Sediment Considerations For Potential Dam Removal Projects PDF
Sediment Considerations For Potential Dam Removal Projects PDF
SRH-2009-39
October 2009
Mission Statements
The mission of the Department of the Interior is to protect and
provide access to our Nations natural and cultural heritage and
honor our trust responsibilities to Indian Tribes and our
commitments to island communities.
Cover Figure: Looking upstream at Elwha Dam located on the Elwha River in Washington
State, USA (photo taken in June, 2009)
Peer Review Certification: This document has been peer reviewed per guidelines established by the Technical
Service Center and is believed to be in accordance with the service agreement and standards of the profession.
Questions concerning this report should be addressed to Timothy Randle, Group Manager of the Sedimentation
and River Hydraulics Group (86-68240) at 303-445-2557.
PREPARED BY:
_____________________________________
Jennifer Bountry, M.S., P.E.
Hydraulic Engineer
Sedimentation and River Hydraulics Group (86-68240)
DATE:________________
_____________________________________
Blair Greimann, Ph.D., P.E.
Hydraulic Engineer
Sedimentation and River Hydraulics Group (86-68240)
DATE:________________
_____________________________________
Timothy Randle, M.S., P.E.
Hydraulic Engineer
Sedimentation and River Hydraulics Group (86-68240)
DATE:________________
Table of Contents
Page
1.0
Introduction ....................................................................................................... 1
2.0
Deciding on Dam Removal ............................................................................... 2
2.1
Available Guidance........................................................................................... 2
2.2
Dam Removal Options...................................................................................... 3
3.0
Sediment Management Plan ............................................................................. 4
3.1
Potential Sediment Impacts............................................................................... 4
3.2
Consideration of Contaminants......................................................................... 5
3.3
Scale of the Erodible Reservoir Sediment Volumes ......................................... 6
3.3.1
Coarse Sediment ......................................................................................... 7
3.3.2
Fine Sediment ............................................................................................. 8
3.4
Determining What Portion of Reservoir Sediment is Erodible ........................ 9
4.0
Data Collection and Analysis.......................................................................... 10
4.1
Reconnaissance ............................................................................................... 10
4.2
Reservoir Sediment Characteristics ................................................................ 11
4.3
Selecting Analysis Techniques ....................................................................... 12
5.0
References ....................................................................................................... 12
Appendix A: Elwha and Glines Canyon Dams................................................................. 14
Introduction ................................................................................................................... 14
Reservoir Sedimentation ............................................................................................... 15
Elwha River Restoration Plan ....................................................................................... 18
Reservoir Sediment Erosion ......................................................................................... 18
Downstream Sediment Transport and Geomorphic Effects ......................................... 20
Adaptive Management .................................................................................................. 21
Study References .......................................................................................................... 22
Appendix B: Matilija Dam................................................................................................ 23
Introduction ................................................................................................................... 23
Hydrology ..................................................................................................................... 23
River Characteristics ..................................................................................................... 23
Reservoir Sedimentation ............................................................................................... 24
Sediment Impact Concerns ........................................................................................... 24
Dam Removal Plans...................................................................................................... 24
Study References .......................................................................................................... 32
Appendix C: Savage Rapids Dam..................................................................................... 33
History........................................................................................................................... 33
Setting ........................................................................................................................... 35
Reason for Removal ...................................................................................................... 37
Project Challenges ........................................................................................................ 37
Reservoir Sediment Characteristics .............................................................................. 37
Pre-Removal Evaluation ............................................................................................... 39
Dam Removal Plan ....................................................................................................... 42
Monitoring Accomplished ............................................................................................ 43
Lessons Learned............................................................................................................ 43
Study References .......................................................................................................... 44
i
ii
Index of Figures
Page
Figure 1. The Elwha River is located within the United States of America. .................... 14
Figure 2. Elwha and Glines Canyon Dams are located on the Elwha River near Port
Angeles, Washington, U.S.A.. .......................................................................................... 15
Figure 3. Photograph looking downstream at Lake Mills, behind Glines Canyon Dam,
and the reservoir delta composed of sand, gravel, and large woody debris...................... 17
Figure 4. Photograph looking downstream at Lake Aldwell, behind Elwha Dam, and the
reservoir delta composed of sand, gravel, and large woody debris. ................................. 17
Figure 5. Photographs of Lake Mills during the 1994 drawdown experiment: Eroded
delta sediments re-deposited across the width of the receded reservoir (a) and sediment
terraces were deposited along the margins of the reservoir (b). ....................................... 19
Figure 6. Physical Model Experiments of Lake Mills sediment erosion by Chris Bromley
without a pilot channel (a) and with a pilot channel (b). .................................................. 21
Figure 7. Overview of Ventura Watershed. ...................................................................... 26
Figure 8. Peak Discharge at USGS gage 11115500, downstream of Matilija Dam on
Matilija Creek. Flows between Oct 1 1988 and Sept 30 1990 were not available at this
gage. .................................................................................................................................. 27
Figure 9. Comparison of 15-minute instantaneous hydrographs and daily average
hydrographs for the 1992 flood at Foster Park gage on the Ventura River (USGS gage
11118500). ........................................................................................................................ 28
Figure 10. Annual flow volume at USGS gage 11115500, downstream of Matilija Dam
on Matilija Creek. ............................................................................................................. 28
Figure 11. Overview of site. ............................................................................................. 29
Figure 12. River profile downstream of Matilija Dam. Matilija Dam is at RM 16.3. ...... 30
Figure 13. Surface bed material in Ventura River. ........................................................... 31
Figure 14. Picture of sediment trapped behind Matilija Dam while the reservoir was
drawn down. Picture was taken in July 2003 by Paul Jenkin of the Surfrider Foundation.
........................................................................................................................................... 31
Figure 15. View of Savage Rapids Dam, located on the Rogue River in southwestern
Oregon, U.S.A. on February 23, 1999 when the mean-daily flow was 7400 ft3/s (210
cms). .................................................................................................................................. 33
Figure 16. Illustration of pre-dam and existing reservoir bottom and elevation influence
of stop logs. ....................................................................................................................... 34
Figure 17. Looking upstream at Savage Rapids reservoir in upstream areas during
riverine conditions in the non-irrigation season................................................................ 35
Figure 18. Upstream face of Savage Rapids Dam - During a reservoir drawdown in May
1999, gravel-sized sediment was observed on the crest of the dam, indicating that
sediment is transported past the dam during spillway releases......................................... 39
Figure 19. View downstream showing Reclamations custom built, floating drilling
platform in operation on drill hole AP-99-10. The spillway and pumping plant portions of
Savage Rapids Dam are present in the background of this photograph. (Reclamation
photograph by Richard Link; September 30, 1999.)......................................................... 40
Figure 20. View of survey boat configuration equipped with global positioning software
(GPS) equipment, depth sounder, and laptop to document channel bathymetry. ............. 41
iii
iv
Index of Tables
Page
Table 1. Reservoir Sedimentation Volumes and Size ....................................................... 16
Table 2. Reservoir Sediment Erosion Summary ............................................................... 20
Table 3. Flow rate at various return periods on Matilija Creek and Ventura River. ........ 27
Table 4. Gradations and Sediment Volume Determined from Drill Data. ....................... 32
1.0 Introduction
The purpose of this report is to provide planning level guidance to determine the types
and level of sediment data collection and analysis needed for potential dam removal
projects. This report documents work accomplished in 2009 by Reclamation under the
Appendix 8 agreement for Task 5, dam removal consultation. The agreement is part of
the technical assistance and cooperation for water resources program between the
American Institute in Taiwan (AIT) and the Taipei Economic and Cultural
Representative Office (TECRO).
