
For leaky irrigation canals, the best way is to reduce the water losses by lining. Where
that is impossible, and damage is occurring by nearby waterlogging or salinization,
interceptor drains are a second option. Then, the incoming flow per metre, q1, is half of
the losses from the canal. These losses can be estimated by measuring the fall in water
level in an isolated section.
However, these losses are
proportional to the difference in
FIGURE A21.3
head between the canal water and
Drain trench or ditch in low-permeable topsoil
the nearby groundwater. Therefore,
drainage will increase both head and
inflow (Figure A21.4). Lowering the
groundwater increases the flow with
a factor h2/h1.
h
The incoming inflow can be
b
calculated if the original loss and the
factor h2/h1 and q0 are determined:
(8)
where:
q0 = original outflow from
canal (m2/d);
q1 = outflow from canal after
interceptor drainage (m2/
d);
D = thickness of aquifer (m);
h1 = hydraulic head in the
canal (m) above original
groundwater level;
h2 = hydraulic head in the canal
(m) above drain level.
On the other hand, losses from
upstream irrigated or rainfed lands
will not be influenced by interceptor
FIGURE A21.4
h2
h1
Groundwater before
and after drainage
Drain
Groundwater before
D
Impermeable base
Drain
206
Guidelines and computer programs for the planning and design of land drainage systems
FIGURE A21.5
Impermeable base
RESULTS
In many cases, the width is such that a regular drainage is to be preferred, for which the
program ARTES gives some guidelines. Alternatively, a wide ditch can be considered,
especially at intermediate values for the required width. However, as side slopes tend to
become unstable under such circumstances, it is often necessary to stabilize them. This
can be achieved by covering the side slopes with a gravel cover or by making a wide,
gravel-filled trench provided with an outlet pipe.
REFERENCE
Donnan, W.W. 1959. Drainage of agricultural lands using interceptor lines. J. Irri. Drain. Div.
Proc. ASAE, 85, IR 1:1323.
207
Annex 22
INTRODUCTION
Vertical drainage is possible under
favourable geological circumstances:
a good aquifer underneath;
an aquifer containing water
with a low salt content, so that
the water can be used;
not too large resistance between
soil and aquifer.
Figure A22.1 gives a sketch of the
method.
Two types of wells are considered:
those fully penetrating the aquifer;
and non-penetrating cavity wells.
They are supposed to form a large
array of squares (Figure A22.2)
or triangles (Figure A22.3). In
Figures A22.2 and A22.3, for one
well, the flow region and the sphere
of influence are indicated.
This method is mainly used in
arid regions where use of the water
for irrigation has often led to serious
overpumping. In some areas, the
lowering of the water levels in
the aquifer has led to attraction of
salty water from elsewhere, often
from deeper layers, sometimes
from the sea. In the long run, in
an arid climate, salt will inevitably
accumulate. However, this process
is usually very slow, owing to the
large amount of water stored in an
aquifer. Thus, vertical drainage may
be a temporary solution to a high
water table situation.
Nevertheless, the method can be
used to control groundwater levels.
This is illustrated by the following
(steady-state) theory.
FIGURE A22.1
5
Well
Surface
Groundwater
Head aquifer
-5
Resistance
-10
Cavity well
Permeability K
Fully
penetrating
well
Impermeable base
Thickness D
-15
-20
0
10
15
20
FIGURE A22.2
25
Guidelines and computer programs for the planning and design of land drainage systems
208
(1)
where:
resistance of semi-confining layer (d);
D = thickness of aquifer (m);
d = thickness of semi-confining layer (m);
K = permeability of aquifer (m/d);
K = permeability of semi-confining layer (m/d);
= characteristic length (m).
Greater insight is obtained from formulae describing the lowering of the
groundwater when an aquifer is pumped by a network of wells under the following
conditions (Figure A22.1):
the wells are fully penetrating and tap the aquifer over its entire depth;
between groundwater and aquifer, there is a layer of low permeability that gives a
certain resistance to vertical flow, but still allows its passage;
there is equilibrium between the amounts pumped and the recharge (steady
state);
no water is entering the well-field laterally from outside.
