Passivhaus Airtightness Guide
Passivhaus Airtightness Guide
uk
The Swimming House, floating Passivhaus, Lake Weissensee, Austria (Source: R. McLeod)
Background
The Larch Passivhaus, under construction at Ebbw Vale, Wales. Source: R. McLeod
Passivhaus Primer Airtightness guide 3
Windward
(+ve pressure)
Leeward
(-ve pressure)
Inside: 20C;
50% relative humidity
Figure 3 Implications of moisture vapour ingress through a 1mm crack (Source PHI/ Sariri)
Passivhaus Primer Airtightness guide 5
Very low air leakage rates are required It is important to note that achieving a heating It is worth noting that in practice an
by the Passivhaus standard and must be demand of 15kWh/m2yr or a peak load airtightness level of n50 = 0.6 h-1 @ 50 Pa is
demonstrated for each certified building by of 10 W/m2 often requires the elemental roughly equivalent to having a hole in the
means of a blower door air tightness test. specifications to be far better than the envelope area of the building less than the size
The air change rate must be less than or recommended Passivhaus limiting values. of a 5 pence piece for every 5 m2 of building
equal to 0.6 air changes per hour, under test This is particularly the case for buildings that envelope (see Figure 4). In comparison a
conditions. do not have an optimum form. Therefore building that achieves the limiting figure
the limiting value of n50 being 0.6 h-1 @ for airtightness to comply with the Building
Passivhaus airtightness (n50) 0.6 h-1 @ 50 Pa
50 Pa should be seen as the maximum air Regulations Part L (2013) (Section 6 of the
Note: The limiting value of 0.6 h-1 @ 50 Pa leakage permissible. Attaining the Passivhaus Building Standards, Scotland and Building
should be used as the default design air standard of airtightness is challenging, but Regulations Part F, Northern Ireland) will have
tightness value in all preliminary Passive House achievable when a clear and well thought out an equivalent hole the size of a 20 pence piece
Planning Package (PHPP) calculations until a strategy is arrived at during the design stage. for every 1m2 of envelope.
verified pressure test reading is available. This strategy must be maintained and fully
implemented during the construction phases.
It is therefore imperative that the contractors
clearly understand the airtightness strategy
and are able to easily implement the sequence
of work on site.
1m
Passivhaus
Compliant
5m
UK Building Regulations
and the Passivhaus Standard
1 2
Internal External
Stage 1 Stage 3
2 Detailed Design/Production Lay airtightness Lay a continuous
stage installation barrier over roof sheet of
truss and RHS. membrane across
sequence Fix in place using whole face of
double sided OSB. Tape over
tape. Leave membrane
Final production drawings should also contain hanging down encasing roof
sequenced illustrations of the key stages trussess
involved in installing the airtight barrier at
complex junctions. Any careful sequencing
needed to install a membrane or create an Stage 2 Stage 4
air-tight seal should be annotated on these Fix 18mm OSB to Fix 12mm
drawings (right). SW purlin. Fold plasterboard soffit
back membrane
and tape to inside
face of OSB. Fill
voids with
insulation from
above
Figure 7 Staged sequence drawings, showing steps to achieving final airtight detail
(courtesy bere: architects)
Passivhaus Primer Airtightness guide 9
Details and drawings must be clearly is to the correct element of the wall. This may
presented to ensure they can be understood involve installing pipes or spigots to seal into
and are able to be achieved on site. It is the air line and then allowing the actual pipe
recommended that critical airtight details are or cable connections to be sealed to when
prepared in large scale (1:10) and colour coded subsequently installed
for clear reference. Consideration needs to
Select and specify materials that are robust
be given to the sequencing and buildability
and durable to form the air barrier. The
of air tight junction details particularly around
objective is to achieve an airtight structure for
windows and doors and this should be clearly
the life of the building, not one which will be
indicated on production drawings.