Case studies on sediment analysis are also provided where Reclamations Sedimentation
and River Hydraulics Group at the Technical Service Center was significantly involved in
the sediment impact analyses of dam removal. The following case studies are presented:
In these case studies, the Bureau of Reclamation was not the owner or manager of the
dam, but was hired to provide technical assistance because of our extensive experience
dealing with reservoir and river sedimentation issues. In the cases discussed in this
report, dam removal was selected as the management alternative for river ecological
restoration purposes for the following reasons:
2.1
Available Guidance
The decision to remove a dam is an iterative process that involves establishing and
evaluating alternatives in a collaborative framework with several entities. The H. John
Heinz III Center for Science, Economics, and the Environment has produced some
guidelines to help in the decision making process of whether to remove a dam. This
information can be found at www.heinzctr.org. The Aspen Institute has also published a
document that provides guidance on dam removal which can be found at
http://www.aspeninstitute.org/publications/dam-removal-new-option-new-century-2002.
The United States Society of Dams is in the process of developing guidelines to help with
determination of construction and engineering considerations for dam removal. The
document is expected to be completed in 2010 and more information can be found at
http://www.ussdams.org/c_decom.html. Another reference that has been produced is by
the American Society of Civil Engineers and can be found at
http://cedb.asce.org/cgi/WWWdisplay.cgi?9705367.
In addition, the U.S. Subcommittee on Sedimentation is in the process of developing dam
removal sediment analysis guidelines, which are expected to be published in 2010 or
2011.
2.2
When a decision has been made to decommission a dam, structural alternatives range
from leaving the dam in place, partial dam removal, complete dam removal, or staged
breaching (Morris and Fan, 1997). Partial dam removal could mean leaving a lower
portion of the dam in place to retain coarse sediments or leaving portions of the dam near
the abutments to retain sediments along the reservoir margins. The selection of which
dam removal option is appropriate is usually an iterative process that is not determined
until project objectives are defined and alternatives are evaluated, including cost and
impacts to people and the environment.
Another important consideration is the timing of dam removal construction that is usually
coordinated between sediment management planning and logistical and safety needs
associated with construction activities. The rate and magnitude of sediment erosion is
closely tied to the rate of reservoir drawdown and the stream discharge available to erode
and transport the reservoir sediment. Many dam are removed during low-flow periods,
which may have limited erosion immediately following dam removal, but increased
sediment erosion and transport during subsequent floods. However, in some cases dam
removal is specifically timed to coincide with a high streamflow discharge to maximize
the river erosion potential of reservoir sediment and transport the reservoir sediment
through the downstream channel over in a shorter timeframe. Downstream impacts may
be reduced by removing the dam when there is less risk to water supply and aquatic
organisms and their habitat. In systems with multiple reservoirs, it may be possible to
coordinate sediment flushing with flow release and sediment sluicing operations of
upstream or downstream reservoirs to maximize or limit potential sediment transport and
deposition.
The potential for erosion resistant materials within the reservoir should also be
considered when selecting a dam removal alternative. Either native or man-made erosion
resistant materials could create fish or boat passage problems after dam removal and
prevent the erosion of reservoir sediments. For example, investigations may discover that
remnants of an older dam or other infrastructure exist in the reservoir impoundment. If
field investigations and reconnaissance results indicate a potential for erosion resistant
materials, it may be useful to evaluate whether this material is likely to erode through
natural river processes. If it is not expected to be eroded, decision makers can consider
whether it is desirable to mechanically remove the obstructions as part of the dam
removal plan.
A sediment management plan can also consist of a combination of these categories. For
example, fine sediments could be mechanically removed from the downstream portion of
the reservoir to reduce the impacts on water quality. At the same time, the river could be
allowed to erode coarse sediments from the reservoir delta to resupply gravel for fish
spawning in the downstream river channel. A good reference that provides more
information on sediment excavation and dredging methods is Chapter 16 of the Reservoir
Sedimentation Handbook (Morris and Fan 1997).
The higher the risk and the more uncertainty associated with sediment impacts, the
greater the need for an adaptive management plan that includes monitoring of predicted
outcomes. The adaptive management plan should clearly specify initial predictions on
sediment processes including rate, duration, and volume of reservoir erosion, sediment
transport deposition locations of downstream river changes, and other key areas of
concern. Potential monitoring ideas are included in several of the case studies listed at
the end of this report.
3.1
The potential impacts from the erosion and subsequent downstream transport and
deposition of reservoir sediment should be considered in all dam removal studies. In
many cases, there are benefits from the release of reservoir sediment such as the
introduction of gravel, woody debris, and nutrients for the restoration of downstream
channel morphology (degradation) and aquatic habitats. Alternatively, short-term acute
or long-term chronic impacts could result depending on the volume, extent, and particle
grain size of reservoir sediment erosion and the duration and timing of the erosion.
Specifically for river systems with high upstream sediment loads, example consequences
of dam removal might include increased sedimentation in downstream reservoir(s)
causing a reduction in reservoir life or functionality. In this scenario, it may be desirable
to consider reservoir sediment excavation or stabilization prior to dam removal.
3.2
Consideration of Contaminants
Were there any historical land use activities (e.g. industrial, urban, and
agricultural, etc), in the watershed upstream from the dam, that would have
potentially contributed to contaminants within the reservoir?
What are the most likely contaminants that might be discovered?
When did reservoir sedimentation occur?
Have reservoir sediments been periodically flushed from the reservoir?
Is there a present upstream source of contaminants?
Is there a substantial (greater than 10%) volume of silt and clay-sized reservoir
sediments that would increase the potential for presence of contaminants?
3.3
If the reservoir sediment mass that could be eroded following dam removal is large
relative to the downstream sediment transport capacity, then alternative dam removal and
sediment management strategies should include staged dam removal, partial dam
removal, partial sediment stabilization or excavation. Items that may be useful to
consider when determining the scale of the reservoir sediment volume include the
following concepts (Reclamation, 2008):
The reservoir sediment trap efficiency, which may be estimated from the original
reservoir storage capacity (at the normal pool elevation) relative to the mean
annual volume of river flow. The smaller the ratio, the smaller the reservoir
sediment trap efficiency and the volume of reservoir sediment.
The reservoir sediment mass relative to the mean annual sediment transport
capacity of the river or the capacity during a flow or flood hydrograph likely to
occur during or following dam removal. This can be accomplished for each of the
particle size gradations of the reservoir sediment or for the typical reservoir
sediment size if the reservoir sediment is fairly uniform.
One potential method for scaling the reservoir sediment is being developed by the U.S.
Subcommittee on Sediment, which has been convening workshops of individuals with
technical background and experience in sediment processes associated with dam removal
in the United States. This information is planned to be published in 2010 in a guidelines
to assist with determining the level of sediment data collection and analysis needed based
6
Median discharge at time of dam removal (upper limit for negligible mass),
2-year flood hydrograph (upper limit for small mass),
10-year flood hydrograph (upper limit for medium mass), and
50-year flood hydrograph (upper limit for large mass and lower limit for very
large mass).