209
The yield of each well Qw is taken to be positive, as is the flow Q towards the
well. According to Darcys Law and taking absolute values for Q, for the flow in the
aquifer:
Q = 2 rKD
dH
(2)
dr
On the other hand, the rainfall or irrigation excess should create the same flow:
Q = R2 r 2 q
(3)
so that both expressions for Q are equal, provided that there is no lateral inflow
from around the well-field.
Finally, the vertical resistance c of the layer between groundwater and aquifer leads
to a recharge:
q=
h(r ) H(r )
c
(4)
(5)
rw r R
(7)
Midway between the surrounding wells, the groundwater table should be lowered to
the required depth, but it will be deeper near the well. The head in the aquifer is lower
than the groundwater level because of the resistance between the two. If more water
is being pumped than the recharge, there will be overpumping, leading to a gradual
depletion of the aquifer. Although this is usually not sustainable, overpumping can be
210
Guidelines and computer programs for the planning and design of land drainage systems
(8)
For a triangular array (Figure A22.3), the region drained by a well is hexagonal,
where:
or
(9)
CAVITY WELLS
In some areas, wells are made by removing sand from the aquifer by heavy pumping.
A washed-out cavity is formed at the top of the aquifer, which remains intact during
the following period of less heavy abstraction (Figure A22.1, in blue). Compared with
fully penetrating wells, they encounter an extra resistance, but their diameter is larger,
although the actual size is rarely known.
The cavity is supposed to be a half-sphere with radius rw. In its vicinity, the flow is
spherical and an extra resistance occurs. This effect is estimated by assuming that the
flow to such non-penetrating wells breaks down as follows:
cylindrical flow from the outer limit R to a distance rd from the well, so that
Equation 6 can be used for r > rd; arbitrarily, rd can be taken as the lowest value of
D or R;
spherical flow from distance rd to the spherical cavity with radius rw.
For rd, arbitrarily:
(10)
where:
D = thickness of aquifer (m);
and D < R.
For very thick aquifers or a very dense network, D can become larger than R. Then,
for D > R:
(11)
The cylindrical part of the flow is described by Equation 6 for rd < r R.
The head in the aquifer is calculated (or approximated) by:
rw r rd
(12)
There are several assumptions involved, but the greatest uncertainty lies in the
unknown diameter (thus, radius rw) of the cavity. Although this is an approximation,
the errors are small enough for practical purposes.
APPLICABILITY OF THE METHOD
If more water is being pumped than the recharge, there will be overpumping, leading
to a depletion of the aquifer. Moreover, an equilibrium abstraction will also not be
sustainable in an arid region. This is because its use for irrigation will lead ultimately
to a harmful accumulation of salt in the aquifer. However, both overpumping and
equilibrium abstraction may be used as temporary solutions for water scarcity, high
groundwater, and soil salinity. The time horizon depends on the local circumstances
and requires further study.
The program WELLS is based on these considerations. The differences between
fully penetrating and cavity wells relate to an extra radial resistance in the vicinity of
the latter (red and blue lines in Figure A22.1). This extra resistance is caused by flow to
a sphere instead of a long cylinder.
211
213
Annex 23
214
Guidelines and computer programs for the planning and design of land drainage systems
All project files obtained are listed in a file LIST**, beginning with LIST, followed
by two characters for its kind (LISTSP.TXT contains all drain spacing [SP] calculations
made).
Output files
For each project, the results are written to a file, the name of which is mentioned by
the program.
If reading in DOS, take care to copy this indication literally, including the signs -, --,
and --- used if some of the four positions are blanks (project A leads to file A---.TXT,
and project AB to file AB--.TXT).
Under Microsoft Windows, this difficulty is avoided. Just double-click the icon.
GUMBELS METHOD
GUMBEL, for estimating extreme values
After the three general questions (notation of decimal, project name, and location), the
program moves on to specifics:
Input of the extreme values (e.g. the highest three-day precipitation in a given
month, in millimetres) from keyboard or from data file. They are processed using
Kendalls method.