adequate for the air pressure test, but then
Try, where possible, to keep penetrations degrade in a short space of time. Never try to
through the airtight envelope to a minimum. make savings by specifying cheaper alternative
Take care when grouping services together materials (for example cheap building
(electrical cables, pipes and ventilation ducts) tapes), as these will not offer the robustness
to ensure adequate space is left to seal around required to achieve a Passivhaus standard
individual penetrations using proprietary of airtightness. A review of the comparative
seals (top hats and gaskets). Avoid services performance of common European
penetrations, MVHR units, boilers etc. being airtightness tapes can be found in the German
located too close to a corner or a wall as it Test magazine (Stiftung Warentest, 2012).
may be impractical to access the gap for
sealing. Ideally all penetrations are made as the
building element is installed to ensure the seal
calculation will naturally exclude these). Beams be overestimated at any time, it will result
and visible rafters are not typically deducted in an under estimate of the airtightness
Calculating the pressure test from the volume of the building however. result, so it is imperative that it is agreed
reference volume (Vn50) The loft space is generally excluded (in cold
upon as early as possible in the build and
design process. Having to downward revise
roof constructions) as it is not conditioned and
the calculated volume at a late stage of
in such cases the loft door has been designed
the design could jeopardise compliance
Airtightness performance of a Passivhaus to be airtight. The opening for stairs should
with Passivhaus certification criteria. It is
is measured in air changes per hour at a be calculated and included, while the solid
therefore imperative that the Vn50 volume
50 Pascal pressure difference between the element of the actual stairs should be ignored
used to calculate the airtightness result is
inside and outside of the building. This is such that the entire stair volume is included in
checked by a competent third party and this
referred to as the n50 value, and is determined the Vn50. Internal wall voids, floor voids and
calculation must be documented within the
by calculating the volumetric flow of air (m3/h) ceiling voids are excluded from the Vn50. In
Passivhaus certification folder. Where there
required to maintain a pressure difference of practice this may require detailed plans of the
is any uncertainty/ discrepancy over the
50 Pascals (v50) divided by the internal (heated) final construction to be issued to the person
interpretation of the Vn50 dimensions the
air volume (m3) (Vn50). It should be noted that carrying out the calculations, since some
lower figure should be used (until further
the v50 (volumetric flow rate at 50Pa) value is of these volumes may not be enclosed or
clarification has been provided by the
the same as the ATTMA q50 value. formed at the time of the initial pressure test.
Passivhaus certifying body).
v Measurements should therefore be taken
n50 = 50 off drawings to allow direct comparisons Figure 10 and Figures 11a-b provide an
Vn50 between different peoples calculations in a illustration of the volumes which are to be
way that is not affected by different individuals included (blue) and excluded (yellow) from
The Vn50 volume is the conditioned volume measuring different lengths etc. Dimensions the Vn50 calculation. In general the Vn50
of the building in normal operation with used should be checked on site to ensure that should be calculated on a room by room basis
measurements taken from the visible wall, the calculation of volume is reliable, and that by measuring the room volume from the
floor and ceiling finishes. the built form complies with the plans. Window finished floor/wall/ceiling surface. In general
reveals are not normally included but external all conditioned air spaces within the thermal
This is not the same as the air permeability
door revels (which are 13cm deep or deeper envelope are included in the Vn50 however
envelope area (A E permeability) approach
are included). Hidden risers, wall and floor voids enclosed air spaces behind partitions or
generally used in the UK, which ignores
are not included in the volume but any large above suspended ceilings are excluded, as are
internal walls and floors and is measured to
store cupboards inside the finished surface (e.g. window reveals and door reveals (if less than
the air barrier element. This means that voids
containing MVHR etc.) are included. 13cm deep). Full height reveals greater than
between the ceilings and floors, internal
13cm deep should be included in the Vn50. A
wall voids are not included in the Passivhaus The calculated Vn50 volume is critical to the
summary table of volumes to be included and
volume calculation (room by room volume final test result. Should the calculated volume
excluded from the is provided in Table 1.