The sediment transport capacity does not have to be computed for all of the above
discharge frequencies, only the frequencies that bracket the coarse reservoir sediment
mass. The first step is to estimate (using best judgment) the significance of the coarse
reservoir sediment mass: Negligible, small, medium, large, or very large.
For coarse sediment (sand and larger), scale the reservoir sediment mass by comparing
the reservoir sedimentation mass of sand and gravel to the downstream sediment
transport capacity 1 :
Reservoir sediment mass is less than the transport capacity of the median
discharge during the estimated month or season of dam removal [Negligible
coarse sediment mass]
Reservoir sediment mass is greater than the transport capacity of the median
discharge, during the estimated month or season of dam removal, but less than the
sediment transport capacity of the 2-year flood hydrograph [Small coarse
sediment mass]; if no dam removal timing has been determined, consider a range
of months in the computation
Reservoir sediment mass is between the transport capacity of the 2-year and 10year flood hydrographs [Medium coarse sediment mass]
Reservoir sediment mass is greater than the transport capacity of the 10-year flood
hydrograph [Large coarse sediment mass]
Reservoir sediment mass is greater than the transport capacity of the 50-year flood
hydrograph [Very large coarse sediment mass]
Compute the ratio of the original reservoir storage capacity to the mean annual
inflow.
o Ratio is less than or equal to 0.001 (or 0.1%) and the percent of silt and
clay in the total reservoir volume is less than 5 % [Negligible fine
sediment mass]
Compute the average annual fine sediment load (see analysis steps below)
o Average annual fine sediment load less than or equal to 1 year [Small fine
sediment mass]
o Average annual fine sediment load between 1 and 5 years [Medium fine
sediment mass]
o Average annual fine sediment load greater than 5 years [Large fine
sediment mass]
Analysis tips:
Determine the trap efficiency of the reservoir using the Brune trap efficiency
curve (see Morris and Fan, 2001)
Compute the total fine sediment load (Qs) over the period of reservoir
sedimentation by dividing the fine reservoir sediment volume(Vfine) by the trap
efficiency of the reservoir
Determine the total years to fill (T) based on the number of years where sediment
trapping occurred (e.g. no flushing, excavation, or other removal); include all
years regardless of flow magnitude (e.g. dry and wet years);
o If not sure and the reservoir is still filling with sediment, estimate the total
years of sediment as the age of the reservoir
o If not sure and the reservoir filled long ago, estimate the total years of
sediment conservatively as 1 year
Compute the average annual fine sediment load (Qs avg) by dividing the total
sediment load (Qs) by the total years to fill (T)
4.1
Reconnaissance
The following reconnaissance questions should be answered to help guide the initial data
collection for a dam removal study. These questions can be initially answered using
relatively low-cost methods including literature review, interviews with dam operators
and local residents, field visit and observations, and gathering of easy to obtain data
available from public sources.
Dam history and watershed context questions:
When was the reservoir constructed and by who?
Who is the present owner of the dam?
What were the original and present purposes of the dam and reservoir?
What is the hydraulic height and crest length of the dam?
Has the dam been raised or lowered?
Where is reservoir located within the watershed?
What are the upstream and downstream channel slopes?
What is the controlling geology at the dam site?
What is the hydrologic regime, particularly when do floods occur?
Are there any upstream or downstream storage reservoirs?
What and where are the major coarse and fine sediment sources and sinks in the
watershed where the dam is located? (e.g. tributaries, debris flows, landslides, etc)
Where are the significant tributaries that affect the downstream reach?
What is the bed material size of the upstream and downstream channels (e.g.,
clay, silt, sand, gravel, cobble, D50, D90)
Local impact concern questions:
Why is the dam being considered for removal?
Who are the local stakeholders?
What are the key impact concerns?
o Flooding?
o Water quality?
o Infrastructure (e.g. water diversion)?
o Water supply?
o Aquatic habitat?
o Fish passage?
o Recreation?
o Cultural resources?
o Downstream estuary or reservoir sedimentation?
10
4.2
Determining the reservoir sediment volume, size gradation, and spatial distribution is a
critical step in assessing the potential impacts from release of reservoir sediment during
dam removal. Errors in these estimates can result in drastic under or over estimations of
impacts that can potentially negatively alter dam removal planning and decision making.
Answers to the following questions are useful to estimate the reservoir sediment volume.
Data collection methods to determine the reservoir sediment volume and mass may
include dive inspections, drill holes and sediment cores, estimation of the pre-dam
thalweg profile (based on upstream and downstream thalweg profiles), and comparison of
bathymetric contour maps of present and pre-dam conditions. The level of investigation
should be greater for larger reservoirs than smaller reservoirs. Sediment samples should
be taken from representative locations within the reservoir to measure the various types
of sediment deposits (tributary deltas, lakebed, and margin deposits).
Reservoir sediment volume questions:
What is the ratio of the original maximum reservoir depth to maximum natural
river pool depth?
What are the normal operations of the reservoir pool?
o Run of the river for river diversion or hydropower
o Moderate to considerable drawdown and refilling for water supply
o Normally empty for flood control
Is sediment periodically sluiced from the dam?
Is there periodic flushing of reservoir sediment due to floods or reservoir
drawdown operations?
What is the ratio of the original reservoir storage volume (at the normal pool
elevation) to the mean annual river flow?
What is the reservoir sediment trap efficiency for fine sediment?
What was the pre-dam river and floodplain morphology and how would it be
expected to influence the magnitude and locations of reservoir sediment
deposition? (e.g. is it a riffle-pool morphology, braided, meandering, etc)
What is the volume of the reservoir sediment?
What is the ratio of reservoir sediment volume to the original reservoir storage
capacity?
If the reservoir is already filled with sediment, over what period of time did the
filling take place?
11
4.3
What portion of the reservoir sediment is expected to be eroded past the dam
within a few weeks after dam removal, a few months after dam removal, one year
after dam removal, and several years to decades after dam removal?
How quickly will the sediment erode past the dam?
What will be the fate of the eroded reservoir sediments after they enter the
downstream river channel?
The level of analysis completed is dependent on the scale of reservoir sediment volume
and the potential consequences associated with release of reservoir sediment. Analysis
techniques should at a minimum include a conceptual model of how the reservoir
sediment will be eroded. One such conceptual model is available from Doyle et al
(2003). Special consideration in the conceptual model is necessary when there is a
substantial portion of cohesive sediment or potential for vegetation recruitment in the
reservoir that may slow or stop the erosion process following dam removal.
As the scale of the reservoir sediment and potential risk of consequences increases,
analysis techniques may be expanded to include analytical tools, physical models, and
numerical modeling techniques. Several tools are available and sample techniques are
provided in a recently published Erosion and Sedimentation Manual (Reclamation 2006).
5.0 References
American Society of Civil Engineers (1997). Guidelines for Retirement of Dams and
Hydroelectric Facilities, New York, 222 p.
Aspen Institute (2002). Dam Removal, A New Option for a New Century, Aspen Institute
Program on Energy, the Environment, and the Economy, Queenstown, Maryland, 66 p.
