Femap 154 - 508
Femap 154 - 508
FEMA P-154
THIRD EDITION
Rapid Visual Screening of Buildings for Potential
Seismic Hazards: A Handbook
Prepared by
APPLIED TECHNOLOGY COUNCIL
201 Redwood Shores Parkway, Suite 240
Redwood City, California 94065
www.ATCouncil.org
Prepared for
FEDERAL EMERGENCY MANAGEMENT AGENCY
Michael Mahoney, Project Officer
Mai Tong, Task Monitor
Erin Walsh, Task Monitor
John Gillengerten, Technical Monitor
Washington, D.C.
January 2015
Notice
Any opinions, findings, conclusions, or recommendations expressed in this publication do not
necessarily reflect the views of the Applied Technology Council (ATC), the Department of
Homeland Security (DHS), or the Federal Emergency Management Agency (FEMA).
Additionally, neither ATC, DHS, FEMA, nor any of their employees, makes any warranty,
expressed or implied, nor assumes any legal liability or responsibility for the accuracy,
completeness, or usefulness of any information, product, or process included in this publication.
Users of information from this publication assume all liability arising from such use.
Preface
In 2011, the Applied Technology Council (ATC), with funding from the
Federal Emergency Management Agency (FEMA) under Task Order
Contract HSFEHQ-08-D-0726, commenced a series of projects (ATC-71-4,
ATC-71-5, and ATC-71-6) to update the FEMA 154 Report, Rapid Visual
Screening of Buildings for Potential Seismic Hazards: A Handbook (FEMA,
2002a). The purpose of FEMA 154, which was developed by ATC under
contract to FEMA (ATC-21 Project) and published in 1988, was to provide a
methodology to evaluate the seismic safety of a large inventory of buildings
quickly and inexpensively, with minimum access to the buildings, and
determine those buildings that require a more detailed examination. In 2002,
FEMA 154 was updated to create a Second Edition, based on (1) experience
from the widespread use of FEMA 154 by federal, state, and municipal
agencies and others; (2) new knowledge about the performance of buildings
during damaging earthquakes; (3) new knowledge about seismic hazards; and
(4) other then-new seismic evaluation and performance prediction tools, such
as the FEMA 310 report, Handbook for the Seismic Evaluation of Buildings A Prestandard (FEMA, 1998). Both the original FEMA 154 Handbook and
the Second Edition were accompanied by a Supporting Documentation report
(FEMA 155), which described the technical basis for the scoring system and
other guidance provided in FEMA 154.
Since the publication of the second edition of FEMA 154, there have been
several initiatives that have advanced the state-of-the-art in rapid visual
screening of buildings for seismic risk. One of these was the development of
the FEMA P-154 Rapid Observation of Vulnerability and Estimation of Risk
(ROVER) software for use on smart phones (FEMA, 2014), which enables
users to document and transmit data gathered in the field. The rapid visual
screening application of FEMA P-154 ROVER is based on the second
edition of FEMA 154 and incorporates several improvements made possible
by the electronic calculation capability of the device (e.g., site-specific
determinations of the seismic shaking hazard). In addition, users in Oregon
and Utah have suggested modifications to the FEMA 154 screening process
in the course of performing extensive seismic screenings of schools and other
buildings.
FEMA P-154
Preface
iii
The objective of the Third Edition remains the same as its predecessors: to
identify, inventory, and screen buildings that are potentially hazardous.
Although some sections of the text remained unchanged from the Second
Edition, the Third Edition incorporates several major enhancements,
including:
Update of the Data Collection Form, and the addition of an optional
more detailed page to the form,
Update of the Basic Scores and Score Modifiers,
Update of the ground motion definitions,
Preparation of additional reference guides,
Inclusion of additional building types that are prevalent,
Inclusion of additional considerations, such as nonstructural hazards,
existing retrofits, building additions, and adjacency,
Addition of an optional electronic scoring methodology, and
Additional information on how to run an effective screening program.
The technical basis for the rapid visual screening procedure is documented in
the FEMA P-155 report, Rapid Visual Screening of Buildings for Potential
Seismic Hazards: Supporting Documentation, (FEMA, 2015), which was
also updated to the Third Edition. Note that per FEMAs current report
numbering system, the third editions of FEMA 154 and FEMA 155 are now
referred to as FEMA P-154 and FEMA P-155, respectively.
ATC is indebted to the leadership of Bret Lizundia, Project Technical
Director, and to the members of the ATC-71-4, ATC-71-5, and ATC-71-6
Project Teams for their efforts in developing this updated Handbook. The
Project Technical Committee, consisting of Michael Griffin, William
Holmes, Brian Kehoe, Keith Porter, and Barry Welliver, managed and
performed the technical development efforts. Updated scores were
developed by Charles Kircher. Sarah Durphy, as a Project Working Group
member, provided special assistance in the development of the updated
Handbook. Andrew Bishop, Brian Kehoe, and Scott Hiner prepared the
illustrations for the report. Nicolas Luco and Kenneth Rukstales prepared the
seismicity maps in the document. The Project Review Panel, consisting of
Charles Scawthorn (chair), Timothy Brown, Melvyn Green, Laura Kelly,
Stephanie King, John Osteraas, Steven Sweeney, and Christine
Theodoropoulos, provided technical review, advice, and consultation at key
stages of the work. A workshop of invited experts was convened to obtain
feedback on the updated Handbook, and input from this group was
iv
Preface
FEMA P-154
instrumental in shaping the final methodology and report. The names and
affiliations of all who contributed to this report are provided in the list of
Project Participants.
ATC also gratefully acknowledges Michael Mahoney (FEMA Project
Officer), Mai Tong (FEMA Task Monitor), Erin Walsh (FEMA Task
Monitor), and John Gillengerten (FEMA Technical Monitor) for their input
and guidance in the preparation of this document. Ayse Hortacsu and
Thomas McLane managed the project and Amber Houchen and Peter N.
Mork provided report production services.
Jon A. Heintz
ATC Director of Projects
FEMA P-154
Christopher Rojahn
ATC Executive Director
Preface
Table of Contents
Preface........................................................................................................... iii
1.
Audience................................................................................... 1-5
Tools......................................................................................... 1-8
2.
2.3.4 D
etermining Screeners ................................................ 2-8
2.3.6 E
lectronic Scoring ....................................................... 2-9
Programs.................................................................... 2-10
FEMA P-154
Table of Contents
vii
2.6.3
2.7
2.8
2.9
2.10
2.11
2.12
3.
viii
2.8.1 A
ssessors Files .........................................................2-23
2.8.2 Building Department Files .........................................2-24
Available Tools..........................................................2-31
3.1 Introduction...............................................................................3-1
3.2.3 S
creener Identification .................................................3-4
3.3 B
uilding Characteristics............................................................3-4
3.6 B
uilding Occupancy ...............................................................3-10
3.10 Irregularities............................................................................3-15
Scores.........................................................................3-34
Table of Contents
FEMA P-154
4.
5.
4.3.7 R
etrofits..................................................................... 4-17
4.4 Determining the Final Level 2 Score...................................... 4-19
4.5.2 O
ther Conditions ....................................................... 4-20
4.6 Observable Nonstructural Hazards ......................................... 4-20
4.7 C
omments............................................................................... 4-22
4.8 Transferring the Level 2 Results to the Level 1 Form ............ 4-22
5.5.1 O
verview ..................................................................... 5-8
Safety......................................................................... 5-11
Safety......................................................................... 5-11
Programs.................................................................... 5-12
FEMA P-154
Table of Contents
ix
5.6.1
Development ..............................................................5-14
Procedure ...................................................................5-15
6.
6.1 Introduction...............................................................................6-1
6.2 Changes from and Comparisons with the Paper Forms ............6-1
6.3.1 S
ite-Specific Seismicity ...............................................6-3
Approach ..................................................................................6-3
C and D........................................................................6-6
Scoring......................................................................................6-7
7.
7.1 I ntroduction...............................................................................7-1
USA ..........................................................................................7-1
Form.............................................................................7-5
Form...........................................................................7-27
Table of Contents
FEMA P-154
B.1 Level 1 and Level 2 Forms for Very High, High, Moderately
Appendix D: Exterior Screening for Seismic System and Age ............. D-1
FEMA P-154
Table of Contents
xi
E.10
E.11
E.12
E.13
E.14
F.1 Introduction...............................................................................F-1
Wood ........................................................................................F-1
Concrete....................................................................................F-4
Unreinforced Masonry..............................................................F-7
References ...................................................................................................J-1
Project Participants...................................................................................K-1
xii
Table of Contents
FEMA P-154
List of Figures
Figure 1-1
Figure 1-2
Figure 1-3
Figure 2-1
Figure 2-2
Figure 2-3
Figure 2-4
Figure 2-5
Figure 2-6
Figure 2-7
Figure 2-8
Figure 3-1
Figure 3-2
Figure 3-3
Figure 3-4
Figure 3-5
Figure 3-6
Form................................................................................. 3-10
Figure 3-7
FEMA P-154
List of Figures
xiii
xiv
Figure 3-8
Figure 3-9
Figure 3-10
Form. ................................................................................3-13
Figure 3-11
buildings ...........................................................................3-14
Figure 3-12
Figure 3-13
Figure 3-14
Figure 3-15
Form .................................................................................3-16
Figure 3-16
Figure 3-17
wall...................................................................................3-18
Figure 3-18
Figure 3-19
Figure 3-20
Figure 3-21
Figure 3-22
Figure 3-23
Figure 3-24
Figure 3-25
Figure 3-26
List of Figures
FEMA P-154
Figure 3-27
Figure 3-28
Figure 3-29
floor.................................................................................. 3-25
Figure 3-30
Figure 3-31
Figure 3-32
Figure 3-33
Figure 3-34
Figure 3-35
Figure 3-36
Figure 3-37
Figure 3-38
Figure 3-39
Figure 3-40
Figure 3-41
Figure 3-42
Figure 3-43
FEMA P-154
List of Figures
xv
xvi
Figure 3-44
Figure 3-45
Figure 3-46
Figure 3-47
Form .................................................................................3-57
Figure 3-48
Figure 3-49
Form .................................................................................3-58
Figure 3-50
Form .................................................................................3-59
Figure 4-1
Figure 4-2
Figure 4-3
Figure 4-4
Figure 4-5
Figure 4-6
Figure 4-7
Illustration of a building with piers that are less than one half
Figure 4-8
Figure 4-9
Figure 4-10
Figure 4-11
Figure 4-12
Figure 4-13
Figure 4-14
List of Figures
FEMA P-154
Figure 7-1
Figure 7-2
Figure 7-3
Figure 7-4
Figure 7-5
Figure 7-6
Figure 7-7
Figure 7-8
Figure 7-9
Figure 7-10
Figure 7-11
Figure 7-12
Figure 7-13
Figure 7-14
Figure 7-15
Figure 7-16
Figure 7-17
Figure 7-18
Figure 7-19
FEMA P-154
List of Figures
xvii
xviii
Figure 7-20
Figure 7-21
School...............................................................................7-36
Figure 7-22
Figure 7-23
Figure A-1
Figure A-2
Figure A-3
Figure A-4
Figure A-5
Figure A-6
Figure A-7
Figure A-8
Figure A-9
Figure A-10
Figure A-11
Figure A-12
Figure C-1
Figure C-2
List of Figures
FEMA P-154
Figure D-1
Figure D-2
Figure D-3
Figure D-4
Building with both shear walls (in the short direction) and
Figure D-5
Figure D-6
Figure D-7
Figure D-8
Figure D-9
Figure D-10
Figure D-11
Figure D-12
Figure D-13
Figure D-14
Figure D-15
Figure D-16
Figure D-17
Figure E-1
Figure E-2
Figure E-3
spans ..................................................................................E-2
FEMA P-154
List of Figures
xix
xx
Figure E-4
Figure E-5
Figure E-6
Figure E-7
Figure E-8
Figure E-9
Failed cripple stud wall, 1992 Big Bear earthquake ......... E-7
Figure E-10
Figure E-11
Figure E-12
Figure E-13
Figure E-14
Figure E-15
Figure E-16
Figure E-17
Figure E-18
Figure E-19
Figure E-20
Figure E-21
Figure E-22
Figure E-23
Example of steel frame with URM infill walls (S5) ....... E-21
Figure E-24
Figure E-25
Figure E-26
List of Figures
FEMA P-154
Figure E-27
Figure E-28
Figure E-29
Figure E-30
Figure E-31
Figure E-32
Figure E-33
URM infill (left wall), and face brick (right wall) ...........E-32
Figure E-34
Figure E-35
Figure E-36
Figure E-37
Figure E-38
Figure E-39
Figure E-40
Figure E-41
Figure E-42
Figure E-43
installation........................................................................E-41
Figure E-44
Figure E-45
Figure E-46
FEMA P-154
List of Figures
xxi
xxii
Figure E-47
Figure E-48
Figure E-49
Figure E-50
Figure E-51
Figure E-52
Figure E-53
Figure E-54
Figure F-1
Figure F-2
Figure F-3
Figure F-4
Figure F-5
Figure F-6
Figure F-7
Figure F-8
Figure F-9
Figure G-1
Figure G-2
Figure G-3
Figure G-4
List of Figures
FEMA P-154
Figure G-5
earthquake......................................................................... G-8
Figure G-6
Figure G-7
Figure G-8
Figure G-9
earthquake....................................................................... G-10
FEMA P-154
List of Figures
xxiii
List of Tables
Table 1-1
Table 2-1
Table 2-2
Table 2-3
Table 2-4
Table 2-5
Table 2-6
Table 3-1
Table 3-2
Table 4-1
Table 5-1
Table 6-1
Table 6-2
Table 6-3
Table 7-1
Table 7-2
Table 7-3
Table 7-4
Table A-1
FEMA P-154
List of Tables
xxv
xxvi
Table B-1
Table B-2
Table B-3
Table B-4
Table B-5
Table B-6
Table D-1
Table D-2
Table D-3
Table D-4
Table D-5
Table D-6
Table D-7
List of Tables
FEMA P-154
Chapter 1
1.1
Introduction
The FEMA P-154 Report, Rapid Visual Screening of Buildings for Potential
Seismic Hazards: A Handbook, is the first of a two-volume publication on
recommended methodology for rapid visual screening of buildings for
potential seismic hazards. The technical basis for the methodology,
including the scoring system and its development, is contained in the
companion volume, FEMA P-155 report, Rapid Visual Screening of
Buildings for Potential Seismic Hazards: Supporting Documentation
(FEMA, 2015). Both this document and the companion document are third
editions of similar documents first published by FEMA in 1988 and updated
in 2002.
The rapid visual screening (RVS) procedure has been developed to identify,
inventory, and screen buildings that are potentially seismically hazardous.
Once identified as potentially hazardous, such buildings should be further
evaluated by a design professional experienced in seismic design to
determine if, in fact, they are seismically hazardous. The RVS procedure
uses a methodology based on a sidewalk survey of a building and a Data
Collection Form, which the person conducting the survey completes, based
on visual observation of the building from the exterior, and if possible, the
interior. The two-page Data Collection Form (shown in Figures 1-1 and 1-2)
includes space for documenting building identification information,
including its use and size, a photograph of the building, sketches, and
documentation of pertinent data related to seismic performance. Based on
the data collected during the survey, a score is calculated that provides an
indication of the expected seismic performance of the building.
Once the decision to conduct rapid visual screening for a community or
group of buildings has been made, the screening effort can be expedited by
pre-field planning, including the training of screeners, and careful overall
management of the process.
Completion of the Data Collection Form in the field begins with identifying
the primary structural seismic force-resisting system and structural materials
of the building. Basic Scores for various building types are provided on the
form, and the screener circles the appropriate one. The screener modifies the
FEMA P-154
1: Introduction
1-1
Figure 1-1
1-2
FEMA P-154
Figure 1-2
FEMA P-154
RVS Level 2 Optional Data Collection Form for High seismicity region.
1: Introduction
1-3
1: Introduction
FEMA P-154
The updated RVS procedure presented in this Handbook has been formulated
to identify, inventory, and screen buildings that are potentially seismically
hazardous. The target audience for the Handbook includes (1) those agencies
or organizations that are considering conducting a rapid visual screening
program; and (2) the screeners who will conduct the evaluations. The
screeners can be civil engineers, structural engineers, architects, design
professionals, building officials, construction contractors, firefighters,
architectural or engineering students, or other individuals with general
familiarity or background in building design or construction. The
instructions in this Handbook are intended to minimize ambiguity and limit
the need for judgment, making the methodology accessible to a wide array of
potential screeners.
The RVS procedure can be implemented relatively quickly and
inexpensively to develop a list of potentially seismically hazardous
buildings without the high cost of performing a detailed seismic analysis of
every individual building. If a building receives a high score (i.e., above a
specified cut-off score), the building is considered to have adequate seismic
resistance to prevent collapse during a rare earthquake. The building score
reflects probability of collapse or partial collapse only (as defined in the
sidebar), and is not meant to be an indicator of the probability that the
building will be usable following an earthquake. If a building receives a
low score on the basis of this RVS procedure, it should be evaluated by a
design professional experienced in seismic design. On the basis of a
detailed inspection, engineering analyses, and other detailed procedures, a
final determination of the seismic adequacy and the need for retrofit can be
made. Typically, an evaluation based on ASCE/SEI 41-13, Seismic
Evaluation and Retrofit of Existing Buildings (ASCE, 2014), will be most
appropriate for those buildings that require a Detailed Structural Evaluation.
Identification of selected nonstructural hazards is included in the
methodology. Where a Detailed Nonstructural Evaluation is recommended
based on the results of the rapid visual screening, FEMA E-74, Reducing the
Risks of Nonstructural Earthquake Damage A Practical Guide, Fourth
Edition (FEMA, 2012e), can be used.
FEMA P-154
1: Introduction
Definition of Collapse
FEMA P-154 defines collapse
probability as the probability that
the building will suffer partial or
complete collapse. In that part of
the building, the gravity loadcarrying system (such as beams,
columns, floors, and shear walls)
loses the ability to carry its own
weight and the weight of whatever
else it supports. That failure leads
to severe structural deformation of
a potentially life-threatening
nature, especially falling of all or
portions of a structure. A
potentially seismically hazardous
building is one where, within the
accuracy of the RVS procedure, the
collapse probability is estimated to
be more than 1% in rare
earthquake shaking (using the
default cut-off score of 2.0). See
FEMA P-155 Section 4.4.1 for
further details.
1-5
1: Introduction
FEMA P-154
Figure 1-3
FEMA P-154
Map showing Very High, High, Moderately High, Moderate, and Low seismicity
regions in the United States. A different RVS Data Collection Form has been
developed for each of these regions.
1: Introduction
1-7
1-8
1: Introduction
FEMA P-154
FEMA P-154
1: Introduction
1-9
1-10
1: Introduction
FEMA P-154
Table 1-1
Undamaged
Buildings
FEMA P-154
ASCE/SEI 41 Tier 1
ASCE/SEI 41 Tier 2
ASCE/SEI 41 Tier 3
FEMA P-807
FEMA P-58
HAZUS
EarthquakeDamaged
Buildings
ATC-20 Rapid
ATC-20 Detailed
FEMA 352
ATC-52-4
FEMA 306
ATC-52-4
Time Required
Minutes
Hours
Days
Weeks
Relative Cost
$$
$$$
$$$$
Qualifications
1.4
FEMA P-154
1: Introduction
1-11
This third edition of FEMA P-154 comes about after the second decade of
extensive use of the procedure, which has identified several areas of
necessary enhancement. The Third Edition also takes into consideration the
evolution of computer-aided tools for more efficient implementation of the
procedure.
Major enhancements in the Third Edition include the following:
The Data Collection Form (Level 1) has been reorganized to enhance
usability.
An optional Level 2 Data Collection Form has been added. The goal of
the Level 2 screening is to obtain valuable additional information and a
more accurate assessment without a substantial increase in effort or time.
1-12
1: Introduction
FEMA P-154
FEMA P-154
1: Introduction
1-13
1.6
The Data Collection Form used for rapid visual screening has now been
extended with an optional second page, where the first page represents a
Level 1 screening and the second page represents an optional Level 2
screening. The Level 1 screening is similar to the procedure used in the
second edition of the Handbook, with the same objectives and the same
general level of expertise required from the screeners. The Level 2 screening
is more detailed than the Level 1 screening, and requires greater expertise to
complete, but it is still rapid and visual. In both levels, the screener fills out
the form and determines a score for the building. This score provides an
indication of the expected seismic performance of the building. The Level 2
score can be higher than the Level 1 score (indicating less seismic risk),
because Score Modifiers within the Level 1 screening score have more
conservative values. In some instances, the Level 2 score can be lower than
the Level 1 score, because the Level 2 screening evaluates some items in
more detail and includes some items not covered by the Level 1 screening.
For both levels, the screeners require training, and, for quality assurance
purposes, the screening program must be overseen by a design professional
knowledgeable in seismic design, evaluation, and risk assessment.
There are five versions of each form, one each for regions of Low, Moderate,
Moderately High, High, and Very High seismicity. The forms for Moderate,
Moderately High, High, and Very High seismicity regions vary only in the
values assigned to the Basic Scores and Score Modifiers and in the criteria
used to assess pounding.
1.7
Data Collection Forms have been set up to be used as paper forms with
simple arithmetic to determine a score for the building. This Third Edition
also introduces an optional use of electronic scoring. There are a number of
alternative methods that can be developed to implement electronic scoring
for RVS, as described in Chapter 6. The use of electronic scoring is intended
to improve the process by reducing errors when transferring data and to
allow for more refinement in the scoring based on site-specific seismic
hazard and soil information.
1.8
1-14
1: Introduction
FEMA P-154
Edition procedures and automates several RVS tasks. ROVER is platformindependent, currently operating through a web browser on Android, iPad,
Blackberry, Windows Phone, or any web-connected smart device
(smartphone, tablet, or other device with a browser).
Data are entered through the browser and transmitted to a secure, webaccessible server that is controlled by the user or optionally by a web service
provider. The web server places the FEMA 154 RVS data into a database
that allows for access to the data by the screener or other authorized person.
Field data can be entered into the database either directly through the smart
devices browser, or collected on paper forms and manually transcribed later
into the database through a web browser. At the time of the preparation of
the FEMA P-154 Third Edition, data entry into the web browser closely
resembled the FEMA 154 Second Edition paper form with the addition that
FEMAP-154 ROVER provides the following capabilities: geolocation,
digital photos, automated site-specific hazard and soil lookup, automatic
score calculation, integration with HAZUS-MH, ShakeCast, ATC-20, and
user data files.
FEMA P-154 ROVER can be acquired on CD from the FEMA warehouse or
downloaded from www.roverready.org. It is recommended that the reader
check the website for the latest updates on FEMA P-154 ROVER, which
may have since evolved. FEMA offers FEMA P-154 ROVER training in
addition to FEMA 154 training through NETAP.
1.9
FEMA P-154
1: Introduction
1-15
1.10
The primary advantages of the RVS method are speed and ability to use
screeners who are not necessarily structural engineers. The procedure in this
Handbook has been designed to minimize ambiguity and limit the need for
judgment by the screeners. As noted above, it fills a unique niche in the
spectrum of available seismic evaluation tools, as other tools require greater
effort, expertise, and cost. Because screening can be done quickly, large
portfolios of buildings can be evaluated in a cost effective manner. The
method has also been used by many different people and jurisdictions
throughout the United States for over 25 years. As a result, it has had a long
track record of actual use and opportunities for scrutiny and improvement,
including both the second and third edition updates.
1.10.2 Limitations
1-16
1: Introduction
FEMA P-154
The Handbook has been designed to facilitate the planning and execution of
a rapid visual screening program. It is assumed that the RVS Authority has
already decided to conduct the survey, and that detailed guidance is needed
for all aspects of the surveying process. Therefore, the main body of the
Handbook focuses on the three principal activities in the RVS procedure:
planning, execution, and data interpretation. Chapter 2 contains detailed
information on planning and managing an RVS program. Chapter 3
describes in detail how to complete the Level 1 Data Collection Form, and
Chapter 4 describes in detail how to complete the optional Level 2 Data
Collection Form. Chapter 5 provides guidance on interpreting and using the
RVS results. Chapter 6 describes how to use optional electronic scoring.
Finally, Chapter 7 provides example applications of the RVS procedure on
sample buildings.
FEMA P-154
1: Introduction
1-17
1-18
1: Introduction
FEMA P-154
Chapter 2
2.1
Once the decision to conduct rapid visual screening (RVS) for a community
or group of buildings has been made by the RVS Authority, the screening
effort can be expedited by planning and careful overall management of the
process. This chapter provides detailed information on important planning
and management aspects of conducting an RVS program, including a
description of the overall screening implementation sequence. Instructions
on how to complete the Data Collection Forms are provided in Chapters 3
and 4.
Pre-field planning, including selection and development of a recordkeeping system, development of electronic scoring tools (if desired), and
compilation and development of maps that document local seismic
hazard information,
FEMA P-154
2-1
Selection of the Data Collection Form based on the seismic hazard and
review and modification of the Data Collection Form for the individual
needs of the RVS program,
The RVS Authority determines who will manage the RVS program. The
Program Manager is responsible for defining the program scope, developing
the program budget, and overseeing implementation of the screening
program. The Program Manager must be knowledgeable about RVS and
capable of managing the project. Whether the RVS Authority decides to
manage the program itself or whether it decides to hire an outside consultant
will depend on the capabilities of the RVS Authority, as well as the size and
complexity of the program. If the RVS Authority is a building department,
for example, it may be possible for individuals within the department to
manage the program. If the RVS Authority is a state legislature, on the other
hand, it will be desirable to hire a consultant to manage the program or assign
the task to a qualified technical branch of government.
A Supervising Engineer is also required to run a successful RVS program.
The Supervising Engineer should be a local practicing structural engineer
with a background in seismic evaluation and risk assessments. The
Supervising Engineer should ideally also have experience with the FEMA
RVS methodology. If the Supervising Engineer is not knowledgeable about
the technical basis of FEMA P-154, he or she should become so by
reviewing both FEMA P-154 and FEMA P-155.
2-2
FEMA P-154
Perform pre-field
planning
Review existing
construction drawings, if
available
Figure 2-1
FEMA P-154
2-3
Defining the scope of an RVS program involves many choices. This section
presents some of the most important choices and describes the consequences
of various decisions. Decisions generally vary based on the goals and
objectives of individual programs and the resources available.
If the RVS program is to be a public or community project, the local
governing body and local building officials should formally approve of the
program plan and general procedure. Then, the public or the members of the
community should be informed about the purpose of the screening process
and how it will be carried out.
2.3.1
2-4
FEMA P-154
Table 2-1
Entity
Description
Examples
Qualifications
Responsibilities
RVS
Authority
Has authority to
conduct an RVS
program.
Program
Manager
Building department,
qualified technical
branch of government,
outside consultant.
Knowledgeable about
RVS. Capable of
managing the project.
Supervising
Engineer
Structural engineer
with a background in
seismic evaluation and
risk assessments.
Understands RVS
methodology and its
technical basis as
described in FEMA P155.
Level 1
Screener
Civil or structural
engineer, architect,
design professional,
building official,
construction contractor,
facility manager,
firefighter, architectural
or engineering student,
or another individual
with a general familiarity
or background in
building design or
construction.
Receives appropriate
FEMA P-154 training.
Level 2
Screener
Civil or structural
engineering professional,
architect, or graduate
student with background
in seismic evaluation or
design of buildings.
Receives appropriate
FEMA P-154 training.
FEMA P-154
2-5
The RVS Program Manager may decide that because of budget, time, or
other constraints, priorities should be set and certain areas within the region
should be surveyed immediately, whereas other areas can be surveyed at a
later time because they are assumed to be less hazardous. An area may be
selected because it contains an older building stock and may have a higher
density of potentially seismically hazardous buildings relative to other areas.
For example, an area with older buildings within the RVS Authority region
that consists mainly of unreinforced masonry buildings may be of higher
priority than a newer area with mostly warehouse facilities, or a residential
section of a city consisting of wood frame single-family dwellings.
2-6
FEMA P-154
The Program Manager may also decide that only buildings with certain
attributes, such as a particular building type or occupancy, will be screened.
For example, it may be decided to screen only school buildings.