Table 1 Air volumes and solid elements to be included and excluded from the calculationTest method
Figure 11
Passivhaus Primer Airtightness guide 15
The airtightness performance of a building risk of error rises significantly, particularly for
is measured by an air pressure test (often exposed buildings (Table 2). This error can be
referred to as an airtightness test or
Preparation for the test reduced by using four reference tapping points
blower door test). To achieve a result that around each side of the building, to more
is compliant for Passivhaus Certification accurately gauge the mean internal/ external
the test must conform to BS EN 13829 Maximum acceptable wind speed pressure differential (Table 2).
(2009) Thermal Performance of Buildings
In preparation for the air pressure test the The effect of wind is effectively measured by
Determination of air permeability of
local weather conditions must be observed; the fan off pressures taken at the start of the
buildings Fan pressurisation method. Both
in particular the mean wind speed and any test they must be within +/- 5Pa. Higher
pressurisation and depressurisation tests must
gusting. Testing should not be undertaken building differential pressures (above 50 Pa)
be undertaken for Passivhaus certification
when wind speeds are above 6m/s (i.e. should also be achieved up to 80-90 Pa (with
purposes, with the combined result of both
above Beaufort Force 3). Even wind speeds 10 measurement points taken as a minimum).
demonstrating that an air change rate of
above a light breeze (Beaufort Force 2) will Care must be taken to ensure these higher
less than or equal to 0.6h-1 @50Pa being
begin to introduce an element of error into pressures do not affect the seals and/or fan in
achieved. For final testing the building should
the test results (Table 2). When wind speeds the doorway.
be prepared in accordance with BS EN 13829
exceed 3 m/s caution is needed since the
Test Method A (test of a building in use), with
all external doors and windows closed (except
the one being tested from) and water in
traps. The only temporary seals to be applied
should be to designed ventilation which in
most cases will just mean sealing the inlet
and exhaust of the MVHR for the test. Other
temporary seals to non-designed ventilation
(i.e. around door frames, any holes in the
fabric) will lead to the test result being invalid.
Note that this only applies to the final test,
for pre-tests sealing incomplete or missing
elements is acceptable to gain a benchmark
for that which has been completed. Table 3
(below) provides a Passivhaus n50 pressure
test openings protocol checklist.
To demonstrate competency for airtightness
testing in the UK the air pressure tester should Table 2. Influence of wind speed and number of pressure tapping points on max error margin
either be accredited by the British Institute (source Dr.-Ing. Achim Geiler)
of Non-Destructive Testing (BINDT) for air
pressure testing dwellings or be a member of
the Air Tightness Testing and Measurement
Association (ATTMA) for testing dwellings and
non-dwellings and be fully versant with the
Passivhaus n50 test procedure, as described in
this document.
16 Passivhaus Primer Airtightness guide
casement seals, where inadequate or poorly dwellings) and TSL2 (for non-dwellings). It is
tuned gearing mechanisms fail to hold the important to note that the existing procedure
Testing protocol window casement tightly in the frame. for measuring the volume of a building in
the ATTMA guidance documents does not
A series of pressures between 10 to 60
comply with the requirements of Passivhaus
Passivhaus guidance recommends that the Pascals are used for the test, this corresponds
certification, see Calculating the Vn50 volume
air pressure testing fan equipment should to the pressure generated by wind speeds
of a Passivhaus (above).
be fitted into a window opening rather than of 4-10 m/s on a building. The results of the
an external door opening; this is because an pressurisation and depressurisation tests are It should be noted that with respect to the
external door may have a letter box, key holes averaged and the resultant figure is valid for sealing of openings in preparation for the test
and potential air leakage issues, particularly demonstrating compliance with Passivhaus that neither BS EN 13829 Method A or Method
where there is a level access threshold. requirements. This is different to compliance B can be directly followed. A summary table
However, as most testing bodies in the UK use testing for UK Building Regulations, where below has therefore been provided (below)
fan testing equipment that is designed to fit either a pressurisation or depressurisation test for the purposes of carrying out a Passivhaus
into a door frame it is usually more practical is required (but not both) - so it is important compliant n50 test. The air pressure test
to adopt this more conventional method of that the person undertaking the test is aware report must document the condition of every
testing. If there are doubts about a doors air of this additional requirement. opening. Furthermore, in accordance with the
tightness separate tests should be conducted standard, the person carrying out the test must
BS EN 13829 Thermal Performance of
using front and rear doors, or a window test comprehensibly document the net interior
Buildings Determination of air permeability
may be commissioned. volume and the net floor area, either based
of buildings Fan pressurisation method
on the production drawings (final plans) or
For Passivhaus Certification it is compulsory provides the overarching testing protocol
on-site measurements. If the net volume and
to carry out both a pressurisation test and which needs to be followed to ensure a
net area are provided by another consultant,
a depressurisation test on the building. valid test result is achieved. This testing
the pressure tester must independently verify
The depressurisation test can be particularly methodology is also provided in the UK
these values.
