0 ratings0% found this document useful (0 votes) 631 views24 pagesFSDI-CATIC-1634 Submission of Method Statement of Capping Beam
method statement-capping beam construction
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
HER SS — Rit RA ARR D al
CHINA RAILWAY FIRST SURVEY & DESIGN INSTITUTE GROUP CO., LTD.
Mr. Wudianwei
Executive Project Manager
China National Aero-Technology International Engineering Corporation
30" July 2016
Ref: FSDI-(S01)-CATIC-1634
Dear Sir,
Subject: Submission of Method Statement of Cay
This refers to the letter No.: CATIC-EPW-FSDI-1438 dated on 29” July 2016 on the above subject.
\Wereviewed the letter and attachment and approved it.
You are kindly requested to get the approval from the Engineer promptly if there is any change or
adjustment for the construction process, method, material and machinery during the construction.
Yours faithfully,
MEH.
Team leader of Section 01
RECEIVED
Compa le TENG.
Thawe)s
Ret 7! BO
Name
Date :..ee
WAAR A LARA A
Carte China National Aero-Technology International Engineering Corporation
Mr. Colin Aspinall,
‘Team Leader,
China Railway First Survey & Design Institute Group Co Ltd,
Dear Sir,
‘Subject: Submission of Method Statement of Capping Beam
No.: CATIC-EPW-FSDI-1438
Date: - 29 July 2016
Referring to your letter ref: FSDI-($01)-CATIC-1564 dated June 26" 2016, we have revised
the method statement in accordance with the Consultant's comments and we are herewith
submitting the revised Method Statement of Capping Beam to you for your review and
approval at the earliest please.
Attachment: MS for Capping Beam
Yours teuly,
Nid
HSI 7
Executive Project Manager
R CEIVED |
Coreg y Namo: FSOL
99.104, late
3
checked By re teeCONSTRUCTION OF EXTENSION OF SUTHERN EXPRESSWAY
FROM MATARA TO HAMBANTOTA
SECTION I - FROM MATARA TO BELIATTA.
CONTRACT NO: RDA/SEEP/CONT-SL
(CH. 00+000 - 30+000 km )
METHOD STATEMENT FOR CAPPING BEAM
(BAILEY BEAM SUPPORT)
CATIC
CHINA NATIONAL AERO-TECHNOLOGY INTERNATIONAL
ENGINEERING CORPARATION.
Submitted Date: 28" July, 2016EXTENSTION OF SOUTHERN EXPRESSWAY FROM MATARA TO.
HAMBANTHOTA
‘SECTION | FROM MATARA TO BELIATTA CH 0+000 TO 30+000 KM
Contract No: RDA/SEEP/CONT-S1
EMPLOYER CONTRACTOR :
FF [roxopevenormenrauTuonty) |
CHINA NATIONAL AERO-
F7 ENGINEER ‘TECHNOLOGY INTERNATIONAL
fA | Cia RAILWAY FIRSTSURVEY AND ENGINEERING CORPARATION.
FSDI | “DESIGN INSTTTUTE GROUP CO.,LTD
File No: CATIC/SEEP/MS/
Method Statement For Capping re
; : E
Liotta St
Sheet
INDEX
CLAUSE DESCRIPTION REVISION STATUS,
B c :
PAGE 0 A |B jc |p
INDEX 0
10 AIM. 1 0
20 SCOPE I 0
30 REFERENCE 1 0
40 RESOURCE 1-3 0
Go | CONSTRUCTION ear
0 _| TECHNOLOGY PROCESS
Go |CULCULATION FORLOADOF| 51, |
0 | THE HOOP
CONSTRUCTION QUALITY
70 | contROL bee
go | CONSTRUCTION SAFETY e A
0 | GuaRANTEE
CIVILIZATION
99 | CONSTRUCTION SAFETY 18 0
GUARANTEE
10.0 MEASUREMENT 18 0
PREPARED BY | | yoy Signature: dy J. Date: off. 7.8
CHECKED BY | foun 04) Fon Signature" Moe. Date: or. J
¢ :
[APPROVED BY] Ua Suche. Signature: } $y be Date'go /. 7.24)Table of Content
1 Aim ..., . seteneeseaaens seeeeaneeeeeees ee ve 1
2 Scope 1
3 Reference .. se seseeeeeee o eereeteeete se asnens 1
4 Resource
4.1. Manpower ..
4.2. Equipment... a
4.3, Material.....scccccccesseeee tn eerie fee?
4.4 Organization chart 3
5 Construction Technology Process.
5.1 Construs
n Technology
5.2. Preliminary work for construetion
5.3 Column chiseling
Ss A\Sebting outlets tires neter terre
5.5.Formwork support, Making & Installation.