2.3.3
FEMA P-154
2-7
above and below the cut-off score. Level 2 screenings of these particular
buildings may change the action required from No Detailed Stuctural
Evaluation Required to Detailed Structural Evaluation Required, or
vice versa. The added cost of the Level 2 screening per building is more
than it would be if it were performed as part of the first round of
screening because familiarization with the building, travel time, and the
Level 1 review may need to be repeated. An advantage is that the
number of detailed evaluations required may be reduced, benefiting the
overall project results.
Level 1 and Level 2 for all buildings. This option requires that all
members of the screening team be structural engineers or other qualified
professionals. If the RVS Authority has few buildings to screen or a
large budget with which to screen them, and experienced engineers are
available to perform the screenings, it may be appropriate to perform
both Level 1 and Level 2 screenings of all the buildings. Although this
approach will likely lead to the most accurate results, it will likely come
with the highest cost as well. With a fixed budget, this may mean fewer
buildings can be screened.
Some programs may wish to conduct screening programs that are as simple
as possible, and may wish to base screening scores solely on the Basic Score
associated with each building being screened, or similarly, the Minimum
Score. This simplified approach is not recommended and is not expected to
provide the RVS Authority with meaningful or accurate data on the seismic
hazard of their building stock.
2.3.4
Determining Screeners
Potential RVS screeners for Level 1 range from individuals with a general
familiarity or background in building design or construction to experienced
engineers and architects. Engineers and architects are likely to be more
costly on an hourly basis than nonprofessionals, but this cost may be offset
by the efficiency of the screener in the field, and the increased accuracy of
the screenings, which in turn reduces the Supervising Engineers effort. Of
course, if the decision has been made to perform Level 1 and Level 2
screenings of all buildings at the same time, then all the screeners must be
engineers or other qualified professionals.
Level 1 screeners should be generally familiar with the design and
construction of buildings. This could include knowledge or hands-on
experience with the structural elements of a building or historical interest in
building materials or construction practices. All Level 1 and Level 2
2-8
FEMA P-154
Electronic Scoring
The Program Manager can decide to incorporate the use of electronic scoring
as part of the RVS program. Important considerations include whether the
RVS program includes a large number of buildings and whether the
FEMA P-154
2-9
2-10
FEMA P-154
If an RVS Authority has performed screening per the Second Edition and
developed a set of scores for a portfolio of buildings, but has not yet begun to
implement a mitigation program, the RVS Authority could continue to
proceed using the Second Edition score. However, to obtain a more current
assessment of relative risk and prioritization, the RVS Authority is
encouraged to consider re-screening using the Third Edition methodology in
some situations. These include how close the existing score was to the cutoff score, whether buildings had used the mid-rise or high-rise Score
Modifiers, and if the buildings would be affected by the increased number of
seismicity regions used in the Third Edition. Other factors that may lead the
RVS Authority to consider re-screening might be new knowledge and data
on seismicity. If the Final Score for a building screened using the Second
Edition was within 0.5 points of the adopted cut-off score (i.e., it had a Final
Score of 1.5 to 2.5), then re-screening these buildings should be considered.
Buildings that used the mid-rise and high-rise Score Modifiers in the Second
Edition may also be considered for re-screening since these Score Modifiers
were eliminated in the Third Edition in favor of combining that effect with
soil type Score Modifiers. Because the Third Edition now uses updated
ground motion maps and has divided the older High seismicity region into
three smaller regions, a re-screening of buildings that used the Second
Edition High seismicity form may warrant consideration.
2.4
Many of the decisions that are made about the project scope will depend
upon budget constraints. Funds should be allocated to cover the cost of the
screenings, as well as for pre-field planning (8 to 40 hours), selection and
optional modification of the Data Collection Form and determination of key
seismic code adoption dates (8 to 12 hours), screener training (6 to 8 hours
per screener), acquisition and review of pre-field building data (15 to 75
minutes per building), quality assurance (5 to 10 minutes per building),
administrative costs (10% of total costs), development of the record keeping
system (2% to 5% of costs), and post-processing of the data (15 to 30
minutes/building). See Chapter 7 for a suggested budget for an example
RVS program.
It is expected that the field screening of each building should take about 15 to
30 minutes. If access to the interior is obtained, screenings may take an
additional 15 to 30 minutes per building. If Level 2 screenings are
performed, screenings may take an additional 5 to 15 minutes per building.
The budget should also consider travel time. If the distance between
buildings to be screened is large, then the corresponding costs will be greater.
If the number of buildings to be screened is large, there is no urgency to
FEMA P-154
2-11
completing the screening, and in-house staff who ordinarily visit the
buildings for other reasons will do the screening, the RVS Authority may
wish to integrate the data collection with the screeners day-to-day activities,
thus avoiding the cost of special trips to the buildings.
Opportunities exist to control the costs of an RVS program. Partnering with
local colleges and universities to involve students as screeners can reduce
costs. Upper division undergraduates and graduate students enrolled in
programs that emphasize the design of building structures, such as civil,
structural or architectural engineering, architecture, or construction can be
well prepared to learn and implement screening procedures.
Additionally, if a public program is being performed, training materials and
an instructor could be coordinated through the states Earthquake Program
Manager using FEMAs National Earthquake Technical Assistance Program
(NETAP).
2.5
Pre-Field Planning
2-12
FEMA P-154
FEMA P-154
2-13
2.6
There are five Data Collection Forms, one for each of the following five
regions of seismicity: Low, Moderate, Moderately High, High, and Very
High. Each Data Collection Form has a Level 1 page and an optional Level
2 page. Full-sized versions of each form are provided in Appendix B.
Electronic versions of the forms are available on ATCs website.
The structural scoring system consists of a matrix of Basic Scores (one for
each FEMA Building Type and its associated seismic force-resisting system)
and Score Modifiers to account for observed attributes that modify seismic
performance. The five forms vary from each other only in the values of these
Basic Scores and Score Modifiers and the Level 2 pounding criteria. The
Basic Scores and Score Modifiers are based on (1) time-dependent seismic
design and construction practices in the region; (2) attributes known to
decrease or increase seismic resistance capacity; and (3) maximum
considered ground motions for the seismicity region under consideration.
The Basic Score, Score Modifiers, and Final Score all relate to the
probability of building collapse, should the maximum ground motions
considered by the RVS procedure occur at the site. Final Scores typically
range from 0 to 7, with higher scores corresponding to better seismic
performance.
The scoring system in the Third Edition considers risk-targeted (MCER)
ground motions. These ground motions are consistent with the BSE-2N
ground motions specified in ASCE/SEI 41-13, Seismic Evaluation and
Retrofit of Existing Buildings (ASCE, 2014).
2.6.1
FEMA P-154
Figure 2-2
Input tool for determining site-specific seismicity using the USGS online tool (USGS,
2013a).
2-15
Figure 2-3
Output summary report from USGS online tool for determining sitespecific seismicity (USGS, 2013a).
Table 2-2
Seismicity Region
Spectral Acceleration
Response, SS (short-period,
or 0.2 seconds)
Spectral Acceleration
Response, S1 (long-period,
or 1.0 second)
Low
Moderate
Moderately High
High
Very High
2-16
FEMA P-154
One of the key issues that must be addressed in the planning process is the
determination of: (1) the year in which seismic codes were initially adopted
and enforced by the local jurisdiction; and (2) the year in which significantly
improved seismic codes were adopted and enforced (this latter year is known
as the benchmark year).
On the Very High, High, Moderately High, and Moderate seismicity forms,
Basic Scores are provided for buildings built after the initial adoption of
seismic codes, but before substantially improved codes were adopted
(benchmark year). This generally corresponds to buildings designed based
on the Uniform Building Code (UBC) in the period between 1941 and 1975.
Score Modifiers designated as Pre-Code and Post-Benchmark are
provided, respectively, for buildings built before the adoption of codes and
for buildings built after the adoption of substantially improved codes. In
Low seismicity regions, the Basic Scores have been calculated assuming the
buildings were built without consideration of seismic codes. For buildings in
these regions, the Score Modifier designated as Pre-Code is not applicable
(N/A), and the Score Modifier designated as Post-Benchmark is applicable
for buildings built after the adoption of seismic codes.
In some jurisdictions, seismic anchorage requirements for heavy cladding
have been adopted and enforced. Determining the dates that these
requirements were adopted and enforced enables the screener to determine
whether observed heavy cladding is a falling hazard or whether it is likely to
be properly braced, and therefore should not be flagged during screening as a
falling hazard.
FEMA P-154
2-17
2-18
FEMA P-154
suggested that a default code adoption year of 1992 be used for all building
types.
In addition to determining the year in which seismic codes were initially
adopted and enforced, the Supervising Engineer must also determine the
benchmark years in which substantially improved seismic codes were
adopted and enforced for the various building types. Table 2-3 provides the
benchmark years for NBC/SBC and UBC for each FEMA Building Type.
Benchmark years are also shown for the International Building Code (IBC)
which more recently combined and replaced the NBC, SBC, and UBC. The
IBC should only be used if the jurisdiction did not adopt the NBC, SBC or
UBC. If one of these codes has been both adopted and enforced in the area
being screened, the Supervising Engineer may select the benchmark years for
each building type from the column for that code. If the area has both
adopted and enforced a set of codes not listed in the table, the Supervising
Engineer must determine the benchmark years based on an understanding of
when the seismic codes were substantially improved for the various building
types. If the area has not both adopted and enforced any seismic codes, no
benchmark year is applicable. In this case, the screeners should be directed
not to use the Post-Benchmark Score Modifiers.
The Supervising Engineer must also determine the year in which anchorage
requirements for cladding were adopted and enforced. Heavy cladding
installed prior to the year noted is considered an exterior falling hazard.
Once the Supervising Engineer has determined the dates corresponding to the
initial adoption and enforcement of seismic codes and the benchmark years,
and to the initial adoption of anchorage requirements for heavy cladding,
these years should be inserted on the Quick Reference Guide in Appendix B,
repeated here as Table 2-4.
Table 2-4 has been created to facilitate the use of the Data Collection Form.
In order to consider the lapse in time that typically occurs between design
date and year built, the Supervising Engineer may choose to add a few years
to each date so that the screener can compare the year built directly to the
years on the Quick Reference Guide.
FEMA P-154
2-19
Table 2-3
RVS Benchmark Years for FEMA Building Types (based on ASCE/SEI 41-13)
Model Building Seismic Design Provisions
2-20
National Building
Code/ Standard
Building Code
Uniform Building
Code
International
Building Code
1993
1976
2000
W1
W1A
1997
2000
W2
1993
1976
2000
S1
19942
2000
S2
1997
2000
S3
2000
S4
1993
1994
2000
S5
2000
C1
1993
1994
2000
C2
1993
1994
2000
C3
2000
PC1
Tilt-up buildings
1997
2000
PC2
2000
RM1
1997
2000
RM2
1993
1994
2000
URM
MH
Manufactured housing
No benchmark year.
Steel moment-resisting frame shall comply with the 1994 UBC Emergency Provisions, published September/October
1994.
The model building codes in this table do not apply to manufactured housing. In California, relevant requirements
appeared in the Mobile home Parks Act, the California Health and Safety Code, and the California Code of
Regulations. They evolved between 1985 and 1994; the year 1995 is recommended here as the benchmark year for
California. In other states, the U.S. Department of Housing and Urban Developments Installation Standards required
tie-downs after October 2008. The year 2009 is recommended here as the benchmark year for states other than
California.
FEMA P-154
Table 2-4
W1A
W2
S1
S2
S3
S4
S5
C1
C2
C3
PC1
Tilt-up construction
PC2
RM1
RM2
URM
MH
Manufactured housing
Year Seismic
Codes
Initially
Adopted and
Enforced
Benchmark Year
when Codes
Improved
2.6.4
FEMA P-154
2-21
2-22
FEMA P-154
with an understanding of how the FEMA P-154 methodology works and how
to complete the Level 1 and Level 2 Data Collection Forms. For graduate
students, the Supervising Engineer should determine on a case-by-case basis
whether the student has the necessary knowledge and experience to perform
Level 2 screenings.
Screener information, such as names, email addresses, and other contact
information, should be archived with the survey results. This will allow for
follow-ups during the final stages of reviewing the data and also for future
references.
2.8
Information on the structural system, age or occupancy (that is, use) of the
building may be available from supplemental sources. These data, from
assessor and building department files, insurance (Sanborn) maps, and
previous studies, should be reviewed and collated for a given area before
commencing the field survey for that area. It is recommended that this
supplemental information be either written directly on the Data Collection
Forms as it is retrieved or entered into an electronic database. The advantage
of a database is that selected information can be printed directly onto Data
Collection Forms for the screeners to use in the field. Following the field
screening, data collected in the field can be entered into the database and
later used to generate reports and maps.
Some sources of supplemental information are described in Sections 2.8.1
through 2.8.7.
2.8.1
Assessors Files
Assessors files may contain information about the floor area and the number
of stories of a building. These files often also include coordinates and zip
codes that can be used to pre-populate an electronic database. The
construction type may be indicated, but should be verified during screening.
Property type and building style may also be available and can provide clues
about the specific use of the property and its exterior wall finishes. Caution
must be exercised with the age of a building retrieved from assessors files,
because usually assessors files contain the year that the building was first
eligible for taxation. Because the criteria for this may vary, the date may be
several years after the building was designed or constructed. If no other
source of information is available, this year will give a good estimate of the
period during which the building was constructed. However, this date should
not be used to establish conclusively the code under which a building was
designed. Assessors offices may also have parcel or lot maps, which may be
FEMA P-154
2-23
useful for locating sites or may be used as a template for sketching building
adjacencies on a particular city block.
2.8.2
These maps, published primarily for the insurance industry since the late
1800s, exist for about 22,000 communities in the United States. The Sanborn
Map Company stopped routinely updating these maps in the early 1960s, and
many communities have not kept these maps up-to-date. Thus, they may not
be useful for newer construction. However, the maps may contain useful
data for older construction. They can be found at the library or in some cases
in building department offices. There exist services that provide digitized
libraries of Sanborn maps with search engines and GIS capabilities.
Figure 2-4 shows a Sanborn map and photographs of the associated city
block. Building descriptions obtained from the Sanborn maps are also
included. Figures 2-5 and 2-6 show keys to identifiers on Sanborn maps.
Information found on a Sanborn map includes height of building, number of
stories, year built, thickness of walls, building size (square feet), type of roof
(tile, shingle, composite), building use (dwelling, store, apartment), presence
of garage under structure, and structural type (wood frame, fireproof
construction, adobe, stone, concrete). The structural type can be helpful in
identifying the FEMA Building Type. Although the information on Sanborn
maps may be useful, it is the responsibility of the screener to verify any
information derived from these maps in the field.
Parcel maps are also available and contain lot dimensions. If building size
information cannot be obtained from another source such as the assessors
file, the parcel maps are particularly helpful for determining building
dimensions in urban areas where buildings cover the entire lot. However,
even if the building does not cover the entire lot, it will be easier to estimate
building dimensions if the lot dimensions are known.
2-24
FEMA P-154
Figure 2-4
FEMA P-154
2-25
Figure 2-5
2-26
FEMA P-154
Figure 2-6
FEMA P-154
2-27
2.8.4
Municipal Databases
Many jurisdictions have made digital maps or databases available online for
use by the general public. Figure 2-7 shows an example from a municipal
database.
Figure 2-7
2-28
FEMA P-154
Previous Studies
Soil Information
Soil Type, also known as Site Class, has a major influence on amplitude and
duration of shaking, and thus structural damage. Generally speaking, the
greater the depth of soil to bedrock at a site, the more damaging the
earthquake motion will be. Table 2-5 provides measurable parameters that
define soil type using the site class definitions of ASCE/SEI 7-10 (ASCE,
2010).
Soil type cannot be readily identified by visual methods in the field. The soil
type should be identified during the planning stage and put into a readily
usable map format for use during RVS. During the screening, or the
planning stage, the soil type should be documented on the Data Collection
Form by checking the correct soil type, as designated by the letters A through
F.
There are various sources of data for the soil conditions at a site, including
geotechnical engineering reports. For the purpose of a rapid visual
screening, the use of geotechnical engineering reports may be impractical. In
some areas of the country, such as the San Francisco Bay Area, maps that
provide the applicable soil types are publically available and can be used to
determine site-specific soil type information.
If soil maps of the area are not available, soil type can be estimated based on
average shear wave velocity in the top 30 meters of soil, VS30. These values
FEMA P-154
2-29
have been derived using topographic slopes and using geological conditions
of the surface soil. These values are available as maps or site-specific values
from the U.S. Geological Survey web site http://earthquake.usgs.gov
/hazards/apps/vs30/ (see Figure 2-8).
Table 2-5
Soil Type/Site
Class
Standard Blow
Count1, N
Undrained Shear
Strength of the
upper 100ft1, su
A. Hard Rock
B. Rock
C. Very Dense
Soil and Soft
Rock
N >50
su>2000 psf
D. Stiff Soil
15 < N <50
N < 15
More than 10 feet of soft soil with plasticity index PI > 20,
water content w > 40%, and su < 500 psf
F. Poor Soil
Average values.
The USGS also provides a tool called OpenSHA Site Data Viewer/Plotter
(http://opensha.org/apps-SiteData) to download and plot data and maps for
site-related data from various sources.
The most commonly encountered soil types are Soil Type C and Soil Type
D. The average of these soil types is known as Soil Type CD. This average
is used as the basis of the Basic Scores. If the soil type cannot be identified
or estimated during the planning stage, Soil Type D should be assumed.
Buildings on Soil Type F cannot be screened effectively by the RVS
procedure, other than to recommend that buildings on this soil type be further
evaluated by a geotechnical engineer and design professional experienced in
seismic design.
2-30
FEMA P-154
Figure 2-8
2.8.7
VS30 map of Alaska from USGS website showing soil type (USGS,
2013b).
FEMA P-154
2-31
2-32
FEMA P-154
Field Equipment
Binoculars, if high-rise buildings are to be evaluated
Camera, preferably digital and spare batteries
Clipboard for holding Data Collection Forms
Copy of the FEMA P-154 Handbook
Copies of the Quick Reference Guide and other reference guides (see Appendix
B)
Pen or pencil
Straight edge (optional for drawing sketches)
Graph paper (optional for drawing sketches)
Flashlight for interior observations
Manual or digital measuring device to assist in measuring distances and
calculating building square footage
Smartphone or tablet computer if using electronic tools for RVS review with spare
batteries or car charger
2.11
Quality Assurance
FEMA P-154
2-33
The last step in the implementation of rapid visual screening is filing the
RVS data in the record-keeping system established for this purpose. If
FEMA P-154 ROVER is used to collect field data, then this step is
unnecessary, as the data are already stored in a database when the field data
are entered. Alternatively, if RVS data are recorded on paper they can be
transcribed into FEMA P-154 ROVERs database, which can serve as the
record-keeping system. If the data are to be stored in file folders or
envelopes containing data for each building that was screened, the process is
2-34
FEMA P-154
FEMA P-154
2-35
Chapter 3
Completing the
Level 1 Data Collection Form
3.1
Introduction
FEMA P-154
3-1
Figure 3-1
3-2
FEMA P-154
10. Determining the Final Level 1 Score, SL1 (by adjusting the Basic Score
from Step 8 with the Score Modifiers identified in Step 9); and
11. Completing the summary section at the bottom of the form (i.e., Extent
of Review, Other Hazards and Action Required).
Full-sized copies of the Level 1 Data Collection Forms (one for each
seismicity region) are provided in Appendix B. The form has been designed
to be filled out from top to bottom, with a minimum of writing (most items
can simply be checked or circled). The following sections provide
instructions and guidance on completing sections of the form from top to
bottom.
3.2
Figure 3-2
3.2.1
Building Identification
3-3
Fields are provided to document the latitude and longitude of the building
and to document SS and S1 values, which describe the site-specific ground
motion. These fields may be completed during pre-field planning. Latitude
and longitude can be determined using tools found on the internet. Once
latitude and longitude are known, S1 and SS can be determined as described in
Section 2.6.
It is not expected that the screener will use these fields while performing the
screening. However, they may be useful later for data keeping purposes or if
electronic scoring will be performed (as described in Chapter 6). If a GPS
device is available to the screener while at the building site, the screener
should verify the latitude and longitude information on the form.
3.2.3
Screener Identification
Building Characteristics
3-4
FEMA P-154
Figure 3-3
3.3.1
Number of Stories
Information pertaining to the design and code year of the building is one of
the key elements of the RVS procedure. Building age is tied directly to
design and construction practices. Therefore, age can be a factor in
determining FEMA Building Type and thus can affect the Final Score. This
information is not typically available at the site and thus should be obtained
in advance of the fieldwork.
If information on year built is not available during pre-field planning (see
Chapter 2), a rough estimate of the buildings age can be made on the basis
of architectural style and building use. Appendix D provides guidance on
determining building attributes from the street. An additional source of
obtaining the building vintage is from a dedication placard or plate. These
are more common for public buildings and usually are located near the main
entrance of the building. If the year built is only an approximation, check the
EST box to indicate the entry is estimated.
Code year is the year of the building code that was used to design the
building. The building may have been designed several years before it was
FEMA P-154
3-5
The total floor area, in some cases available from building department or
assessor files (see Chapter 2), will most likely be estimated by multiplying
the estimated area of one story by the total number of stories in the building.
The length and width of the building can be paced off in the field or
estimated during the pre-field planning stage from Sanborn or other parcel
maps or satellite images. Repeating modules on the faade of the building
can also be measured and extrapolated to determine the building dimensions.
Total floor area may be useful at a later time for estimating the value of the
building or for estimating occupancy load. If the value is an estimate, EST
should be noted.
3.3.4
3-6
FEMA P-154
3.4
Figure 3-4
Large buildings are difficult to photograph from the street and the camera
lens introduces distortion for high-rise buildings. If possible, the photograph
should be taken from a sufficient distance to include a full building elevation,
FEMA P-154
3-7
such that adjacent faces are included. Two examples are shown in Figure
3-5. A wide angle lens may be helpful. Strong sunlit faades should be
avoided, as harsh contrasts between shadows and sunlit portions of the
faade will be introduced. Lastly, if possible, the photographed elevation of
the building should not be obscured by trees, vehicles or other objects, as
they obscure the lower stories.
Figure 3-5
It is expected that screeners will most often use a digital camera. In this case,
one or two of the photographs can later be electronically added to the Data
Collection Form. Additional photographs can be saved in an electronic file
or printed and arranged on an additional page to be saved along with the
paper copy of the Data Collection Form.
3-8
FEMA P-154
3.5
FEMA P-154
3-9
3.6
Building Occupancy
The occupancy of a building refers to its use. Although it does not usually
bear directly on the structural hazard or probability of sustaining major
damage, the occupancy of a building is of interest and used when
determining priorities for mitigation.
3.6.1
Occupancy Classes
Figure 3-6
FEMA P-154
Additional Designations
FEMA P-154
3-11
If the building is any of these, the screener should circle the occupancy and
check the appropriate box. For example, when screening a school designated
as an emergency shelter, the screener will circle School and check the
Shelter box.
3.7
Soil Type
Figure 3-7
3.8
Geologic Hazards
Liquefaction, landslide potential, and surface fault rupture are three types of
geologic hazards. Any one of these three conditions can increase a
buildings risk of sustaining damage and collapse during an earthquake. If
any of these hazards are identified at a building site, a Detailed Structural
Evaluation of the building is triggered.
Geologic hazards may be identified and documented on the Data Collection
Form (see Figure 3-8) during pre-field planning.
Figure 3-8
3-12
FEMA P-154
Figure 3-9
presence of the geologic hazard has not been determined as part of the pre
field planning process and cannot be determined during the screening, the
screener should circle DNK (do not know).
3.9
Adjacency
Figure 3-10
FEMA P-154
3-13
Figure 3-11
For example, for two adjacent six-story buildings, the minimum gap is 12 in
Very High seismicity, 9 in High seismicity, 6 in Moderately High
seismicity, and 3 in Moderate or Low seismicity.
Pounding is considered when the actual gap is less than the minimum
separation gap and when at least one of three additional conditions also
applies:
1. Floors are separated vertically by more than two feet, as shown in Figure
3-12. Damage and potential collapse are considered to be more likely
when the floor mass of one building can directly impact the columns or
walls of the adjacent building.
Figure 3-12
2. One building is two or more stories taller than the adjacent building, as
illustrated in Figure 3-13. Damage may concentrate in the taller building
at the roof level of the shorter building.
3. The building is at the end of a row of three or more buildings, as
illustrated in Figure 3-14. Higher demands are imposed on the end
building when the adjacent building moves toward it and because it does
not have a building on the other side to balance the loads. Higher levels
of damage have been observed at end buildings in past earthquakes.
3-14
FEMA P-154
Figure 3-13
Figure 3-14
If the building meets any of the three criteria above, the screener checks the
Pounding box and a Detailed Structural Evaluation is triggered in the
Other Hazards and Action Required fields at the bottom of the Level 1
form. Similarly, if falling hazards from an adjacent building are identified,
the screener checks the Falling Hazards box and a Detailed Structural
Evaluation is triggered in the Other Hazards and Action Required fields
at the bottom of the Level 1 form.
3.10
Irregularities
FEMA P-154
3-15
Figure 3-15
Vertical irregularities can affect all building types. There are seven common
types of vertical irregularities, as shown in the Vertical Irregularity Reference
Guide (see Appendix B, Table B-4) and as described below:
Sloping Site. If the building is on a steep hill, as illustrated in Figure
3-16, a problem may exist because the horizontal stiffness along the
lower side may be different from the uphill side. In addition, in the up
slope direction, the stiff short columns attract more of the seismic shear
forces and may fail. For all FEMA Building Types other than light wood
frame buildings (W1), the Moderate Vertical Irregularity Score Modifier
should be applied when there is at least a one-story slope from one side
of the building to the other. For W1 buildings, the effect of a sloping site
is more severe and the Severe Vertical Irregularity Score Modifier should
be applied when there is at least a one-story slope from one side of the
building to the other.
Weak and/or Soft Story. A weak story exists when one story has less
strength (fewer walls or columns) than the story above or below it. A
soft story exists if the stiffness of one story is dramatically less than that
of most of the others. In a rapid visual screening, it is not possible to
quantitatively determine and compare the strength and stiffness of each
story. Certain observable conditions, however, provide clues that a soft
or weak story may exist. If any of the conditions described below exist,
the screener checks the vertical irregularity box on the form and indicates
the type and severity of the irregularity. If there is doubt about whether
any of the following conditions exist, it is best to be conservative and
assume that it does exist. Use an asterisk and the comment section to
explain the source of uncertainty.
3-16
FEMA P-154
Figure 3-16
FEMA P-154
3-17
Figure 3-18
Figure 3-19
o One of the stories has fewer walls or columns (or more windows and
openings) than the floor above it. In many commercial buildings, the
3-18
FEMA P-154
Figure 3-20
Figure 3-21
FEMA P-154
3-19
Figure 3-22
3-20
FEMA P-154
Figure 3-23
Short Column/Pier. When some columns (or wall piers) are shorter than
the typical columns, these shorter, stiffer columns attract more of the
lateral load. Consequently, they can experience significant damage.
Short columns can occur when there are partial height infill walls that
shorten the clear height of the column or when a slab has been added
between floor levels (e.g., for a mezzanine floor). Columns or piers that
are narrow compared to the depth of the spandrels are also a concern. In
these cases, damage concentrates in the columns rather than the beams,
increasing the potential for loss of vertical support and subsequent
collapse. Short columns or piers are considered severe vertical
irregularities. This deficiency is typically seen in older concrete and
steel buildings. Figure 3-25 shows three short column conditions.
Split Levels. This condition occurs where floor or roof levels in one part
of the building do not align with floor or roof levels in other parts of the
buildings. Damage can become concentrated in the elements that
connect the offset floor level to the vertical framing. This is considered a
moderate vertical irregularity and is shown in Figure 3-26.