The return period (T) related to hydrological data (usually in years). The program
gives the expected values.
End the series of T with 999. A graph appears on screen with the data on the
vertical axis, and the Gumbel distribution on the horizontal, with the data plotted
according to Kendall. The Kendall line is shown in red. The graph is useful to
visually detect upward or downward trends, which make the prediction less valid
and indicate that the method may not be applicable in this case: too low if upward,
too high if downward.
Leave the graph with ENTER.
Continuation, output and example
The process can be repeated in a new case belonging to the same project. With another
project or END, the files are closed and the results written to file GU****.txt, where
GU stands for Gumbel and **** is the abbreviated project name. These filenames
are mentioned in LISTGU.TXT.
Figure A23.1 gives the output for extremes of total precipitation occurring during 1
to 7 successive days (1d to 7d) in an area in eastern Spain. The climate is Mediterranean,
with heavy rainfall in autumn.
PERMEABILITY MEASUREMENTS
AUGHOLE, for permeability from auger-hole measurements
After the three general questions (notation of decimal, project name, and location), the
program moves on to specifics:
Which unit is chosen? Answer 1, 2 or 3. Recommended is 2, the use of centimetres,
in contrast to most other programs.
Diameter and depth of the auger hole in the chosen units?
Location of the impermeable base?
Groundwater present of no? This determines the method: normal or inverse (less
reliable).
Normal method
For the normal method, the initial depth of the water in the hole is measured after
equilibrium. Then, some water is pumped out and the position of the water table is
given at different times:
215
Inverse method
In dry soils, the groundwater may be
too deep to measure the permeability
of the upper layers. In this case, the
inverse method can be used. Water
is poured in, and its lowering is
measured over time. The method
is less reliable and should be used
only if there is no other possibility.
Moreover, some soils swell slowly
and have a lower permeability in the
wet season.
Option no groundwater is
followed, and the fall of the water
level and the time interval are
entered.
Continuation
The resulting permeability appears
on screen.
Next items:
Same or new auger hole or
END? The first option allows
another measurement in the
same auger hole, e.g. in the
subsequent interval. The other
two finish the calculation and
show the mean value and its
standard deviation on screen.
The next item can be in the
same project or not. In the
first case, the existing project
file is continued. Otherwise,
it is closed and the filename
mentioned on screen as
AU****.txt where AU denotes
auger hole and **** is the
abbreviated project name.
This name is also added to
the listing LISTAU.TXT,
mentioning all existing augerhole files.
If Other project or END
is selected, new names are
required for project and
location; END returns the
user to the initial screen.
FIGURE A23.1
216
Guidelines and computer programs for the planning and design of land drainage systems
FIGURE A23.2
Example
In the project OFL1, at location
Swifterb, an auger hole of 8 cm in
diameter and 150 cm deep is made.
The impermeable base is at a depth
of 200 cm. Groundwater establishes
a water level in the hole at a depth
of 50 cm. Several measurements are
taken after lowering to 90 cm below
the surface. This gives K = 0.63 m/d,
as shown by Figure A23.2.
Continuation
The resulting permeability appears on screen.
Next items:
Same or new piezometer hole or END? The first option allows another measurement
in the same piezometer, e.g. in the subsequent interval. The other two finish the
calculation and show the mean value and its standard deviation on screen.
The next item can be in the same project or not. In the first case, the existing
project file is continued. Otherwise, it is closed, and the filename mentioned
on screen as PZ****.TXT where PZ indicates piezometer and **** is the
abbreviated project name.
This name is also added to the listing LISTPZ.TXT, mentioning all existing
piezometer files.
If Other project is selected, new names are required for project and location.
END returns the user to the initial screen.
Output
The output is similar to that of AUGHOLE. Figure A23.3 gives an example.