12
13
Introduction
The U.S. Department of the Interior has purchased, and plans to remove, two large
hydroelectric dams on the Elwha River, near Port Angeles, Washington, U.S.A. (Figure
1) to restore the ecosystem and native anadromous fisheries (U.S. Department of the
Interior, National Park Service, 1996, 2004, and 2005). Elwha Dam is a 32-m high
concrete gravity dam that was constructed 7.9 km upstream from the river mouth in 1913
(U.S. Department of the Interior, National Park Service, 1996). Glines Canyon Dam is a
64-m high concrete arch dam that was constructed 21.7 km upstream from the river
mouth in 1927 (Figure 2). Neither dam has provisions for fish passage and there have
been significant impacts to native Chinook salmon (spring and summer/fall), steelhead
(winter and summer), Coho, chum, pink, and sockeye salmon, coastal cutthroat trout,
native char, and forage fish (U.S. Department of the Interior, National Park Service,
1996). After dam removal these fish will have access to more than 100 km of mainstem
and tributary-stream habitat.
The headwaters of the Elwha River begin within Olympic National Park and flow
northward to the sea in the Strait of Juan de Fuca (Figure 2). The river flows through a
series of alluvial valleys and bedrock canyons. Pools, riffles, and rapids are common.
Alluvial bars are common upstream from the reservoirs, but the channel bed is
characterized by cobbles, boulders, and bed rock in the lower reach that is downstream
from the reservoirs. Average river slope in the lower 8 km is 0.4 percent.
Figure 1. The Elwha River is located within the United States of America.
14
Figure 2. Elwha and Glines Canyon Dams are located on the Elwha River near Port Angeles,
Washington, U.S.A..
Lake Aldwell is formed behind Elwha Dam and has a storage capacity of 10 million m3.
Lake Mills is formed behind Glines Canyon Dam and has a storage capacity of 50 million
m3, which is 3.7 percent of the mean annual river flow of 1,300 million m3/yr (average
flow rate of 42 m3/s). Both dams are operated to keep the reservoir elevations constant
(within 15 cm) over time, so flood peaks and durations have not been significantly
altered.
Reservoir Sedimentation
The reservoirs behind the two dams have trapped the entire upstream load of sand and
gravel (67-year average of 82,000 m3/yr) and are estimated to have trapped 70 percent of
the silt and clay load (Randle et al., 1996).
Reservoir sediment volumes were last measured in 1994 (U.S. Department of the Interior,
Bureau of Reclamation, 1996a). By 2012, when dam removal may begin, the two
reservoirs are predicted to contain 8.4 million m3 of silt and clay-sized sediments and 8.0
15
100%
16
Vol (m3)
5,060,000
5,510,000
Vol (m3)
6,420,000
6,990,000
1994
2012
Vol (m3)
1,980,000
990,000
Vol (m3)
1,980,000
990,000
1994
2012
Vol (m3)
Vol (m3)
7,040,000 8,400,000
6,500,000 7,980,000
13,540,000 16,380,000
Figure 3. Photograph looking downstream at Lake Mills, behind Glines Canyon Dam, and the
reservoir delta composed of sand, gravel, and large woody debris.
Figure 4. Photograph looking downstream at Lake Aldwell, behind Elwha Dam, and the
reservoir delta composed of sand, gravel, and large woody debris.
17
18
a.
b.
Figure 5. Photographs of Lake Mills during the 1994 drawdown experiment: Eroded delta
sediments re-deposited across the width of the receded reservoir (a) and sediment terraces
were deposited along the margins of the reservoir (b).
The predicted reservoir sediment erosion volumes are presented in table 2 under four
separate hydrologic scenarios (Randle, et al., 1996). Between one-quarter and one-third
of the sand and gravel-sized sediments (1.7 million to 2.4 million m3) are expected to
erode from the reservoirs and be transported downstream to the sea as bed-material load.
Between one-half and two-thirds of the silt and clay-sized sediments (4.1 million to 5.0
million m3) are expected to erode from the reservoirs and be transported downstream to
the sea as suspended load (Randle et al., 1996). The remaining reservoir sediments are
expected to stabilize and become covered with woody vegetation over the long term.
The reservoir sediment erosion model results are based on the simulation of four historic
hydrologic periods:
(1) 1950 to 1963 begins with one year of relatively high annual peak discharge,
followed a year of relatively low peak discharge, and then a year of moderate peak
discharge.
(2) 1968 to 1981 begins with the lowest peak discharge for any three consecutive
water years of record.
(3) 1971 to 1984 begins with progressively higher annual peak discharges in each
of the three years.
(4) 1989 to 2002 begins with the highest peak discharge for any three consecutive
water years of record.
Reservoir drawdown and Elwha River flows are expected to be the primary causes of
reservoir sediment erosion, but tributary streams that enter the reservoirs are also
expected to erode gullies through the reservoir sediments. In addition, rainfall runoff is
expected to cause some additional erosion of sediment deposits along the reservoir
margins.
19
1950 to
1963
4,700,000
3,700,000
700,000
280,000
1,900,000
1,200,000
590,000
110,000
6,600,000
4,900,000
1,300,000
390,000
1968 to
1981
5,300,000
3,900,000
1,000,000
400,000
1,900,000
1,200,000
590,000
110,000
7,100,000
5,000,000
1,600,000
510,000
1971 to
1984
5,000,000
3,900,000
800,000
320,000
1,900,000
1,200,000
600,000
110,000
6,900,000
5,000,000
1,400,000
430,000
1989 to
2002
4,600,000
3,000,000
1,100,000
460,000
1,900,000
1,200,000
610,000
110,000
6,500,000
4,100,000
1,800,000
570,000
20
Adaptive Management
An adaptive management monitoring plan will be used to determine if actual sediment
impacts agree with predictions and if the new water treatment plants and flood control
levees can accommodate the increases in suspended sediment concentration and river-bed
aggradation. Initially, monitoring will focus on the erosion and redistribution of reservoir
sediments. Once sediments are released from the reservoirs, downstream monitoring will
focus on turbidity and suspended sediment concentration and on aggradation of the
channel bed. Early detection of significant channel-bed aggradation will trigger
additional monitoring. Detection of system-wide aggradation or high sediment
concentrations that begin to approach flood-control or water-treatment capacities will
trigger a slower rate of dam removal or a temporarily halt to dam removal. If localized
problems are identified through monitoring, then attempts will be made to treat the
problem locally.
Physical modeling (Bromley, et al., 2005) and field evidence suggest that the reservoir
deltas are most like to naturally erode along their reservoir margins. Even though
multiple channels may initially erode the deltas, a single erosion channel in each reservoir
may eventually capture Elwha River flow from other erosion channels. If a single
erosion channel incises the delta along the reservoir margin, then a substantial portion of
the delta could be left in place immediately after dam removal (Figure 6a). These delta
sediments would be vulnerable to uncontrolled erosion after dam removal is complete.
Physical modeling has demonstrated that the initial formation of a pilot channel along the
delta centre was effective at eventually eroding and redistributing a substantial portion of
the reservoir delta (Figure 6b).
b.
a.
Figure 6. Physical Model Experiments of Lake Mills sediment erosion by Chris Bromley
without a pilot channel (a) and with a pilot channel (b).
