SAP Service Order Process

The document outlines the steps for processing a service order in SAP CS: 1. A notification is created in CS upon receipt of a customer complaint, and warranty status is checked. 2. A repair order is created which can include adding components, assigning a work center, and confirming the service order. 3. The service order is then planned, operations are confirmed, a billing request is made, and the order is billed depending on whether service, materials, or both are required.

Uploaded by

Harish Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views2 pages

SAP Service Order Process

The document outlines the steps for processing a service order in SAP CS: 1. A notification is created in CS upon receipt of a customer complaint, and warranty status is checked. 2. A repair order is created which can include adding components, assigning a work center, and confirming the service order. 3. The service order is then planned, operations are confirmed, a billing request is made, and the order is billed depending on whether service, materials, or both are required.

Uploaded by

Harish Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

SAP Service order process

In CS once will recipt of complaint from customer will create notification - iw51.

If maintained wrranty master (BGM1) it pop up Whether in warranty or not.and here in


notification "activity"tab we can Enter incoming and outgoing calls in action box -
"Log Telephone Calls". or how complaint recived from the customer.

Create Repair Order-IW52 :

Select document flow and check if the repair order is created or not

Come to service order-iw32 : (create service order -IW52)

Add the component (RM) in to the component list. (if required any material for the repair) once
SAVE PR get genrated for the entered material (Purchasing view). PR--PO--GR (materia cost get
captured)

In service order add the work centre and control key (Operation tab)- IW32

Confirm the service order-iw42

Put actual Quality hours in final confirmation and save the confirmation

Come to service order again, check the actual cost against all elements (material, Cost of Quality
inspection + operation cost)

complete the service order & notification

Scenario: if only service required...


Notification--Service order--Plan Opration--confirmation--billing request--Billing

Scenario:if only material required...


Notification--service order--component--issue material--sale order--delivery--billing

Scenario: both serive and material required..

Notification--service order--Plan Opration & Component-- for opration confirmation of service & for
component issue the material---Billing request--Invoice

Thanks

Harish K