CALCULATION OF DRAIN SPACINGS
SPACING, for drainage under normal (non-artesian) conditions
After the three general questions (notation of decimal, project name, and location), the
program moves on to specifics:
217
Continuation
The project can be continued and
then the data for the new location
are added to the same file. If a new
project is taken or the existing one
is ended, the files are closed and the
filename is mentioned on screen and
added to LISTSP.TXT. Any new
project needs another name.
Output and example
The results are visible on screen
and put on file SP****.TXT, where
SP denotes spacing and ****
the abbreviated project name.
Figure A23.4 gives an example of
the output for project aa, location
amandabad. The radial resistance Wr
can be used as input in the programs
NSDEPTH and NSHEAD.
218
Guidelines and computer programs for the planning and design of land drainage systems
NSABOVE, for drain spacing at non-steady flow above drain level only
After the three general questions (notation of decimal, project name, and location), the
program moves on to specifics:
Thickness of permeable layer (equal to drain depth or ditch bottom).
Pipe drains or ditches. For pipes and dry and almost dry ditches, the Boussinesq
approach is followed; for water-holding ditches, the Schilfgaarde method is used.
For pipe drains and nearly dry ditches, there is choice between an elliptic
initial situation, where the shallowest depth is midway between drains, or a total
ponding of the entire area.
In the elliptic case, the initial groundwater depth midway is asked (in ponding it
is zero everywhere). In the Schilfgaarde method, the shape is initially elliptic.
The required groundwater depth at time t and the value of t.
For water-holding ditches, the (constant) water depth must be specified.
If these data are correct, the soil characteristics are required: the permeability
and the available storage (moisture volume fraction between saturation and field
capacity).
Calculations are made and the resulting drain spacing appears on screen.
If initially ponded, a lag time is mentioned, an estimation of the time span
between total saturation and the first lowering midway between drains.
FIGURE A23.5
2.00 m/d
.12 --
Continuation
The process can be repeated in a new
case belonging to the same project.
With another project or END, the
files are closed and the results written
to file NA****.txt, where NA stands
for Nonsteady Above and ****
is the abbreviated project name.
These filenames are mentioned in
LISTNA.TXT.
Output and examples
Figure A23.5 gives results at two
locations in project a, of which
location a1 has pipe drains, location
a2 water-holding ditches. In the first
case, the surface is considered ponded
at the beginning; in the second case,
the water table is initially elliptic. The
difference in lag time to reach a
nearly elliptic shape explains most of
the difference in drain spacing.
NSDEPTH and NSHEAD, for
drains above impermeable base
NSDEPTH gives the depth of
the groundwater below surface,
NSHEAD gives the head above
drain level.
After the three general questions
(notation of decimal, project name,
and location), the programs move on
to specifics:
The
The
The
The
The
permeability (equal above and below drain level), in metres per day.
storage coefficient, as volume fraction.
drain depth, in metres below surface.
thickness of the layer below the drains, in metres.
initial groundwater depth, the same everywhere: ponded or specified. If
ponded, it is automatically zero; if specified, the initial depth is required.
The radial resistance Wr near the drain (d/m). An estimate can be obtained from
the program SPACING. The entrance resistance, met by flow into the drain, is
ignored. For ditches, it is near zero; for good working drains, it is negligible, of
the order of 0.1 d/m.
For abnormally high discharges, the outflow system can be handled by the pipes and
ditches, but at higher heads and water levels. The following data allow an estimate:
The design discharge of the outflow system, in metres per day. Divide millimetres
per day by 1 000.
The design head loss in this system, in metres. At high discharges, higher head
losses are to be expected, leading to higher levels in this system.
After a heavy rain (or snowmelt), evaporation may help to lower the groundwater
tables, but the influence diminishes the deeper they are. The following items allow an
estimate:
The potential evaporation, in metres per day. Divide millimetres per day by
1 000.
The relationship of potential evaporation with groundwater depth, linear or
exponential.
The depth where evaporation becomes zero (linear) or the characteristic depth
where it is reduced to 1/e times the value at the surface (exponential).
Check the input. If correct, continue with:
Proposed drain spacing, in metres.
Number of days to be calculated.
Time-step for the calculation (lower than a given maximum), in days.
