Implementation of Indoor Dry Type Distribution Transformer For Power Supply To Commercial Complexes, Apartments & Hospitals

1. Several suggestions are provided to improve the electrical network and operations in SKP, including developing indoor dry type distribution transformers to save space, designing on-load break switch fuse panels to replace ABS and DOF structures, improving overhead networks through legal agreements with telecom companies, implementing earth modules in MCCBs, using handy thermography for inspections, providing drain covers near electrical equipment, designing trolley-mounted transformers for emergency power supply, integrating SCADA systems for remote RMU operation, modifying networks to serve areas more efficiently, and installing fire alarm systems. The benefits would be increased coverage, reliability, safety, and customer satisfaction.

Uploaded by

Abhishek Ranjan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views6 pages

Implementation of Indoor Dry Type Distribution Transformer For Power Supply To Commercial Complexes, Apartments & Hospitals

1. Several suggestions are provided to improve the electrical network and operations in SKP, including developing indoor dry type distribution transformers to save space, designing on-load break switch fuse panels to replace ABS and DOF structures, improving overhead networks through legal agreements with telecom companies, implementing earth modules in MCCBs, using handy thermography for inspections, providing drain covers near electrical equipment, designing trolley-mounted transformers for emergency power supply, integrating SCADA systems for remote RMU operation, modifying networks to serve areas more efficiently, and installing fire alarm systems. The benefits would be increased coverage, reliability, safety, and customer satisfaction.

Uploaded by

Abhishek Ranjan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

1.

Subject *
Problem/Present Method *
Root Cause Analysis:
Implementation of Indoor dry type Presently in SKP we are using As per IE rule & safety regulation
Distribution Transformer for power oil filled Distribution
it is required to maintain six
supply to commercial complexes,
Transformer for power supply directional clearances for the
apartments & hospitals.

Suggestion for department*


Seraikela Operation

to LT industrial & Domestic


Consumers.

erection of the Distribution


Transformer. But in SKP due to
presence of JSEB overhead lines
& confined space, it is not always
possible to maintain a safer
distance from all the six
directions although we have
underground HT network. This
problem is very common in
Domestic areas where
commercial complexes,
apartments & hospitals are
present.
For this reason we cannot give
the power to these locations
which leads to less coverage of
network & therefore low
customer satisfaction.

Idea/Innovation/Suggested
Method *

Results/Benefits:

1)Increase in coverage of
To develop & designed indoor network & therefore low
type dry transformer.
customer satisfaction.
Following are the advantages
for the same:
1)Easy & smooth in operation.
2)No overhead lines required
3)Electrically safe being as
enclosed cubical system.
4)Elegant look
5)Lesser space is required.

2.
Subject *
Problem/Present Method *
Root Cause Analysis:
develop & designed ON LOAD BREAK Presently in SKP we are using ABS As per IE rule & safety regulation it
SWITCH FUSE panel for the replacement & DOF with overhead D.P. structure required to maintain six directional
of ABS & DOF DP structure.

is

Suggestion for department*


Seraikela Operation

to power supply to HT industrial &


Domestic Consumers. .

clearances for the erection of the ABS


& DOF structure. But in SKP due to
presence of JSEB overhead lines &
confined space, it is not always
possible to maintain a safer distance
from all the six directions although we
have underground HT network. This
problem is very common in Domestic
areas where commercial complexes,
apartments & hospitals are present.
For this reason we cannot give the
power to these locations which leads
to less coverage of network &
therefore low customer satisfaction.

Idea/Innovation/Suggested Method *

Results/Benefits:

To develop & designed ON LOAD


BREAK SWITCH FUSE panel for
the replacement of ABS & DOF DP
structure. Following are the
advantages for the same:
1)Easy & smooth in operation.
2)No overhead lines required
3)Electrically safe being as enclosed
cubical system.
4)Semiskilled person can operate
safely, as provision of safety
interlocks,
5)Elegant look
6)Lesser space is required.
7)Low maintenance cost

1)Reduction in property loss from


rodents. Safety of equipment
2)Increase in Customer Satisfaction,
Increase in Consumer coverage,
Reduction in breakdown

3.
Subject *
Problem/Present Method *
Root Cause Analysis:
Improvement of O/H network in Adityapur Presently in Adityapur area, most of 1)Lack of legal procedure &
area.
the telecom companies operating in Regulations

Aadityapur have created a messed up 2)No co-ordination between telecom


condition in Domestic network
agencies & JUSCO
(O/H) of JUSCO. They have erected
their FO network without any rule &
regulation in the existing PSC poles
of JUSCO. Also they have not
followed any Road Safety norms.
Resulting of the same had created
two numbers accident by heavy

vehicles in past. Fortunately any


casualty didnt happen but it
damaged physical assets of JUSCO.
Further which leads to breakdown
and therefore low customer
satisfaction.
Suggestion for department*
Seraikela Operation

Idea/Innovation/Suggested Method *

Results/Benefits:

To develop well designed & safe


network following needs to be done:
1)Process oriented stringing of FO
network by telecom agencies.
2)Legal approval from JUSCO if
they will utilize JUSCO assets
3) Monthly rental to be impose to
telecom companies for utilization of
JUSCO poles

1)Reduction in property loss of


JUSCO
2)Reduction in breakdown, Reduction
in O&M budget
3)Increase in Customer Satisfaction

4
Subject *
Problem/Present Method *
Implementation of earth module in MCCB Presently in SKP area there is
for secondary connection in Distribution
earth module in MCCB for
Transformer.