FEMA P-154
3-21
Although plan irregularity can occur in all building types, the primary
concern lies with wood, tilt-up, pre-cast frame, reinforced masonry, and
unreinforced masonry construction. Damage at roof connections may
significantly reduce the capacity of a gravity load-carrying element, leading
to partial or total collapse. There are five common types of plan
irregularities, as shown in the Plan Irregularity Reference Guide (see Table
B-5 in Appendix B) and as described below:
Torsion. This condition applies when a building has a definable or good
lateral-load resistance in one direction but not the other, or when there
are major stiffness eccentricities in the seismic force-resisting system
which may cause twisting (torsion) around a vertical axis. Plan
irregularities causing torsion are especially prevalent among corner
3-22
FEMA P-154
Short columns
with reduced
height
(a)
Typical column
height
Deep Spandrels
(c)
(b)
Figure 3-25
Figure 3-26
FEMA P-154
Infill Walls
3-23
Setback
Soft Story
Figure 3-27
Building with multiple vertical irregularities: setbacks and a soft first story.
buildings, in which the two adjacent street sides of the building have
significant window openings, whereas the other two sides are generally
solid. Figure 3-28 shows an unreinforced masonry bearing wall building
with similar pier and window patterns at all stories on all sides. This
building does not have a plan irregularity. Figure 3-29 shows a common
condition where the front or street faade on the ground story has
windows such as for a store, with the walls in a C-shaped configuration.
This would be considered a plan irregularity. Figure 3-30 shows a
building with windows on two adjacent sides and more solid walls on the
other two sides. This would also be considered a plan irregularity.
Figure 3-28
3-24
FEMA P-154
Figure 3-29
Figure 3-30
FEMA P-154
3-25
3-26
Figure 3-31
Figure 3-32
Figure 3-33
FEMA P-154
Figure 3-34
Figure 3-35
FEMA P-154
3-27
Figure 3-36
3.11
Figure 3-37
3-28
FEMA P-154
Figure 3-38
FEMA P-154
3-29
RVS process (see Chapter 2). If the jurisdiction has not adopted cladding
ordinances or the building predates adopted ordinances, then it should be
indicated that heavy cladding hazards exist. If the building postdates the
adopted ordinances, then the cladding connections may be properly
designed and not pose a hazard.
Appendages. Building appendages may fall off the building during an
earthquake if improperly anchored. Such appendages include canopies
and architectural elements that add detail and decorative interest to the
faade. The concern is greater with larger elements that pose a significant
falling hazard risk. The box should be checked only if heavier
appendages exist.
Other. The screener may observe a falling hazard that does not fit into
any of the above categories. If so, the Other box should be checked
and additional details should be provided in the space next to it and in the
comments section, if needed. For example, tall and heavy roof
equipment and components near the perimeter of the building, such as
the elevated tank shown in Figure 3-37, could be considered an Other
falling hazard.
If any of the above nonstructural falling hazards exist, the appropriate box (or
boxes) should be checked. Additional details can be provided in the
comments section. Taking a photograph of the falling hazard is also
recommended. The RVS authority may later use this information to develop
a mitigation program.
3.12
3-30
FEMA P-154
deterioration; however, this issue should not be ignored. The focus should be
on examining the major elements of the seismic force-resisting system for
significant damage that could weaken the building.
The key question is whether the level of deterioration and damage rises to the
level of significant and thus triggers a Detailed Structural Evaluation under
the Other Hazards and Action Required boxes on the Level 1 form. This
is best determined by an experienced engineer, but general guidance is
provided below to assist the screener in conducting a RVS.
Ideally, the focus should be on inspecting the major components of the
seismic force-resisting system for signs of distress. Corroded steel columns,
deteriorated mortar joints in a masonry wall, concrete walls with large cracks
from previous earthquakes, and wood cripple walls with termite damage are
examples of damage and deterioration that increase the probability of
collapse of the building in a future earthquake. Deteriorated or compromised
foundation elements or significant erosion of confining soils may also reduce
the buildings ability to withstand earthquake loads.
For the purpose of the Level 1 screening, where access to the interior of the
building is limited, it is recommended that the screener focus on observable
conditions such as the following:
Is the building abandoned? An abandoned structure may have not had
adequate maintenance. As a result, there is a greater likelihood of
significant deterioration inside the structure that will not be observable
during a rapid visual screening based on an exterior review only.
Are there beams, floors, or roofs that are visibly sagging?
Are there beams or columns that are visibly broken?
Are there sloping floors or large exterior cracks that indicate significant
settlement has occurred?
Is there visible distress from prior earthquakes that has not been repaired
(i.e., the building is leaning slightly or there are large x-cracks in the
concrete or masonry walls)?
Is there visible fire damage that has not been repaired?
For wood buildings, is there extensive wood rot and/or water staining
that is visible?
For unreinforced masonry buildings, is the mortar eroding away, leaving
areas of uneven depth?
FEMA P-154
3-31
For concrete buildings, has the concrete been damaged or eroded such
that the rebar is exposed?
For steel buildings, are there members that are corroded? (Note that it is
common for steel to appear rusted; the focus should be on members that
actually have reduced cross-section due to corrosion.)
Are there visible foundation elements with large cracks?
Are foundation elements exposed due to significant erosion of adjacent
soil?
If the screener observes any of these conditions, or another example of
visible damage or deterioration, the condition should be described in the
comments section. The screener should also take additional photographs of
the condition.
Refer to Appendix F for additional guidance on assessing damage and
deterioration for common building materials.
3.13
C
omments Section
This section of the form is for recording any comments the screener may
wish to make regarding the building, occupancy, condition, quality of the
data, or unusual circumstances of any type. For example, if not all
significant details can be effectively photographed or drawn, the screener
could describe additional important information in the comments area.
Comments may be made on building features that can be seen at or through
window openings. If the screener is unsure of certain conditions, such as
whether a vertical irregularity is severe or moderate, the source of the
uncertainty should be described here. Other examples where comments are
helpful are described throughout Chapter 3. If the screener elects to provide
additional comments on a separate page, the Additional sketches or
comments on separate page box should be checked to notify the Supervising
Engineer that additional comments exist.
3.14 Identifying the FEMA Building Type and
Documenting the Related Basic Score
Two key characteristics of seismic performance are construction material
(e.g., wood, concrete) and type of seismic force-resisting-system (moment
frame, braced frame, or shear wall). A building classification system allows
buildings with similar materials and seismic force-resisting systems to be
grouped together, facilitating the fast identification of a buildings likely
strengths and vulnerabilities, and thus the buildings expected performance
during an earthquake. The FEMA P-154 RVS procedure groups the most
3-32
FEMA P-154
FEMA P-154
3-33
Following are the 17 FEMA Building Types considered in the FEMA P-154
RVS procedure. Alpha-numeric reference codes used on the Data Collection
Form are shown in parentheses.
Light wood frame single- or multiple-family dwellings of one or more
stories in height (W1)
Light wood frame multi-unit, multi-story residential buildings with plan
areas on each floor of greater than 3,000 square feet (W1A)
Wood frame commercial and industrial buildings with a floor area larger
than 5,000 square feet (W2)
Steel moment-resisting frame buildings (S1)
Braced steel frame buildings (S2)
Light metal buildings (S3)
Steel frame buildings with cast-in-place concrete shear walls (S4)
Steel frame buildings with unreinforced masonry infill walls (S5)
Concrete moment-resisting frame buildings (C1)
Concrete shear-wall buildings (C2)
Concrete frame buildings with unreinforced masonry infill walls (C3)
Tilt-up buildings (PC1)
Precast concrete frame buildings (PC2)
Reinforced masonry buildings with flexible floor and roof diaphragms
(RM1)
Reinforced masonry buildings with rigid floor and roof diaphragms
(RM2)
Unreinforced masonry bearing-wall buildings (URM)
Manufactured housing (MH)
Using available damage and loss estimation functions, a Basic Score has
been computed for each FEMA Building Type that reflects the estimated
likelihood that building collapse will occur if the building is subjected to
risk-targeted maximum considered earthquake (MCER) ground motions. For
3-34
FEMA P-154
more information about the development of the Basic Scores, see FEMA P
155 Third Edition (FEMA, 2015).
The Basic Scores are provided on the Level 1 Data Collection Form. The
scores vary by seismicity region. As such, the Very High, High, Moderately
High, Moderate, and Low seismicity forms each have a unique set of basic
scores. Figure 3-39 shows Basic Scores as they appear on the High
seismicity Data Collection Form.
Figure 3-39
In Very High, High, Moderately High, and Moderate seismicity regions, the
Basic Scores apply to buildings built after the initial adoption and
enforcement of seismic codes, but before the relatively recent significant
improvement of codes (that is, before the applicable benchmark year, as
determined during the pre-planning phase). In Low seismicity regions, they
apply to all buildings except those designed and constructed after the
applicable benchmark year, as determined during the pre-planning phase.
The identification of those years in which seismic codes were initially
adopted and later significantly improved is a key issue to be addressed in the
planning stage (as described in Chapter 2). As described later in this chapter,
the Level 1 Data Collection Form includes Score Modifiers that provide a
means for modifying the Basic Score as a function of design and construction
date.
Brief summaries of the physical characteristics and expected earthquake
performance of each of the 17 FEMA Building Types, along with a
photograph of a sample exterior view, and the Basic Scores for regions of
Very High (VH), High (H), Moderately High (MH), Moderate (M), and Low
(L) seismicity are provided in Table 3-1.
FEMA P-154
3-35
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
W1
Light wood frame
single- or multiplefamily dwellings of one
or more stories in
height
W1A
Light wood frame
multi-unit, multi-story
residential buildings
with plan areas on
each floor of greater
than 3,000 square feet
3-36
Photograph
Characteristics and
Performance
Basic Score
(VH) = 2.1
(H) = 3.6
(MH) = 4.1
(M) = 5.1
(L) = 6.2
(VH) = 1.9
(H) = 3.2
(MH) = 3.7
(M) = 4.5
(L) = 5.9
FEMA P-154
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
W2
Wood frame
commercial and
industrial
buildings with a
floor area larger
than 5,000 square
feet
Photograph
Basic Score
(VH) = 1.8
(H) = 2.9
(MH) = 3.2
(M) = 3.8
(L) = 5.7
S1
Steel momentresisting frame
(VH) = 1.5
(H) = 2.1
(MH) = 2.3
(M) = 2.7
(L) = 3.8
FEMA P-154
3-37
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
Photograph
Basic Score
(VH) = 1.4
(H) = 0 2
(MH) = 2.2
(M) = 2.6
(L) = 3.9
S2
Braced steel
frame
S3
Light metal
building
3-38
(VH) = 1.6
(H) = 2.6
(MH) = 2.9
(M) = 3.5
(L) = 4.4
FEMA P-154
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
S4
Steel frames with
cast-in-place
concrete shear
walls
S5
Steel frames with
unreinforced
masonry infill
walls
FEMA P-154
Photograph
Basic Score
(VH) = 1.4
(H) = 2.0
(MH) = 2.2
(M) = 2.5
(L) = 4.1
(VH) = 1.2
(H) = 1.7
(MH) = 2.0
(M) = 2.7
(L) = 4.5
3-39
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
C1
Concrete
moment-resisting
frames
C2
Concrete shear
wall buildings
3-40
Photograph
Basic Score
(VH) = 1.0
(H) = 1.5
(MH) = 1.7
(M) = 2.1
(L) = 3.3
(VH) = 1.2
(H) = 2.0
(MH) = 2.1
(M) = 2.5
(L) = 4.2
FEMA P-154
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
Photograph
(VH) = 0.9
(H) = 1.2
(MH) = 1.4
(M) = 2.0
(L) = 3.5
C3
Concrete frames
with unreinforced
masonry infill
walls
PC1
Tilt-up buildings
Basic Score
(VH) = 1.1
(H) = 1.6
(MH) = 1.8
(M) = 2.1
(L) = 3.8
FEMA P-154
3-41
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
Photograph
Basic Score
(VH) = 1.0
(H) = 1.4
(MH) = 1.5
(M) = 1.9
(L) = 3.3
PC2
Precast concrete
frame buildings
3-42
FEMA P-154
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
Photograph
Basic Score
RM1
Reinforced
masonry buildings
with flexible
Truss-joists support plywood and light-weight
diaphragms
concrete slab
(VH) = 1.1
(H) = 1.7
(MH) = 1.8
(M) = 2.1
(L) = 3.7
FEMA P-154
3-43
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
RM2
Reinforced
masonry buildings
with rigid
diaphragms
URM
Unreinforced
masonry buildings
3-44
Photograph
Basic Score
(VH) = 1.1
(H) = 1.7
(MH) = 1.8
(M) = 2.1
(L) = 3.7
(VH) = 0.9
(H) = 1.0
(MH) = 1.2
(M) = 1.7
(L) = 3.2
FEMA P-154
Table 3-1
FEMA Building Type Descriptions, Basic Scores, and Performance in Past earthquakes
(continued)
FEMA Building
Type
Photograph
Basic Score
(VH) = 1.4
(H) = 1.8
(MH) = 2.2
(M) = 2.9
(L) = 4.6
MH
Manufactured
housing
At the heart of the RVS procedure is the task of identifying the FEMA
Building Type from the street. Once the FEMA Building Type is identified,
the screener finds the appropriate alpha-numeric code on the Level 1 Data
Collection Form and circles the Basic Score immediately beneath it.
Each FEMA Building Type corresponds to a construction material and a type
of seismic force-resisting system. Ideally, the FEMA Building Type for each
building to be screened would be identified prior to field work through the
review and interpretation of construction documents for each building (i.e.,
during the planning stage, as discussed in Chapter 2). More commonly, the
screener must determine the FEMA Building Type in the field. When
possible, the screener should enter the building to verify the FEMA Building
Type selected. See Section 3.14.3 for additional information on interior
inspections.
FEMA P-154
3-45
3-46
FEMA P-154
Figure 3-40
Figure 3-41
FEMA P-154
3-47
Another example is where the loads are carried by both interior columns and
a perimeter wall. Both of these examples should be considered as bearing
wall structures, because lateral loads are resisted by the bearing walls.
Bearing wall structures sometimes utilize only two walls for load bearing.
The other walls are non-load-bearing and thus may have large openings.
Therefore, the openness of the front elevation should not be used to
determine the structure type. The screener should also look at the side and
rear faades. If at least two of the four exterior walls appear to be solid then
it is likely that it is a bearing wall structure.
Window openings in older frame structures can sometimes be misleading.
Since wide windows were excessively costly and fragile until relatively
recently, several narrow windows separated by thin mullions are often seen
in older buildings. These thin mullions are usually not load bearing. When
the narrow windows are close together, they constitute a large opening
typical of a frame structure, or a window in a bearing wall structure with
steel lintels.
Whereas open faades on all sides clearly indicate a frame structure, solid
walls may be indicative of a bearing wall structure or a frame structure with
solid infill walls. Bearing walls are usually much thicker than infill walls,
and increase in thickness in the lower stories of multi-story buildings. This
increase in wall thickness can be detected by comparing the wall thickness at
windows on different floors. Thus, solid walls can be identified as bearing or
non-bearing walls according to their thickness, if the structural material is
known.
Unreinforced masonry and tilt-up buildings are usually bearing-wall type,
steel buildings and pre-cast concrete buildings are usually frame type,
concrete buildings may be of either type.
There will be some buildings for which the FEMA Building Type cannot be
identified because of their faade treatment. In this case, the screener should
eliminate those FEMA Building Types that are not possible and assume that
any of the others are possible. If two or three possibilities remain, the Basic
Scores for all the possible FEMA Building Types would be circled on the
Data Collection Form. If more than three possibilities remain, the screener
circles Do Not Know and does not calculate a score for the building.
3.14.3 Interior Inspections
Ideally, whenever possible, the screener should seek access to the interior of
3-48
FEMA P-154
the building to identify, or verify, the FEMA Building Type. In the case of
reinforced masonry buildings, entry is particularly important so that the
screener can distinguish between RM1 buildings, which have flexible floor
and roof diaphragms, and RM2 buildings, which have rigid floor diaphragms
and either flexible or rigid roof diaphragms. Flexible diaphragms are
typically wood framed. Whether the floor is concrete or wood can usually be
determined from the sound of footfall or tapping with a hard object on the
floor. The screener should look in storage or mechanical rooms where
ceilings are not present to view the underside of the floor construction.
The RVS procedure does not require the removal of finish materials that are
otherwise permanently affixed to the structure. There are a number of places
within a building where it is possible to see the exposed structure. The
following are some ways to determine the structure type.
If the building has a basement that is not occupied, the first-floor framing
may be exposed. The framing will usually be representative of the floor
framing throughout the building.
If the structural system is a steel or concrete frame, the columns and
beams will often be exposed in the basement. The perimeter basement
walls will likely be concrete, but this does not mean that they are
concrete all the way to the roof.
High rise and mid-rise structures usually have one or more levels of
parking below the building. When fireproofed steel columns and girders
are seen, the screener can be fairly certain that the structure is a steel
building (S1, S2, or S4; see Figure 3-42).
Figure 3-42
FEMA P-154
3-49
Figure 3-43
FEMA P-154
more for each story, the structure type is either steel frame with
unreinforced masonry infill (S5) or concrete frame with unreinforced
masonry infill (C3). However, if the exterior walls are constructed of
thick brick masonry and there is no discernible frame system, the FEMA
Building Type may be unreinforced masonry (URM).
Pre-1930 brick masonry buildings that are six stories or less in height and
that have wood-floor framing supported on masonry ledges in pockets
formed in the wall are unreinforced masonry bearing-wall buildings
(URM).
3.14.4 Screening Buildings with More Than One FEMA Building
Type
In some cases, the screener may observe buildings having more than one
FEMA Building Type. Examples might include a wood frame building atop
a precast concrete parking garage, or a building with reinforced concrete
shear walls in one direction and a reinforced moment-resisting frame in the
other.
A building that has one FEMA Building Type in one direction and another
FEMA Building Type in the other direction should be evaluated for both
types, and the lowest Final Score should govern.
A building with one FEMA Building Type above another should be
evaluated for both types. For example, in the case of a three-story wood
frame residential structure over a one-story concrete moment frame podium,
one score can be calculated for the three-story W1A and another score can be
calculated for the one-story C1. Use the lowest score as the Final Score.
Other, more complicated scenarios also exist. If in doubt about how to
screen the building, the screener should note the complication in the
Comments section of the form and the Supervising Engineer should
determine whether the building requires a Detailed Structural Evaluation.
3.14.5 Screening Buildings with Additions
Some buildings are modified with additions after the original construction.
There are a number of aspects of building additions that need to be
considered when evaluating the significance of the addition and its effect on
the seismic resistance of the structure as a whole. The additions can be
horizontal, adding to the plan area of the building (as shown in Figure 3-44),
or vertical, adding stories to the building (as shown in Figure 3-45).
FEMA P-154
3-51
Figure 3-44
Figure 3-45
FEMA P-154
Score Modifiers
Once the screener has completed the top half of the Level 1 Data Collection
Form and identified the FEMA Building Type, he or she is ready to calculate
the buildings RVS score using the scoring matrix. The scoring matrix,
shown in Figure 3-46, provides the Basic Score and Score Modifiers related
to building characteristics or performance attributes. Building characteristics
that positively affect the performance of the building have positive Score
Modifiers and increase the score. Building characteristics that negatively
affect the performance of the building have negative Score Modifiers and
decrease the score.
The severity of the impact of the performance attribute on structural
performance varies with the FEMA Building Type; thus the assigned Score
Modifiers depend on FEMA Building Type. If a performance attribute does
FEMA P-154
3-53
Table 3-2
Response
Yes
No
See Criterion 2
Yes
No
Screening Guidance
not apply to a given FEMA Building Type, the Score Modifier is indicated
with N/A, which indicates that this Score Modifier is not applicable. Score
Modifiers associated with each building characteristic are indicated in the
scoring matrix on the Level 1 Data Collection Form.
Figure 3-46
Scoring Matrix portion of the Level 1 Data Collection Form for High seismicity.
The screener circles Score Modifiers for the building in the appropriate
column (i.e., under the reference code for the identified FEMA Building
Type). Following are instructions for when to apply each Score Modifier.
3.15.1 Vertical Irregularity
3-54
FEMA P-154
Score Modifiers are provided for Soil Type A or B and for Soil Type E. If
Soil Type A or B has been identified in the Soil Type portion of the form, the
screener circles the Soil Type A or B Score Modifier. If Soil Type E has
been identified and there are three or fewer stories, the screener circles the
FEMA P-154
3-55
Soil Type E (1-3 stories) Score Modifier. If Soil Type E has been
identified, and there are more than three stories, the screener circles the Soil
Type E (>3 stories) Score Modifier.
Basic Scores were calculated assuming Soil Type CD (the average of Soil
Type C and Soil Type D). Therefore, no Score Modifier applies when one of
these soil types occurs. There is no Score Modifier for Soil Type F because
buildings on Soil Type F cannot be screened effectively with the RVS
procedure. If the building is on Soil Type F, the screener should note that
Geologic hazards or Soil Type F are present under the Other Hazards
portion of the form, which will trigger a Detailed Structural Evaluation for
the building.
3.15.6 Minimum Score, SMIN
The Final Level 1 Score, SL1, is determined for a given building by adding
the circled Score Modifiers for that building to the Basic Score for the
building. The screener should check the sum of Basic Score and Score
Modifiers against the Minimum Score, SMIN, and use the Minimum Score if it
is larger than the sum.
The result is documented on the bottom line of the scoring matrix next to
Final Level 1 Score, SL1.
When the screener is uncertain of the FEMA Building Type, an attempt
should be made to eliminate all unlikely FEMA Building Types. If the
screener is still left with several choices, the screener calculates SL1 for all the
remaining FEMA Building Types and chooses the lowest score. This is a
conservative approach, and has the disadvantage that the assigned score may
indicate that the building presents a greater risk than it actually does.
If the screener has little or no confidence about any choice for the structural
system, as in the case of buildings with uncertain faade treatment (see
3-56
FEMA P-154
Section 3.14.2), the screener should circle DNK for FEMA Building Type,
which indicates the screener does not know. In this case, no SL1 score is
calculated.
3.17
Figure 3-47
There are also fields to document the resources that were used during pre
field planning. The soil type source, geologic hazards source, and whether
drawings were reviewed should be noted on the form prior to the field visit.
The information collected in this portion of the form reflects on the accuracy
of the buildings score. If fewer sources of information were available, it is
less likely that the FEMA Building Type and the building attributes were
accurately discerned. This information is expected to be valuable to the
Program Manager in the analysis of the RVS results and the Supervising
Engineer during the quality assurance review.
3.18
If the screener has also completed the optional Level 2 portion of the form,
the results of the Level 2 screening are recorded in this section of the Level 1
form (see Figure 3-48).
3.19
3-57
Figure 3-48
negative effect on the performance of the building. If these hazards exist, the
building may be seismically hazardous even if the Level 1 score is greater
than the designated cut-off score. Therefore, a Detailed Structural
Evaluation is required if the screener identifies that any of the following
hazardous conditions exist (see Figure 3-49).
Pounding potential (unless SL2 > cut-off, if known). This box is checked
if Pounding has been checked in the Adjacency section of the form. If
a Level 2 screening has been performed, however, and the Final Level 2
score (which considers pounding) is greater than the cut-off score, then
the box does not need to be checked.
Falling hazards from a taller adjacent building. This box is checked if
the Falling Hazards from Taller Adjacent Building has been checked in
the Adjacency section of the form.
Geologic hazards or Soil Type F. If Yes has been circled for any
geologic hazards in the Geologic Hazards section of the Data Collection
Form or if the building is on Soil Type F, the screener checks this box in
the Other Hazards section. If all of the geologic hazards are noted as
No or as DNK, the screener does not check this box.
Significant damage/deterioration. If the screener has identified any
significant damage or deterioration during the screening, the Significant
damage/deterioration to the structural system box should be checked. A
Detailed Structural Evaluation is recommended of any building with
significant damage or deterioration.
Figure 3-49
3-58
FEMA P-154
3.20
The final step to complete the Level 1 Data Collection Form is to indicate the
action required. Based on information collected during the screening, the
screener indicates whether detailed evaluation of the building is required (see
Figure 3-50).
Figure 3-50
FEMA P-154
3-59
3-60
FEMA P-154
Chapter 4
4.1
Introduction
FEMA P-154
4-1
Figure 4-1
4-2
FEMA P-154
4.2
B
uilding Information and Adjusted Baseline Score for
Level 2
The screener records the building name and the Level 1 score, SL1, at the top
of the page. The Level 1 score includes Level 1 Score Modifiers for vertical
and plan irregularities (VL1 and PL1). These Score Modifiers are removed
from the score so that the refined Level 2 Irregularity Score Modifiers (VL2
and PL2) can be used instead. To accomplish this, the screener calculates an
Adjusted Baseline Score, S, by subtracting VL1 and PL1 from SL1. This
Adjusted Baseline Score is the basis for the Level 2 score (see Figure 4-2).
Figure 4-2
For the purpose of calculating the Adjusted Baseline Score, the Minimum
Score on the Level 1 form should not be considered. The Final Level 1
Score, SL1, shall be taken as the sum of the Basic Score and all applicable
Level 1 Score Modifiers.
4.3
The middle section of the Level 2 form is shown in Figure 4-3. The
statements address vertical and plan irregularities, pounding, and seismic
retrofit. Some statements are specific to particular FEMA Building Types.
For each true statement, the screener circles the Score Modifier. For false
statements, the screener crosses out the Score Modifier. The screener notes
subtotals for VL2 and PL2. These are the effective Level 2 Score Modifiers for
vertical and plan irregularities, respectively. The screener also notes the
subtotal, M, which includes the remainder of the Level 2 Score Modifiers.
The screener can also record comments in this subtotal area.
4.3.1
Vertical Irregularities
The Vertical Irregularity section of the Level 2 form includes statements and
Score Modifiers for each of the vertical irregularities discussed and shown in
Chapter 3 and the Vertical Irregularity Reference Guide in Appendix B. The
sum of Score Modifiers in this section, subject to a cap, is the Level 2
Vertical Irregularity Score Modifier, VL2, and should be noted in the space
provided in the subtotals column. The cap for VL2 is defined on the Level 2
form and varies by seismicity region. A building with a vertical irregularity
will be more vulnerable if there is a second irregularity present; however, the
addition of Vertical Irregularity Score Modifiers (each of which represents a
FEMA P-154
4-3
Figure 4-3
Portion of the Level 2 High seismicity Data Collection Form for adjusting the baseline score.
Sloping Site
o
4-4
FEMA P-154
one side of the building to the other. The Score Modifier for this
statement is smaller than the Score Modifier for the first statement,
since a sloping site condition has a greater impact on W1 buildings
than other types of buildings.
Weak and/or Soft Story: Several statements on the form capture
conditions related to weak or soft story. Each condition is unique;
however, for certain buildings, more than one of the statements may be
true. To avoid double counting the irregularity, the screener is directed
to circle one at most. If more than one applies to the building, the
screener should select the worst case of the applicable Score Modifiers.
o W1 building cripple wall: An unbraced cripple wall is visible in
garage opening without a steel moment frame, and there is less than
8' of wall on the same line (for multiple occupied floors above, use
16' of wall minimum). This question is more specific than the
general description provided in the Vertical Irregularity Reference
Guide in Appendix B. For Level 2, even if there is an occupied story
above the garage opening, the modifier need not be triggered if a
steel moment frame is present at the opening or if there is a shear
wall (i.e., a stud wall sheathed with plywood or OSB) adjacent to the
opening. The minimum wall length increases if there are multiple
occupied floors above the opening.
o W1A building open front: There are openings at the ground story
FEMA P-154
4-5
50% of that at story above or height of any story is more than 2.0
times the height of the story above. In the case of shear walls,
length of the lateral system is the length of shear walls. In the case
of moment frames, the length of the lateral system is measured in
terms of number of bays. The exclusion of W1 is intended to avoid
double-counting of the open-front Score Modifier. An illustration of
a building that meets this definition is shown in Figure 4-4.
Figure 4-4
50% and 75% of that at story above or height of any story is between
1.3 and 2.0 times the height of the story above. This statement
represents a less severe irregularity and has a smaller Score Modifier.
An illustration of a building that meets this definition is shown in
Figure 4-5.
Setback
o Vertical elements of the lateral system at an upper story are
4-6
FEMA P-154
Figure 4-5
the interior of the building, rather than simply span between lateral
elements. If there are columns under the discontinuous upper story
walls, they can undergo large overturning forces from the walls
above and may sustain large drifts from cantilever action of the floor
diaphragm just above them.
o Vertical elements of the lateral system at upper stories are inboard
of those at lower stories. In this case, the upper story is set back
from the lower story such that the footprint of the building at the
lower story is larger than at an upper story.
o There is an in-plane offset of the lateral elements that is greater
than the length of the elements. For example, a braced frame has
braces at Story X+1 in one bay, but the brace in Story X is in a
different bay. In the case of a shear wall, the shear wall in Story X+1
does not overlap with the shear wall in Story X.