21
Study References
Bromley, C. Randle, T., Grant, G., Thorne, C. (2005), Physical modeling of the removal
of Glines Canyon Dam and Lake Mills from the Elwha River, WA. in Proceedings of
the 2005 Watershed Management Conference, July 19-22, 2005, Williamsburg, VA.,
ASCE.
Childers, D.; Kresch, D.L.; Gustafson, A.S.; Randle, T.J.; Melena, J.T.; Cluer, B. (2000),
Hydrologic Data Collected During the 1994 Lake Mills Drawdown Experiment,
Elwha River, Washington, Water-Resources Investigations Report 99-4215, U.S.
Geological Survey, Tacoma, Washington, 115 pages.
Randle, T.J.; Young, C.A.; Melena, J.T.; and Ouellette, E. M. (1996), Sediment Analysis
and Modeling of the River Erosion Alternative, Elwha Technical Series PN-95-9, U.S.
Bureau of Reclamation, Technical Service Center, Denver, 136 p.
U.S. Department of the Interior, Bureau of Reclamation (1996a), Alluvium Distribution in
Lake Mills, Glines Canyon Project and Lake Aldwell, Elwha Project, Washington,
Elwha Technical Series PN-95-4, Pacific Northwest Region, Boise, ID, 60 p.
U.S. Department of the Interior, Bureau of Reclamation (1996b), Removal of Elwha and
Glines Canyon Dams, Elwha Technical Series PN-95-7, Pacific Northwest Region,
Boise, ID, 90 p.
U.S. Department of the Interior, National Park Service (1996), Final Elwha River
Ecosystem Restoration Implementation Environmental Impact Statement, Olympic
National Park, Port Angeles, Washington.
U.S. Department of the Interior, National Park Service (2004), Draft Supplement to the
Final Elwha River Ecosystem Restoration Implementation Environmental Impact
Statement, Olympic National Park, Port Angeles, Washington.
U.S. Department of the Interior, National Park Service (2005), Record of Decision,
Elwha River Ecosystem Restoration Implementation, Final Supplemental
Environmental Impact Statement, Olympic National Park, Port Angeles, Washington.
22
Introduction
Matilija Dam was built in 1947 with an initial reservoir capacity of 7,018 ac-ft. It is
located on Matilija Creek, which joins with North Fork Matilija Creek approximately 0.6
miles downstream to form the Ventura River (Figure 7). It was original constructed as a
160 ft sill height, but a 30 foot notch was cut in 1965 in the dam and approximately 2600
ac-ft was lost. The upper part of the dam had alkali-aggregate reaction that caused the
concrete in the upper section of the dam to be weakened. The original purpose of the dam
was water storage for the local community. However, the dam is now practically full of
sediment and its usefulness is lost. The dam is an impediment to southern steelhead trout
passage, and the trout is an endangered species. Under the authority of the Endangered
Species Act, the US Army Corp of Engineers and the County of Ventura are now funding
studies to design the removal of the dam.
Hydrology
The flows in the Ventura River basin are highly variable. The historic peak flows are
shown in Figure 8. The annual peak flow has varied between essentially zero and 20,000
ft3/s. The flows with a specific return period are given in Table 3. The large flows events
are very short lived and the flow can quickly recede after the rain stops (Figure 9). The
annual flow volumes at Matilija Dam are shown in Figure 10. The average annual flow is
about 30,000 ac-ft, but is highly variable from year to year and the average flow is not a
good indicator of an average year. It is more likely that the flow at the dam will be
significantly higher or lower than this value.
River Characteristics
Just downstream of the dam, Matilija Creek is confined in a canyon for approximately 1
mile. The river has then joined with North Fork Matilija Creek and is called the Ventura
River. The Ventura River is primarily a braided river channel downstream (see Figure
11). The river slope is approximately 1.5% at its beginning and gradually decreases to
about 0.5 % just upstream from its mouth (Figure 12). The river width varies between
about 150 feet for the first 2 miles downstream of the dam, to about 350 feet in the flatter
downstream sections. Because of its steep slope and high flow rates, it has a high
sediment transport capacity during flood events. The suspended sediment loads are very
high during floods and commonly exceed 10,000 mg/l. The representative surface bed
material in the river is given in Figure 13.
23
Reservoir Sedimentation
Sedimentation in the Matilija Reservoir has been a concern since its construction and a
photograph of the current reservoir is shown in Figure 14. Matilija Reservoir currently
has less than 500 ac-ft of capacity remaining and its usefulness as a water storage facility
is significantly decreased. There is currently about 6 million yd3 of sediment deposited
behind the dam, at a maximum depth of about 80 ft against the face of the dam. The dam
currently traps all sand-sized and larger material. It is estimated that most of the silts and
clays pass over the dam during flood flows. An extensive drilling program was performed
on the reservoir sediment and the physical properties of the sediment are given in Table
4. Eighteen drill holes were collected in the reservoir deposit. The sediment collected
from these holes was analyzed for its physical and chemical properties. No significant
contamination was found in the reservoir sediment.
The sediment deposit was broken in to three sections. The reservoir area is the area
currently still under water and it primarily silts and clays. The delta region is above water
and is dominated by sands, but has silts, clays, and some gravels. The upstream channel
area is just upstream of the delta and has few fines and is a mixture of sands, gravels, and
cobbles. The reservoir width is approximately 3 times greater than the river width. The
reservoir delta extends about 7,000 ft upstream from the dam.
24
25
26
Table 3. Flow rate at various return periods on Matilija Creek and Ventura River.
Return
Period
(yr)
2
5
10
20
50
100
500
Upstream of
Confluence
with N. Fork
Matilija Creek
3,060
7,090
12,500
15,200
18,800
21,600
27,900
Shell
Chemical
Plant
5,080
12,250
41,300
52,700
67,900
78,900
105,500
25000
peak discharge (cfs)
15-yr moving average
Discharge (cfs)
20000
15000
10000
5000
0
1933
1943
1953
1963
1973
1983
1993
Year
Figure 8. Peak Discharge at USGS gage 11115500, downstream of Matilija Dam on Matilija
Creek. Flows between Oct 1 1988 and Sept 30 1990 were not available at this gage.
27
50000
45000
15 min flows
40000
daily average
Flow (cfs)
35000
30000
25000
20000
15000
10000
5000
0
2/8
2/10
2/12
2/14
2/16
2/18
2/20
Day
140000
annual flow volume (ac-ft)
120000
100000
80000
60000
40000
20000
0
1927 1932 1937 1942 1947 1952 1957 1962 1967 1972 1977 1982 1987 1992 1997
Year
Figure 10. Annual flow volume at USGS gage 11115500, downstream of Matilija Dam on
Matilija Creek.
28
Matilija Dam
29
7a
7b
0.03
1200
2
6a 6b
1000
0.025
800
0.02
600
0.015
400
0.01
200
0.005
0
0
10
12
14
16
18
River Mile
thalweg elevation
reach breaks
Figure 12. River profile downstream of Matilija Dam. Matilija Dam is at RM 16.3.
30
20
Slope (-)
Elevation (ft
1000
#7
100
10
# 15
# 12
1
d16
d50
d84
#3
0.1
0
10
15
20
River Mile
Figure 14. Picture of sediment trapped behind Matilija Dam while the reservoir was drawn down.
