Tank Data Sheet.

This document provides specifications for storage tank 120-T-01F which is being converted from crude oil storage to FCCU feed storage. It details the tank's nominal capacity, materials of construction, nozzle configurations, insulation requirements, and other process parameters. The document also includes 17 notes providing additional details and requirements for the tank conversion.

Uploaded by

Ranjan Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views4 pages

Tank Data Sheet.

This document provides specifications for storage tank 120-T-01F which is being converted from crude oil storage to FCCU feed storage. It details the tank's nominal capacity, materials of construction, nozzle configurations, insulation requirements, and other process parameters. The document also includes 17 notes providing additional details and requirements for the tank conversion.

Uploaded by

Ranjan Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Page 130 of 135

Document No.
A758-701-79-DS-1701
Rev. No. 0
Page 1 of 3

STORAGE TANK
PROCESS DATA SHEET
PROJECT
UNIT

Visakh Refinery Modernization Project


CLIENT HPCL VISAKH
INTERMEDIATE STORAGE TANKS AND TRANSFER FACILITIES
JOB NO. A758

120-T-01E (NOTE-13)
ITEM NO.
EXTERNAL FLOATING ROOF
TYPE
FLUID HANDLED
PROCESS DATA
NOMINAL CAPACITY
M3
LIQUID STORED
M3
STORAGE TEMPERATURE
DEG C
STORAGE PRESSURE
KG/CM2G
POSITIVE PRESSURE
VACUUM PRESSURE
MMWC
FLUID PROPERTIES @OPERATING P & T
LIQUID DENSITY
KG/M3
CP
VISCOSITY
FLASH POINT
DEG C
POUR POINT
DEG C
BLANKETING REQUIRED
IF YES, BLANKETING GAS
MECHANICAL DATA
DIAMETER
MM
HEIGHT
MM
DESIGN PRESSURE
KG/CM2G
POSITIVE PRESSURE
VACUUM PRESSURE
MMWC
DESIGN TEMPERATURE
DEG C
AMBIENT TEMPERATURE
DESIGN MINIMUM
YES DEG C
DESIGN MAXIMUM
NO
DEG C
COIL REQUIRED
IF YES, PURPOSE OF COIL
KG/CM2G
COIL DESIGN PRESSURE
COIL DESIGN TEMPERATURE
DEG C
COIL NOMINAL SIZE
INCH
COIL AREA
M2
FLUID CIRCULATED IN COIL
COIL MATERIAL OF CONSTRUCTION
INSULATION REQUIRED
IF YES, TYPE OF INSULATION
INSULATION THICKNESS
MM
BREATHER VALVE REQUIRED
WITH
VENT
FLAME
WITH/
ARRESTOR
WITHOUT FLAME ARRESTER
WITHOUT
SUCTION
FLAME
EXCHANGER
ARRESTOR
REQUIRED
GAUGING & SAMPLING HATCH
MIXER REQUIRED
IF YES, MIXER DATA SHEET NO.
CODE REQUIREMENT
MATERIAL OF CONSTRUCTION
SHELL BOTTOM COURSE
SHELL OTHER COURSE
BOTTOM
ROOF
ROOF WHERE VAPOR CAN ACCUMULATE
NO
INNER TANK
NO
OUTER TANK
SUSPENDED DECK
ANY OTHER
CATHODIC PROTECTION AT TANK BOTTOM
NOZZLES AND CONNECTIONS
MARK
NUMBER
SIZE (INCHES)
N1A
(NOTE-7,13)
N2A
(NOTE-13)
N3A/B
(NOTE-13)
N6A/B
(NOTE-13)
N8A/B/C/D
(NOTE-13)
N9A/B/C/D
(NOTE-13)
N7A/B/C
(NOTE-13)
N4A/B
(NOTE-7,13)
N5
(NOTE-13)
M1A/B
(NOTE-13)
N2B
(NOTE-7,13)