Short Column/Pier
o
C1, C2, C3, PC1, PC2, RM1, RM2: At least 20% of columns (or
piers) along a column line in the lateral system have height/depth
ratios less than 50% of the nominal height/depth ratio at that level.
These columns or piers tend to be stiffer and will undergo higher
forces and may suffer severe damage before loads are redistributed
to the other columns or piers. An illustration of a building that meets
this definition is shown in Figure 4-6.
FEMA P-154
4-7
o C1, C2, C3, PC1, PC2, RM1, RM2: The column depth (or pier
width) is less than one half of the depth of the spandrel, or there are
infill walls or adjacent floors that shorten the column. The two
conditions described in this statement are less severe than the
condition in the first short column/pier statement. An illustration of
a building that meets this definition is shown in Figure 4-7.
3'-0" deep
piers (typical)
Illustration of a building with piers that are less than one half as deep
as the spandrels.
Split Level
o There is a split level at one of the floor levels or at the roof. This
4-8
FEMA P-154
Plan Irregularities
The Plan Irregularity section of the Level 2 form includes statements and
Score Modifiers for each plan irregularity in the Plan Irregularity Reference
Guide, Table B-5 in Appendix B. The sum of Score Modifiers in this
section, subject to a cap, is the Level 2 Plan Irregularity Score Modifier, PL2,
and should be noted in the space provided in the subtotals column. The cap
for PL2 is defined on the Level 2 form and is the same value as the Plan
Irregularity Score Modifier on the Level 1 form, PL1. The cap is used as an
approximation of the expected performance of the structure. See FEMA P155 for more information about why PL2 is capped. The Level 2 plan
irregularities are as follows. See Chapter 3 for additional discussion,
including photographs and illustrations of the various types of irregularities.
Torsional irregularity: Lateral system does not appear relatively well
distributed in plan in either or both directions. (Do not include the W1A
open front irregularity listed above.) W1A with an open front is
excluded because the penalty has already been applied in the vertical
irregularity section and need not be double counted.
Non-parallel systems: There are one or more major vertical elements of
the lateral system that are not orthogonal to each other. This means
that column lines or shear walls do not meet at right angles. This is
considered to be only a moderate irregularity.
Reentrant corner: Both projections from an interior corner exceed
25% of the overall plan dimension in that direction. This is considered
to be only a moderate irregularity. Damage tends to concentrate at the
reentrant corner, but overall collapse is expected to be less likely than a
building that is torsionally irregular. An illustration of a building that
FEMA P-154
4-9
288'-0"
216'-0"
projection >
25% of overall
plan dimension
Figure 4-8
168'-0"
projection >
25% of
overall plan
dimension
4-10
FEMA P-154
Figure 4-9
Rigid wall, flexible diaphragm building with short wall at small reentrant
corner.
Redundancy
Pounding
4-11
Figure 4-10
One of the buildings is two or more stories taller than the other.
Illustrated in Figure 4-11.
The building is at the end of the block. This statement is applicable for
a building at the end of a row of three or more buildings. Illustrated in
Figure 4-12.
4-12
FEMA P-154
Figure 4-11
Figure 4-12
4.3.5
The Level 2 screening form does not have statements specific to building
additions. Instead, the effect of different addition configurations on the
seismic performance of the building is addressed by considering vertical or
plan irregularities, or some combination of these depending on the
configuration of the addition. See Section 3.14.5 for a general discussion
regarding additions and the screening approach used in Level 1.
For Level 2 screening, the Building Additions Reference Guide in Table 4-1
(also repeated in Appendix B) provides guidance for considering additions.
Based on the characteristics of the addition, the guide directs the screener to
consider the original building and addition either as a single building or as
two separate buildings and perform two separate screenings. However, if the
addition is separated from the original building with an obvious gap, the
building and the addition should be screened as two separate buildings and
both scores should be recorded. Pounding criteria in Section 4.3.4 should be
considered in this case.
In a Level 2 screening, a vertical addition is evaluated for its effect on the
presence of a vertical irregularity. A vertical addition is defined as the
addition of one or more stories to a building after the initial construction.
FEMA P-154
4-13
Table 4-1
Addition
Orientation
Type of Addition
Example
RVS Screening
Recommendation
Vertical
Evaluate as a single
building using the total
number of stories of
the original building
and addition and
indicate a setback
vertical irregularity.
Vertical setback
irregularity applies if
the area of the
addition is less than 90
percent of the area of
the story below or if
two or more walls of
the addition are not
aligned with the walls
below.
Vertical
Evaluate as a single
building using the total
number of stories of
the building plus the
addition.
Vertical
Evaluate as a single
building with another
observable moderate
vertical irregularity.
Horizontal
Evaluate as a single
building with a
torsional irregularity
plan irregularity.
If the difference in
horizontal dimension is
between 50% and
75%, indicate a
reentrant corner
irregularity. If the floor
heights are not aligned
within 2 feet, presence
of pounding is
indicated.
Horizontal
Evaluate as a single
building using the
height of the taller
building and indicate a
Pounding Score
Modifier if the heights
of the buildings differ
by more than 2 stories
or if the floors do not
align with 2 feet.
If the horizontal
dimension of the
narrower of the two
buildings along the
interface is less than
75% of the dimension
of the wider, the
reentrant corner plan
irregularity should be
indicated.
The above horizontal addition scenarios assume that there is not an obvious separation gap between the addition and the
original building.
4-14
FEMA P-154
Table 4-1
Addition
Orientation
Type of Addition
Example
RVS Screening
Recommendation
Horizontal
Evaluate a single
building with torsional
irregularity using the
FEMA Building Type
with the lower Basic
Score.
Horizontal
Evaluate as a single
building. Evaluate for
the presence of a
setback irregularity if
there is a difference in
the number of stories
and plan irregularity if
there is a difference in
horizontal dimension
of the original building
and addition along the
interface.
The above horizontal addition scenarios assume that there is not an obvious separation gap between the addition and the
original building.
FEMA P-154
4-15
The Level 2 form includes several building type specific statements. These
statements allow the Level 2 screener to modify the building score for
several conditions that are known to affect building performance.
S2 building: K bracing geometry is visible. K bracing is when the
braces intersect the column at mid-height without a horizontal member or
connection to a diaphragm. When one of the braces buckles in
compression, it can place high horizontal demands on the column, and
the column can be at increased risk of failure and collapse.
C1 building: Flat plate serves as the beam in the moment frame. In
many older concrete moment frame buildings, the flat plate floor serves
as an effective beam in the moment frame system. However, the flat
plate is not detailed like a beam with stirrups and does not have a drop
capital like a flat slab. The flat plate can thus be at increased risk of a
punching shear failure, leading to local collapse.
PC1/RM1 building: There are roof-to-wall ties that are visible or
known from drawings that do not rely on cross-grain bending. Do not
4-16
FEMA P-154
GableWall
Figure 4-13
Retrofits
In the Level 2 screening, the screener may apply a positive Score Modifier
when there is evidence that the building has been retrofitted. The Score
Modifier should only be applied when the retrofit is comprehensive. A
FEMA P-154
4-17
comprehensive retrofit is one that addresses all of the elements in the lateral
load path. Added elements that mitigate localized hazards, such as added
wall ties or parapet bracing, do not qualify for the Score Modifier.
Partial retrofits and in-progress or incremental retrofits should be noted in the
comments section, without applying the Score Modifier. If the retrofit
appears to effectively counteract an observed deficiency, the screener can
simply apply neither the deficiency nor the retrofit Score Modifier, but
mention both in the comments. The screener can recognize a retrofit that
introduces a deficiency (e.g., by introducing a torsional irregularity) by
applying the appropriate Score Modifier for the deficiency and by
commenting that it is the retrofit that produced it.
In a visual screening, it is unlikely that all elements in a lateral load path can
be observed. However, it is often possible to see the vertical elements of a
seismic retrofit, such as moment frames, braced frames, and sometimes shear
walls. Because of the cost and disruption involved, when these elements are
added, it is likely that these elements are part of a comprehensive retrofit.
For example, when braced frames are added in a URM building, it would be
expected that ties between the diaphragm and walls have been installed, as
well as parapet and gable bracing. Thus, if vertical elements in a retrofit are
observed, the Score Modifier can be applied.
Common observable retrofit measures that are indicative of a sufficiently
comprehensive retrofit include:
Added cripple wall bracing and holdowns in a W1.
Added steel moment frames in a W1 house over garage or W1A open
front building.
Added steel moment frames or braced frames in a S5, C3, or URM.
Ideally, the retrofit will be documented in available construction drawings. In
this case, the pre-field planning should identify whether the Score Modifier is
applicable. If drawings are not available but the screener observes evidence
of a retrofit in the field, the screener may use judgment about the efficacy of
the retrofit. For example, a URM building that has been retrofitted with
small braced frames adjacent to URM walls may not warrant the retrofit
Score Modifier because the braced frame likely has insufficient stiffness to
attract much load away from the URM wall.
The screener should describe the observed retrofit in the comments section.
In general, the value of the Retrofit Score Modifier has been set to be
4-18
FEMA P-154
The Final Level 2 Score, SL2, is calculated by summing the baseline score, S',
and the Level 2 Score Modifiers, VL2, PL2, and M subject to the same
minimum score that applies to the Level 1 Score. In many cases, the Level 2
screening results in a higher score than the Level 1 screening. Because
building attributes are examined in more detail in the Level 2 screening, the
Score Modifiers can be less conservative. The Final Score more accurately
represents the expected performance of the building with less built-in
conservatism.
The Final Level 2 Score is subject to the same minimum, SMIN, as the Level 1
Score.
4.5
FEMA P-154
4-19
4.5.2
Other Conditions
The bottom portion of the Level 2 form focuses on nonstructural hazards (see
Figure 4-14). Nonstructural modifiers do not strongly affect collapse
probability, thus these modifiers do not affect the building Final Score.
Figure 4-14
In areas of low seismicity, nonstructural hazards can be important for lifesafety considerations in a large rare earthquake. Heavy exterior cladding and
parapets have dislodged during past earthquakes and killed passers-by.
Nonstructural ceilings, light fixtures, heavy cabinets, and shelves can also
injure occupants and block exitways. Glass shards from untempered
windows and doors can also be hazardous, particularly if located near
emergency exits.
The statements on this portion of the form primarily relate to falling hazards,
but unlike the Level 1 form, they also include some other nonstructural
hazards as well. The screener notes whether each statement is true and
makes any relevant comments as the statements are reviewed. There are
seven statements addressing exterior falling hazards and two statements
addressing interior falling hazards. These later statements should be
addressed if access to the interior of the building is available. The statements
4-20
FEMA P-154
on the Level 2 form reflect similar falling hazards as those listed on the Level
1 form, but the Level 2 statements are more specific.
Exterior:
o There is an unbraced unreinforced masonry parapet, or unbraced
pedestrian walkways.
o There is a sign posted on the building that indicates hazardous
Interior:
o There are hollow clay tile or brick partitions at any stair or exit
corridor.
o Other observed interior nonstructural falling hazard:
FEMA P-154
4-21
Comments
A space is provided on the Level 2 form for comments. The screener should
use this area to note any special conditions that have been observed or to
indicate issues that could not be verified in the field. In particular, the
screener should describe in detail any observed damage or deterioration or
any observed other vertical or plan irregularities. If additional space is
needed for notes or sketches, the screener can use the comments section and
the sketch space on the Level 1 form or attach a separate sheet of paper.
4.8
The Final Level 2 Score, SL2, is transferred to the Level 1 form and
supersedes the Final Level 1 Score. The Level 2 screener should also
indicate on the Level 1 form the results of the Level 2 nonstructural
screening. The screener then completes or revises the Other Hazards and
Action Required portions of the Level 1 form based on these results.
4-22
FEMA P-154
Chapter 5
5.1
FEMA P-154
5-1
5.2
Having employed the RVS procedure and determined the buildings Final
Score, S, which is based on the Basic Score and Score Modifiers associated
with the various performance attributes, the RVS Authority is faced with the
question of what these S scores mean. Fundamentally, the final S score is an
estimate of the collapse probability (as described in Chapter 1) if an
earthquake occurs with ground motions called the risk-targeted maximum
considered earthquake, MCER, as described in Chapter 2. These estimates of
the score are based on limited observed and analytical data, and the
probability of collapse is therefore approximate.
A Final Score, S, of 3 implies there is a chance of 1 in 103, or 1 in 1,000, that
the building will collapse if such ground motions occur. A Final Score, S, of
2 implies there is a chance of 1 in 102, or 1 in 100, that the building will
collapse if such ground motions occur. (Additional information about the
basis for the RVS scoring system is provided in the third edition companion
FEMA P-155 Report, Rapid Visual Screening of Buildings for Potential
Seismic Hazards: Supporting Documentation.) An understanding of the
physical essence of the scoring system, as described above, will facilitate the
interpretation of results from implementation of the RVS procedure
5.3
5-2
FEMA P-154
FEMA P-154
5-3
It is important to keep in mind that the final S score relates specifically to the
probability of collapse. Use of a higher cut-off score implies less probability
of collapse, but it does not ensure that other performance objectives, such as
continued operation after an earthquake, will be met. If higher performance
objectives are desired, for example for special structures such as hospitals,
the use of a more detailed structural evaluation, along with a nonstructural
evaluation, is necessary.
Further guidance on cost and other societal implications of seismic
rehabilitation of hazardous buildings is available in other publications of the
FEMA report series on existing buildings. See FEMA 156 and FEMA 157,
Typical Costs for Seismic Rehabilitation of Buildings, 2nd Edition, Volumes
1 and 2 (FEMA, 1994a and FEMA, 1995), and FEMA 255 and FEMA 256,
Seismic Rehabilitation of Federal Buildings A Benefit/Cost Model,
Volumes 1 and 2 (FEMA, 1994b and FEMA, 1994c).
5.4
Following publication of the first edition of the FEMA 154 Handbook, the
rapid visual screening procedure was used by private-sector organizations
and government agencies to evaluate more than 70,000 buildings nationwide
(FEMA, 2002b). As reported at the FEMA 154 Users Workshop in San
Francisco in September 2000 (see second edition of FEMA 155 report for
additional information), these applications included surveys of the following
buildings: (1) commercial buildings in Beverly Hills, California; (2) National
Park Service facilities; (3) public buildings and designated shelters in
southern Illinois; (4) U. S. Army facilities; (5) facilities of the U. S.
Department of the Interior; and (6) buildings in other local communities and
for other government agencies. The results from some of these efforts are
described below.
In its screening of 11,500 buildings using the FEMA 154 RVS procedure, the
U. S. Army Corps of Engineers Civil Engineering Research Laboratory
(CERL) used a cut-off score of 2.5, rather than 2.0 (S. Sweeney, oral
communication, September 2000), with the specific intent of using a more
conservative approach. As a result of the FEMA 154 screening,
approximately 5,000 buildings had final S scores less than 2.5. These
buildings, along with a subset of buildings that had FEMA 154 scores higher
than 2.5, but were of concern for other reasons, were further evaluated in
detail using the FEMA 178 report, NEHRP Handbook for the Seismic
Evaluation of Existing Buildings (FEMA, 1992). Results from the
subsequent FEMA 178 evaluations indicated that some buildings that failed
the FEMA 154 RVS procedure (that is, had scores less than 2.5) passed the
5-4
FEMA P-154
FEMA 178 evaluations and that some that passed the FEMA 154 RVS
procedure (with scores higher than 2.5) failed the FEMA 178 evaluation (that
is, were found to have inadequate seismic resistance). This finding
emphasizes the concern identified at the beginning of this chapter that the use
of FEMA 154 may not always identify potentially earthquake hazardous
buildings as such, and that buildings identified as potentially hazardous may
prove to be adequate.
Other conclusions and recommendations pertaining to the use of the FEMA
154 RVS procedure that emanated from these early applications included the
following:
Involve design professionals in RVS implementation whenever possible
to ensure that the seismic force-resisting systems are correctly identified
(such identification is particularly difficult in buildings that have been
remodeled and added to over the years);
Conduct intensive training for screeners so that they fully understand
how to implement the methodology, in all of its aspects;
Inspect both the exterior and, if at all possible, the interior of the
building;
Review construction drawings when available as part of the screening
process;
Review soils information prior to implementation of the methodology in
the field; and
Interpret the results from FEMA 154 screenings in a manner consistent
with the level of resources available for the screening (for example, cutoff scores may be dictated by budget constraints).
Most of these recommendations were incorporated into the second edition of
the Handbook. In this Third Edition, the recommendation to involve a
design professional in RVS implementation has been further stressed with
the introduction of the Supervising Engineer. See Chapter 2 for more details.
More recent uses of the RVS procedure include several efforts in Oregon and
Utah.
The state of Oregon has conducted many assessments of the vulnerability of
facilities using the rapid visual screening method based upon the second
edition of FEMA 154. One example is for Clackamas County where all the
schools and emergency facilities were screened, which helped lead to a
statewide assessment (Wang et al., 2004).
FEMA P-154
5-5
FEMA P-154
FEMA P-154
5-7
5.5
5.5.1
Overview
As noted in the foreword to the first edition of FEMA 155, The publication
is one of a series that FEMA is sponsoring to encourage local decision
makers, the design professions, and other interested groups to undertake a
program of mitigating risks that would be posed by existing hazardous
buildings in case of an earthquake.
Perhaps one of the primary reasons for performing rapid visual screening of
buildings is to advocate for greater seismic safety in our communities. An
uninformed public cannot be expected to make decisions about risk without
fully realizing the impact inaction may have on the quality of life following
an earthquake. Recognizing the potential impacts and planning to reduce
them only comes when good information is available and that understanding
starts with rapid visual screening.
Finding support for performing RVS can often be a challenging task.
Identifying vulnerable buildings in communities is sometimes seen as a
liability with the inherent responsibility to fix or eliminate the danger. But
these concerns can often be assuaged by noting that the RVS survey points
toward the need for additional investigation to better determine the
vulnerability of the identified buildings. If public buildings are the focus of
the survey, specific language can often be added to legislation that
effectively limits the liability associated with identifying dangerous buildings
and creates a form of governmental immunity from lawsuits.
If surveys are performed on public buildings, strong consideration should be
given to making the information directly available to the general public.
When doing so, the information should be clearly explained, including the
limitations of the assessment and that it is a first step in identifying
vulnerable buildings.
Rapid visual screening can provide better information when developing
seismic rehabilitation programs that benefit communities in becoming more
resilient to the effects of earthquakes. Surveys will help quantify the
problem and help communities make informed decisions about their risk.
Rehabilitation programs will inevitably require accepting some portion of
risk and knowing the potential extent of damage to buildings through RVS
will provide support for those decisions.
Pilot programs that sample a small percentage of buildings have been
effectively used in Utah to promote the need for an inventory of all Utah
5-8
FEMA P-154
Audience Types
FEMA P-154
5-9
5-10
FEMA P-154
Rapid visual screening can be a valuable tool for supporting efforts to raise
awareness about building vulnerabilities in communities. Information can be
gathered both in advance of seeking support and as the result of wanting to
better assess and plan for the needs for mitigation efforts. The following
examples illustrate these two approaches.
The findings of the 2010 pilot study conducted by USSC and SEAU
surveying school buildings were used in legislative committee hearings to
help substantiate the need for a complete survey. As a result, FEMA
provided a grant to survey 2,500 additional buildings in the county.
In Oregon, the results of the RVS program directed by DOGAMI in 2005
were later used to create a grant program for local communities to strengthen
FEMA P-154
5-11
Once an RVS program has helped establish the need for consideration of
seismic vulnerabilities in a community, there are a number of additional tools
available to promote mitigation efforts.
The Seismic Rehabilitation Cost Estimator (SRCE) provides a simple way to
estimate approximate rehabilitation costs by answering a series of questions
about the building(s) being evaluated. This can be valuable in determining
orders of magnitude costs when discussing the implications of a mitigation
program.
When advocating for seismic mitigation programs, actual rehabilitation costs
are often stumbling blocks if perceived as single stage expenses. FEMA has
developed the Incremental Seismic Rehabilitation series of documents to
address alternative ways to integrate seismic improvements over extended
periods of time by integrating seismic work into regular and planned
maintenance and improvement projects.
The SRCE and the Incremental Seismic Rehabilitation series of documents
are both available from FEMAs website (www.fema.gov/earthquake).
When RVS data include information on numbers of occupants and square
footage, FEMAs HAZUS Advanced Engineering Building Module (FEMA,
2003) could further help characterize impacts into estimated casualties, as
well as structural and nonstructural economic losses. This information
greatly helps in translating vulnerability into easily understood potential
impacts and can be used to further prioritize additional evaluation and
mitigation strategies.
A further step could involve use of FEMA P-58, Seismic Performance
Assessment of Buildings, Volume 1 The Methodology (FEMA, 2012d), to
evaluate selected buildings that do not meet the cut-off score to provide
refined estimates of deaths and injuries, repair and replacement costs, repair
time and post-earthquake safety evaluation tagging or placarding status.
Additionally, advocates may consider other resources such as FEMA state
earthquake programs that support funding of RVS surveys to determine
seismic vulnerability.
5-12
FEMA P-154
5.6
FEMA P-154
5-13
Rapid visual screening data can be used to establish building inventories that
characterize a communitys seismic risk. For example, RVS data could be
used to improve the HAZUS characterization of the local inventory, which
has a default level based on population, economic factors, and regional trends
by importing RVS data for use in the HAZUS Advanced Engineering
Building Module. Similarly, RVS data could be incorporated directly into a
communitys GIS, allowing the community to generate electronic and paper
maps that reflect the building stock of the community. Electronic color
coding of the various types of buildings under the RVS Authority, based on
their ultimate vulnerability, allows the community to see at a glance where
the vulnerable areas of the community are found. This information can then
inform comprehensive pre-earthquake evaluation and mitigation efforts.
5-14
FEMA P-154
5.6.3
FEMA P-154
5-15
Matrix of Recommended Personnel and Material Resources for Various FEMA P-154 RVS
Applications
RVS Manager
and
Supervising
Engineer
Application
5-16
Trained
Screeners
Screening
Equipment
and
Supplies
Accumulated
Building
Information
Computerized
Record
Keeping
System
GIS
FEMA P-154
Chapter 6
6.1
Introduction
The major difference in the scores between the paper form and an electronic
scoring approach will depend primarily on the difference in seismic hazard at
a specific site and the median response values that were used to generate the
Basic Scores and Score Modifiers on the paper forms. In some geographic
areas, the use of electronic scoring may result in an increase in the building
score compared to the values provided on the paper RVS forms for the
applicable region of seismicity; in many areas, however, the building score
will go down. The use of electronic scoring can make the difference between
a building having a Final Score below or above the cut-off score. Example
comparisons are provided in Section 6.5.
6.3
6-1
the median response value of seismicity for each of these five regions. Many
sites will have a seismic hazard that is different than one of the median
values. For these sites, the difference between the median seismic hazard
and the site-specific seismic hazard will probably affect the score for a given
building. A building that passes the rapid visual screening under the
assumption of the median shaking for the region might not pass when
accounting for local seismicity (an overlooked life-safety problem). Or the
reverse might be true: the building does not pass the RVS methodology, but
it would, if the site-specific hazard was used (an efficiency problem, because
now a Detailed Structural Evaluation is required).
The purpose of the electronic scoring methodology is to use site-specific
seismic hazard data to produce a refined Basic Score. There are many
sources of data available that can be used to develop site-specific information
for providing a better estimate of the seismic hazards for a given building, as
described in the following sections. The geographically referenced data are
generally publically available. A sites geolocation can be estimated as
precisely as ten feet with commonly available Global Positioning System
(GPS) technology. Site-specific seismic hazards can be accurate within
perhaps a few hundred feet, using publically available data from the U.S.
Geological Survey (USGS), whereas the location upon which the median
hazard is based may be dozens or more miles away. The available sitespecific hazard precision is generally not necessary as part of a rapid visual
screening, but given the ease with which site-specific soil and hazard can be
estimated with an electronic system, it seems unnecessary to add location
error to other uncertainties in the scoring system.
Optional electronic scoring is not intended as a substitute for more detailed
building evaluations. Electronic scoring is still considered part of a rapid
visual screening methodology. As such, the precision of the results should
be considered to be only moderately more accurate than scores obtained
using the paper-based forms described in Chapter 3. Where large differences
occur, it is typically when a site is near the transition from one seismicity
region to another and thus the assumption of the median seismicity for the
region is less accurate.
Electronic scoring can be implemented using various available technologies
and can be utilized as part of pre-field activities, during the field screening,
or as part of the post-field activities. Some approaches to implementation are
described below in Section 6.4.
6-2
FEMA P-154
6.3.1
Site-Specific Seismicity
Soil conditions at a site will affect the seismic shaking at a site. There are
various sources of data for determining the soil type at a site, including
geotechnical engineering reports. As discussed in Chapter 2, VS30 values can
also be used to determine soil type. These values can be obtained from the
U.S. Geological Survey web site or by using a site data viewer application
distributed by OpenSHA at http://www.opensha.org/apps.
6.4
FEMA P-154
6-3
could be done manually or with the aid of some form of technology, such as
a smartphone, tablet, or laptop computer.
A post-field approach to implementing electronic scoring could involve the
use of a database or spreadsheet when compiling the RVS screening results.
With this approach, the RVS forms would be filled out in the field using the
standard paper forms and then the results would be compiled electronically
after the field screening. The database, spreadsheet, or other electronic data
file in which the data are compiled could be programmed to determine the
site-specific seismicity and soil class for the building based on the longitude
and latitude. The Basic Score and Score Modifiers determined using the
paper form during the field screening could then be updated using the
electronically-calculated score or other means and then the Final Score
would be re-calculated.
The implementation of electronic scoring could also be accomplished using a
methodology that determines the seismic hazard and soil class while at the
site and then calculates a Basic Score, Score Modifiers, and Final Score
while at the building. This approach requires the use of an electronic device
that has been programmed to perform the necessary calculations and
determine the site location using a GPS device or a service that geolocates
the building based on its street address. An example of such an approach is
FEMA P-154 ROVER (FEMA, 2014). Alternative hardware and software
can also be developed to provide similar functionality as needed. As a
minimum, the hardware and software needs to be able to locate the site,
determine the seismic hazard and soil type based on the sites location, adjust
the Basic Score and Score Modifiers for the building based on the sitespecific hazards and building height, and sum the applicable Score Modifiers
to the Basic Score to produce a Final Score.
6.4.1
Any approach chosen for electronic scoring should follow the general steps
described below.
1. Determine the site-specific risk-targeted Maximum Considered
Earthquake (MCER) ground motion response acceleration values for Ss
(5%-damped, spectral response acceleration parameter at short period)
and S1 (5%-damped spectral response acceleration parameter at a period
of 1 second).
2. Use Table 6-1 and Table 6-2 to calculate the site coefficients, Fa and Fv,
for the short-period acceleration and the 1-second period acceleration on
Soil Type CD.
6-4
FEMA P-154
Table 6-1
Site Coefficient Fa
Mapped Spectral Response Acceleration at Short Period
Soil Type
SS 0.25
SS = 0.5
SS = 0.75
SS = 1.0
SS 1.25
1.2
1.2
1.1
1.0
1.0
CD
1.4
1.3
1.15
1.05
1.0
1.6
1.4
1.2
1.1
1.0
Table 6-2
Site Coefficient Fv
Mapped Spectral Response Acceleration at One-Second Period
Soil Type
S1 0.1
S1 = 0.2
S1 = 0.3
S1 = 0.4
S1 0.5
1.7
1.6
1.5
1.4
1.3
CD
2.05
1.8
1.65
1.5
1.4
2.4
2.0
1.8
1.6
1.5
(6-2)
FEMA P-154
6-5
6.4.2
The foregoing approach is reasonable for all site conditions, but if the user
desires additional accuracy for sites whose Soil Type is in the higher half of
the range of VS30 for Soil Type C (1850 ft/sec VS30 < 2500 ft/sec) or in the
lower half of the range of VS30 for Soil Type D (600 ft/sec VS30 < 900
ft/sec), an alternative approach is offered here.
1. Determine the site-specific risk-targeted Maximum Considered
Earthquake (MCER) ground motion response acceleration values for Ss
(5%-damped, spectral response acceleration parameter at short period)
and S1 (5%-damped spectral response acceleration parameter at a period
of 1 second).