Picture was taken in July 2003 by Paul Jenkin of the Surfrider Foundation.
31
Reservoir
100.0
100.0
100.0
100.0
100.0
99.9
99.8
99.7
99.7
99.5
99.0
97.2
92.2
82.8
70.9
57.3
43.1
30.1
18.0
2,100,000
Delta
100.0
100.0
100.0
99.8
98.4
95.1
92.5
89.9
87.3
83.7
77.5
66.5
50.8
33.2
21.9
14.5
9.7
5.3
0.0
2,800,000
Upstream
Channel
100.0
87.9
75.9
60.9
48.9
36.9
29.9
24.9
21.9
18.4
15.0
12.0
9.0
6.0
4.0
2.0
1.0
0.0
0.0
1,000,000
Study References
Reclamation, 2006, "Hydrology, Hydraulics, and Sediment Studies for the Matilija Dam
Ecosystem Restoration Project, Ventura, CA DRAFT Report" Technical Service
Center, Denver, CO.
32
History
When was the reservoir constructed and by who?
Savage Rapids Dam was built in 1921 to divert river flows for irrigation (Figure 15). The
dam is operated by the Grants Pass Irrigation District (GPID). Modifications were made
to the dam in the 1950s that included installation of two radial gates and excavation of a
channel in bedrock that allow the reservoir to be partially drawn down and sluice
sediment for purposes of installing or removing stop logs.
Figure 15. View of Savage Rapids Dam, located on the Rogue River in southwestern Oregon,
U.S.A. on February 23, 1999 when the mean-daily flow was 7400 ft3/s (210 cms).
What is the purpose of the dam and reservoir?
The dam is utilized to divert water for irrigation customers during the months of April
through October. The reservoir is also utilized for recreational boating and fishing,
mostly during the irrigation season when the pool is extended from mile to 2 miles
(0.8 to 4.0 km).
What is the size of the dam?
The dam is a combination gravity and multiple arch concrete dam with a crest length of
464 feet (141 m) and a structural height (total height of the dam from the foundation to
the top of the crest, including the stop logs) of 39 feet (12 m) (Reclamation, 1997). The
33
970
Dam Crest With Stoplogs
960
Elevation (feet)
930
920
910
107
107.2
107.4
107.6
107.8
108
108.2
River Mile
Figure 16. Illustration of pre-dam and existing reservoir bottom and elevation influence of
stop logs.
34
Figure 17. Looking upstream at Savage Rapids reservoir in upstream areas during riverine
conditions in the non-irrigation season.
Does the dam have a sediment sluiceway and, if so, has it been used?
The river outlet for the dam consists of two 7- by-16- foot (2.1 by 4.9 m) radial gates with
a combined capacity of 6,000 ft3/s (169 m3/s). The radial gates are used in the spring and
fall to lower the reservoir and either place or remove stop logs that raise the reservoir 11
feet (3.4 m). The radial gate operation causes a partial sluicing of sediment during the
multi-day operation twice a year.
Setting
Where is reservoir located within watershed?
The Rogue River is a designated wild and scenic waterway from its junction with
the Applegate River, just west of Grants Pass, Oregon, downstream to Lobster
Creek Bridge, about 10 miles upstream from the mouth of the river.
The annual mean flow of the Rogue River is 3,372 cubic feet per second (ft3/s).
The total drainage area is 2,459 square miles.
The mean annual runoff is 19 inches, the highest recorded peak flow was 152,000
ft3/s on December 23, 1962, and the lowest mean-daily flow recorded was 744
ft3/s.
Flood peaks on the Rogue River typically occur from November to March, with
most occurring in December and January. Rainstorms occur during spring and
summer months that also result in higher flows.
Are there any upstream or downstream tributaries and dams that impact sediment
storage?
Of the total drainage area upstream from Savage Rapids Dam, 30 percent (686
square miles) is regulated by Lost Creek Reservoir, primarily a flood control
reservoir built and maintained by the U.S. Army Corps of Engineers (Corps). Lost
Creek Dam also traps virtually all of the sediment transported into the reservoir
by the Rogue River during these peak flows.
A few other reservoirs, such as Emigrant Lake, may also trap a small amount of
sediment that would otherwise be delivered to the Rogue River. However, these
drainage areas are small relative to that of the Rogue River, and they were not
within the scope of this study. Lost Creek Reservoir, which began storage in
February 1977, reduces flood peaks at Savage Rapids Dam by storing water
during high flood peaks.
The Applegate River enters the Rogue River 12.5 miles downstream from Savage
Rapids Dam. This tributary contributes large quantities of sediment (sand and
gravel) to the Rogue River.
Just downstream from the confluence with the Applegate River, the Rogue River
enters Hellgate Canyon, a steep, narrow, bedrock canyon that is 65 miles long.
The Rogue River exits the canyon approximately 30 miles from the ocean, and the
slope of the river flattens out.
36
The Illinois River enters the Rogue River just downstream from the canyon mouth
and contributes additional water and sediment to the river.
Project Challenges
What were the main concerns from stakeholders and/or managers?
Among the many significant concerns with this project are the volume, particle size
gradation, and spatial distribution of sediment accumulated within the reservoir, the
chemical composition of the reservoir sediment, and the rate at which the reservoir
sediment would be eroded if the dam is removed. Specifically, stakeholders identified
the following sediment issues that needed to be addressed before dam removal could be
considered:
1. The sediment may contain hazardous contaminants from upstream mining and
other human activities.
2. The sediment might plug pumps or cause elevated maintenance costs for pumps
proposed for construction immediately downstream from the dam to supply water
to the GPID.
3. Release of the sediment could affect fisheries and fish habitat downstream from
the dam.
4. Release of sediment might possibly affect the municipal water supply system of
the City of Grants Pass, which is located 5 miles downstream from the dam.
5. Release of the sediment could cause barriers to safe navigation of the Rogue
River downstream from the dam.
6. Landowners along the reservoir shoreline were concerned regarding how the new
riverine conditions would change the property value and aesthetics at their homes.
37
38
Figure 18. Upstream face of Savage Rapids Dam - During a reservoir drawdown in May
1999, gravel-sized sediment was observed on the crest of the dam, indicating that sediment is
transported past the dam during spillway releases.
Pre-Removal Evaluation
39
Figure 19. View downstream showing Reclamations custom built, floating drilling platform
in operation on drill hole AP-99-10. The spillway and pumping plant portions of Savage
Rapids Dam are present in the background of this photograph. (Reclamation photograph by
Richard Link; September 30, 1999.)
Channel and Reservoir Surveys
A 2-foot contour map of Savage Rapids Reservoir was developed based on a sonar
survey of the reservoir completed in July 1999 by Reclamation. The survey was
performed from a raft equipped with a high precision global positioning system and
depth-sounding equipment (Figure 20). Using the same equipment, data were also
collected along the river bottom downstream from the dam to the confluence with the
Applegate River, approximately 12 miles downstream. These data were used to develop
river cross sections for computer modeling purposes.
40
Figure 20. View of survey boat configuration equipped with global positioning software
(GPS) equipment, depth sounder, and laptop to document channel bathymetry.
What modeling of sediment transport was accomplished?
To address flooding, water quality, fish passage, and infrastructure concerns a
one-dimensional hydraulic and sediment transport model was utilized.