SERVICE
FCCU FEED

65000 (EXISTING)
60000 (EXISTING)
70-80
ATM
FULL OF LIQUID

890-930
13.3-23.2
>100
48
NO
AS EXISTING
AS EXISTING
FULL OF WATER
100
12.5
45
AS EXISTING
TO MAINTAIN TEMPERATURE
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING
YES
25 (NOTE-6)
NO
NO
AS EXISTING
AS EXISTING
A758-701-79-DS-1901
AS EXISTING
MATERIAL
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING

CORROSION ALLOWANCE, MM
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING

NO

AS EXISTING

PIPING SPEC. FOR NOZZLES


SERVICE
MARK
NUMBER
TANK INLET
R1A/B
TANK OUTLET
R2
DRAIN WITH SIPHON
R3
CLEAN OUT DOOR
R4
STEAM INLET
IH
STEAM OUTLET
L-1
PROPELLER MIXER NOZZLE
HLA
DRAIN WITHOUT SIPHON (NOTE-7)L-2
ROOF DRAIN (SHELL)
R6
MANWAY
N1B
TANK OUTLET
LSHH
1

0
A

15.01.2016
02.11.2015

ISSUED FOR ENGINEERING


ISSUED FOR COMMENTS

Rev. No.

Date

Purpose

Format No,3-0241-1052 Rev. 1

UNIT NO. 701

FCCU FEED (NOTE-1)

AS EXISTING
SIZE (INCHES)
(NOTE-13)
(NOTE-13)
(NOTE-13)
(NOTE-13)
(NOTE-13)
(NOTE-13,15)
(NOTE-13,15)
(NOTE-13,15)
(NOTE-13)
(NOTE-7,13)
BY ENGG

SERVICE
ROOF MANWAY
GUAGE HATCH
VENT FOR SEALING DEVICE
BLEEDDER VENT
INSPECTION HATCH
LEVEL INDIACATOR
HIGH LEVEL ALARM
LEVEL TRANSMITTER
ROOF DRAIN (ROOF)
SLOP INLET
LEVEL SWITCH HH (NOTE-14)

KW
KW

AS
AS

DCA
DCA

Prepared Reviewed Approved


By
By
By
Copyrights EIL - all rights reserved (Generated through PDSIS)

Page 131 of 135

STORAGE TANK
PROCESS DATA SHEET
PROJECT
UNIT

CLIENT HPCL VISAKH


Visakh Refinery Modernization Project
JOB NO. A758
INTERMEDIATE STORAGE TANKS AND TRANSFER FACILITIES

Document No.
A758-701-79-DS-1701
Rev. No. 0
2 of 3
Page
UNIT NO.