NSDEPTH shows the resulting groundwater depths on screen, with t is the time,
dp the groundwater level in the drainpipe, d0 the groundwater level near the drain and
d1d10 the depths between the drain and midway, where d0 is drain and d10 is midway.
Finally, d11 is equal to d9 (symmetry).
If unsatisfactory, other drain spacing can be taken. A slow retreat in dp values
suggests an insufficient main system or unsatisfactory performance of the drainpipe.
Large differences between dp and d0 indicate a considerable influence of the radial
resistance Wr.
NSHEAD is similar, but it gives the heads above drain level instead of the
depths.
Continuation
After ending with 999, the process can be repeated for a new case belonging to the
same project. With another project or END, the files are closed and the results written
to file ND****.txt or NH****.txt, where ND stands for Nonsteady Depth, NH
for Nonsteady Head and **** is the abbreviated project name. These filenames are
mentioned in LISTND.TXT and LISTNH.txt.
Output and examples
Figure A23.6 and A23.7 show examples from NSDEPTH and NSHEAD for project
aa, location aa1. The first shows the groundwater depths as function of time, the
second the heads above drain level. Together they form the drain depth of 1.50 m.
The initial depth of the water table was 0.2 m below surface, giving the initial head
as 1.30 m.
219
220
Guidelines and computer programs for the planning and design of land drainage systems
221
FIGURE A23.7
hp
h0
h1
h2
h3
h4
h5
h6
h7
h8
h9
.00 1.11 1.29 1.30 1.30 1.30 1.30 1.30 1.30 1.30 1.30 1.30
.15 1.03 1.21 1.24 1.25 1.27 1.28 1.28 1.28 1.29 1.29 1.29
.30 1.00 1.17 1.20 1.22 1.24 1.25 1.26 1.27 1.27 1.27 1.28
.45 .97 1.14 1.17 1.19 1.21 1.22 1.24 1.25 1.25 1.26 1.26
.60 .95 1.12 1.14 1.17 1.19 1.20 1.22 1.23 1.23 1.24 1.24
.75 .92 1.09 1.12 1.14 1.16 1.18 1.19 1.21 1.21 1.22 1.22
.90 .90 1.07 1.10 1.12 1.14 1.16 1.17 1.18 1.19 1.20 1.20
1.05 .88 1.05 1.08 1.10 1.12 1.14 1.15 1.16 1.17 1.18 1.18
1.20 .86 1.03 1.06 1.08 1.10 1.12 1.13 1.14 1.15 1.16 1.16
1.35 .84 1.01 1.03 1.06 1.08 1.10 1.11 1.12 1.13 1.14 1.14
1.50 .83 .99 1.01 1.04 1.06 1.08 1.09 1.10 1.11 1.12 1.12
1.65 .81 .97 .99 1.02 1.04 1.06 1.07 1.08 1.09 1.10 1.10
1.80 .79 .95 .98 1.00 1.02 1.04 1.05 1.06 1.07 1.08 1.08
1.95 .77 .93 .96 .98 1.00 1.02 1.03 1.04 1.05 1.06 1.06
2.10 .75 .91 .94 .96 .98 1.00 1.01 1.02 1.03 1.04 1.04
2.25 .73 .89 .92 .94 .96 .98 .99 1.01 1.02 1.02 1.03
2.40 .72 .87 .90 .92 .94 .96 .98 .99 1.00 1.00 1.01
2.55 .70 .85 .88 .90 .92 .94 .96 .97 .98 .98 .99
2.70 .68 .84 .86 .89 .91 .92 .94 .95 .96 .97 .97
2.85 .67 .82 .84 .87 .89 .91 .92 .93 .94 .95 .95
3.00 .65 .80 .83 .85 .87 .89 .90 .91 .92 .93 .93
h10 h11
1.30
1.29
1.28
1.26
1.24
1.22
1.20
1.18
1.16
1.14
1.12
1.10
1.08
1.07
1.05
1.03
1.01
.99
.97
.95
.94
1.30
1.29
1.28
1.26
1.24
1.22
1.20
1.18
1.16
1.14
1.12
1.10
1.08
1.06
1.04
1.03
1.01
.99
.97
.95
.93
222
Guidelines and computer programs for the planning and design of land drainage systems
DRAIN DIAMETERS
DRSINGLE, for single drain
After the three general questions (notation of decimal, project name, and location), the
program moves on to specifics:
Type of drains: options are available for laterals and collectors. The latter are
characterized by greater spacing, and often also greater length.