980
Evans
Creek
960
Elevation (feet)
940
920
Grants Pass
Savage Rapids
Dam
900
Applegate River
confluence
880
Pool 1
Pool 4
Pool 2
Pool 5
Pool 3
Pool 6
860
Pool 7
Pool 8
840
95
96
97
98
99
100 101 102 103 104 105 106 107 108 109 110 111
River Miles
A partial dam removal plan was selected and is planned for October 2009 during a
low-flow period. October was recommended because this will be just after the
end of the irrigation season so the new pumping plant located downstream will
not need to be operating. Additionally, this will provide an entire winter flood
season to erode and transport reservoir sediments before the next irrigation season
in the following spring.
The portion of the dam extending across the pre-dam river channel will be
entirely removed. The remaining dam section is located on top of bedrock that
will cause a small amount of ponding at the 5-year flood but be largely drowned
out during the 100-year flood.
The dam will be removed in two phases. The portion of the dam on the pre-dam
river bed will be blocked off with a cofferdam and removed in the dry. During
this period all flow will be passed over the left (south) side of the dam to maintain
42
fish passage. The new pumping plant intake located downstream of the dam will
be operational during this period.
A small pilot channel is planned to be excavated in the sediment deposit upstream
of Savage Rapids Dam to initiate the breaching of the sediment and help speed up
the reservoir sediment erosion process. This is desired to ensure the river is
restored as fast as possible to its original pre-dam location to limit impacts to fish
migration through the former dam site.
Monitoring Accomplished
What monitoring questions were important to study team?
Ensuring that the river was restored to its pre-dam position, fish passage was
adequately restored, and sediment impacts did not exceed predictions.
What data was collected and over what time period?
Turbidity data upstream and downstream of the dam site before, during, and after
dam removal.
Time-lapse photography of dam removal construction and post-dam removal river
changes.
Topographic survey of pre-dam removal and planned post-dam removal reservoir
topography to verify volume and locations of reservoir sediment erosion.
Topographic survey of pre-dam downstream river channel elevations and planned
post-dam survey to validate deposition locations and magnitude from release of
reservoir sediment.
Lessons Learned
What were the most valuable data and analysis that helped guide the dam removal
process?
Getting additional reservoir sediment data to improve the volume estimate was very
helpful and improved predictions and reduced potential estimates of sediment
impacts.
Hydraulic modeling and geologic investigations of bedrock at the site were very
useful to determine how much of the dam needed to be removed in order to provide
the most benefit for restoring fish passage balanced with cost.
Two-dimensional hydraulic modeling was very helpful to determine how to construct
cofferdams during dam removal and to meet fish passage requirements during and
post-dam removal.
Unique to this project, several iterations of the two-dimension model were important
to assist with design of a new, downstream pumping plant intake to replace the dams
diversion capabilities.
43
Study References
Bureau of Reclamation, 2001, Savage Rapids Dam Sediment Evaluation Study, prepared
by the Pacific Northwest Regional Office and the Denver Technical Service Center.
44
History
When was the reservoir constructed and by who?
The Gold Hill Diversion Dam has existed in various forms for over 80 years. The Pacific
Oregon Power Company originally built the dam and used stop logs to divert water into
the canal. In the mid-1940s, the left dam crest was built perpendicular to the rivers flow
and all stop logs were replaced with concrete (Figure 22). The power plant, canal, and
diversion facilities were transferred to various owners, mostly cement companies, until
the city of Gold Hill took title in 1968.
Figure 22. Looking upstream at Gold Hill Dam on the Rogue River in Oregon, U.S.A..
What is the purpose of the dam and reservoir?
The Pacific Oregon Power Company built the dam to provide a water diversion to a
power plant located approximately 2,000 feet downstream from the head works. Though
the power plant is not operational, the City uses the diversion canal as its municipal and
industrial water supply intake.
What is the size of the dam and how is it operated?
45
The existing diversion dam is a 1,000-foot-long L-shaped concrete gravity structure. The
dams crest varies in elevation from 1 to 8 feet above the downstream water surface
elevation. The dams uncontrolled crest elevation is approximately 1077.0 feet, and the
depth of flow over the crest for low to normal flows (1,500 cfs to 3,000 cfs) is 3 to 6
inches. The diversion dam backs water approximately 1 mile upstream near the base of
Gold Nugget Rapids. The backwater effect from the dam does not extend past the base of
this rapid. The dam is located at the top of a bedrock rapid.
The Gold Hill Diversion Dam diverts water from the Rogue River into a 2,000-foot-long
canal where the city of Gold Hill draws its municipal and industrial water supply.
Setting
Where is the reservoir located within the watershed?
The Gold Hill Diversion Dam is 121 river miles (RM) upstream from the mouth of the
Rogue River at the Pacific Ocean. The Rogue River is a relatively steep gravel and
cobble-bed river with several pools, riffles, and rapids (Figure 23). In the vicinity of
Gold Hill the river channel slope has a 0.0040 gradient.
Gold
Nugget
Rapids
1080
Bridge
Elevation (feet)
1060
Bridge
1040
1020
Powerhouse
Rapids:
25-foot drop
Valley of the
Rogue State Park
1000
980
960
114
115
116
117
118
119
120
121
122
Figure 23. Longitudinal profile of Gold Hill resevoir and downstream river channel.
46
123
140,000
120,000
100,000
80,000
60,000
40,000
20,000
1/1/97
70,500 cfs
0
'05
'18
'32
'46
'59
'73
'87
'01
Date
Figure 24. Historical river flows at a U.S. Geological Survey stream gage located slightly
upstream of the Gold Hill Dam.
Are there any upstream or downstream dams?
Savage Rapids Dam is located downstream of Gold Hill Dam. Gold Ray Dam and Lost
Creek Dam are located upstream of Gold Hill Dam. The United States Geological
Survey Rogue River at Raygold gage, located 5 miles upstream from Gold Hill Diversion
Dam, has measured river flow since 1905. The rivers peak flows substantially changed
in 1977 when the Army Corps of Engineers built Lost Creek Dam and began regulating
flow out of Lost Creek Lake. Though flooding peaks have decreased, the additional
47
Project Challenges
What were main concerns from stakeholders and/or managers?
The stakeholders identified the following objectives to be addressed:
Identify a pump intake location to give the City a reliable municipal water supply
Provide adequate and permanent fish passage and protection to adult and juvenile
anadromous fish
Reduce the Citys water diversion to their legal water right of 3 cfs
Keep all formerly-diverted water in the Rogue River main stem
Retain or mitigate, as much as possible, the aesthetic, historic, and recreational
values associated with the site
48
Pre-Removal Evaluation
Evaluation was done in three phases as follows:
49
Phase 1 appraisal-level review developed from October 6, 1999, through May 17, 2000.
This review included identifying specific fish passage problems and examining concepts
for resolving these problems. After reviewing the options, the City of Gold Hill and the a
group of local stakeholders agreed to relocate the water pump intake outside of the canal.
Phase II, feasibility-level evaluation included analysis of removing all or parts of the
diversion dam and relocating and screening the pump intake structure. Major tasks of this
evaluation are listed below:
Data Collection and Analysis
Engineering and Design
City and Committee Review
Study Documentation
Canal Area Enhancement Concepts
Phase III activities included preparing final engineering drawings and specifications
suitable for bidding, constructing, screening the pump intake structure, and breaching the
diversion dam.