2. Use Tables 6-1 and 6-2 to calculate the site coefficients, Fa and Fv, for
the short-period acceleration and the one-second period acceleration on
Soil Type CD, and for the sites Soil Type, denoted here by Fa* and Fv*.
3. Calculate the MCER, 5%-damped spectral response acceleration
parameter at short periods adjusted for Soil Type CD, SMS, and the
MCER, 5%-damped spectral response acceleration parameter at a period
of 1 second adjusted for Soil Type CD, SM1, using Equations 6-1 and 6-2.
4. Calculate the MCER, 5%-damped spectral response acceleration
parameter at short periods adjusted for sites Soil Type, SMS*, and the
MCER, 5%-damped spectral response acceleration parameter at a period
of 1 second adjusted for the sites Soil Type, SM1*, using the following
equations.
(6-3)
SMS* = Fa* SS
SM1* = Fv* S1
(6-4)
6-6
FEMA P-154
in the ranges 1850 ft/sec VS30 < 2500 ft/sec (higher-VS30 Soil Type C) or
600 ft/sec VS30 < 900 ft/sec (lower-VS30 Soil Type D), do not apply a
Score Modifier for Soil Type.
6.5
Building
Type
Seismicity
Location
Paper-Based
Final Score
Electronic
Final Score
S1
Moderately High
Sacramento, CA
2.3
2.4
S1
High
Memphis, TN
2.3
2.2
S2
Low
Boston, MA
3.9
3.8
S2
Very High
Emeryville, CA
1.4
1.6
C3
High
Memphis, TN
1.4
1.3
C3
Low
Boston, MA
3.5
3.4
RM1
Very High
Emeryville, CA
1.1
1.3
RM1
Moderate
New York, NY
2.1
2.3
URM
Moderate
New York, NY
1.7
2.0
URM
Moderately High
Sacramento, CA
1.2
1.3
Table 6-3 compares the Final Scores computed using both the forms and the
electronic scoring methodology for five different building types located in
six different cities with Soil Type CD, representing ten different city/building
type combinations. The results show that for six of the ten city/building type
combinations, the Final Scores increased; for four of the city/building type
combinations the scores decreased, and none stayed the same. The
differences are due to the difference between the actual seismicity at the
cities and the median seismicity for which the Basic Scores were derived and
the effects of site conditions.
FEMA P-154
6-7
6-8
FEMA P-154
Chapter 7
7.1
Introduction
The city council of Anyplace, USA tasked the local building department with
conducting an RVS program to identify all buildings in the city, excluding
detached single-family and two-family dwellings, that are potentially
seismically hazardous and that should be further evaluated by a design
professional experienced in seismic design (the principal purpose of the RVS
procedure). It was understood that, depending on the results of the RVS
program, the city council might adopt future ordinances that establish policy
on when, how, and by whom low-scoring buildings should be evaluated and
on future seismic rehabilitation requirements. It was desired that the results
from the RVS program be incorporated in the citys geographic information
system (GIS).
In this scenario, the city council was the RVS Authority. The head of the
local building department acted as the Program Manager. An experienced
structural engineer from a local firm was selected to serve as the Supervising
Engineer. The city council was able to provide a budget of $120,000 for the
program.
7.2.1
FEMA P-154
7-1
some of the buildings are at least 100 years old. In order to perform
screenings of all 1,000 buildings as quickly as possible, and within the given
budget, Level 2 screenings were not performed as part of this program. The
Program Manager also decided to focus on the downtown sector of Anyplace
during the initial phase of the RVS field work, and to expand to the outlying
areas later.
The Program Manager tasked the Supervising Engineer with selecting and
reviewing the Data Collection Form, determining the code and benchmark
years for the city, and performing quality assurance of the completed forms.
The Supervising Engineer was tasked with attending the training and being
available during the field screening to advise the screeners.
Three building department staff members, as well as 15 architectural and
engineering undergraduates from the local university, received FEMA P-154
training and then served as screeners.
The Program Manager explored possible sources of information about the
citys buildings and decided to commit resources to extracting data from the
citys existing GIS database, permitting files, Sanborn maps, and any
available construction drawings. The information gathered from these
sources during pre-field data acquisition reduced the amount of field time
required and increased the accuracy of the screenings.
An electronic database was created for the RVS program. Pre-field data were
entered into the RVS database and then extracted and placed on Data
Collection Forms to be used by the screeners in the field. After the field
screening, the data collected in the field were entered back into the RVS
database. A building department staff member was tasked with creating the
database and automating the transfer of the pre-field data onto the Data
Collection Forms to be printed and used in the field.
Electronic scoring was not used.
7.2.2
Costs to conduct the RVS program were estimated per Table 7-1. The entire
process was scheduled to take 6 months.
7.2.3
During the pre-field planning process, the Program Manager confirmed that
the citys existing GIS was capable of being expanded to include RVSrelated information and results. A member of the building departments staff
extracted street addresses and parcel numbers for most of the properties in
7-2
FEMA P-154
Table 7-1
Task
Task Description
Program
Manager
$120/hr
Structural
Engineer
$150/hr
Cost
Staff
$60/hr
Task
Cost
40
$6,000
40
$2,400
250
$15,000
150
$9,000
50
$3,000
40
$2,400
24
120
$3,600
16
40
160
880
$17,520
24
120
24
120
24
120
24
120
24
120
24
120
80
80
20
100
$17,400
400
Subtotal Cost
$24,000
$100,320
Screeners
(no cost1)
$10,032
$110,352
Volunteer student screeners are assumed. Alternatively, if screeners are paid at a rate of $60/hr, the total program cost
increases to $176,352.
FEMA P-154
7-3
the city (developed earlier from the tax assessors files) from the existing
GIS and imported them into a standard off-the-shelf electronic database as a
table. See Figure 7-1 for a screen capture of GIS display showing parcel
number and other available information for an example site.
Figure 7-1
To facilitate later use in the GIS, the street addresses were subdivided into
the following fields: the numeric part of the address; the street prefix (for
example, North); the street name; and the street suffix (for example,
Drive). A zip code field was added, zip codes for each street address were
obtained using zip code lists available from the U.S. Postal Service, and these
data were also added to the database. This process yielded 950 street
addresses, with parcel number and zip code, and established the initial
information in Anyplaces electronic Building RVS Database. Additional
fields were added to this new database for RVS-related information such as
date of construction, number of stories, soil type, FEMA Building Type, and
RVS score.
Next, the Supervising Engineer confirmed that sufficient soil information
was available from the State Geologist to develop an overlay for the GIS
containing soils information for the entire city. The Supervising Engineer
concluded that GIS overlays for geologic hazards were not warranted since
the city included only isolated pockets of low liquefaction potential, and no
areas with landslide or fault rupture potential.
7-4
FEMA P-154
7.2.4
Figure 7-2
USGS web page showing SS and S1 values for MCER ground motions
(USGS, 2013a).
These values were compared to the criteria in Table 2-2. It was determined
that the ground motions at the city center meet the High seismicity criteria
for both short-period and long-period motions (that is, 1.372g is greater than
1.000g and less than 1.500g for the 0.2 second [short-period] motions, and
0.497g is greater than 0.400g and less than 0.600g for the 1.0 second [long-
FEMA P-154
7-5
7-6
FEMA P-154
Figure 7-3
FEMA P-154
7-7
Table 7-2
Year Seismic
Codes Initially
Adopted and
Enforced
Benchmark Year
when Codes
Improved
W1
1941
1976
W1A
1941
1997
W2
1941
1976
S1
1941
1994
S2
1941
1997
S3
1941
None
S4
1941
1994
S5
1941
None
C1
1941
1994
C2
1941
1994
C3
1941
None
PC1
Tilt-up construction
1973
1997
PC2
1941
None
RM1
1941
1997
RM2
1941
1994
URM
None
None
MH
Manufactured housing
1941
None
1967
RVS Database for each of these attributes, and data were added to the
appropriate records (based on parcel number) in the database; in the case of
structure type, the entry included an asterisk to denote uncertainty. If an
address was missing in the database, a new record containing that address
and related data was added. On average, 30 minutes per building were
required to extract the correct information from the permitting files and insert
it into the electronic database.
The citys librarian provided copies of available Sanborn maps, which were
reviewed to identify information on number of stories, year built, building
size (square footage), building use, and limited information on structural type
for approximately 200 buildings built prior to 1960. These data were added
to the appropriate record (based on address) in the Building RVS Database;
in the case of structure type, the entry included an asterisk to denote
uncertainty. If an address was missing in the database, a new record
containing that address and related data was added. For this effort, 45
7-8
FEMA P-154
Fortuitously, the city had retained many of the microfilm or pdf copies of
building construction documents submitted with each permit filing during the
last 30 years. Copies of these construction documents were available for 100
buildings. Building department plans examiners reviewed these documents
to verify, or identify, the FEMA Building Type for each building. Any new
or revised information on structure type derived as part of this process was
then inserted in the Building RVS Database, in which case previously
existing information in this field, along with the associated asterisk denoting
uncertainty, was removed. On average, this effort required approximately 30
minutes per plan set, including database corrections.
7.2.7
The screeners for the RVS program included staff from the building
department and architectural and engineering students from the local
university. All of these screeners underwent training obtained through
FEMAs National Earthquake Technical Assistance Program (NETAP). The
Program Manager and the Supervising Engineer attended the training as well.
The training was conducted in a classroom setting and consisted of the
following: (1) discussions of FEMA Building Types and how they behave
when subjected to seismic loads; (2) how to use the Level 1 Data Collection
FEMA P-154
7-9
Form and the Reference Guides; (3) a review of the Basic Scores and Score
Modifiers; (4) how to identify building irregularities; (5) what to look for in
the field; (6) how to account for uncertainty; and (7) an exercise in which
screeners were shown interior and exterior photographs of buildings and
asked to identify the FEMA Building Type and vertical and plan
irregularities. The training class also included focused group interaction
sessions, principally in relation to the identification of structural systems and
irregularities using exterior and interior photographs. Screeners were also
instructed on items to take into the field.
7.2.8
Figure 7-4
In those instances where the FEMA Building Type was included in the
database, this information was noted next to the parcel number, with an
asterisk if still uncertain.
Where drawings were reviewed, the drawings reviewed Yes box was
checked. Soil Type and Geologic Hazards sources were noted as State
Geologist.
7-10
FEMA P-154
Field screening of all 1,000 buildings was scheduled to occur over the course
of eight (nonconsecutive) days. For the first two days, fifteen student
volunteer screeners worked in five teams, each led by the Program Manager,
the Supervising Engineer, or one of the three building department staff
members. Each of these five team leaders was experienced in identifying the
FEMA Building Type and was able to provide oversight and additional
training of the student volunteers during these first days. For the following
six days, the screeners worked individually. The Supervising Engineer
remained available throughout the field screening to advise and consult.
The Data Collection Forms, including blank forms for use with buildings not
yet in the Building RVS Database, were distributed to the RVS screeners
along with their RVS assignments (on a block-by-block basis). Screeners
were advised that the information printed on the form from the database
should be verified in the field, particularly items denoted with an asterisk.
Prior to field work, each screener was reminded to complete the Data
Collection Form at each site before moving on to the next site, including
adding his or her name as the screener and the screening date (in the building
identification section of the form).
Following are several examples illustrating rapid visual screening in the field
and completion of the Data Collection Form. Some examples use forms
containing relatively complete building identification information, including
FEMA Building Type, obtained during the pre-field data acquisition and
review process; others use forms containing less complete building
identification information; and still others use blank forms completely filled
in at the site.
7.2.8.1
Upon arriving at the site, the screener observed the building as a whole
(Figure 7-5) and began the process of verifying the information in the
building identification portion of the form (upper right corner), starting with
the street address. The screener added her name and the date and time of the
field screening to the building identification portion of the form.
The FEMA Building Type (S2, steel braced frame) was verified by looking
at the building with binoculars (see Figure 7-6). The number of stories (10)
was confirmed by inspection, and the year built noted on the form (1986)
appeared appropriate. The base dimensions of the building were estimated
by pacing off the distance along each face, assuming 3 feet per stride,
resulting in the determination that it was 75 feet by 100 feet in plan. On this
FEMA P-154
7-11
basis, the listed square footage of 76,000 square feet was verified as correct.
No additions to the building were observed.
7-12
Figure 7-5
Figure 7-6
FEMA P-154
Sketches of the plan and elevation views of the building were drawn in the
Sketch portion of the form. Several digital photographs were taken of the
building, to be added to the form later.
The building use (office) was circled in the Occupancy portion of the form.
No adjacent buildings were observed.
The next step for the screener was to identify any vertical or plan
irregularities. The screener consulted the Vertical and Plan Irregularity
Reference Guides and found that none of the listed irregularities applied to
the building being screened.
No falling hazards were observed, as glass cladding is not considered as
heavy cladding.
The next step in the process was to circle the appropriate Basic Score and the
appropriate Score Modifiers. Having verified the FEMA Building Type as
S2, the screener circled S2 on the form along with the Basic Score beneath
it. No irregularities were observed, so none of the irregularity modifiers was
circled. The screener checked the Quick Reference Guide and found that the
building did not qualify for the Post-Benchmark modifier. Since the building
is on Soil Type D, no soil modifiers were applied. The Final Level 1 Score,
SL1, was determined to be 2.0.
The screener completed the Extent of Review portion of the form, indicating
that she viewed the exterior of the building from all sides, but was not able to
enter the building to inspect the interior. The soil type source and geologic
hazards source were entered during the pre-field phase.
The screener noted that no Level 2 screening was performed. She then
reviewed the Other Hazards portion of the form and did not identify any
other hazards that might trigger a detailed evaluation. Because this score was
equal to the cut-off score of 2.0, the screener checked the Yes box in the
Detailed Structural Evaluation Required field and No in the Detailed
Nonstructural Evaluation Required field as no nonstructural hazards were
identified.
Figure 7-7 shows the completed form for 3703 Roxbury, including the
photograph that was added digitally at a later date.
7.2.8.2
Upon arrival at the site, the screener observed the building as a whole (Figure
7-8). Unlike Example 1, there was little information in the building
FEMA P-154
7-13
Figure 7-7
7-14
FEMA P-154
Figure 7-8
identification portion of the form (only street address, zip code, parcel
number and soil type were provided). The screener determined the number
of stories to be 12and the building use to be commercial and office. He
paced off the building plan dimensions and estimated the plan size as 58 feet
by 50 feet. Based on this information, the total square footage was estimated
to be 34,800 square feet (12 stories by 50 feet by 58 feet), and the number of
stories, use, and square footage were written on the form. Based on a review
of information in Appendix D of this Handbook, the construction era was
estimated to be in the 1940s. The screener wrote in the year of construction
as 1945 and checked the EST box to note that the date was estimated. The
screener circled both Office and Commercial to indicate the observed
occupancies.
The screener noted that an adjacent 11-story building was separated from the
building being screened by only 12 inches. The screener determined the
minimum separation gap for pounding per the Level 1 Pounding Guide (1 1/2
inches per story for 11 stories equals 16.5 inches) and found that the actual
separation was less than the minimum. In addition, the building being
FEMA P-154
7-15
screened was at the end of the block. Based on these two conditions, the
screener checked the Pounding box in the Adjacency section of the form.
The screener consulted the Vertical and Plan Irregularity Reference Guides
and determined that the four individual towers extending above the base
represented an out-of-plane offset. The screener noted this severe vertical
irregularity,
Sketches of the plan and elevation views of the building were drawn in the
Sketch portion of the form. The cornices at roof level were observed, and
entered on the form.
Noting that it was a 12-story building, a review of the material in Table D-6
(Appendix D), indicated that the likely options for FEMA Building Type
were S1, S2, S5, C1, C2, or C3. On more careful examination of the building
exterior with the use of binoculars (see Figure 7-9), it was determined the
building was Type C3, concrete frame with unreinforced masonry infill, and
this alpha-numeric code, and accompanying Basic Score, were circled on the
Data Collection Form.
Figure 7-9
Because the four individual towers extending above the base represented a
vertical irregularity, this modifier was circled. The screener checked the
Quick Reference Guide and compared the estimated date of construction to
the pre-code year for FEMA Building Type C3. Since 1945 was after the
pre-code year of 1941, the screener did not circle the pre-code modifier.
7-16
FEMA P-154
Noting that the soil is Type E, as determined during the pre-field data
acquisition phase, and that the number of stories was 12, the modifier for Soil
Type E (> 3 stories) was circled. The total of the Basic Score plus applicable
Score Modifiers was 1.2 - 0.7 - 0.3 = 0.2. Noting that this is less than the
minimum score, SMIN = 0.3, the screener indicated that the Final Level 1
Score, SL1, was 0.3.
Under Extent of Review, the screener noted that he was not able to view all
sides of the building by checking the Partial box under Exterior. He
indicated that he was not able to view the interior of the building by checking
None under Interior.
Under Other Hazards, he noted that pounding potential of the building with
its neighbor triggers a Detailed Structural Evaluation.
Because the buildings Final Score was less than the cut-off score of 2.0, and
because of the other hazards present (pounding), the building required a
Detailed Structural Evaluation by an experienced seismic design
professional. Because of the cornices, the building required a Detailed
Nonstructural Evaluation. A completed version of the form, including
photographs attached at a later date, is provided in Figure 7-10.
7.2.8.3
FEMA P-154
7-17
Figure 7-10
7-18
FEMA P-154
Figure 7-11
the plan view of the building in the space on the form allocated for a
Sketch.
The screeners did not know the soil type, but assumed Soil Type D, based on
the instructions in the Handbook for when soil type is unknown, as well as
their knowledge that an adjacent site only a quarter mile away was on Soil
Type D.
The screeners observed the buildings plan irregularity (reentrant corners)
and noted it on the form.
Given the design date of 2000, the anchorage for the heavy cladding on the
exterior of the building was assumed to have been designed to meet the
anchorage requirements initially adopted in 1967 (per the information
provided in the Quick Reference Guide). No other falling hazards were
observed.
The window spacing in the upper stories and the column spacing at the first
floor level indicated the building was either a steel moment frame building,
or a concrete moment frame building. The screeners attempted to view the
interior but were not provided with permission to do so. They elected to
indicate that the building was either an S1 (steel moment-resisting frame) or
C1 (concrete moment-resisting frame) type on the Data Collection Form and
circled both types, along with their Basic Scores.
FEMA P-154
7-19
7-20
FEMA P-154
Figure 7-12
FEMA P-154
7-21
Figure 7-13
any form that included screener comments indicating some uncertainty. She
also reviewed any form that had more than two FEMA Building Types
circled. She spot checked 10% of the remaining forms. This resulted in
approximately 250 reviews of individual forms.
The Supervising Engineer also reviewed the screening results after they were
compiled into the RVS database to check for systematic errors. As expected,
URMs generally received low scores, and new buildings generally received
passing scores providing confidence that the scores were correctly calculated.
These results were discussed with the Program Manager.
7.2.10 Step 10: Transferring the RVS Field Data to the Electronic
Building RVS Database
The last step in the implementation of rapid visual screening for Anyplace,
USA was transferring the information on the RVS Data Collection Forms
into the relational electronic Building RVS Database. This required that all
photos and sketches on the forms be scanned and numbered (for reference
purposes), and that additional fields (and tables) be added to the database for
those attributes not originally included in the database.
For quality control purposes, data were entered separately into two different
versions of the electronic database, except photographs and sketches, which
were scanned only once. A double-entry data verification process was then
used, whereby the data from one database were compared to the same entries
in the second database to identify those entries that were not exactly the
7-22
FEMA P-154
Figure 7-14
FEMA P-154
7-23
The state legislature, who is in this case the RVS Authority, is interested in
understanding how many of the states K-12 school buildings may be
potentially hazardous in the event of an earthquake. They have partnered
with the states Structural Engineers Association to conduct RVS screenings
of a sample of K-12 school buildings located throughout the state. A project
team consisting of two structural engineers, one architect, and four members
appointed by the State Superintendent has been assembled to plan and
manage the program. The legislature plans to use the results of the RVS
screenings to help prepare a preliminary budget for upgrading the schools.
Since the scope of the program was defined by the legislature, this step is not
discussed here.
7.3.1
The project team has determined that there are approximately 1,000 K-12
school buildings within the state. Rapid visual screening will be performed
on a subset of these school buildings to obtain an initial estimate of the
expected performance of the full building stock.
For this subset, the team plans to perform the following: (1) create an
electronic record-keeping system including the capability for electronic
scoring; (2) determine key seismic code adoption dates throughout the state;
(3) acquire and review pre-field data from existing files; (4) review available
building plans prior to field screening; (5) document building location and
other information on the Data Collection Forms prior to field screening; and
(6) perform Level 1 and Level 2 screenings including inspection of the
interiors of buildings whenever possible.
The team has been granted a budget of $80,000 to perform the screening and
present the results to the legislature. Based on this allowance, the team has
7-24
FEMA P-154
decided to use eight engineers to screen 100 of the 1000 total school
buildings in the state. The 100 school buildings are located across the state at
35 different school sites. Members of the project team are assumed to bill at
a rate of $150 per hour. The screeners will all be experienced engineers and
are assumed to bill at a rate of $120 per hour. Administrative tasks will be
performed by personnel at a rate of $60 per hour. The RVS budget was
developed and is shown in Table 7-3.
Table 7-3
Hours
Task Description
Project
Team
$150/hr
Staff
$60/hr
Cost
Screeners
$120/hr
Task
Cost
10
$1,500
40
$6,000
16
40
20
15
$6,000
83
$7,980
$2,250
20
16
$960
36
64
$10,080
162
$19,440
$5,400
40
$1,200
$2,400
$1,200
40
$6,000
Subtotal Cost
$70,410
FEMA P-154
$7,041
$77,451
7-25
7.3.2
A record-keeping system was created for the RVS program using an Excel
spreadsheet. The street address, name, and site number of each of the 100
schools were entered into the spreadsheet.
The site-specific hazard values, SS and S1, were determined using the USGS
tool for each school location based on the school address
(http://earthquake.usgs.gov/designmaps/usapp). The reported values of
latitude and longitude and SS and S1 were entered into the spreadsheet for
each school building.
Vs30 maps for the state were downloaded from the USGS website and were
used to determine the soil type in different parts of the state
(http://earthquake.usgs.gov/hazards/apps/vs30/). It was observed that the
majority of the state has Soil Type B or C with some pockets of Soil Type D.
The map was reviewed for each school building location, and the soil type
was noted in the spreadsheet.
An existing state geologic hazards report indicated liquefaction potential
existed in the westernmost portion of the state. The spreadsheet was updated
to indicate liquefaction potential for the eight school buildings located within
this hazard area.
Electronic scoring was integrated into the spreadsheet, allowing an electronic
score to be calculated based on the site-specific soil type and seismic hazard
and building information collected in the field.
7-26
FEMA P-154
7.3.4
The project team selected eight experienced engineers from around the state
to perform the screenings. The eight engineers, plus two members of the
project team attended a one-day training session. They learned about the
FEMA P-154 methodology and learned how to complete the Level 1 and
Level 2 Data Collection Forms. Using photographs of actual buildings, they
identified FEMA Building Types and building irregularities. Because of how
common building additions are in older school buildings, special attention
was paid during the training to screening buildings with additions. Buildings
were assigned to screeners based on location to minimize the cost of travel
time.
7.3.6
In addition to the database of information that the project team had received
from the states Department of Education, permit files were also obtained at
the local building departments and reviewed for information on the school
buildings. From these permit files, the project team extracted information on
building size, building age, number of stories, and, occasionally, FEMA
Building Type.
FEMA P-154
7-27
Each building was assigned to a screener located nearest the building. The
pre-filled forms were provided to the assigned screener. Each screener had
three weeks to complete their assigned screenings and send the completed
Data Collection Forms back to the project team.
Following are several examples illustrating rapid visual screening in the field
and completion of the Level 1 and Level 2 Data Collection Forms. All of the
examples are located in High seismicity. Some examples use forms
containing relatively complete building identification information, including
FEMA Building Type, obtained during the pre-field data acquisition and
review process, while others use forms containing less complete building
identification information.
7.3.7.1
7-28
FEMA P-154
Figure 7-15
plan of the building. All of the interior walls were finished, but she was able
to identify which walls were structural versus nonstructural by tapping on
them. Those walls that sounded solid were deemed structural, and those that
sounded hollow were deemed nonstructural. She added this information to
the sketch.
Using the Vertical Irregularity Reference Guide, she identified the building
as having a short column irregularity due to the presence of infill walls at the
first floor that effectively shortened the length of the columns. Because the
east-west walls were all concentrated at the center of the building, the
screener identified the building as torsionally irregular. Considering the plan
and vertical irregularities, the screener calculated a score of 0.1, but used SMIN
to set the Level 1 Final Score at 0.3.
The screener completed the Level 2 portion of the form, reviewing each of
the Level 2 statements, and the nonstructural portion of the Level 2 form.
The Level 2 Final Score, which included a more modest penalty for short
columns and a positive modifier for redundancy, was calculated as +0.8.
This score was transferred back onto the Level 1 form.
Under Other Hazards, the screener checked the Geologic Hazards or Soil
Type F box to acknowledge that liquefaction potential at the site is a trigger
for a Detailed Structural Evaluation. Under Action Required, the screener
checked both Yes, score less than cut-off and Yes, other hazards present
(because of the liquefaction potential). No exterior falling hazards were
observed in either the Level 1 or the Level 2 screening.
The completed Level 1 Data Collection Form for the main classroom
building is shown in Figure 7-16. The completed Level 2 Data Collection
Form is shown in Figure 7-17. Additional buildings on site, including an
auditorium structure and a cafeteria building, were screened separately.
FEMA P-154
7-29
Figure 7-16
7-30
Completed Level 1 Data Collection Form for the main building at Roosevelt Elementary School.
7: Example Application of Rapid Visual Screening
FEMA P-154
Figure 7-17
FEMA P-154
Completed Level 2 Data Collection Form for the main building at Roosevelt Elementary School.
7: Example Application of Rapid Visual Screening
7-31
7.3.7.2
Figure 7-18
The screener verified the pre-field information. He checked Soil Type C and
indicated that no geologic hazards were present, based on the pre-filled
information in the Extent of Review portion of the form.
After walking around the building and through the interior of the building, he
identified the original building as a C2 (concrete shear wall). He confirmed
that the walls were concrete and not stucco over metal or wood framing by
knocking on the walls and verifying that they were solid. He observed steel
braces at the addition and concluded that it was an S2 (steel braced frame).
He sketched a plan of the building, including the addition, and an elevation.
He calculated the area of the building and found that the area provided on the
form did not appear to include the area of the addition. He crossed out the
provided area and wrote in a revised value.
The screener consulted the Level 1 Building Additions Reference Guide,
which indicated that because the addition and the original building had
different structural framing, they should be evaluated separately and
7-32
FEMA P-154
FEMA P-154
7-33
Figure 7-19
7-34
Completed Level 1 Data Collection Form for the main building (original plus addition) at
Washington Middle School.
FEMA P-154
Figure 7-20
FEMA P-154
Completed Level 2 Data Collection Form for the main building (original plus addition) at
Washington Middle School.
7: Example Application of Rapid Visual Screening
7-35
7.3.7.3
While screening the main building and auditorium at New City High School,
the screener noted a group of portable buildings being used as temporary
classrooms. The screener decided to perform Level 1 and Level 2 screenings
of these buildings using a blank Data Collection Form. He extracted soil
type information and geologic hazards from the pre-filled Data Collection
Form for the main building.
Figure 7-21
The screener counted two rows of five portables, all of apparently identical
size, use, and construction. Because of their uniformity, the screener opted
to complete only one Data Collection Form for all ten of the buildings.
The screener was able to speak directly to the facilities manager of the high
school, who recalled that the portables had been installed in 2006 with
seismic bracing systems. The screener noted this information in the
comments section of the form and included in the name of the facilities
manager on the contact portion of the form. The screener attempted to
confirm the existence of the bracing by looking under the portables, but all of
the portables had continuous skirts that blocked his view.
Using FEMA Building Type MH (manufactured housing), the screener
calculated a Level 1 Final Score of 1.8. He then completed the Level 2
portion of the form, which provides a positive modifier for MH buildings
7-36
FEMA P-154
with seismic bracing systems. The resulting Level 2 Final Score was 3.0.
Based on the Level 2 score, the screener indicated that additional detailed
structural evaluation of the portables was not required. He reviewed each
portable for potential falling hazards, but none were observed.
The completed Level 1 and Level 2 Data Collection Forms are shown in
Figure 7-22 and 7-23, respectively.