revealing of leakage paths around window via ATTMA Technical Standards TSL1 (for
Vn50
Test fan
Negative Cellar with volumetric
pressure Door flow and
50 Pa differential
pressure
measurement
Airtight
cover
Figure 12 Air flow paths during under-pressurisation test - 50Pa negative pressure
18 Passivhaus Primer Airtightness guide
Table 3 Checklist for preparing the building openings for the n50 Passivhaus test
Note: The above guidance has been translated and compiled from Appendix 3 Checklist for approved measurement Method A as presented in
Fachverband Luftdichtheitim Bauwesene. V.(FLIB, April 2008)
Passivhaus Primer Airtightness guide 19
Testing regime:
Flat 1 with flat 2 co pressurised
Flat 2 with 1 and 3 co pressurised
Flat 3 with flat 2 co pressurised
Figure 15
Passivhaus Primer Airtightness guide 21
An air leakage audit is helpful when carrying Thermo-anemometers are able to detect
out an air pressure test to identify any air localised air movement by inserting an
leakage paths that may need to be sealed to electrically heated probe element into an
improve airtightness performance, and also to airstream. The air speed is then inferred from
provide helpful guidance on areas to tighten the increase in heating power necessary to
up in future projects. maintain the probe at a given temperature.
These devices can pinpoint fine air leakage
Smoke pencils, thermo-anemometers and
paths, and can be used over and over again,
infrared thermographic cameras and even the
which is an advantage over smoke pencils -
back of a hand can all be helpful to identify air
which can only be used once.
leakage paths in the buildings fabric.
Infrared thermographic cameras can also be
While the building is being pressurised smoke
used to identify internal cold patches in the
pencils can be used to release small controlled
fabric caused by air leakage paths and heat
quantities of dense white smoke that allows
being lost externally by warm air escaping
air to be visualised as it leaves the building
through an air leakage path. Care must be
through gaps in the envelope. Not all gaps will
taken when using infrared thermographic
necessarily result in an air leakage path; the air
cameras to ensure the inside of the building
barrier may be robust inside the fabric even
has been heated to a temperature that is at
if there is a large gap visible in the finish layer
least 100C above the external temperature.
inside the building. If smoke moves quickly
If taking external images it is necessary
through a gap it indicates that the opening is
to avoid sunshine on the fabric and rain/
connected with a lower pressure zone (i.e. it is
dampness which will show as hot and cool
connected to the outside).
patches respectively, and do not necessarily
For very leaky buildings, or a preliminary correspond to heat loss paths or air leakage.
air leakage audit prior to an EnerPHit Some high quality infra-red cameras are
refurbishment project it can sometimes be capable of photographing laminar air flow
helpful to use larger scale smoke machines through door and window seals. These
that can fill large voids with smoke. Standing cameras are expensive and must be used by
outside of the building it will be possible to a competent person, their use is not typically
see smoke emanating from the fabric through required if the building has been pressure
gaps, which can then pinpoint where remedial tested and thoroughly audited at the first fix
sealing is necessary. stage.
Passivhaus
BRE
Bucknalls Lane
Watford
Hertfordshire
WD25 9XX
E [email protected]
W www.passivhaus.org.uk
R +44 (0) 845 873 5552