5.6 Reinforcement binding and installation....... eee eee eee)
5.7 Side formwork installation... 7
5.8 Pour concrete (Specification of Sri Lanka, 10083 (g)... pas?)
5,9 Remove formwork......+s+
5.10 Conerete curing.
6 Culculation for load of the hoop system. eee ere 9
6.1 Calculation principle. : 9
(6.2\Load calculation et tere cerita sree cmeteatese cemteneererer ter 9
7 Construction Quality Control... 14
7.1 The control of Materials Source........... errant eea a
7.2 Supervision for concrete at site. 157.3 The preparing work before conerete pouring...
7.4 The site concrete vibratory quality contro.
7.5. Thermal control of concrete...
8 Construction safety guarantee...
9 Civilization construction and environmental protection measures ..
10 Measurement ...
lo)
16
16
aly
18,Supervisor: Responsible for completing the works stated as the method statement
and taking corrective/ preventive action
Site Engineer: Plan and conduct construction work, inspect the quality of works.
Maintain construction site records and facilitate engineer for necessary inspections.
Materials Engineer: Responsible for site tests, collection of materials samples,
carryout testing and reporting.
4.2 Equipment
Equipment use for capping beam construction.
* Water Bowser
‘Survey Equipment
© Vibrator & vibrating tamper
¢ Mixer Concrete truck
4.3 Material
‘© Material sample approved by engineer,
© Use for the construetion works.
Site Manager
4.4. Organization chart
Mining
Engineer
‘ Material Safety
Technician
Surveyor
EngineerBar Benders,
Skill
Helpers,
5. Methodology
5.1. Construction Technology
‘The Construction Technology process of Capping beam are as follows.
+
+
Make Formwork — J» Bottom formwork installation
Reinforcement Binding Reinforcement Installation
+
Make Formwork Side Formwork Installation
+
+
aye (_Powing conse)
A P ce tt
transport, trial and test pera Read
Removing Formwork
I
Thermal controla Curing
nerete
5.2 Preliminary work for construction
1) Equipment: ensure all the machine & equipment are under good condition before
starting the construction.
2) Power supply: power supplied from the high tension line, there will have one generator
for stand-by use.
3) Technology: be familiar with the design drawings & other technical documents, and
technical disclosure is necessary, furthermore, the worker shall clear about the exact
details of each Capping beam, such as material amount, size.
4) Workshop: a flat reinforcement yard with completed canopy is necessary.
5) Confide a technology & safety secret to every construction personnel
6) Setting out according the approved drawing by Surveyors lofting the Capping beam
position and its elevation.
7) After completion of abutment construction works, back calculate the exaet place of the
lower beam clamp at column according to the design elevation of cap beam, Mark it clear to ensure
hoop accurately in the place.
8) For the convenience of capping beam bottom formwork installation. When pouring
concrete, the pier column top elevation shall be 5 cm higher than the design top elevation.
5.3 Column chiseling
When the concrete strengthen of pier meet the 75% of the designed strengthen or more, take pier
chiseling for the its surface, Chiseling off the cement mortar or weak layer until the conerete layer,
also clean with the air pressure. Make sure the top elevation is $ em higher than design elevation to
censure the installation of eapping beam bottom formwork.
Pier column top surface shall be chipped off or green cut to remove the grout until exposure of
aggregate to form a rough surface before placing any fresh concrete.
5.4 Setting Out
Before capping beam construction, survey the pier as the basis of bottom formwork installation of
capping beam, The measurement & control items including: measurement for center position of
column top elevation. Use total station for the center position measurement, Height measurement
points are set up according to the construction of temporary level, with level machine directly.
5.5 Formwork support, Making & Installationorton formar
Isley
Gaard rail
b Stee!
‘Transverse slope
aaustaent block
hoop
a
4
(1) Asshown on the sketch above are standard sized formwork fabricated according to the
dimensions of the approved cap beam design drawings, column hoops and operating platforms.
(2) The column hoop installation
Column hoop size 2542*600mm,radius 750mm,plate thickness 14mm;Clamp two column hoops
tightly to the column for supporting of the cross beams, capping beam formwork and weight of
concrete.
Determination of the hoop top elevationHoop top elevation:
-apping beam bottom elevation-thickness of bottom mould -thickness of U
steel-bailey height-adjustment block height. Setting out the exact top elevation of the hoop with
level station and tape and mark it,
Installation of the hoop
Lift the two hoops with cranes to the level of the installation for assembling and installing .The top
of the two hoops must be level, tighten with high-strength bolts so that the hoops will be firmly
installed onto the columns.