7.3.8
Following the completion of the field screening, the screeners scanned their
completed forms and any additional notes or sketches. These scans, along
with photographs of the buildings, were transmitted to the Supervising
Engineers. The two engineers on the project team reviewed the forms,
comparing the photographs and sketches to the building characteristics noted
(such as number of stories, irregularities, and FEMA Building Type), at
times correcting inconsistencies. The score calculations were doublechecked with particular emphasis on reviewing that the proper Basic Score
and Score Modifiers were applied and that the transfer of the Level 2 score to
the Level 1 form was correct. Notes from screeners were carefully reviewed,
particularly where the note indicated the screeners uncertainty. If a screener
indicated uncertainty (such as building age or whether an observed condition
qualified as an irregularity), the Supervising Engineers reviewed the photos
and the sketches to make a determination. Finally, the Supervising Engineer
checked that no Other Hazards were overlooked in determining whether to
require a Detailed Structural Evaluation. In a few cases, the Supervising
Engineer performed a follow-up screening to verify building age and FEMA
Building Type.
When the reviewers were satisfied with the completed forms, the data
recorded on the paper forms were entered into the record-keeping
spreadsheet. Photographs, sketches, and additional pages of notes were
scanned and saved to a file folder.
Electronic scores were calculated within the spreadsheet using the
automation that had previously been developed.
7.3.9
The project team discussed the RVS results looking for patterns and
inconsistencies. They presented the results in a report to the State
Legislature. The report summarized methodology and criteria used in the
screening program, and gave findings and conclusions, including scoring
results and trends.
FEMA P-154
7-37
Figure 7-22
7-38
Completed Level 1 Data Collection Form for portable classrooms at New City High School.
7: Example Application of Rapid Visual Screening
FEMA P-154
Figure 7-23
FEMA P-154
Completed Level 2 Data Collection Form for portable classrooms at New City High School.
7: Example Application of Rapid Visual Screening
7-39
7.3.10
The site-specific seismic hazard values, Ss and S1, for Roosevelt Elementary
School were determined to be 1.48g and 0.39g, respectively. The school is a
two-story RM2 located on Soil Type D with Severe Vertical and Plan
irregularities. Electronic scores for the school are calculated below using the
guidance presented in Chapter 9 of FEMA P-155 (FEMA, 2015):
1. Building height, H = 2 stories x 12/story = 24
2. Building period, T = 0.025 x H0.75 = 0.27sec
3. SS/S1 = 1.48g/0.39g = 3.79 > T; therefore, interpolate using SS (adjusted
for Soil Type CD). Linear interpolation will be used FEMA P-155
Chapter 9 discusses other types of interpolation that could be used.
4. Adjust SS for Soil Type CD: SS = 1.48g > 1.25g, therefore, Fa = 1.0.
5. Fa SS = 1.0 1.48g = 1.48g (This is between High, Fa SS = 1.21g
with Basic Score for RM2 = 1.7, and Very High, Fa SS = 2.25g with
Basic Score for RM2 = 1.1.)
7-40
FEMA P-154
The site-specific seismic hazard values, Ss and S1, for Washington Middle
School were determined to be 1.21g and 0.54g, respectively. This is close to
the median values used in High seismicity. The main portion of the building
is a three-story C2, while the addition is a one-story S2. The school is located
on Soil Type C.
The Basic Score for Building Type C2 using electronic scoring and
considering the above site-specific seismicity is 1.99, and the Pre-Code Score
Modifier is -0.70. The resulting electronic Level 1 Score is 1.30. The Basic
Score for Building Type S2 using electronic scoring and considering the sitespecific seismicity is also 1.99, and the Plan Irregularity Score Modifier is
0.70. The resulting electronic Level 1 Score for the addition is 1.30. This is
equal to the score for the main portion of the building. Hence, the Final Level
2 Score using electronic scoring is 1.30.
The Final Level 2 Score using electronic scoring considers the pre-code C2
building with irregularities due to the addition. Redundancy is also
considered. The Final Level 2 Score is 1.99 (Basic Score) - 0.70 (Pre-Code)
-0.50 (Vertical Setback) - 0.50 (Split Level) - 0.70 (Torsion) - 0.4 (Reentrant)
+ 0.30 (Redundancy) = -0.51. This is less than the minimum score, hence,
the Final Level 2 Score is taken as 0.30.
7.3.10.3 Example 3: New City High School
The site-specific seismic hazard values, Ss and S1, for New City High School
were determined to be 1.05g and 0.36g, respectively. This indicates a lower
seismicity than at Roosevelt Elementary School or Washington Middle
School sites even though all are in High seismicity. The building is a onestory MH located on Soil Type B.
The Basic Score for Building Type MH using electronic scoring and
considering Soil Type CD is 1.67. The Soil Type B Score Modifier is -0.42.
The Final Level 1 Score using electronic scoring is 1.67 + 0.45 = 2.12.
The Final Level 2 Score is 2.12 (Basic Score plus Soil Type B) + 1.20
(Supplemental Seismic Bracing) = 3.32.
The Final Level 1 and Level 2 paper-based and electronic scores are
summarized in Table 7-4. Where site-specific seismicity is similar to the
FEMA P-154
7-41
median seismicity of the region, such as for Washington Middle School, the
electronic scores will be similar to the paper-based scores. Where sitespecific seismicity is greater than the median seismicity of the region, such as
for Roosevelt Elementary School, the electronic scores will be smaller than
the paper-based scores. Finally, where site-specific seismicity is less than the
median seismicity of the region, such as for New City High School, the
electronic scores will be greater than the paper-based scores.
Table 7-4
School
7-42
Electronic Score
Level 1 Score
Level 2 Score
Level 1 Score
Level 2 Score
Roosevelt
Elementary
School
0.3
0.8
0.3
0.7
Washington
Middle School
1.3
0.3
1.3
0.3
1.5
2.7
2.1
3.3
FEMA P-154
Appendix A
Seismicity Region
Spectral Acceleration
Response, SS (short-period, or
0.2 seconds)
Spectral Acceleration
Response, S1 (long-period,
or 1.0 second)
Low
Moderate
Moderately High
High
Very High
The maps have been developed by the U.S. Geological Survey. Figure A-1
provides a map of the seismicity regions in the entire United States. The
following maps in Figure A-2 through Figure A-11 present seismicity
regions in different geographical regions of the United States and its
territories.
FEMA P-154
A-1
Figure A-1
A-2
Very High, High, Moderately High, Moderate, and Low seismicity regions in the
United States. A different RVS Data Collection Form has been developed for each of
these regions.
FEMA P-154
Figure A-2
FEMA P-154
A-3
Figure A-3
A-4
FEMA P-154
Figure A-4
FEMA P-154
A-5
Figure A-5
A-6
Seismicity regions in Iowa, Michigan, Nebraska, North Dakota, Minnesota, South Dakota,
and Wisconsin.
FEMA P-154
Figure A-6
FEMA P-154
A-7
Figure A-7
A-8
FEMA P-154
Figure A-8
FEMA P-154
A-9
Figure A-9
A-10
Seismicity regions in Delaware, Maryland, New Jersey, Pennsylvania, Virginia, and West
Virginia.
FEMA P-154
Figure A-10
FEMA P-154
A-11
(a)
(b)
Figure A-11
A-12
FEMA P-154
Figure A-12
FEMA P-154
A-13
Appendix B
B.1
Level 1 and Level 2 Forms for Very High, High, Moderately High, Moderate,
and Low Seismicity
Electronic versions of these forms are also available for download at www.atcouncil.org.
FEMA P-154
B-1
Level 1
Zip:
Other Identifiers:
Building Name:
Use:
Latitude:
SS:
Screener(s):
PHOTOGRAPH
Longitude:
S 1:
Date/Time:
Assembly
Industrial
Utility
Soil Type:
Commercial
Office
Warehouse
Year Built:
Code Year:
Emer. Services
School
Residential, # Units:
Historic
Government
DNK
Hard
Rock
Avg
Rock
Dense
Soil
Stiff
Soil
Soft
Soil
Poor
Soil
EST
Shelter
Pounding
Irregularities:
Vertical (type/severity)
Plan (type)
Exterior Falling
Hazards:
Unbraced Chimneys
Heavy Cladding or Heavy Veneer
Parapets
Appendages
Other: _______________________________________________
COMMENTS:
SKETCH
W1
W1A
W2
2.1
-0.9
-0.6
-0.7
-0.3
1.9
0.5
0.0
-0.4
0.7
1.9
-0.9
-0.5
-0.7
-0.3
1.9
0.5
-0.2
-0.4
0.7
1.8
-0.9
-0.5
-0.6
-0.3
2.0
0.4
-0.4
-0.4
0.7
(MRF)
S1
(BR)
(LM)
(RC
SW)
(URM
INF)
(MRF)
(SW)
(URM
INF)
C3
PC1
PC2
RM1
RM2
URM
MH
1.5
-0.8
-0.4
-0.5
-0.3
1.0
0.3
-0.3
-0.3
0.5
1.4
-0.7
-0.4
-0.5
-0.2
1.1
0.3
-0.2
-0.3
0.5
1.6
-0.8
-0.5
-0.6
-0.3
1.1
0.4
-0.2
NA
0.5
1.4
-0.7
-0.4
-0.4
-0.2
1.5
0.3
-0.2
-0.3
0.5
1.2
-0.7
-0.3
-0.4
-0.1
NA
0.2
-0.1
-0.1
0.5
1.0
-0.7
-0.4
-0.4
-0.1
1.4
0.2
-0.1
-0.1
0.3
1.2
-0.8
-0.4
-0.5
-0.2
1.7
0.3
-0.2
-0.3
0.3
0.9
-0.6
-0.3
-0.3
0.0
NA
0.1
0.0
-0.1
0.3
1.1
-0.7
-0.4
-0.5
-0.2
1.5
0.3
-0.2
NA
0.2
1.0
-0.7
-0.4
-0.4
-0.1
1.7
0.2
-0.1
-0.1
0.2
1.1
-0.7
-0.4
-0.4
-0.2
1.6
0.3
-0.2
-0.2
0.3
1.1
-0.7
-0.4
-0.4
-0.2
1.6
0.3
-0.2
-0.2
0.3
0.9
-0.6
-0.3
-0.3
0.0
NA
0.1
0.0
0.0
0.2
1.1
NA
NA
NA
0.0
0.5
0.1
-0.1
NA
1.0
S2
S3
S4
S5
C1
C2
(TU)
(FD)
(RD)
All Sides
Visible
No
Aerial
Entered
No
No
OTHER HAZARDS
ACTION REQUIRED
Where information cannot be verified, screener shall note the following: EST = Estimated or unreliable data OR DNK = Do Not Know
Legend:
RC = Reinforced concrete
SW = Shear wall
MH = Manufactured Housing
LM = Light metal
FD = Flexible diaphragm
RD = Rigid diaphragm
Level 2 (Optional)
Optional Level 2 data collection to be performed by a civil or structural engineering professional, architect, or graduate student with background in seismic evaluation or design of buildings.
Bldg Name:
Screener:
Date/Time:
SL1 =
Vertical Irregularity, VL1 =
Comments:
Level 1
HIGH Seismicity
Zip:
Other Identifiers:
Building Name:
Use:
Latitude:
SS:
Screener(s):
PHOTOGRAPH
Longitude:
S 1:
Date/Time:
Assembly
Industrial
Utility
Soil Type:
Commercial
Office
Warehouse
Year Built:
Code Year:
Emer. Services
School
Residential, # Units:
Historic
Government
DNK
Hard
Rock
Avg
Rock
Dense
Soil
Stiff
Soil
Soft
Soil
Poor
Soil
EST
Shelter
Pounding
Irregularities:
Vertical (type/severity)
Plan (type)
Exterior Falling
Hazards:
Unbraced Chimneys
Heavy Cladding or Heavy Veneer
Parapets
Appendages
Other: _______________________________________________
COMMENTS:
SKETCH
W1
W1A
W2
3.6
-1.2
-0.7
-1.1
-1.1
1.6
0.1
0.2
-0.3
1.1
3.2
-1.2
-0.7
-1.0
-1.0
1.9
0.3
0.2
-0.6
0.9
2.9
-1.2
-0.7
-1.0
-0.9
2.2
0.5
0.1
-0.9
0.7
(MRF)
S1
(BR)
(LM)
(RC
SW)
(URM
INF)
(MRF)
(SW)
(URM
INF)
C3
PC1
PC2
RM1
RM2
URM
MH
2.1
-1.0
-0.6
-0.8
-0.6
1.4
0.4
-0.2
-0.6
0.5
2.0
-1.0
-0.6
-0.7
-0.6
1.4
0.6
-0.4
-0.6
0.5
2.6
-1.1
-0.7
-0.9
-0.8
1.1
0.1
0.2
NA
0.6
2.0
-1.0
-0.6
-0.7
-0.6
1.9
0.6
-0.1
-0.6
0.5
1.7
-0.8
-0.5
-0.6
-0.2
NA
0.5
-0.4
-0.4
0.5
1.5
-0.9
-0.5
-0.6
-0.4
1.9
0.4
0.0
-0.5
0.3
2.0
-1.0
-0.6
-0.8
-0.7
2.1
0.5
0.0
-0.7
0.3
1.2
-0.7
-0.4
-0.5
-0.1
NA
0.3
-0.2
-0.3
0.3
1.6
-1.0
-0.6
-0.7
-0.5
2.0
0.6
-0.3
NA
0.2
1.4
-0.9
-0.5
-0.6
-0.3
2.4
0.4
-0.1
-0.4
0.2
1.7
-0.9
-0.5
-0.7
-0.5
2.1
0.5
-0.1
-0.5
0.3
1.7
-0.9
-0.5
-0.7
-0.5
2.1
0.5
-0.1
-0.6
0.3
1.0
-0.7
-0.4
-0.4
0.0
NA
0.3
-0.2
-0.2
0.2
1.5
NA
NA
NA
-0.1
1.2
0.3
-0.4
NA
1.0
S2
S3
S4
S5
C1
C2
(TU)
(FD)
(RD)
All Sides
Visible
No
Aerial
Entered
No
No
OTHER HAZARDS
ACTION REQUIRED
Where information cannot be verified, screener shall note the following: EST = Estimated or unreliable data OR DNK = Do Not Know
Legend:
RC = Reinforced concrete
SW = Shear wall
MH = Manufactured Housing
LM = Light metal
FD = Flexible diaphragm
RD = Rigid diaphragm
Level 2 (Optional)
HIGH Seismicity
Optional Level 2 data collection to be performed by a civil or structural engineering professional, architect, or graduate student with background in seismic evaluation or design of buildings.
Bldg Name:
Screener:
Date/Time:
SL1 =
Vertical Irregularity, VL1 =
Comments:
Level 1
Zip:
Other Identifiers:
Building Name:
Use:
Latitude:
SS:
Screener(s):
PHOTOGRAPH
Longitude:
S 1:
Date/Time:
Assembly
Industrial
Utility
Soil Type:
Commercial
Office
Warehouse
Year Built:
Code Year:
Emer. Services
School
Residential, # Units:
Historic
Government
DNK
Hard
Rock
Avg
Rock
Dense
Soil
Stiff
Soil
Soft
Soil
Poor
Soil
EST
Shelter
Pounding
Irregularities:
Vertical (type/severity)
Plan (type)
Exterior Falling
Hazards:
Unbraced Chimneys
Heavy Cladding or Heavy Veneer
Parapets
Appendages
Other: _______________________________________________
COMMENTS:
SKETCH
W1
W1A
W2
4.1
-1.3
-0.8
-1.3
-0.8
1.5
0.3
0.0
-0.5
1.6
3.7
-1.3
-0.8
-1.2
-0.9
1.9
0.6
-0.1
-0.8
1.2
3.2
-1.3
-0.8
-1.1
-0.9
2.3
0.9
-0.3
-1.2
0.8
(MRF)
S1
(BR)
(LM)
(RC
SW)
(URM
INF)
(MRF)
(SW)
(URM
INF)
C3
PC1
PC2
RM1
RM2
URM
MH
2.3
-1.1
-0.7
-0.9
-0.5
1.4
0.6
-0.4
-0.7
0.5
2.2
-1.0
-0.6
-0.8
-0.5
1.4
0.9
-0.5
-0.7
0.5
2.9
-1.2
-0.8
-1.0
-0.7
1.0
0.3
0.0
NA
0.9
2.2
-1.0
-0.6
-0.8
-0.6
1.9
0.9
-0.4
-0.7
0.5
2.0
-0.9
-0.6
-0.7
-0.2
NA
0.9
-0.5
-0.6
0.5
1.7
-1.0
-0.6
-0.7
-0.4
1.9
0.6
-0.2
-0.6
0.3
2.1
-1.1
-0.6
-0.9
-0.7
2.1
0.8
-0.2
-0.8
0.3
1.4
-0.8
-0.5
-0.6
-0.1
NA
0.7
-0.4
-0.4
0.3
1.8
-1.0
-0.6
-0.8
-0.4
2.1
0.9
-0.5
NA
0.3
1.5
-0.9
-0.6
-0.7
-0.3
2.4
0.7
-0.3
-0.5
0.2
1.8
-1.0
-0.6
-0.7
-0.5
2.1
0.8
-0.4
-0.6
0.3
1.8
-1.0
-0.6
-0.7
-0.5
2.1
0.8
-0.4
-0.7
0.3
1.2
-0.8
-0.5
-0.5
-0.1
NA
0.6
-0.3
-0.3
0.2
2.2
NA
NA
NA
-0.3
1.2
0.9
-0.5
NA
1.4
S2
S3
S4
S5
C1
C2
(TU)
(FD)
(RD)
All Sides
Visible
No
Aerial
Entered
No
No
OTHER HAZARDS
ACTION REQUIRED
Where information cannot be verified, screener shall note the following: EST = Estimated or unreliable data OR DNK = Do Not Know
Legend:
RC = Reinforced concrete
SW = Shear wall
MH = Manufactured Housing
LM = Light metal
FD = Flexible diaphragm
RD = Rigid diaphragm
Level 2 (Optional)
Optional Level 2 data collection to be performed by a civil or structural engineering professional, architect, or graduate student with background in seismic evaluation or design of buildings.
Bldg Name:
Screener:
Date/Time:
SL1 =
Vertical Irregularity, VL1 =
Comments:
Level 1
MODERATE Seismicity
Zip:
Other Identifiers:
Building Name:
Use:
Latitude:
SS:
Screener(s):
PHOTOGRAPH
Longitude:
S 1:
Date/Time:
Assembly
Industrial
Utility
Soil Type:
Commercial
Office
Warehouse
Year Built:
Code Year:
Emer. Services
School
Residential, # Units:
Historic
Government
DNK
Hard
Rock
Avg
Rock
Dense
Soil
Stiff
Soil
Soft
Soil
Poor
Soil
EST
Shelter
Pounding
Irregularities:
Vertical (type/severity)
Plan (type)
Exterior Falling
Hazards:
Unbraced Chimneys
Heavy Cladding or Heavy Veneer
Parapets
Appendages
Other: _______________________________________________
COMMENTS:
SKETCH
W1
W1A
W2
5.1
-1.4
-0.9
-1.4
-0.3
1.4
0.7
-1.2
-1.8
1.6
4.5
-1.4
-0.9
-1.3
-0.5
2.0
1.2
-1.3
-1.6
1.2
3.8
-1.4
-0.9
-1.2
-0.6
2.5
1.8
-1.4
-1.3
0.9
(MRF)
S1
(BR)
(LM)
(RC
SW)
(URM
INF)
(MRF)
(SW)
(URM
INF)
C3
PC1
PC2
RM1
RM2
URM
MH
2.7
-1.2
-0.8
-1.0
-0.3
1.5
1.1
-0.9
-0.9
0.6
2.6
-1.2
-0.7
-0.9
-0.2
1.5
1.4
-0.9
-0.9
0.6
3.5
-1.4
-0.9
-1.2
-0.2
0.8
0.6
-1.0
NA
0.8
2.5
-1.1
-0.7
-0.9
-0.3
2.1
1.5
-0.9
-0.9
0.6
2.7
-1.2
-0.7
-0.9
-0.3
NA
1.6
-0.9
-1.0
0.6
2.1
-1.1
-0.7
-0.8
-0.3
2.0
1.1
-0.7
-0.8
0.3
2.5
-1.2
-0.7
-1.0
-0.4
2.3
1.5
-1.0
-1.0
0.3
2.0
-1.0
-0.6
-0.8
-0.3
NA
1.3
-0.7
-0.8
0.3
2.1
-1.1
-0.7
-0.9
-0.2
2.1
1.6
-0.8
NA
0.3
1.9
-1.0
-0.6
-0.8
-0.2
2.5
1.3
-0.7
-0.7
0.2
2.1
-1.1
-0.7
-0.8
-0.2
2.3
1.4
-0.8
-0.7
0.3
2.1
-1.1
-0.7
-0.8
-0.2
2.3
1.4
-0.8
-0.8
0.3
1.7
-1.0
-0.6
-0.7
-0.1
NA
1.3
-0.6
-0.6
0.2
2.9
NA
NA
NA
-0.5
1.2
1.6
-0.9
NA
1.5
S2
S3
S4
S5
C1
C2
(TU)
(FD)
(RD)
All Sides
Visible
No
Aerial
Entered
No
No
OTHER HAZARDS
ACTION REQUIRED
Where information cannot be verified, screener shall note the following: EST = Estimated or unreliable data OR DNK = Do Not Know
Legend:
RC = Reinforced concrete
SW = Shear wall
MH = Manufactured Housing
LM = Light metal
FD = Flexible diaphragm
RD = Rigid diaphragm
Level 2 (Optional)
MODERATE Seismicity
Optional Level 2 data collection to be performed by a civil or structural engineering professional, architect, or graduate student with background in seismic evaluation or design of buildings.
Bldg Name:
Screener:
Date/Time:
SL1 =
Vertical Irregularity, VL1 =
Comments:
Level 1
LOW Seismicity
Zip:
Other Identifiers:
Building Name:
Use:
Latitude:
SS:
Screener(s):
PHOTOGRAPH
Longitude:
S 1:
Date/Time:
Assembly
Industrial
Utility
Soil Type:
Commercial
Office
Warehouse
Year Built:
Code Year:
Emer. Services
School
Residential, # Units:
Historic
Government
DNK
Hard
Rock
Avg
Rock
Dense
Soil
Stiff
Soil
Soft
Soil
Poor
Soil
EST
Shelter
Pounding
Irregularities:
Vertical (type/severity)
Plan (type)
Exterior Falling
Hazards:
Unbraced Chimneys
Heavy Cladding or Heavy Veneer
Parapets
Appendages
Other: _______________________________________________
COMMENTS:
SKETCH
W1
W1A
W2
6.2
-1.5
-1.0
-1.6
NA
2.2
0.9
-1.2
-1.7
2.7
5.9
-1.5
-0.9
-1.4
NA
2.4
1.1
-1.7
-2.0
2.1
5.7
-1.5
-0.9
-1.3
NA
2.5
1.3
-2.3
-2.2
1.5
(MRF)
S1
(BR)
(LM)
(RC
SW)
(URM
INF)
(MRF)
(SW)
(URM
INF)
C3
PC1
PC2
RM1
RM2
URM
MH
3.8
-1.4
-0.9
-1.2
NA
2.0
1.0
-1.2
-1.2
0.9
3.9
-1.3
-0.8
-1.1
NA
1.6
1.2
-1.4
-1.4
0.8
4.4
-1.6
-1.0
-1.4
NA
1.4
0.8
-1.0
NA
1.2
4.1
-1.2
-0.7
-1.0
NA
2.1
1.3
-1.7
-1.7
0.8
4.5
-1.3
-0.7
-1.1
NA
NA
1.4
-2.0
-1.9
0.9
3.3
-1.3
-0.7
-1.0
NA
2.3
0.9
-1.4
-1.3
0.5
4.2
-1.2
-0.7
-1.0
NA
2.2
1.2
-2.0
-1.9
0.6
3.5
-1.1
-0.6
-0.9
NA
NA
1.2
-1.6
-1.6
0.5
3.8
-1.3
-0.8
-1.2
NA
1.9
1.3
-1.7
NA
0.6
3.3
-1.1
-0.6
-0.9
NA
2.6
1.3
-1.6
-1.6
0.4
3.7
-1.1
-0.6
-0.9
NA
2.3
1.4
-1.7
-1.6
0.6
3.7
-1.1
-0.6
-0.9
NA
2.3
1.4
-1.7
-1.7
0.5
3.2
-1.2
-0.7
-1.0
NA
NA
1.3
-1.5
-1.4
0.4
4.6
NA
NA
NA
NA
1.8
0.9
-2.1
NA
2.5
S2
S3
S4
S5
C1
C2
(TU)
(FD)
(RD)
All Sides
Visible
No
Aerial
Entered
No
No
OTHER HAZARDS
ACTION REQUIRED
Where information cannot be verified, screener shall note the following: EST = Estimated or unreliable data OR DNK = Do Not Know
Legend:
RC = Reinforced concrete
SW = Shear wall
MH = Manufactured Housing
LM = Light metal
FD = Flexible diaphragm
RD = Rigid diaphragm
Level 2 (Optional)
LOW Seismicity
Optional Level 2 data collection to be performed by a civil or structural engineering professional, architect, or graduate student with background in seismic evaluation or design of buildings.
Bldg Name:
Screener:
Date/Time:
SL1 =
Vertical Irregularity, VL1 =
Comments:
B.2
Table B-1
W1A
W2
S1
S2
S3
S4
S5
C1
C2
C3
PC1
Tilt-up construction
PC2
RM1
RM2
URM
MH
Manufactured housing
Year Seismic
Codes
Initially
Adopted and
Enforced
Benchmark Year
when Codes
Improved
These tables shall be filled out by the Supervising Engineer. See Section 2.6.3 of the Handbook for additional information.
If seismic codes have never been adopted and enforced in the jurisdiction, apply the Pre-Code Score Modifier regardless of
Pre-Code:
Building designed and constructed prior to the year in which seismic codes were initially adopted and
enforced in the jurisdiction; pre-code years are not applicable in regions of Low seismicity.
Post-Benchmark: Building designed and constructed after significant improvements in seismic code requirements
(e.g., ductile detailing) were adopted and enforced; the benchmark year when codes improved may be
different for each building type and jurisdiction.
Heavy Cladding: Heavy cladding on buildings designed and constructed prior to the year noted is considered an exterior
falling hazard and should be noted as such on the Level 1 form.
B-12
FEMA P-154
B.3
Table B-2
Response
Yes
No
See Criterion 2
Yes
No
FEMA P-154
Screening Guidance
B-13
B.4
Table B-3
Consider pounding when the separation between adjacent buildings is less than:
2 times number of stories in shorter building (in Very High seismicity region)
1 1/2 times number of stories in shorter building (in High seismicity region)
1 times number of stories in shorter building (in Moderately High seismicity region)
1/2 times number of stories in shorter building (in Moderate and Low seismicity regions)
Examples:
a) Two 2-story buildings next to each other in High seismicity region:
Minimum Separation = 1 1/2 x 2 = 3
b) 6-story building next to a 4-story building in Moderate seismicity
region: Minimum Separation = 1/2 x 4 = 2
2.
3.
B-14
FEMA P-154
B.5
Table B-4
Sloping Site
(a)
(b)
Unbraced
Cripple Wall
Severity
Level 1 Instructions
Varies
Moderate
Weak and/or
Soft Story
Out-of-Plane
Setback
FEMA P-154
(a)
(b)
(c)
(d)
(a)
(b)
Severe
Apply:
Figure (a): For a W1 house with occupied
space over a garage with limited or short
wall lengths on both sides of the garage
opening.
Figure (b): For a W1A building with an
open front at the ground story (such as for
parking).
Figure (c): When one of the stories has
less wall or fewer columns than the others
(usually the bottom story).
Figure (d): When one of the stories is taller
than the others (usually the bottom story).
Severe
B-15
Table B-4
In-plane
Setback
Short
Column/Pier
(a)
(a)
Severity
Level 1 Instructions
(b)
Moderate
(b)
Severe
Apply if:
Figure (a): Some columns/piers are much
shorter than the typical columns/piers in
the same line.
Figure (b): The columns/piers are narrow
compared to the depth of the beams.
Figure (c): There are infill walls that shorten
the clear height of the column.
Note this deficiency is typically seen in
older concrete and steel building types.