Type of pipe: smooth (theoretical) (1); technically smooth (in practice) (2); or
corrugated (two options, general (3) or according to Zuidema for small pipes,
[maximum diameter 0.12 m]). Option general (3) will ask for the spacing of
corrugations.
Maintenance status, that is the amount of sediment to be expected in this soil
under usual maintenance. In some soils, drains will keep clean, even without or
with infrequent maintenance; in others, the pipes will clog with iron hydroxides,
223
FIGURE A23.9
FIGURE A23.10
224
Guidelines and computer programs for the planning and design of land drainage systems
with the available diameters, total length and spacing. The program then calculates the
length of the different sections.
After the three general questions (notation of decimal, project name, and location),
the program moves on to specifics:
Type of drains (laterals, collectors, or interceptor drains).
For laterals and collectors, data are asked for allowed head loss in drain and
specific discharge; for interceptors allowed head loss and inflow per m length
(obtained from INCEP or INCEP2).
The number of different sections is required.
Type of pipe used in each section: smooth (theoretical) (1), technically smooth (in
practice) (2), or corrugated (two options, general (3) or according to Zuidema for
small pipes [maximum diameter 0.12 m]). Option general (3) will ask for the
spacing of corrugations.
Maintenance status for the entire drain. This is the amount of sediment to be
expected in this soil under usual maintenance. In some soils, drains will keep
clean, even without or with infrequent maintenance; in others, the pipes will clog
with iron hydroxides, sediments, or roots, even with regular (e.g. annual) cleaning.
The former will have a good status, the latter a poor one. The quantity must be
estimated from earlier experience. Where unknown, try 3.
Diameter of each section.
For laterals and collectors: spacing and length; for interceptors: their length only.
Results
The necessary calculations are made and the result appears on screen, first for two
sections only. Then:
ENTER to see a graph showing the head at design discharge and the slope of the
drain.
ENTER again to leave the graph.
If more than two sections are being considered, this procedure is repeated for all
sections involved: lengths of all sections on screen, followed by a graph. Then:
ENTER to continue.
Same project, other one, or end? The first option allows another measurement in
the same project. The others finish the calculation.
Continuation
In the same project case the existing project file is continued. Otherwise, it is closed,
and the filename is mentioned on screen as DM****.TXT, where DM denotes Drain,
Multiple and **** is the given project name. All these names are collected in the file
LISTDM.TXT.
If Other project is selected, new names are required for project and location. With
END, the user returns to the initial screen.
Output and example
Figure A23.11 gives an example for laterals of 350 m in length in a humid climate.
MAIN DRAINAGE SYSTEM
BACKWAT, for backwater effects in the outlet channel of the main system
If an open channel of the main drainage system discharges via an open connection
or sluice into a river, lake or sea, fluctuations in outside water level will influence
the level in that channel. Especially high outside levels have an unfavourable and
sometimes disastrous effect. Apart from a steady-state influence, also non-steady
effects can be important in such cases. However, to form an idea of such effects,
225
FIGURE A23.11
Program
After the three general questions
(notation of decimal, project name,
and location), the program moves on
to specifics:
Dimensions of watercourse:
bottom width in metres, side
slopes. The results are shown
on screen and can be corrected
if necessary.
Longitudinal profile: length
of section, land and bottom
elevation, first upstream and
then downstream, in metres.
Water elevation downstream, in
metres. The results are shown
on screen and can be corrected
if necessary.
Discharge from upstream, in cubic metres per second. Correction is possible. The
program gives the equilibrium depth far upstream. As a check, the discharge is
recalculated.