Data used in determining the feasibility of dam removal include bathymetric surveys,
hydraulic modeling, geologic investigations, underwater inspections, and a sediment
contamination analysis.
The one-dimensional hydraulic model indicated that a pool about 150 feet upstream from
the dam would have sufficient depths at a minimum design flow of 662 ft3/s for a pump
intake structure. This area has sufficient sweeping velocities to prevent sediment from
depositing around the pump intake structure.
If the diversion dam did not exist, the high bedrock elevations at the top of the
Powerhouse Rapids (where the dam is located) would still have a backwater influence
upstream. Without the dam in place, small pools would form upstream of each currently
submerged riffle and rapid, rather than one large reservoir pool as now exists.
A U.S. Army Corps of Engineers river hydraulics model, HEC-RAS 3.0, was applied to
the study reach. HEC-RAS is a one-dimensional, steady flow backwater model that
computes hydraulic parameters for any given cross section at any discharge. The model
was calibrated to measured water surface elevation data to accurately predict hydraulic
parameters. Model results were used to compare water surface elevation, average
velocity, and water depth for existing river and reservoir conditions for various dam
removal options.
An additional 6 miles of river downstream were evaluated with a conceptual model to
determine the available sediment storage capacity.
50
Monitoring Accomplished
Time lapse photography was collected during the construction period of July to
September 2008 to visually document day to day river responses during construction
activities and post-dam removal (Figure 25). Four pictures were taken per day, or once
every 6 hours.
Turbidity measurements were collected upstream and downstream of Gold Hill Dam to
measure and document sediment impacts related to construction activities during July to
September 2008. No turbidity impacts were detected during the dam removal above
upstream (background) levels.
51
Figure 25. Looking at Gold Hill Dam in August 2009 after removal from an upstream view
(left photo) and a downstream view (right photo).
Lessons Learned
What management or collaboration steps were helpful in navigating the dam removal
discussion?
Collaboration throughout the project among technical staff, resource managers,
landowners, and stakeholders helped make the dam removal a success. Parties involved
included the following:
City of Gold Hill
Jackson Soil and Water Conservation District
Little Butte Creek and Bear Creek Watershed Councils
National Marine Fisheries Service (NMFS)
Oregon Department of Fish and Wildlife (ODFW)
Oregon Watershed Enhancement Board
Oregon Water Resources Department (OWRD)
Rogue Valley Council of Governments (RVCOG)
U.S. Army Corps of Engineers (Corps)
U.S. Bureau of Reclamation (Reclamation)
U.S. Fish and Wildlife Service (USFWS)
Several local irrigation districts
52
Study References
Bureau of Reclamation, September 2001, City of Gold Hill Fish Passage Improvements
at the Municipal Water Supply Diversion: Phase II, prepared for Rogue River Basin Fish
Passage Technical Committee.
53
History
Setting
Project Challenges
55
What is the ratio of maximum reservoir depth to maximum river pool depth?
o They are about the same
Does the reservoir have a sediment delta?
o No
What is the reservoir sediment size gradation relative to the upstream river
channel?
o 0.145mm / 78mm (0.00186)
If the reservoir is already filled with sediment, over what period of time did the
filling take place?
o The reservoir most likely filled with sediment to the extent possible within
one or two years of operation.
Pre-Removal Evaluation
Monitoring Accomplished
What monitoring questions were important to study team?
How would reservoir sediment be redistributed downstream and how long would
it take?
What data was collected and over what time period?
Time-lapse photography was collected during the dam removal period using two
solar powered cameras in weather proof boxes (note that one camera was stolen
during monitoring) (Figure 27).
Profiles and cross sections and bed material samples were collected in 2006 and
2007 before the dam was removed and again in 2008 and 2009 following dam
removal.
Low elevation aerial photography was also collected in 2008 and 2009 following
dam removal to address issues with large amounts of timber in the reservoir.
56
Figure 27. Looking at time-lapse photography setup utilized on Chiloquin Dam removal
project.
Was monitoring adequate to address questions or were there limitations due to funding,
access, logistics, etc?
Overall the level of monitoring was appropriate and maybe even excessive. One of the
difficulties on this project was that much of the river downstream from the dam is either
very swift with boulders or deep making wading difficult if not impossible. In steeper
and faster sections sediment deposition would likely be limited to the channel margins
where a boat based survey was not possible due to shallow depths and fast moving water.
In the pools the challenge is that small amounts of deposition may not be detectable due
to limitations in the accuracy of survey equipment. Deposition amounts of 6 inches or
less may be difficult to separate from equipment noise while larger amounts of deposition
are easily detectable.
Lessons Learned
What was the most valuable data and analysis done up front that helped guide the dam
removal process?
Sediment samples from the reservoir showed that there were a large percentage of fines
in the bed. We also used a probabilistic approach with the sediment transport analysis to
consider different hydrologic scenarios. This approach prepared us for the possibility of
a longer adjustment period if water levels were low following dam removal.
Any surprises from dam removal that resulted in new needs for construction, analysis, or
monitoring?
There were reports of logs in the reservoir, but when the dam was removed in August
2008, we were surprised by the large number of logs. Initial log counts showed that there
57
Figure 28. Looking at Chiloquin reservoir following removal showing the large number of
logs that were uncovered.
Did reservoir sediment and river conditions behave as expected from predictions?
Except for all the logs in the reservoir pool, the reservoir sediment and river response has
been predictable. The largest factor in the response has been the lack of high flows to
mobilize and redistribute reservoir sediment. It is taking longer to move sediment
downstream and it is only moving short distances. High flows should quickly remove
any remaining sediment in the reservoir and move it from the Sprague River to the
Williamson River.
Another important consideration for this project is that the data collected in 2007 prior to
dam removal showed that there might only be a small amount of sediment in the reservoir
and that the original estimate of sediment might be very high. Surveys of the reservoir
pool in 2007 showed that the water was nearly as deep as the dam was high. Visual
inspection of the reservoir bottom showed that there was only a small section of the
reservoir actually covered with fine grained sediment. Further upstream in the reservoir
much of the bed was covered with cobbles and boulders. Much of the fine grained
sediments were confined to areas on the inside of bends. After the dam was removed this
was confirmed as much of the riverbed was filled with boulders and cobble and a pool
riffle sequence was clearly present in the reservoir pool. In addition, the areas on the
inside of the bends were identified as point bars that had additional fine grained sediment
deposits on them. There were cut stumps on these surfaces clearly identifying them as
surfaces prior to dam construction.
58
Study References
Randle, Timothy and Joseph Daraio, March 2003, Sediment And Geomorphic
Assessment For The Potential Removal Of Chiloquin Dam, prepared by Technical
Service Center, Bureau of Reclamation, Denver, Colorado.
Bauer, Travis, and Timothy Randle, February 2005, Computation of Sediment Transport
Rates Downstream from Chiloquin Diversion Dam, prepared by Technical Service
Center, Bureau of Reclamation, Denver, Colorado.
Bauer, Travis, January 2005, Computation of Sediment Transport Rates in Riffles
Downstream from Chiloquin Diversion Dam, prepared by Technical Service Center,
Bureau of Reclamation, Denver, Colorado.
59