As for Content of the test method for checking whether the high-strength bolt has achieved the
working station, we are submitting the test method as follows:
Step 1: Use the torque wrench to check the tightness torque of bolts after the bolts are fully
tightened by tools. The torque of bolts is 1209N.M.
Details: high strength bolts used at site are M30.8.88, Based on JGJ 82-201 1, its sheer and tension
capacity is worked out of Table 3.2.3 as 250N/mm2 and 400N/mm2 respectively.
Formule for calculating torque of bolts is babulated as follow as per Specifications JGJ 82-201 1-
64.13:
TekPtd
d-—nominal diameter of bolt, 30mm.
k-torque coeeficient average value, which is 0,11~0.15 from Table 6.3.1
‘And average value is 0.13.
P-.- preloading in construction is 310KN as per Table 6.4.13
$oT=0.13*310KN*30mm = 1209 N.M
Step 2: When the installation of the platform of bottom formwork for the first capping beam is
completed, pre-loading test shall be carried out, And check the deflection and the total torque for
the central span, the deflection satisfies the requirement in Clause $56.4 of the Specifications.
‘The load which should apply for the trial of capping beam form work is S76KN. The initial loading
of40KN and final loading of S76KN should be tested than Smum.
(3) Fabrication and Installation of formwork support and bottom mould
Capping, beam formwork vertical support will be I steel 56a beam with length of 13.8m,one beam
oneach side Horizontal support will be I steel 14a beam placing from the column and ending by
the column with spacing of 44cm,
‘Standard sized formwork will be used for the capping beam; Installing the formwork support
following by the chiseling and satisfied survey result. The installation shall startin a bottom —up
sequence, which is to install the hoops first then the vertical beam, Fix the 2 vertical I steel beams
with tie bar, install the horizontal U steel beams after the vertical beam is stabilized, and then install
the capping beam bottom mold.5.6 Reinforcement Binding and Installation According to the specification
requirement Division 550 (Sub Section $52.1, 552.2, 552.3, $52.4,
2.5)
(1)The technician can binding reinforcement according to the reinforcement size, length, shape
mentioned at the column design drawing, and then send to the site for installation.
(2)Joints of bars are connected by cold pressed socket or lap.
(After checking & get approval for the bottom formwork installation and top elevation of
capping beam, install the reinforcement. Reinforcement bar is bending at the reinforcement yard
according to the design drawing and specification. To make sure the convenience of construction
and safety construction, the capping beam reinforcement bar can fixed at the ground, then lifting by
the crane. If the crane is not available, can fix the reinforcement bar on the bottom formwork
directly. Pay attention to the bearing pad stone and embedded block reinforcement.
(4)Afier completing the reinforcement installation, first self-check according to the above
siandard, then request the consultant engineer for inspe
n when itis qualified, the consultant will
sign and approve, then install the reinforcement
(5)Reinforcement will be binded with thin wires, reinforcement hood and reinforcement shall
te placed vertically. During reinforcement installing, a temporary framework will be used for
stabilizing and supporting to enhance the overall stability of the reinforcement frame, After the
reinforcement frame is fabricated, place the concrete cushion on both sides of the frame to ensure
sufficient concrete cover. In accordance with the design requirements of the concrete cover, we use
the same grade of concrete made of SemxSem diameter (diameter 3em, height isSem) and
Semx3em(diameter of Scm,height of 3cm) of concrete block.
(6)Lapping of the bars shall be carried out in accordance with the approved drawing,
§.7Side formwork installation
After inspection & get approval for the reinforcement installation of capping beam, install the side
formwork of capping beam according to the construction requirement,
Provide 19mm chamfers at exposed arises of the capping beam concrete as specified in sub clause
$51.8.9 of technical specifications,
5.8 Pour Concrete (Spe
ication of Sri Lanka, 1008.3 ( g ) )
Allconerete of capping beam must pour at one time, Otherwise, shall take relative treatment and
pour concrete according to the construction specificationMake the ingredients list according to the approved mix design by the material engineer,
(Engineer's) batching plant must control all kinds of material source strictly, strengthen the conerete
quality control.
Prior to pouring concrete, check the formwork, scaffold reinforcement & inserted material, Clean.
uw the dirt, water on the steel bar & formwork,
Use the truck mixer for conerete transport to the site, and the crane for concreting layer by layer,
each layer is 30 cm, with a vibrator vibrating at the same time, pay attention to the top elevation at
the end of concreting, After the initial set of concrete, use curing material or gunny bag cover the
concrete surface, keep it wet.
