Construction Weekly Progress Report

This weekly progress report provides updates on the Lake Victoria Water Supply and Sanitation Program Phase-II construction project. According to the report, the overall progress of the project is 46% complete as of the week of November 14-20, 2016. Specific items like the school toilet main buildings and external drainage are both 97% complete, with no additional progress made during the reported week.

Uploaded by

Mhando
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views1 page

Construction Weekly Progress Report

This weekly progress report provides updates on the Lake Victoria Water Supply and Sanitation Program Phase-II construction project. According to the report, the overall progress of the project is 46% complete as of the week of November 14-20, 2016. Specific items like the school toilet main buildings and external drainage are both 97% complete, with no additional progress made during the reported week.

Uploaded by

Mhando
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CONSTRUCTION WEEKLY PROGRESS REPORT

Project: Lake Victoria Water Supply and Sanitation Program Phase-II


Contract No: MWAUWASA/LVWATSAN-II/EAC/W/2014/004
th th
Week from 14 November 2016 -20 November 2016
Week No. 60
Overall Progress 46%
ITEM NO DESCRIPTION UNIT RATE Previous Comulative This week Progress Commulative
E01 SCHOOL TOILET MAIN BUILDINGS 97% 0% 97%
E01.1 EARTHWORK 100% 0% 100%
Excavation works will include cart away, loading of surplus excavated 100% 0% 100%
E01.1.1 Excavate oversite average 150mm deep to remove vegetated soil, convey 100% 0% 100%
E01.1.2 Excavate foundation trench commencing at stripped level and not 100% 0% 100%
E01.1.4 Extra over for the excavation in rock formations (PROVISIONAL SUM) 100% 0% 100%
E01.1.3 Earth backfilling well rammed and consolidated around foundations 100% 0% 100%
E01.1.4 Allow for planking and strutting to uphold the sides of excavations. 100% 0% 100%
E01.1.5 Allow for keeping excavations free from water 100% 0% 100%
E01.1.6 Apply 200mm blinded hardcore bed 100% 0% 100%
E01.2 CONCRETE WORK 100% 0% 100%
E01.3 BLOCK WORK 100% 0% 100%
E01.5 JOINEY WORK 100% 0% 100%
E01.6 FINISHING 100% 0% 100%
E01.7 PAINTING AND DECORATION 100% 0% 100%
E01.9 WASTEWATER INSTALLATIONS 100% 0% 100%
E01.10 WATER SUPPLY INSTALLATIONS 100% 0% 100%
E01.11 PROTECTION OF BUILDING AGAINST TERMITES 100% 0% 100%
E02 EXTERNAL DRAINAGE 97% 0% 97%