Root Cause Analysis:

Unavailability of earth module in


MCCB to sense the leakage current in
secondary connection in Distribution the distribution system.
Transformer. Due to this MCCB is
unable to trip during leakage
current .Which causes burning of
cables or tripping of HT breakers or
RMU.

Suggestion for department*


Seraikela Operation

no

Idea/Innovation/Suggested Method *

Results/Benefits:

Implementation of earth module in 1)Reduction in property loss of


MCCB for secondary connection in JUSCO
Distribution Transformer.
2)Reduction in breakdown,
3)Reduction in O&M budget,
4)Increase in Customer Satisfaction

5.
Subject *
Problem/Present Method *
Root Cause Analysis:
Implementation of Handy
Presently in SKP-DNM area Unavailability small &
thermography in Inspection plan of there is thermography plan for thermography system.
DNM

field equipment. Due to this


inspection job is done by
observation. Health checkup of
the equipment & network is
not done properly.

Suggestion for department*

Idea/Innovation/Suggested

Results/Benefits:

handy

Seraikela Operation

Method *

Implementation & purchase


handy thermography.

1)Reduction in property loss of


JUSCO
2)Reduction in breakdown,
3)Good inputs for Plan

6
Subject *
Problem/Present Method *
Root Cause Analysis:
Drain cover to be provided in AIADA area Presently in AIADA area, new drain Drain is in open condition i.e there
where the electrical equipment are
construction is going on & most of no cover provided for the same.
installed.

is

the field equipment is very nearer to


the drain. It is creating unsafe
condition during maintenance &
breakdown.

Suggestion for department*


Seraikela Operation

Idea/Innovation/Suggested Method *

Results/Benefits:

Drain cover must be provide near


our .

Avoiding accident during working

Subject *
Design & develop trolley mounted
transformer for emergency power supply
in localities of SKP.

Problem/Present Method *

Root Cause Analysis:

Suggestion for department*


Seraikela Operation

Idea/Innovation/Suggested Method *

Results/Benefits:

To design & develop a system in


which electrical equipment
transformer & RMU would be
mounted on the trolley, that will be
utilized during power failure where
the main source of cable or
transformer will fail.

1)Reduction in down time


2)Increase in Customer Satisfaction
3)Improvement in SAFI & SAIDI

7.

Presently in SKP there is no backup There is no readymade solution


arrangement during transformer
presently.
failure or HT cable failure. Therefore
it takes 6 to 8 hrs time for power
restoration. This creating
dissatisfaction in domestic
consumers.

8.
Subject *
Beautification by plantation of the
area outside the Phase#1 S/S

Problem/Present Method *

Suggestion for department*

Idea/Innovation/Suggested

Root Cause Analysis:

Area outside the phase#1 s/s is Area is not leveled & developed
not looking beautiful &
therefore not differentiating as
a JUSCO premise.
Results/Benefits:

Seraikela Operation

Method *

1)Develop the area with civil


work
2)Plantation of the trees &
flowers plant

1)Benefit to the environment


2) Office place looks beautiful
3)add value to the visitors

9.
Subject *
Problem/Present Method *
Design & Integration of SCADA system to 1)During the breakdown or
the distribution level (RMU integration)
overloading whenever RMU

Root Cause Analysis:

Suggestion for department*


Seraikela Operation

Idea/Innovation/Suggested Method *

Results/Benefits:

Implementation of SCADA through


modification in RMU &
Communication with GPRS
technology

1)Reduction in down time


2)Increase in Customer Satisfaction
3)Improvement in SAFI & SAIDI
4)Operation will be easier
5)Smart city

1)There is no system based


trips
communication from the field
the only way of communication to equipment & control room
the SKP control room is consumer 2) There is no option to operate RMU
complain method, which is a delayed from the Remote
process.
2) Shutdown of RMU is possible
only possible from the local.

10.
Subject *
Problem/Present Method *
Modification of Accropoly RMU Network At present 10 nos. consumers

Root Cause Analysis:

Suggestion for department*


Seraikela Operation

Idea/Innovation/Suggested Method *

Results/Benefits:

1)Install new RMU near accropoly


& distribute the network.

1. Lesser no. of consumers affected.


2) Improvement in SAIFI & SAIDI

are
Earlier there was single consumer. Bu
connected in the accropoly RMU
as the demands come no proper
with maximum cable length is
planning was done.
1000Mtrs. Following are the reasons
for modification:
1)During power shutdown/
breakdown it is affecting the all
consumers
2)It takes more time during schedule
maintenance therefore increase in
SAIDI.
3)Maximum route length of the
cable is 1000 mtrs with single per
leg.
4)Requirement of network to extend
in that area

3)Reduction in down time


4)Increase in Customer Satisfaction
11.
Subject *
Fire alarm system for Phase#1
Office

Problem/Present Method *

Root Cause Analysis:

Presently there is no
fire/smoke detection system
Phase#1 office

Not planned

Suggestion for department*


Seraikela Operation

Idea/Innovation/Suggested
Method *

Results/Benefits:

Implementation fire alarm


system
12.

1)Fire control
2)Avoiding accident

You might also like