(c)
Split Levels
B-16
Moderate
FEMA P-154
B.6
Table B-5
Level 1 Instructions
Torsion
(a)
(b)
Non-Parallel
Systems
Reentrant
Corner
Diaphragm
Openings
Beams do
not align
with
columns
FEMA P-154
B-17
B.7
Table B-6
Addition
Orientation
Example
RVS Screening
Recommendation
Vertical
Evaluate as a single
building using the total
number of stories of
the original building
and addition and
indicate a setback
vertical irregularity.
Vertical
Single or multiple
story addition with
similar footprint and
seismic force-resisting
system as the original
building
Evaluate as a single
building using the total
number of stories of
the building plus the
addition.
Vertical
Single or multiple
story addition in
which the addition has
a different seismic
force-resisting system
Evaluate as a single
building with another
observable moderate
vertical irregularity.
Horizontal
Evaluate as a single
building with a
torsional irregularity
plan irregularity.
Horizontal
Addition with a
different height than
the original building
Evaluate as a single
building using the
height of the taller
building and indicate
a Pounding Score
Modifier if the heights
of the buildings differ
by more than 2 stories
or if the floors do not
align with 2 feet.
The above horizontal addition scenarios assume that there is not an obvious separation gap between the addition and the
original building.
B-18
FEMA P-154
Table B-6
Addition
Orientation
Type of Addition
Example
RVS Screening
Recommendation
Horizontal
Evaluate a single
building with torsional
irregularity using the
building type with the
lower basic score.
Horizontal
Evaluate as a single
building. Evaluate for
the presence of a
setback irregularity if
there is a difference in
the number of stories
and plan irregularity if
there is a difference in
horizontal dimension
of the original building
and addition along the
interface.
The above horizontal addition scenarios assume that there is not an obvious separation gap between the addition and the
original building.
FEMA P-154
B-19
Appendix C
Construction Drawings
Drawing styles vary among engineering offices, but the conventions used are
very consistent. The following are some of the common designations:
Around the perimeter of the building, the exterior walls will be shown as
a double line, if the space between the lines is empty, this will usually be
a wood stud wall:
FEMA P-154
C-1
and G stands for girder. Usually, beams are smaller than girders and
span between girders while girders will be larger and frame between
columns.
Columns will be shown on the floor plans as their shape with a shading
designation where appropriate:
o Steel columns will be shown as an H rotated to the correct
or
o Wood columns will be an open square:
FEMA P-154
C-2
Figure C-1
FEMA P-154
Representative construction drawing of a floor plan for an S1 building. S2 detailing also shown.
C-3
Figure C-2
FEMA P-154
C-4
Appendix D
D.1
Introduction
It may be difficult to identify positively the FEMA Building Type from the
street as building veneers often mask the structural skeleton. For example, a
steel frame and a concrete frame may look similar from the outside. Features
typical of a specific type of structure may give clues for successful
identification. In some cases, there may be more than one type of frame
present in the structure. Should this be the case, the predominant frame type
should be indicated on the form.
Following are attributes that should be considered when trying to determine a
building seismic force-resisting system from the street:
Age. The approximate age of a building can indicate the possible FEMA
Building Type, as well as indicating the seismic design code used during
the building design process. Age is difficult to determine visually, but an
approximation, accurate within perhaps a decade, can be estimated by
looking at the architectural style and detail treatment of the building
exterior, if the faade has not been renovated. If a building has been
renovated, the apparent age is misleading. See Section D.3 for additional
guidance.
Faade Pattern. The type of structure can sometimes be deduced by the
openness of the faade, or the size and pattern of window openings. The
faade material often can give hints to the structure beneath. Newer
faade materials likely indicate that modern construction types were used
in the design and may indicate that certain building types can be
eliminated.
FEMA P-154
D-1
The most common inspection that will be utilized with the RVS procedure will
be the exterior or sidewalk or streetside survey. First, the evaluation
should be as thorough as possible and performed in a logical manner. The
street-facing front of the building is the starting point and the evaluation
D-2
FEMA P-154
begins at the ground and progressively moves up the exterior wall to the roof
or parapet line.
Table D-1
Characteristics
Low-Rise Buildings
(1-3 stories):
Typically wood or masonry
May have ground floor or
basement parking, a soft story
Older buildings typically have
more architectural detail,
ornamentation
a. 1965 1980
b. 1965-1980
c. 1965-1980
FEMA P-154
D-3
Table D-2
Characteristics
Pre-1950:
Building has flat roof with
cornices, or several
setbacks.
Ornate decorative work
in concrete, terra cotta,
cast stone or iron.
Large bell tower or clock
tower is common.
Simple pattern of
windows on all sides.
Floors are concrete slabs
on steel or concrete
beams.
Exterior is stone, terra
cotta or concrete.
rehabilitated)
d. 1920-1930
c. 1920-1930
e. 1890-1900
D-4
FEMA P-154
Table D-2
Characteristics
1950-1975:
Flat roof, typically with no
cornice.
Building is square or
rectangular full height, fewer
setbacks.
First story and top story can be
taller than other stories. In
some cases, the top story
could be shorter than others.
g. 1950-1975
i. 1950-1975
h. 1940-1950
j. 1950-1975
FEMA P-154
D-5
Table D-2
Characteristics
Post-1975:
Flat roof, typically with no
cornice.
Building is square or
rectangular for its full
height, fewer setbacks.
k. Post-1975
l. Post-1975
m. Post-1975
n. Post-1975
o. Post-1975
D-6
FEMA P-154
Table D-3
Characteristics
Mixed use (residential with a
commercial first floor), places of
assembly, theatres, triangular
buildings, halls, parking structures:
Long spans
Tall first story (for commercial
use) - soft or weak story
Atria or irregular floor-to-floor
layout
b. 1920-1950
a. 1920-1930
c. 1990-2000
f. Pre-1930
FEMA P-154
D-7
Figure D-1
Photos showing basic construction in steel-frame buildings and reinforced concrete-frame buildings.
FEMA P-154
Table D-4
Original Occupancy
Residential
1-2
4-6
7-15
W1
W1A
W1A
S5
W1A
URM
S5
C3
URM
15-30
30+
C3
URM
Commercial
W2
W2
S1
S1
S1
S4
S4
S2
S2
S2
S5
S5
S4
S4
S4
C1
C1
S5
S5
S5
C2
C2
C1
C1
C1
C3
C3
C2
C2
C2
URM
URM
C3
C3
C3
URM
Industrial
W2
W2
S1
S1
S2
S2
S3
S5
S5
C1
C1
C2
C2
C3
C3
URM
URM
FEMA P-154
D-9
Table D-5
Original Occupancy
Residential
1-2
4-6
7-15
W1
W1A
W1A
S1
W1A
URM
S1
S2
S2
S5
URM
15-30
30+
S5
URM
Commercial
Industrial
D-10
W2
W2
S1
S1
S1
S2
S1
S1
S2
S2
S2
S5
S2
S2
S5
S5
S5
S5
S5
C1
C1
C1
C1
C1
C2
C2
C2
C2
C2
C3
C3
C3
C3
C3
RM1
RM1
RM1
RM2
RM2
RM2
URM
URM
URM
S3
S3
C1
S5
S5
C2
C1
C1
C3
C2
C2
C3
C3
RM1
RM1
RM2
RM2
URM
URM
FEMA P-154
Table D-6
Original Occupancy
1-2
Residential
W1
W1A
W1A
RM
7-15
15-30
30+
S1
S1
S1
S1
RM
S2
S2
S2
S2
URM*
C1
C1
C1
C1
C2
C2
C2
C2
URM*
4-6
RM1
RM2
URM*
Commercial
Industrial
W2
W2
S1
S1
S1
S1
S1
S1
S2
S2
S2
S2
S2
S2
C1
C1
C1
C1
C1
C1
C2
C2
C2
C2
C2
C2
RM1
RM1
RM1
RM2
RM2
RM2
URM*
URM*
URM*
C1
S1
S1
C2
S2
S2
PC1
C1
C1
RM1
C2
C2
RM2
RM1
RM1
URM*
RM2
RM2
URM*
URM*
*By this period, URM was generally not permitted in California or other high-seismicity regions,
so that only in the central or eastern U.S. would buildings of this age be URM.
FEMA P-154
D-11
Table D-7
Original Occupancy
Residential
1-2
4-6
7-15
15-30
30+
W1,
W1A
W1A
S1
W1A
S1
S1
S2
S1
S2
S2
C1
S2
C1
C1
C2
C1
C2
C2
PC2
C2
PC2
PC2
RM1
PC2
RM1
RM1
RM2
RM1
RM2
RM2
W2
W2
W2
S1
S1
S1
S1
S1
S1
S2
S2
S2
S2
S2
S2
C1
C1
C1
C1
C1
C1
C2
C2
C2
C2
C2
C2
PC2
PC2
PC1
PC1
PC2
RM1
PC2
PC2
RM1
RM2
RM1
RM1
RM2
RM2
RM2
S1
S1
S1
S1
C1
S2
S2
S2
S2
C2
S3
C1
C1
C1
PC2
C1
C2
C2
C2
C2
PC1
PC2
PC2
PC1
PC2
RM1
PC2
RM1
RM2
RM1
RM2
RM2
Commercial
Industrial
RM2
D-12
FEMA P-154
Figure D-2
Figure D-3
FEMA P-154
D-13
Figure D-4
Building with both shear walls (in the short direction) and frames
(in the long direction).
Figure D-5
D-14
FEMA P-154
Figure D-6
Figure D-7
FEMA P-154
D-15
Because many buildings have been renovated, the screener should know
where to look for clues to the original construction. Most renovations are
done for commercial retail spaces, as businesses like to have an up-to-date
image. Most exterior renovations are only to the front of the building or to
walls that attract attention. Therefore, the original construction can often be
seen at the sides, or the rear, where people generally do not look. If the
original material is covered in these areas, it is often just painted or lightly
plastered. In this case, the pattern of the older material can often still be seen.
Clues helping identify the original material are apparent if one is looking for
them. Two examples are included here:
Figure D-8 shows a building with a 1970s polished stone and glass faade.
The side of the building indicates that it is a pre-1930 URM bearing-wall
structure.
Figure D-8
Figure D-9 shows a building faade with typical 1960s material. The side
was painted. Showing through the paint, the horizontal board patterns in
the poured-in-place concrete wall of pre-1940 construction could still be
seen.
D.5
D-16
FEMA P-154
Figure D-9
Figure D-10
FEMA P-154
D-17
Figure D-11
Figure D-12
D-18
FEMA P-154
The scupper opening at the top of the wall, probably to let the rainwater on
the roof to drain, also indicates that this is a thin veneer rather than a solid
masonry wall. Good places to look for the evidence of veneer tile are at
door or window openings where the edge of the tile will usually show.
Figure D-13
Hollow Clay Tile. The exposed area of a hollow clay tile masonry unit is
approximately 6 inches by 10 inches and often has strip indentations
running the length of the tile. They are fragile, unreinforced, have limited
structural value, and usually are used for non-load-bearing walls, typically
as infill within a concrete or steel frame. Figure D-14 shows a typical
wall panel which has been punctured.
Figure D-14
FEMA P-154
D-19
False Masonry. Masonry pattern sidings can be made from sheet metal,
plastic, or asphalt material (see Figures D-15 and D-16). These sidings
come in sheets and are attached to a structural backing, usually a wood
frame. These sidings can be detected by looking at the edges and by their
sound when tapped.
Figure D-15
Figure D-16
D-20
FEMA P-154
concrete is cast against plywood formwork, which will reflect the wood
grain appearance of plywood, or against metal or plastic-covered wood
forms, which normally do not show a distinctive pattern.
Figure D-17
FEMA P-154
D-21
Appendix E
E.1
Introduction
For the purpose of the RVS, building structural framing types have been
categorized into the 17 FEMA Building Types listed in Section 3.14 and
shown in Table 3-1. This appendix provides additional information about
each of these structural types, including detailed descriptions of their
characteristics, common types of earthquake damage, and common seismic
retrofitting techniques. See FEMA 547, Techniques for the Seismic
Rehabilitation of Existing Buildings (FEMA, 2006), for detailed discussion of
commonly employed seismic retrofit techniques.
E.2
E.2.1
Characteristics
FEMA P-154
E-1
E-2
Figure E-1
Figure E-2
Figure E-3
FEMA P-154
Figure E-4
FEMA P-154
E-3
Figure E-5
Figure E-6
E-4
FEMA P-154
Figure E-7
In the western United States, it can be assumed that all single detached
residential houses (i.e., houses with rear and sides separate from adjacent
structures) are wood stud frame structures unless visual or supplemental
information indicates otherwise (in the Southwestern United States, for
example, some residential homes are constructed of adobe, rammed earth, and
other non-wood materials). Many houses that appear to have brick exterior
faades are actually wood frame with nonstructural brick veneer or
brick-patterned synthetic siding.
In the central and eastern United States, brick walls are usually not veneer. For
these houses, the brick must be examined closely to verify that it is real brick.
The thickness of the exterior wall is estimated by looking at a window or door
opening. If the wall is more than 9 inches from the interior finish to exterior
surface, then it may be a brick wall. Also, if header bricks exist in the brick
pattern, then it may be a brick wall. If these features all point to a brick wall,
the house can be assumed to be a masonry building, and not a wood frame.
In wetter, humid climates it is common to find homes raised four feet or more
above the outside grade with this space totally exposed (no foundation walls).
This allows air flow under the house, to minimize decay and rot problems
associated with high humidity and enclosed spaces. These houses are
supported on wood posts and small precast concrete pads or piers. A
common name for this construction is post and pier construction.
E.2.2
Stud wall buildings have performed well in past earthquakes due to inherent
qualities of the structural system and because they are lightweight and
low-rise. Cracks in any plaster or stucco may appear, but these seldom
FEMA P-154
E-5
Figure E-8
Many of the older wood stud frame buildings have no foundations or have
weak foundations of unreinforced masonry or poorly reinforced concrete.
These foundations have poor shear resistance to horizontal seismic forces and
can fail.
Another problem in older buildings is the stability of cripple walls. Cripple
walls are short stud walls between the foundation and the first floor level.
Often these have no in- or out-of-plane bracing and thus may collapse when
subjected to horizontal earthquake loading. If the cripple walls collapse, the
house will sustain considerable damage and may collapse. In some older
E-6
FEMA P-154
homes, plywood sheathing nailed to cripple studs may have been used to
retrofit cripple walls. However, if the sheathing is not nailed adequately to
the studs and foundation sill plate, the cripple walls will still collapse (see
Figure E-9).
Figure E-9
Homes with post and pier perimeter foundations, which are constructed to
provide adequate air flow under the structure to minimize the potential for
decay, have little resistance to earthquake forces. When these buildings are
subjected to strong earthquake ground motions, the posts may rotate or slip of
the piers and the home will settle to the ground. As with collapsed cripple
walls, this can be very expensive damage to repair and will result in the home
building red-tagged per the ATC-20 post-earthquake safety evaluation
procedures (ATC, 1995). See Figure E-9.
Garages often have a large door opening in the front wall with little or no
bracing in the remainder of the wall. This wall has almost no resistance to
lateral forces, which is a problem if a heavy load such as a second story is built
on top of the garage. Homes built over garages have sustained damage in past
earthquakes, with many collapses. Therefore, the house-over-garage
configuration, which is found commonly in low-rise apartment complexes and
some newer suburban detached dwellings, should be examined more carefully
and perhaps retrofitted.
Unreinforced masonry chimneys present a life safety problem. They are
often inadequately tied to the house, and therefore fall when strongly shaken.
On the other hand, chimneys of reinforced masonry generally perform well.
Some wood frame structures, especially older buildings in the eastern United
States, have masonry veneers that may represent another hazard. The veneer
usually consists of one wythe of brick (a wythe is a term denoting the width of
one brick) attached to the stud wall. In older buildings, the veneer is either
FEMA P-154
E-7
Figure E-10
E-8
FEMA P-154
E.3.1
Characteristics
FEMA P-154
E-9
Figure E-11
These panels may be precast concrete, stone or masonry veneer, metal, glass or
plastic.
This structural type is used for commercial, institutional, and other public
buildings. It is seldom used for low-rise residential buildings.
Steel frame structures built before 1945 are usually clad or infilled with
unreinforced masonry, such as bricks, hollow clay tiles and terra cotta tiles,
and therefore should be classified as S5 structures (see Section E.6 for a
detailed discussion). Other frame buildings of this period are encased in
concrete. Wood or concrete floor diaphragms are common for these older
buildings.
E.3.1.2
Braced steel frame structures (Figures E-12 and E-13) have been built since
the late 1800s with similar usage and exterior finish as the steel moment-frame
buildings. Braced frames are sometimes used for long and narrow buildings
because of their stiffness. Although these buildings are braced with diagonal
E-10
FEMA P-154
members, the bracing members usually cannot be detected from the building
exterior.
Figure E-12
Figure E-13
Braced steel frame, with chevron and diagonal braces. The braces
and steel frames are usually covered by finish material after the
steel is erected.
From the building exterior, it is usually difficult to tell the difference between
steel moment frames, braced frames, and frames with shear walls. In most
modern buildings, the bracing or shear walls are located in the interior or
covered by cladding material. Figure E-14 shows heavy diagonal bracing
located at the side walls of a high rise building, which will be subsequently
covered by finish materials and will not be apparent. In fact, it is difficult to
differentiate steel frame structures and concrete frame structures from the
exterior. Most of the time, the structural members are clad in finish material.
FEMA P-154
E-11
Figure E-14
In older buildings, steel members can also be encased in concrete. There are
no positive ways of distinguishing these various frame types except in the two
cases listed below:
If a building can be determined to be a braced frame, it is probably a steel
structure.
If exposed steel beams and columns can be seen, then the steel frame
structure is apparent. (Especially in older structures, a structural frame
which appears to be concrete may actually be a steel frame encased in
concrete.)
E.3.2
FEMA P-154
and columns. Cracks in the welds began inside the welds where the beam
flanges were welded to the column flanges. These cracks, in some cases,
broke the welds or propagated into the column flange, tearing the flange.
The damage was found in those buildings that experienced ground
accelerations of approximately 20% of gravity (20%g) or greater. Since 1994
Northridge, many cities that experienced large earthquakes in the recent past
have instituted an inspection program to determine if any steel frames were
damaged. Since steel frames are usually covered with a finish material, it is
difficult to find damage to the joints. The process requires removal of the
finishes and removal of fireproofing just to see the joint.
Possible damage includes the following:
Nonstructural damage resulting from excessive deflections in frame
structures can occur to elements such as interior partitions, equipment, and
exterior cladding. Damage to nonstructural elements was the reason for
the discovery of damage to moment frames as a result of the 1994
Northridge earthquake.
Cladding and exterior finish material can fall if insufficiently or
incorrectly connected.
Plastic deformation of structural members can cause permanent
displacements.
Pounding with adjacent structures can occur.
E.3.3
FEMA P-154
E-13
The kind of damage discovered was not limited to moment frames, although
they were the most affected. Some braced frames were found to have damage
to the brace connections, especially at lower levels.
Structural types other than steel frames are sometimes retrofitted using steel
frames, as shown for the concrete structure in Figure E-15.
Figure E-15
Probably the most common use of steel frames for retrofit is in unreinforced
masonry bearing wall buildings (URM). Steel frames are typically used at
the storefront windows as there is no available horizontal resistance provided
by the windows in their plane. Frames can be used throughout the first floor
perimeter when the floor area needs to be open, as in a restaurant. See Figure
E-16. When a building is encountered with this type of retrofit scheme, the
building is still considered a URM building, but on the Level 2 screening a
Score Modifier for a comprehensive retrofit can be given.
E.4
E.4.1
Characteristics
Most light metal buildings existing today were built after 1950 (Figure E-17).
They are used for agricultural structures, industrial factories, and warehouses.
They are typically one story in height, sometimes without interior columns,
and often enclose a large floor area. Construction is typically of steel frames
E-14
FEMA P-154
Figure E-16
Figure E-17
FEMA P-154
E-15
Figure E-18
E-16
FEMA P-154
The screener should look for signs of a metal building, and should knock
on the siding to see if it sounds hollow. Door openings should be
inspected for exposed steel members. If a gap, or light, can be seen where
the siding meets the ground, it is certainly light metal or wood frame. For
the best indication, an interior inspection will confirm the structural
skeleton, because most of these buildings do not have interior finishes.
E.4.2
E.5.1
Characteristics
The construction of this structure type (Figure E-19) is similar to that of the
steel moment-resisting frame in that a matrix of steel columns and girders is
distributed throughout the structure. The joints, however, are not designed
for moment resistance, and the lateral forces are resisted by concrete shear
walls.
It is often difficult to differentiate visually between a steel frame with concrete
shear walls and one without, because interior shear walls will often be covered
by interior finishes and will look like interior nonstructural partitions. For the
purposes of an RVS, unless the shear wall is identifiable from the exterior (i.e.,
a raw concrete finish was part of the architectural aesthetic of the building, and
was left exposed), this building cannot be identified accurately. Figure E-20
shows a structure with such an exposed shear wall. Figure E-21 is a close-up
of shear wall damage.
E.5.2
The shear walls can be part of the elevator and service core or part of the
exterior or interior walls. This type of structure performs as well in
earthquakes as other steel buildings. Some typical types of damage, other
than nonstructural damage and pounding, are:
FEMA P-154
E-17
E-18
Figure E-19
Figure E-20
FEMA P-154
Figure E-21
Shear cracking and distress that occur around openings in concrete shear
walls.
Wall shear failures that occur at stresses below expected capacity due to
wall construction joints acting as weak planes.
Wall bending failures that occur due to insufficient chord steel lap lengths.
E.5.3
Retrofit techniques for S4 buildings are similar to those for concrete shear wall
buildings (C2).
E.6
E.6.1
Characteristics
This construction type (Figures E-22 and E-23) consists of a steel structural
frame and walls infilled with unreinforced masonry (URM). In older
buildings, the floor diaphragms are often wood. Later buildings have
reinforced concrete floors. Because of the masonry infill, the structure tends
to be stiff. Because the steel frame in an older building is covered by
unreinforced masonry for fire protection, it is easy to confuse this type of
building with URM bearing wall structures. Further, because the steel
columns are relatively thin, they may be hidden in walls.
An apparently solid masonry wall may enclose a series of steel columns and
girders. These infill walls are usually two or three wythes thick. Therefore,
FEMA P-154
E-19
Figure E-22
E-20
FEMA P-154
Figure E-23
header bricks will sometimes be present and thus mislead the screener into
thinking the building is a URM bearing wall structure, rather than infill.
Often in these structures the infill and veneer masonry is exposed. Otherwise,
masonry may be obscured by cladding in buildings, especially those that have
undergone renovation.
When a masonry building is encountered, the screener should first attempt to
determine if the masonry is reinforced, by checking the date of construction,
although this is only a rough guide. A clearer indication of a steel frame
structure with URM infill is when the building exhibits the characteristics of a
frame structure of type S1 or S2. One can assume all frame buildings clad in
brick and constructed prior to about 1940 are of this type.
Older frame buildings may be of several types: steel frame encased with URM,
steel frame encased with concrete, and concrete frame. Sometimes older
buildings have decorative cladding such as terra cotta or stone veneer.
Veneers may obscure all evidence of URM. In that case, the structural type
cannot be determined. However, if there is evidence that a large amount of
FEMA P-154
E-21
In major earthquakes, the infill walls may suffer substantial cracking and
deterioration from in-plane or out-of-plane deformation, thus reducing the
in-plane wall stiffness. This in turn puts additional demand on the frame.
Some of the walls may fail while others remain intact, which may result in
torsion or soft story problems.
The hazard from falling masonry is significant as these buildings can be taller
than 20 stories. As described below, typical damage results from a variety of
factors.
Infill walls tend to buckle and fall out-of-plane when subjected to strong
lateral forces. Because infill walls are non-load-bearing, they tend to be
thin (around 9) and cannot rely on the additional shear strength that
accompanies vertical compressive loads.
Veneer masonry around columns or beams is usually poorly anchored to
the structural members and can disengage and fall.
Interior infill partitions and other nonstructural elements can be severely
damaged and collapse.
If stories above the first are infilled, but the first is not, then a soft story
exists, and the difference in stiffness creates a large demand at the ground
floor columns, causing structural damage.
When the earthquake forces are sufficiently high, the steel frame itself can
fail locally. Connections between members are usually not designed for
high lateral loads (except in tall buildings) and this can lead to damage of
these connections. Complete collapse has seldom occurred, but cannot
be ruled out.
E-22
FEMA P-154
E.6.3
Retrofit techniques for this structural type have focused on the expected
damage. By far the most significant problem, and that which is addressed in
most retrofit schemes, is failure of the infill wall out of its plane. This failure
presents a significant life safety hazard to individuals on the exterior of the
building, especially those who manage to exit the building during the
earthquake. To remedy this problem, anchorage connections are developed
to tie the masonry infill to the floors and roof of the structure.
Another significant problem is the inherent lack of shear strength throughout
the building. Some of the retrofit techniques employed include the following:
Shotcrete (with pneumatically placed concrete) the interior faces of the
masonry wall, creating reinforced concrete shear elements.
Provide cross bracing in steel frames or fully strengthen the connections to
create moment frames. In this latter case, the frames are still not
sufficient to resist all the lateral forces, and reliance on the infill walls is
necessary to provide adequate strength.
E.7
E.7.1
Characteristics
E-23
Figure E-24
E-24
FEMA P-154
Figure E-25
FEMA P-154
E-25
E-26
Figure E-26
Figure E-27
FEMA P-154
E.7.2
Under high amplitude cyclic loading, lack of confinement will result in rapid
disintegration of nonductile concrete members, with ensuing brittle failure and
possible building collapse (see Figure E-28).
Causes and types of damage include:
Excessive tie spacing in columns can lead to a lack of concrete
confinement and shear failure.
Placement of inadequate rebar splices all at the same location in a column
can lead to column failure.
Insufficient shear strength in columns can lead to shear failure prior to the
full development of moment hinge capacity.
Insufficient shear tie anchorage can prevent the column from developing
its full shear capacity.
Lack of continuous beam reinforcement can result in unexpected hinge
formation during load reversal.
Inadequate reinforcing of beam-column joints or the positioning of beam
bar splices at columns can lead to failures.
Figure E-28
FEMA P-154
E-27
E.8.1
Characteristics
E-28
FEMA P-154
Figure E-29
shear wall structure. Concrete shear wall buildings are usually cast in place.
The screener should look for signs of cast-in-place concrete. In concrete
bearing wall structures, the wall thickness ranges from 6 to 10 inches and is
thin in comparison to that of masonry bearing wall structures.
FEMA P-154
E-29
E.8.2
This building type generally performs better than concrete frame buildings.
The buildings are heavy compared with steel frame buildings, but they are also
stiff due to the presence of the shear walls. Damage commonly observed in
taller buildings is caused by vertical discontinuities, pounding, and irregular
configuration. Other damage specific to this building type includes the
following.
During large seismic events, shear cracking and distress can occur around
openings in concrete shear walls and in spandrel beams and link beams
between shear walls (see Figures E-30 and E-31).
Shear failure can occur at wall construction joints usually at a load level
below the expected capacity.
Bending failures can result from insufficient vertical chord steel and
insufficient lap lengths at the ends of the walls.
Figure E-30
E-30
FEMA P-154
Figure E-31
E.8.3
E.9.1
Characteristics
These buildings (Figures E-32 and E-33) have been, and continue to be, built
in regions where unreinforced masonry (URM) has not been eliminated by
code. These buildings were generally built before 1940 in high-seismicity
regions and may continue to be built in other regions. Several construction
subtypes fall under this category: nonductile reinforced-concrete frames with
unreinforced infill walls, and nonductile reinforced-concrete frames with
reinforced infill walls.
FEMA P-154
E-31
Figure E-32
Figure E-33
E-32
FEMA P-154
The hazards of these buildings, which in the western United States are often
older, are similar to and perhaps more severe than those of the newer concrete
frames. Where URM infill is present, a falling hazard exists. The failure
mechanisms of URM infill in a concrete frame are generally the same as URM
infill in a steel frame.
E.9.3
E.10.1 Characteristics
FEMA P-154
E-33
Figure E-34
Drawing of tilt-up construction typical of the western United States. Tilt-up construction in
the eastern United States may incorporate a steel frame (Lagorio et al., 1986).