The step size in water depth, in metres, to be used in the numerical calculations.
The program shows the results. ENTER returns to step size so that another value
may be tried. Indicating END at this stage (type 9) leads to a question about the next
item.
Next item and example
Same project, other one, or end? The first option allows another measurement in the
same project. The others finish the calculation and ask for a new project filename for
another abbreviated filename.
In the same project case, the existing project file is continued. Otherwise, it
is closed, the filename mentioned on screen and added to LISTBW.TXT. If Other
project is selected, new names are required for project and location. With END, the
user returns to the initial screen.
Guidelines and computer programs for the planning and design of land drainage systems
226
FIGURE A23.12
2000. m
6.00 m
3.00 m
land upstream
land downstream
bottom upstream
4.00 m
bottom downstream .00 m
water downstream
2.00 m
land slope
bottom slope
1.500 o/oo
2.000 o/oo
depth
2.000
1.950
1.900
1.850
1.800
1.750
1.700
1.650
1.600
1.550
1.500
1.450
1.400
1.350
1.300
1.250
1.200
1.150
1.144 m
9.998 m3/s
Q-calc
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
An example
Figure A23.12.
is
given
by
INTERCEPTOR DRAINS
INCEP and INCEP2, for
homogeneous profiles and for a
less permeable top layer
Interception drains are needed in
places where waterlogging occurs
in undulating terrain, especially to
protect the downstream fields. This
waterlogging is usually caused by a
decrease in slope, a change in the soil
profile or an abrupt lowering of the
surface. In other cases, it is caused
by leakage from irrigation canals and
watercourses, or from higher lands.
The program allows changes of this
kind for a profile of permeable soil
on an impermeable base. It calculates
the width of a drain trench or ditch
bottom that is sufficient to catch
the intercepted flow. A separate
calculation is needed for the size of
the drain needed, this can be found
by the program DRMULTI.
227
FIGURE A23.13
.00 m
3.00 m/d
8.00 m
2.00 m
6.00 m
.48 d/m
.50 m
1.05 m2/d
1.05 m2/d
.00 m2/d
6.50 m
1.50 m
228
Guidelines and computer programs for the planning and design of land drainage systems
per day.
Permeability of second layer,
Printout of program INCEP2
metres per day.
Thickness of top layer, metres.
***** interceptor drain, two-layered soil *****
================================================= Thickness of second layer, metres.
project: b; location: b1; case: b---01.txt
All entry data appear on screen. If
tangent of slope upstream
.05 m/m 1: 20.0
correct, ENTER 1, else 2 to restart the
downstream slope zero,
flat terrain
questions. If correct, the necessary
calculations are performed and the
no difference in surface level at x=0
permeability top layer
.30 m/d
results shown on screen, the main
permeability second layer
3.00 m/d
one being the width of the trench
thickness top layer
4.00 m
or ditch bottom needed to catch the
thickness second layer
4.00 m
intercepted flow. In contrast to the
depth to impermeable layer
8.00 m
homogeneous case, where a small
width is usually sufficient, a drain
depth of trench or ditch
2.00 m
drain above soil transition
2.00 m
in less permeable topsoil requires
radial resistance near drain
.78 d/m
a much wider trench. As this is
resulting head above drain
.50 m
often not feasible, several drains are
needed. Their mutual distance can be
incoming groundwater flow
.65 m2/d
estimated for the program ARTES
outgoing groundwater flow
.00 m2/d
intercepted by drain
.65 m2/d
for artesian conditions, their number
depth groundwater upstream
1.00 m
from the total flow to be eliminated.
FIGURE A23.14
35
Chinese
* Out of print
E
English
** In preparation
F
French
P
Portuguese
R
Russian
S
Spanish
The FAO Technical Papers are available through the
authorized FAO Sales Agents or directly from Sales and
Marketing Group, FAO, Viale delle Terme di Caracalla,
00153 Rome, Italy.
ISBN 978-92-5-105670-7
ISSN 0254-5284
789251 056707
TC/M/A0975E/1/02.07/1100