701

120-T-01E
ITEM NO.
SERVICE FCCU FEED (NOTE-1)
NOTES:
1.EXISTING TANK SERVICE OF 120-T-01E IS CRUDE. TANK SERVICE SHALL BE CHANGED TO FCCU FEED POST VRMP.
NOZZLE MARK IS BASED ON 120-T-01E DRAWING (VR-120-T-01A-F-0144) & P&ID (120-CRUDE-01) PROVIDED BY HPCL
2.DELETED
3 TANK SHALL BE PROVIDED WITH SUITABLE SCRAPER. ENGG TO DECIDE SCRAPER TYPE.
4.TANK PUMPING IN AND PUMPING OUT RATE WILL BE 360 M3/HR AND 380 M3/HR RESPECTIVELY.
5.TANK EXISTING FIRE FIGHTING FACILITIES ADEQUACY TO BE CHECKED FOR REVISED SERVICE
6.AT PRESENT TANK IS WITHOUT INSULATION. SO INSULATION SHALL BE PROVIDED FOR THE REVISED SERVICE.
7. NOZZLE TO BE BLANKED OFF POST VRMP.
8. DELETED
9.THE EXISTING NOZZLES/CONNECTIONS SHALL BE RETAINED POST VRMP EXCEPT AS MENTIONED IN NOTE-7.
10. EXISTING TANK HAS SEPARATE NOZZLES FOR INLET/OUTLET. POST VRMP ONLY SINGLE NOZZLE IS CONSIDERED FOR INLET/
OUTLET.
11. RIM SEAL ADEQUACY TO BE CHECKED FOR DESIGN TEMPERATURE.
12. DESIGN TEMPERATURE OF EXISTING CRUDE TANK 120-T01E IS 80 DEG C. WITH CHANGE IN SERVICE NEW DESIGN PRESSURE
SHALL BE 100 DEG C. ENGG TO CHECK ADEQUACY OF EXISTING INSTRUMENTS.
13 EXISTING NOZZLE. FOR DETAILS PLEASE REFER EXISTING DRAWING VR-120-T-01A-F-0144
14 NEW REQUIREMENT
15 TWO RADAR (ONE FOR HIGH & LOW ALARM AND OTHER FOR HIGH HIGH, LOW LOW) LEVEL TRANSMITTER REQUIRED FOR
NEW SERVICE ENGINEERING TO CHECK, IF EXISTING NOZZLE/INSTRUMENT CAN BE UTILIZED.
16. MULTIPOINT TEMPERATURE ELEMENT (2"-HOLD, ENGG TO CHECK) IS REQUIRED ON TANK ROOF FOR NEW SERVICE. AS PER
GA DRAWING TEMPERATURE INSTRUMENT NOT SHOWN. BUT AS PER P&ID TG SHOWN ON ROOF. ENGG TO CHECK IF EXISTING
NOZZLE CAN BE UTILIZED
17 AS PER GA DRAWING PRESSURE INSTRUMENT CONNECTIONS NOT SHOWN ON TANK SHELL WHEREAS IN P&ID (120-CRUDE-01)
PRESSURE INSTRUEMNTS ARE FURNISHED. HPCL TO CONFRIM

0
A

15.01.2016
02.11.2015

ISSUED FOR ENGINEERING


ISSUED FOR COMMENTS

KW
KW

AS
AS

DCA
DCA

Rev. No.

Date

Purpose

Prepared
By

Reviewed
By

Approved
By

Format No,3-0241-1052 Rev. 1

Copyrights EIL - all rights reserved (Generated through PDSIS)

