PRE-Commissioning Check List

The document lists 28 check points for pre-commissioning of a 33kV HT panel relay. It includes checking protection functions like overcurrent, earth fault, over/under voltage, frequency protection. It also includes checking breaker operation, indications, metering, binary inputs/outputs, gas pressure monitoring, annunciation and trouble signals. A similar checklist for an 11kV HT panel relay is provided, listing 24 check points to test protection functions, breaker operation, control circuits and indications.

Uploaded by

Srikanta Nayak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
150 views6 pages

PRE-Commissioning Check List

The document lists 28 check points for pre-commissioning of a 33kV HT panel relay. It includes checking protection functions like overcurrent, earth fault, over/under voltage, frequency protection. It also includes checking breaker operation, indications, metering, binary inputs/outputs, gas pressure monitoring, annunciation and trouble signals. A similar checklist for an 11kV HT panel relay is provided, listing 24 check points to test protection functions, breaker operation, control circuits and indications.

Uploaded by

Srikanta Nayak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

HT PANEL Relay PRE-COMMISSIONING CHECK LIST(33KV)

Check Points
Sl.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

Description of Check
Incomer feeder O/C (51-1) IDMT Test
Incomer feeder O/C (50-1)DMT stage-1Test
Incomer Feeder Directional O/C (51-2/67) IDMT
Incomer Feeder E/F (51G-1) IDMT Test
Incomer Feeder E/F (50G-1) DMT Stage -1 Test
Income Feeder Directinal E/F (51G-2/67G) IDMT
Over Voltage Protection,Over Frequency
Under Voltage Protection,Under Frequency
Auto Reclose
Auto Reclose Blocking Check(O/V, U/V)
Differential Protection
Ref Protection
Overflux Protection
Relay LED Configuration Check
Breaker operation in test mode & service mode in electrically
ALL Indiaction Check.
Master Trip & auto Trip Check.
From TNC switch ON/OFF operation check.
Current& Voltage Metering ckt check.
Binary Input & Binary ouput check.
Other Incomer BB and CB SF6 Gas Pressure Low Trip to Incomer through Goose.
All Outgoings BB and CB SF6 Gas Pressure Low Trip to Incomer through Goose and Vice Versa.
Bus PT Tank SF6 Gas Pressure Low Trip to Incomer through Goose.
Annunciation Checks for Alarm and Trip Signal.
Voltage and Current Measurement in MFM and Energymeters.
Disconnector Switch Operation.
Earth switch Operation
Common Trouble or Hooter Check.

Result

Remarks

HT PANEL Relay PRE-COMMISSIONING CHECK LIST(11KV)


Check Points
Sl.No

Description of Check
1
2
3
4
5
6
7
8
9
10
11
12
13

Incomer feeder O/C (51-1) IDMT Test


Incomer feeder O/C (50-1)DMT stage-1Test
Incomer feeder O/C (50-2)DMT stage-2Test
Incomer Feeder E/F (51G-1) IDMT Test
Incomer Feeder E/F (50G-1) DMT Stage -1 Test
Incomer Feeder E/F (50G-2) DMT Stage -2 Test
Outgoing feeder O/C (51-1) IDMT Test
Outgoing feeder O/C (50-1)DMT stage-1Test
Outgoing feeder O/C (50-2)DMT stage-2Test
Outgoing Feeder E/F (51G-1) IDMT Test
Outgoing Feeder E/F (50G-1) DMT Stage -1 Test
Outgoing Feeder E/F (50G-2) DMT Stage -2 Test
Outgoing Feeder Auto reclose test

14
15
16
17
18
19
20
21
22
23
24

CB fail (LBB) to incomer Trip signal check through goose


Reverse Block signal or Indication to Incomer check through goose.
Breaker operation in test mode & service mode in electrically.
All indication check.
Relay LED Configuration Check
Master Trip & auto Trip Check.
From TNC switch ON/OFF operation check.
Incomer & Buscopler Remote operation check.
Current& Voltage Metering ckt check.
Binary Input & Binary ouput check.
Common Trouble or Hooter Check.

Result

Remarks