FEMA P-154
Figure E-35
Figure E-36
Before 1973 in the western United States, many tilt-up buildings did not have
sufficiently strong connections or anchors between the walls and the roof and
floor diaphragms. The anchorage typically was nothing more than the nailing
of the plywood roof sheathing to the wood ledgers supporting the framing.
During an earthquake, the weak anchorage broke the ledgers, resulting in the
panels falling and the supported framing collapsing. When mechanical
FEMA P-154
E-35
anchors were used, they pulled out of the walls or split the wood members to
which they were attached, causing the floors or roofs to collapse. See Figures
E-37 and E-38. The connections between the concrete panels are also
vulnerable to failure. Without these connections, the building loses much of
its lateral-force-resisting capacity. For these reasons, many tilt-up buildings
were damaged in the 1971 San Fernando earthquake. Since 1973, tilt-up
construction practices have changed in California and other high-seismicity
regions, requiring positive wall-diaphragm connection (Such requirements
may not have yet been made in other regions of the country). However, a
large number of these older, pre-1970s-vintage tilt-up buildings still exist and
have not been rehabilitated to correct this wall-anchor defect. Damage to
these buildings was observed again in the 1987 Whittier earthquake, 1989
Loma Prieta earthquake, and the 1994 Northridge earthquake. These
buildings are a prime source of seismic hazard. In areas of low or moderate
seismicity, inadequate wall anchor details continue to be used. Severe
ground shaking in such an area may produce major damage in tilt-up
buildings.
Figure E-37
The retrofit of tilt-up buildings is relatively easy and inexpensive. The most
common form of retrofit is to provide a positive anchorage connection at the
roof and wall intersection (see Figure E-39). This is usually done by using
pre-fabricated metal hardware attached to the framing member and to a bolt
that is installed through the wall. On the outside of the wall a large washer
plate is used.
E-36
FEMA P-154
Figure E-38
Accompanying the anchorage retrofit is the addition of ties across the building
to develop the anchorage forces from the wall panels fully into the diaphragm.
This is accomplished by interconnecting framing members from one side of
the building to the other, and then increasing the connections of the diaphragm
(usually wood) to develop the additional forces.
E.11
E.11.1 Characteristics
Precast concrete frame construction, first developed in the 1930s, was not
widely used until the 1960s. The precast frame (Figure E-40) is essentially a
post and beam system in concrete where columns, beams and slabs are
prefabricated and assembled on site. Various types of members are used.
Vertical-load-carrying elements may be Tsections, cross shapes, or arches
and are often more than one story in height. Beams are often T sections and
double T sections, or rectangular sections. Prestressing of the members,
including pretensioning and post-tensioning, is often employed. The
identification of this structure type cannot rely solely on construction date,
although most precast concrete frame structures were constructed after 1960.
Some typical characteristics are the following:
FEMA P-154
E-37
Figure E-39
Thus, the presence of precast concrete does not necessarily mean that it is
a precast concrete frame.
Precast concrete frames are, in essence, post and beam construction in
concrete. Therefore, when a concrete structure displays the features of a
post-and-beam system, it is most likely that it is a precast concrete frame.
It is usually not economical for a conventional cast-in-place concrete
frame to look like a post-and-beam system. Features of a precast
concrete post-and-beam system include:
E-38
FEMA P-154
Figure E-40
FEMA P-154
E-39
Figure E-41
o exposed ends of beams and girders that project beyond their supports
Figure E-42
E-40
FEMA P-154
T-sections or double Ts. These are deep beams with thin webs and
flanges and with large span capacities. (Figure E-43 shows one end of a
double-T beam as it is lowered onto its seat.)
Figure E-43
FEMA P-154
E-41
Figure E-44
Seismic retrofit techniques for precast concrete frame buildings are varied,
depending on the elements being strengthened. Inadequate shear capacity of
floor diaphragms can be addressed by adding reinforced concrete topping to an
untopped system when possible, or adding new shear walls to reduce the
seismic shear forces in the diaphragm. Corbels with inadequate vertical shear
or bending strength can be strengthened by adding epoxied horizontal shear
dowels through the corbel and into the column. Alternatively, vertical shear
capacity can be increased by adding a structural steel bolster under the corbel,
bolted to the column, or a new steel column or reinforced concrete column can
be added (ATC, 1992).
E-42
FEMA P-154
E.12
E.12.1 Characteristics
Figure E-45
FEMA P-154
E-43
The back of the building should be checked for signs of the original
construction type.
If it can be determined that the bearing walls are constructed of concrete
blocks, they may be reinforced. Load-bearing structures using these blocks
are probably reinforced if the local code required it. Concrete blocks come in
a variety of sizes and textures. The most common size is 8 inches wide by 16
inches long by 8 inches high. Their presence is obvious if the concrete blocks
are left as the finish surface.
E.12.2 Typical Earthquake Damage
E-44
FEMA P-154
load), or by adding new shear walls to reduce the diaphragm span (ATC,
1992).
E.13
E.13.1 Characteristics
FEMA P-154
E-45
Figure E-46
E-46
Drawing of unreinforced masonry bearing wall building, two-story (Lagorio et al., 1986).
FEMA P-154
Figure E-47
FEMA P-154
Drawing of unreinforced masonry bearing wall building, four-story (Lagorio et al., 1986).
E-47
Figure E-48
E-48
Drawing of unreinforced masonry bearing wall building, six-story (Lagorio et al., 1986).
FEMA P-154
Figure E-49
Figure E-50
FEMA P-154
E-49
Figure E-51
Drawings of typical window head features in URM bearing wall buildings (Packard, 1981).
Some structures of this type will have anchor plates visible at the floor and
roof lines, approximately 6-10 feet on center around the perimeter of the
building. Anchor plates are usually square or diamond-shaped steel
plates approximately 6 inches by 6 inches, with a bolt and nut at the center.
Their presence indicates anchor ties have been placed to tie the walls to the
floors and roof. These are either from the original construction or from
retrofit under local ordinances. Unless the anchors are 6 feet on center or
less, they are not considered effective in earthquakes. If they are closely
spaced, and appear to be recently installed, it indicates that the building
has been rehabilitated. In either case, when these anchors are present all
around the building, the original construction is URM bearing wall.
E-50
FEMA P-154
When a building has many exterior solid walls constructed from hollow
clay tile, and no columns of another material can be detected, it is probably
not a URM bearing wall but probably a wood or metal frame structure
with URM infill.
One way to distinguish a reinforced masonry building from an
unreinforced masonry building is to examine the brick pattern closely.
Reinforced masonry usually does not show header bricks in the wall
surface.
If a building does not display the above features, or if the exterior is covered by
other finish material, the building may still be URM.
E.13.2 Typical Earthquake Damage
Figure E-52
E-51
Figure E-53
FEMA P-154
Slender Walls. Some of these buildings have tall story heights and thin
walls. This condition, especially in non-load-bearing walls, will result in
buckling out-of-plane under severe lateral load. Failure of a
non-load-bearing wall represents a falling hazard, whereas the collapse of
a load-bearing wall will lead to partial or total collapse of the structure.
E.13.3 Common Retrofit Techniques
Over the last 20 years or more, jurisdictions in California have required that
unreinforced masonry bearing wall buildings be rehabilitated or demolished.
To minimize the economical impact on owners of having to rehabilitate their
buildings, many jurisdictions implemented phased programs such that the
critical items were dealt with first. The following are the key elements
included in a typical retrofit program.
Parapet and chimneys are braced back to the roof.
Roof and floor diaphragms are connected to the walls for both anchorage
forces (out of the plane of the wall) and shear forces (in the plane of the
wall). Anchorage connections are placed at 6 feet spacing or less,
depending on the force requirements. Shear connections are usually
placed at around 2 feet center to center. Anchors consist of bolts installed
through the wall, with 6-inch-square washer plates, and connected to
hardware attached to the wood framing. Shear connections usually are
bolts embedded in the masonry walls in oversized holes filled with either a
non-shrink grout or an epoxy adhesive. See Figure E-54.
Figure E-54
FEMA P-154
Two existing anchors above three new wall anchors at floor line
using decorative washer plates.
E-53
In cases when the height-to-thickness ratio of the walls exceeds the limits
of stability, retrofit consists of reducing the spans of the wall to a level that
their thickness can support or adding vertical wood or steel posts
(strongbacks) that are anchored to the wall and span between
diaphragms.
If the building has an open storefront in the first story, resulting in a soft
story, part of the storefront is enclosed with new masonry or a steel frame
is provided there, with new foundations.
Walls are retrofitted by either closing openings with reinforced masonry
or with reinforced shotcrete. Loads to the perimeter walls can be reduced
by adding interior steel braces.
Inadequate diaphragms can be strengthened with plywood overlays and
blocking.
E.14
E.14.1 Characteristics
The Manufactured Housing building type has been added to the third edition
of FEMA P-154. Manufactured Housing is part of a larger class of
prefabricated structures that includes modular buildings.
Manufactured homes are built in a factory and transported to the site. Mobile
home is an older term for a manufactured home, though mobile home remains
in widespread use. Construction requirements for manufactured homes are
administered by the U.S. Department of Housing and Urban Development
(HUD), per HUDs Manufactured Home Construction and Safety Standards.
HUD regulation of manufactured housing began in 1976. HUD standards are
published in the Code of Federal Regulations under 24 CFR Part 3280, and
they define a manufactured home as:
a structure, transportable in one or more sections, which in the
traveling mode is 8 body feet or more in width or 40 body feet or more
in length or which when erected on-site is 320 or more square feet,
and which is built on a permanent chassis and designed to be used as
a dwelling with or without a permanent foundation when connected to
the required utilities.
Manufactured homes come in different sizes. A single-wide can be up to 18
feet in width. A double-wide is 20 feet or more in width; it is towed to the site
in two separate units, which are then joined together. Some homes are built
with additional units to create an even larger structure. Manufactured homes
are typically one story. Floors and roofs are usually constructed with
E-54
FEMA P-154
plywood or oriented strand board, and the outside surfaces are covered with
sheet metal.
At the site, the HAZUS-MH MR4 Technical Manual (FEMA, 2009a) notes that
manufactured homes are typically placed on isolated piers, jack stands, or
masonry block foundations (usually without any positive anchorage).
Earthquake resistant bracing systems (ERBS) are available. A 1995 HUD
brochure (National Conference, 1996) notes that Some bracing systems
simply provide a frame that catches the home if, during an earthquake, the
home falls off its pier. Other more elaborate bracing systems actually
minimize both horizontal and vertical movement of the home through
connections between the bracing system, the home, and the footings.
Modular buildings are also factory built in units or modules, but they do not
have a permanent chassis or axles and must be transported to the site on flatbed
trucks. Using a crane, the modules are set on a foundation and joined together
to make a final structure. They may be multistory. Modular buildings are
governed by local building codes.
Prefabricated structures are used not just as residences, but also for schools
and other occupancies, as well as temporary buildings with many uses.
Portable classrooms are often used on school properties to provide additional
temporary space. In California, permanent foundations are required when the
classroom exceeds 2,160 square feet or has more than one story, per the
Division of State Architects IR 16-1 Design and Construction Requirements
for Relocatable Buildings (DSA, 2011).
The focus for the Manufactured Housing screening category is on buildings
that are mobile, raised up off the ground, not anchored to the ground, and may
or may not have an ERBS. This includes mobile homes and modular
buildings, such as those used for portable classrooms, when they are not
permanently anchored.
Prefabricated structures that are anchored to a foundation and are wood framed
are screened using the RVS procedure for W1 buildings; similarly,
prefabricated structures built with a steel superstructure and anchored to a
foundation are screened with the RVS procedure for S1 buildings.
In a rapid visual screening, it may not always be possible to determine whether
a permanent foundation or an ERBS exists, as there is often a cripple wall or
skirt wall covering the underlying conditions. Unanchored Manufactured
Housing should be assumed unless a permanent foundation or ERBS can be
seen.
FEMA P-154
E-55
E-56
FEMA P-154
Appendix F
F.1
Introduction
The scoring system in FEMA P-154 RVS is established assuming that the
building is constructed of sound materials. Deterioration of structural
elements can have a significant impact on the expected performance of a
building and therefore needs to be captured when performing a survey when
possible. Determination of the potential impact on performance is difficult at
best since not all damage and deterioration is visible, nor is it easy to assess.
Chapter 3 provides guidelines for assessing damage and deterioration during
a Level 1 screening.
The following sections describe some of the important conditions to consider
when evaluating this hazard. The key question is whether the level of
deterioration and damage rises to the level of significant and thus triggers a
Detailed Structural Evaluation. This is best determined by an experienced
engineer, but the guidance below is provided to assist the screener in
conducting RVS.
F.2
FEMA P-154
F-1
Figure F-1
Wood post and bracing systems should be checked for rot, splitting and steel
corrosion (Figures F-2 and F-3). Since these can generally be considered to
provide primary lateral resistance, their integrity is essential to the seismic
resistance of the structure and can warrant a more detailed evaluation to
assure safety.
Figure F-2
F-2
FEMA P-154
Figure F-3
FEMA P-154
F-3
Figure F-4
F-4
FEMA P-154
Figure F-5
Figure F-6
FEMA P-154
F-5
Precast concrete walls and precast members generally rely upon mechanical
anchorages to fasten them into a system. Examination of these steel elements
for corrosion and loss of section can also lead to concerns about their
capacity to perform adequately during an earthquake. If excessive rust is
observed, then this should be flagged and commented upon on the screening
forms.
Long-term creep, shrinkage or temperature extremes can produce cracking
near connections. For simplicity in rapid visual screening, concrete crack
widths of 1/8 or greater should be considered significant and reported on the
forms.
Concrete walls and columns can also have cracking which may affect the
overall strength of a building (Figure F-7). Crack width and crack type are
both important considerations. For example, flexural cracks or temperature
and shrinkage cracking are typically not considered to be of serious concern.
Cracks representative of shear demands, on the other hand, can be of more
substantial concern. FEMA 306 report, Evaluation and Repair of
Earthquake Damaged Concrete and Masonry Wall Buildings (FEMA,
1999a), provides excellent additional guidance, but is beyond the level of
effort intended for RVS. For the purposes of the rapid visual screening,
crack widths of 1/8 or greater that appear to go fully through the structural
elements and are at least 25% of the length or width of a member are
sufficient to warrant a Detailed Structural Evaluation.
Figure F-7
F-6
Concrete cracks.
FEMA P-154
F.5
Figure F-8
F.6
Stair-step cracking.
FEMA P-154
F-7
Figure F-9
F-8
FEMA P-154
Appendix G
G.1
Figure G-1
These large pieces of the earths surface, termed tectonic plates, move very
slowly and irregularly. Forces build up for decades, centuries, or millennia at
the interfaces (or faults) between plates, until a large releasing movement
FEMA P-154
G-1
suddenly occurs. This sudden, violent motion produces the nearby shaking
that is felt as an earthquake. Strong shaking produces strong horizontal
forces on structures, which can cause direct damage to buildings, bridges,
and other man-made structures as well as triggering fires, landslides, road
damage, tidal waves (tsunamis), and other damaging phenomena.
A fault is like a tear in the earths crust and its fault surface may be from
one to over one hundred miles deep. In some cases, faults are the physical
expression of the boundary between adjacent tectonic plates and thus are
hundreds of miles long. In addition, there are shorter faults, parallel to, or
branching out from, a main fault zone. Generally, the longer a fault, the
larger magnitude earthquake it can generate. Beyond the main tectonic
plates, there are many smaller sub-plates, platelets and simple blocks of crust
which can move or shift due to the jostling of their neighbors and the major
plates. The known existence of these many sub-plates implies that smaller
but still damaging earthquakes are possible almost anywhere.
With the present understanding of the earthquake generating mechanism, the
times, sizes, and locations of earthquakes cannot be reliably predicted.
Generally, earthquakes will be concentrated in the vicinity of faults, and
certain faults are more likely than others to produce a large event, but the
earthquake generating process is not understood well enough to predict the
exact time of earthquake occurrence. Therefore, communities must be
prepared for an earthquake to occur at any time.
Four major factors can affect the severity of ground shaking and thus
potential damage at a site. These are the magnitude of the earthquake, the
type of earthquake, the distance from the source of the earthquake to the site,
and the hardness or softness of the rock or soil at the site. Larger
earthquakes will shake longer and harder, and thus cause more damage.
Experience has shown that the ground motion can be felt for several seconds
to a minute or longer. In preparing for earthquakes, both horizontal (side to
side) and vertical shaking must be considered.
There are many ways to describe the size and severity of an earthquake and
associated ground shaking. Perhaps the most familiar are earthquake
magnitude and Modified Mercalli Intensity (MMI, often simply termed
intensity). Earthquake magnitude is technically known as the Richter
magnitude, a numerical description of the maximum amplitude of ground
movement measured by a seismograph (adjusted to a standard setting). On
the Richter scale, the largest recorded earthquakes have had magnitudes of
about 9.5. It is a logarithmic scale, and a unit increase in magnitude
corresponds to a ten-fold increase in the adjusted ground displacement
G-2
FEMA P-154
Figure G-2 shows the seismicity of the United States based on the 2014
seismicity catalog of the USGS National Seismic Hazard Mapping Project.
The data are based on Petersen et al. (2014), Wesson et al. (2007), and Klein
et al. (2001).
It is evident that some parts of the country have experienced more
earthquakes than others. The boundary between the North American and
Pacific tectonic plates lies along the west coast of the United States and south
of Alaska. The San Andreas fault in California and the Aleutian Trench off
the coast of Alaska are part of this boundary. These active seismic zones
have generated earthquakes with Richter magnitudes greater than 8. Many
FEMA P-154
G-3
Figure G-2
G-4
Seismicity data for the United States showing earthquake locations with varying size of circles
depending on the magnitude.
FEMA P-154
other smaller fault zones exist throughout the western United States that are
also participating intermittently in releasing the stresses and strains that are
built up as the tectonic plates try to move past one another. Because
earthquakes always occur along faults, the seismic hazard will be greater for
those population centers close to active fault zones.
In California, the earthquake hazard is so significant that special study zones
have been created by the legislature, and named Alquist-Priola Special Study
Zones. These zones cover the larger known faults and require special
geotechnical studies to be performed in order to establish design parameters.
On the east coast of the United States, the sources of earthquakes are less
understood. There is no plate boundary and few locations of faults are
known. Therefore, it is difficult to make statements about where earthquakes
are most likely to occur. Several significant historical earthquakes have
occurred, such as in Charleston, South Carolina, in 1886, New Madrid,
Missouri, in 1811 and 1812, and Mineral, Virginia in 2011, indicating that
there is potential for large earthquakes. However, most earthquakes in the
Eastern United States are smaller magnitude events. Because of regional
geologic differences, specifically, the hardness of the crustal rock, Eastern
and Central United States earthquakes are felt at much greater distances from
their sources than those in the western United States, sometimes at distances
up to a thousand miles.
G.3
Earthquake Effects
FEMA P-154
G-5
G-6
FEMA P-154
soft soils beneath the city amplified the ground shaking enough to cause
weak mid-rise buildings to collapse (see Figure G-3). Resonance of the
building frequency with the amplified ground shaking frequency played a
significant role. Sites with rock close to or at the surface will be less likely to
amplify motion. The type of motion felt also changes with distance from the
earthquake. Close to the source the motion tends to be violent rapid shaking,
whereas farther away the motion is normally more of a swaying nature.
Buildings will respond differently to the rapid shaking than to the swaying
motion.
Figure G-3
Each building has its own vibrational characteristics that depend on building
height and structural type. Similarly, each earthquake has its own vibrational
characteristics that depend on the geology of the site, distance from the
source, and the type and site of the earthquake source mechanism.
Sometimes a natural resonant frequency of the building and a prominent
frequency of the earthquake motion are similar and cause a sympathetic
response, termed resonance. This causes an increase in the amplitude of the
buildings vibration and consequently increases the potential for damage.
Resonance was a major problem in the 1985 Mexico City earthquake, in
which the total collapse of many mid-rise buildings (Figure G-7) caused
many fatalities. Tall buildings at large distances from the earthquake source
have a small, but finite, probability of being subjected to ground motions
containing frequencies that can cause resonance. Similar effects were seen in
the 2010 Chile earthquake where a number of tall concrete buildings in
Santiago were damaged, even though the epicenter was hundreds of miles
away.
Where taller, more flexible, buildings are susceptible to distant earthquakes
(swaying motion) shorter and stiffer buildings are more susceptible to nearby
FEMA P-154
G-7
G-8
Figure G-4
Figure G-5
FEMA P-154
Figure G-6
Figure G-7
The collapse of load bearing walls that support the floor and roof framing for
the structure is a common form of damage in unreinforced masonry
structures (Figure G-8). This damage commonly occurs due to lack of an
adequate structural connection between the floor and roof framing and the
heavy masonry walls.
Similar types of damage have occurred in many older tilt-up buildings
(Figure G-9).
From a life-safety perspective, vulnerable buildings need to be clearly
identified, and then strengthened or demolished.
FEMA P-154
G-9
Figure G-8
Figure G-9
G.4
G-10
FEMA P-154
building. Basically, seismic systems consist of axial-, shear- and bendingresistant elements.
In wood frame, stud-wall buildings, plywood siding is typically used to
prevent excessive lateral deflection in the plane of the wall. Without the
extra strength provided by the plywood or other structural sheathing, walls
would distort excessively or rack, resulting in broken windows and stuck
doors. In older wood frame houses, this resistance to lateral loads may be
provided by either wood or steel diagonal bracing.
The earthquake-resisting systems in modern steel buildings take many forms.
Many types of diagonal bracing configurations have been used, such as
single diagonal braces, X-bracing, V-bracing, or inverted V-bracing. In
braced frames, horizontal loads are resisted through tension and compression
forces in the braces with resulting changed forces in the beams and columns.
Steel buildings are sometimes constructed with moment-resistant frames in
one direction and braced frames in the other.
Moment-resisting steel frames are capable of resisting lateral loads. In this
type of construction the connections between the beams and the columns are
designed to resist the rotation of the column relative to the beam. Thus, the
beam and the column work together and resist lateral movement and lateral
displacement by bending.
In concrete structures, shear walls are sometimes used to provide lateral
resistance in the plane of the wall, in addition to moment-resisting frames.
Ideally, these shear walls are continuous reinforced-concrete walls extending
from the foundation to the roof of the building. They can be exterior walls or
interior walls. They are interconnected with the rest of the concrete frame,
and thus resist the horizontal motion of one floor relative to another. Shear
walls can also be constructed of reinforced masonry, using bricks or concrete
blocks.
FEMA P-154
G-11
Glossary, Abbreviations,
and Symbols
Glossary
Adjusted Baseline Score: The score used at the beginning of the Level 2
page of the Data Collection Form that takes the Final Score on the Level 1
page and subtracts the plan and vertical irregularity Score Modifiers.
Basic Score: Each FEMA Building Type has a Basic Score for each
seismicity region that provides a relative comparison of expected seismic
performance.
Benchmark Year: The year that substantially improved seismic codes were
adopted and enforced. See Chapter 2.
Collapse: Collapse is defined in FEMA P-154 as when the gravity loadcarrying system (such as beams, columns, floors, shear walls) loses the
ability to carry its own weight and the weight of whatever else it supports.
That failure leads to severe structural deformation of a potentially lifethreatening nature, especially falling of all or portions of the structure.
Construction Documents: Drawings and specifications prepared by the
design team that are used by the contractor to build the building. This
includes architectural and structural drawings. These are sometimes referred
to as working drawings.
Cut-off Score: A Final Score established by the RVS Authority to divide
screened buildings into two categories: those that are expected to have
acceptable seismic performance, and those that may be seismically hazardous
and should be studied further. See Chapter 2 and Chapter 5.
Data Collection Form: The form used to document the rapid visual
screening. The first page provides the Level 1 screening. The second page
covers the optional Level 2 screening. Data Collection Forms are available
for the Low, Moderate, Moderately High, High, and Very High seismicity
regions.
Detailed Nonstructural Evaluation: Following a rapid visual screening in
FEMA P-154, if potential nonstructural seismic deficiencies are identified, a
Detailed Nonstructural Evaluation is recommended. FEMA E-74 (FEMA,
2012) can be used to conduct the evaluation.
FEMA P-154
H-1
H-2
FEMA P-154
FEMA P-154
H-3
URM
Unreinforced Masonry
Symbols
H-4
The sum of all Level 2 modifiers except PL2 and VL2. See Chapter 4.
PL1
PL2
S1
SL1
SL2
SMIN
SS
FEMA P-154
VL1
VL2
VS30
FEMA P-154
H-5
Illustration Credits
Illustration and figure credits are provided below, unless referenced with the
figure. All remaining figures and illustrations were prepared by the project
team.
Credit
Figure Number
Charles Scawthorn
3-5, 3-27, 3-31, 3-33, 3-42, 3-43, 7-8, 7-9, 7-15, D-1,
D-2, D-3, D-4, D-5, E-1, E-3, E-5, E-7, E-8, E-9, E-10,
E-13, E-14, E-15, E-16, E-17, E-18, E-20, E-21, E-23,
E-25, E-26, E-27, E-28, E-31, E-32, E-33, E-35, E-36,
E-37, E-39, E-41, E-43, E-45, E-49, E-50, E-52, E-53,
E-54, F-5, F-8, F-9, F-10, F-12, F-12, G-7, G-8, G-9,
G-10, G-11, G-12, G-13; Figures in Table 3-1, Table
D-1 (except a and b), Table D-2, Table D-3 (except f
and g)
Kit Wong
3-40, 3-41, D-6, D-8, D-9, D-10, D-13, D-14, D-15, D16, D-17, E-42, E-44; Figures in Table D-1 a and b,
Table D-3 f and g
Richard Ranous
Sanborn Maps
2-4, 2-5
Robert Bruce
D-7
James Stratta
E-30
FEMA P-154
Illustration Credits
I-1
References
FEMA P-154
J: References
J-1
J-2
J: References
FEMA P-154
J: References
J-3
J-4
J: References
FEMA P-154
FEMA P-154
J: References
J-5
J-6
J: References
FEMA P-154
FEMA P-154
J: References
J-7
Project Participants
FEMA Oversight
Mike Mahoney (Project Officer)
Washington, DC 20472
Washington, DC 20472
Washington, DC 20472
Brian Kehoe
Michael Griffin
Keith Porter
William T. Holmes
FEMA P-154
Barry Welliver
BHW Engineers
K: Project Participants
K-1
John Osteraas
Exponent
149 Commonwealth Drive
Menlo Park, California 94025
Timothy Brown
Bureau of Reclamation
P.O. Box 25007, Mail Code 86-68110
Denver, Colorado 80225
Steven Sweeney
U.S. Army Engineer Research and Development
Center Construction Engineering Research
Laboratory
P.O. Box 9005
Champaign, Illinois 61826
Melvyn Green
Melvyn Green & Associates
21311 Hawthorne Blvd., Suite 230
Torrance, California 90503
Laura Kelly
U.S. Coast Guard Base
Kodiak Cape Sarichef St., N38
PO Box 195025
Kodiak, Alaska 99619
Christine Theodoropoulos
Cal Poly San Luis Obispo
College of Architecture & Env. Design
San Luis Obispo, California 94407
Nicolas Luco
Kenneth Rukstales
Illustrators
Andrew Bishop
Wiss Janney Elstner Associates, Inc.
2000 Powell Street, Suite 1650
Emeryville, California 94608
Scott Hiner
Workshop Participants
John Aho
CH2M Hill, Inc.
2015 Shepherdia Drive
Anchorage, Alaska 99508
K-2
Rebecca Collins
K: Project Participants
FEMA P-154
Murat Saatcioglu
University of Ottawa,
Dept. of Civil Engineering
161 Louis Pasteur Street
Ottawa, Ontario, K1N 6N5 Canada
Alan Scott
KPFF Consulting Engineers
1630 Des Peres Road, Suite 100
St. Louis, Missouri 63131
Hope Seligson
MMI Engineering
2100 Main Street, Suite 150
Huntington Beach, California 92648
FEMA P-154
Nilesh Shome
Risk Management Solutions
1133 Langton Drive
San Ramon, California 94582
Jeff Soulages
Intel Corp.
2501 NW 229th Street, MS: RS6-101
Hillsboro, Oregon 97124
Yumei Wang
Oregon Dept. of Geology & Mineral Industries
800 NE Oregon Street, #28
Portland, Oregon 97232
K: Project Participants
K-3
FEMA P-154
Catalog No. 08211-2