Page 133 of 135

Document No.
A758-701-79-DS-1702
Rev. No. 0
Page 1 of 3

STORAGE TANK
PROCESS DATA SHEET
PROJECT
UNIT

Visakh Refinery Modernization Project


CLIENT HPCL VISAKH
INTERMEDIATE STORAGE TANKS AND TRANSFER FACILITIES
JOB NO. A758

120-T-01F (NOTE-13)
ITEM NO.
EXTERNAL FLOATING ROOF
TYPE
FLUID HANDLED
PROCESS DATA
NOMINAL CAPACITY
M3
LIQUID STORED
M3
STORAGE TEMPERATURE
DEG C
STORAGE PRESSURE
KG/CM2G
POSITIVE PRESSURE
VACUUM PRESSURE
MMWC
FLUID PROPERTIES @OPERATING P & T
LIQUID DENSITY
KG/M3
CP
VISCOSITY
FLASH POINT
DEG C
POUR POINT
DEG C
BLANKETING REQUIRED
IF YES, BLANKETING GAS
MECHANICAL DATA
DIAMETER
MM
HEIGHT
MM
DESIGN PRESSURE
KG/CM2G
POSITIVE PRESSURE
VACUUM PRESSURE
MMWC
DESIGN TEMPERATURE
DEG C
AMBIENT TEMPERATURE
DESIGN MINIMUM
YES DEG C
DESIGN MAXIMUM
NO
DEG C
COIL REQUIRED
IF YES, PURPOSE OF COIL
KG/CM2G
COIL DESIGN PRESSURE
COIL DESIGN TEMPERATURE
DEG C
COIL NOMINAL SIZE
INCH
COIL AREA
M2
FLUID CIRCULATED IN COIL
COIL MATERIAL OF CONSTRUCTION
INSULATION REQUIRED
IF YES, TYPE OF INSULATION
INSULATION THICKNESS
MM
BREATHER VALVE REQUIRED
WITH
VENT
FLAME
WITH/
ARRESTOR
WITHOUT FLAME ARRESTER
WITHOUT
SUCTION
FLAME
EXCHANGER
ARRESTOR
REQUIRED
GAUGING & SAMPLING HATCH
MIXER REQUIRED
IF YES, MIXER DATA SHEET NO.
CODE REQUIREMENT
MATERIAL OF CONSTRUCTION
SHELL BOTTOM COURSE
SHELL OTHER COURSE
BOTTOM
ROOF
ROOF WHERE VAPOR CAN ACCUMULATE
NO
INNER TANK
NO
OUTER TANK
SUSPENDED DECK
ANY OTHER
CATHODIC PROTECTION AT TANK BOTTOM
NOZZLES AND CONNECTIONS
MARK
NUMBER
SIZE (INCHES)
N1A
(NOTE-7,13)
N2A
(NOTE-13)
N3A/B
(NOTE-13)
N6A/B
(NOTE-13)
N8A/B/C/D
(NOTE-13)
N9A/B/C/D
(NOTE-13)
N7A/B/C
(NOTE-13)
N4A/B
(NOTE-7,13)
N5
(NOTE-13)
M1A/B
(NOTE-13)
N2B
(NOTE-7,13)

SERVICE
FCCU FEED

65000 (EXISTING)
60000 (EXISTING)
70-80
ATM
FULL OF LIQUID

890-930
13.3-23.2
>100
48
NO
AS EXISTING
AS EXISTING
FULL OF WATER
100
12.5
45
AS EXISTING
TO MAINTAIN TEMPERATURE
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING
YES
25 (NOTE-6)
NO
NO
AS EXISTING
AS EXISTING
A758-701-79-DS-1902
AS EXISTING
MATERIAL
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING

CORROSION ALLOWANCE, MM
AS EXISTING
AS EXISTING
AS EXISTING
AS EXISTING

NO

AS EXISTING

PIPING SPEC. FOR NOZZLES


SERVICE
MARK
NUMBER
TANK INLET
R1A/B
TANK OUTLET
R2
DRAIN WITH SIPHON
R3
CLEAN OUT DOOR
R4
STEAM INLET
IH
STEAM OUTLET
L-1
PROPELLER MIXER NOZZLE
HLA
DRAIN WITHOUT SIPHON (NOTE-7)L-2
ROOF DRAIN (SHELL)
R6
MANWAY
N1B
TANK OUTLET
LSHH
1

0
A

15.01.2016
02.11.2015

ISSUED FOR ENGINEERING


ISSUED FOR COMMENTS

Rev. No.

Date

Purpose

Format No,3-0241-1052 Rev. 1

UNIT NO. 701

FCCU FEED (NOTE-1)

AS EXISTING
SIZE (INCHES)
(NOTE-13)
(NOTE-13)
(NOTE-13)
(NOTE-13)
(NOTE-13)
(NOTE-13,15)
(NOTE-13,15)
(NOTE-13,15)
(NOTE-13)
(NOTE-7,13)
BY ENGG

SERVICE
ROOF MANWAY
GUAGE HATCH
VENT FOR SEALING DEVICE
BLEEDDER VENT
INSPECTION HATCH
LEVEL INDIACATOR
HIGH LEVEL ALARM
LEVEL TRANSMITTER
ROOF DRAIN (ROOF)
SLOP INLET
LEVEL SWITCH HH (NOTE-14)

KW
KW

AS
AS

DCA
DCA

Prepared Reviewed Approved


By
By
By
Copyrights EIL - all rights reserved (Generated through PDSIS)

Page 134 of 135

STORAGE TANK
PROCESS DATA SHEET
PROJECT
UNIT

CLIENT HPCL VISAKH


Visakh Refinery Modernization Project
JOB NO. A758
INTERMEDIATE STORAGE TANKS AND TRANSFER FACILITIES

Document No.
A758-701-79-DS-1702
Rev. No. 0
2 of 3
Page
UNIT NO.

701

120-T-01F
ITEM NO.
SERVICE FCCU FEED (NOTE-1)
NOTES:
1.EXISTING TANK SERVICE OF 120-T-01F IS CRUDE. TANK SERVICE SHALL BE CHANGED TO FCCU FEED POST VRMP.
NOZZLE MARK IS BASED ON 120-T-01F DRAWING (VR-120-T-01A-F-0144) & P&ID (120-CRUDE-01) PROVIDED BY HPCL
2.DELETED
3 TANK SHALL BE PROVIDED WITH SUITABLE SCRAPER. ENGG TO DECIDE SCRAPER TYPE.
4.TANK PUMPING IN AND PUMPING OUT RATE WILL BE 360 M3/HR AND 380 M3/HR RESPECTIVELY.
5.TANK EXISTING FIRE FIGHTING FACILITIES ADEQUACY TO BE CHECKED FOR REVISED SERVICE
6.AT PRESENT TANK IS WITHOUT INSULATION. SO INSULATION SHALL BE PROVIDED FOR THE REVISED SERVICE.
7. NOZZLE TO BE BLANKED OFF POST VRMP.
8. DELETED
9.THE EXISTING NOZZLES/CONNECTIONS SHALL BE RETAINED POST VRMP EXCEPT AS MENTIONED IN NOTE-7.
10. EXISTING TANK HAS SEPARATE NOZZLES FOR INLET/OUTLET. POST VRMP ONLY SINGLE NOZZLE IS CONSIDERED FOR INLET/
OUTLET.
11. RIM SEAL ADEQUACY TO BE CHECKED FOR DESIGN TEMPERATURE.
12. DESIGN TEMPERATURE OF EXISTING CRUDE TANK 120-T01E IS 80 DEG C. WITH CHANGE IN SERVICE NEW DESIGN PRESSURE
SHALL BE 100 DEG C. ENGG TO CHECK ADEQUACY OF EXISTING INSTRUMENTS.
13 EXISTING NOZZLE. FOR DETAILS PLEASE REFER EXISTING DRAWING VR-120-T-01A-F-0144
14 NEW REQUIREMENT
15 TWO RADAR (ONE FOR HIGH & LOW ALARM AND OTHER FOR HIGH HIGH, LOW LOW) LEVEL TRANSMITTER REQUIRED FOR
NEW SERVICE ENGINEERING TO CHECK, IF EXISTING NOZZLE/INSTRUMENT CAN BE UTILIZED.
16. MULTIPOINT TEMPERATURE ELEMENT (2"-HOLD, ENGG TO CHECK) IS REQUIRED ON TANK ROOF FOR NEW SERVICE. AS PER
GA DRAWING TEMPERATURE INSTRUMENT NOT SHOWN. BUT AS PER P&ID TG SHOWN ON ROOF. ENGG TO CHECK IF EXISTING
NOZZLE CAN BE UTILIZED
17 AS PER GA DRAWING PRESSURE INSTRUMENT CONNECTIONS NOT SHOWN ON TANK SHELL WHEREAS IN P&ID (120-CRUDE-01)
PRESSURE INSTRUEMNTS ARE FURNISHED. HPCL TO CONFRIM

0
A

15.01.2016
02.11.2015

ISSUED FOR ENGINEERING


ISSUED FOR COMMENTS

KW
KW

AS
AS

DCA
DCA

Rev. No.

Date

Purpose

Prepared
By

Reviewed
By

Approved
By

Format No,3-0241-1052 Rev. 1

Copyrights EIL - all rights reserved (Generated through PDSIS)

You might also like