Use the truck mixer for conerete transport to the site, according to the site condition; crane can be
used for conerete the remove of spindle, pouring concrete into the formwork layer by layer, and use
vibrator for vibration, When using vibrator, mobile spacing shall not exceed more than 1.5 times of
the vibrator action radius, and keep a distance of 50 ~ 100 mm to the side, to insert the previous
conerete layer 50 ~ 100mm for vibration. After the completion of each place, should remove
ribrator slowly to avoid collisions formwork, reinforcement and other embedded parts. For each.
vibration area, must be vibrated to the compactness of this area. Strietly control the concrete drop
height, the free pour fell height must be less than 1.5 m height, when the drop height is more than
1.5m, must adopt Chute tube or shuttle tank to decrease drop height.
Concrete vibratory follow the principle of “fast push, slow pull”, make sure the surface of concrete
no longer have sinks down and take no bubble, to prevent phenomenon of honeycomb or pitting
surface. Insert time slightly faster, and puts forward slightly slower and no off while vibration, to
avoid any space or empty inside the concrete.
Concrete vibratory adopts parallel type or quincunx, but shall not be leakage of vibration, less
\ibration, more vibration; After concrete pouring, should vibrating immediately, vibrating to
appropriate time, generally can be controlled in 25 s and 40 sadvisable; Vibrator can't contact to the
layout within the reinforcement in the formwork; The scene have standby vibrator, once
breakdown, can be quickly replaced
As for the concrete dropping height, the target of concrete dropping height of 1.5m cannot be
echieved due to the fact that the height of capping beam in the drawings is 1.6 m, whose surface is
densely covered by reinforcement bars and embedded parts of plinth, stopper and masking wall.
Therefore, the discharge outlet of concrete truck shall be closely next to the reinforcement bars to
lower the dropping height as applicable.
5.9 Remove Formwork
Afier conerete, and strength reach the requirement of Division 550. (551.8.7), can remove the
formwork. As required by the Chapter 551.8.7 of the Specifications, the lateral formwork of
capping beam can be removed on condition that the concrete strength reaches 14Mpa. The bottom
formwork of capping beam and false work can be removed when the conerete strength reaches
21Mpa. When removing formwork, must pay attention to the concrete surface protection and avoid
8collision or damage the capping beam on the surface of concrete, affecting the appearance quality.
The removed formwork must be promptly cleaned up and nap, coated with release agent or clean
the oil alter grinding, turn to the next set of Capping beam construction.
5.10 Concrete curing
As for the concrete curing, the curing shall be strictly executed in accordance with the requirement
of the Chapter of 551.12.1 stated: Concrete surfaces shall be kept completely and continuously
moist. Curing shall be continued for a period of at least 7 days. This curing period may be reduced
ifthe contractor presents evidence that the in place concrete has attained 70% of the specified
strength for the class of concrete under cure. Under no circumstances, shall the period of eure be
less than 3 days. Sackeloth (hessian) shall be used for the concrete curing and kept wet during the
curing period.
6 Calculation for load of the hoop system
6.1 Calculation principle
A Deflection control will be considered in the case that structural load has been satisfied
B Considering the safety of the structure comprehensively;
. Adopting realistic mechanical model
D. Maximize the use of existing components and method of support which has been applied.
E, Steel mold will be used for the capping beam bottom mold. The U steel beam installed under the
‘oll is for the putpose of elevation adjusting and enhancing the strength of the strueture. In the
case, the strength of the steel mold has been sufficient, t's unnecessary to calculate the bearing
strength of the U steel beams.
F For the uniformed distribution of part of the structure, the larger uniform load will be adopted for
its asymmetry
GAs a safety margin, this calculation is not included the capping beam weight bear by the column.6.2 Load calculation
6.2.1 Sketch of the Components for calculation
800
T
|
h
tf
|
|
|
pet, 808
g
grN al
terete 000
1 i
am wee
,15| 3600 L 500 {92s
i I ribs ‘
6.2.2. Selection of the load partial coefficient
Load is & value used to indicate the uncertainty of the bearing capacity associated with the structural
reliability in the design calculation .The permanent load and variable loads require different partial
cvefficients.
(1)Pemmanent load partial coefficient y Gein the case that the permanent load resulting unfavorable
effect on the structure, for the composition under the control of variable load effect y G=1.2while
for the composition under the control of the permanent load effect y G=1.35,In the case that the
effect is favorable, normally y G=1.0;For calculating tipping and slipping y G=0.9;For some special
‘cases, the value of the y G shall comply with the relevant specification,
Variable load factors partial coefficient G normally is 1.4
6.2.2.1.Load analysis
Capping beam bottom area:(10.85-2)*2.4=21.24m’ (calculated as in most unfavorable case, more
of conservative)
(1)Conerete weight of the capping beam:41m'*26KN/m*=1066KN
Q1=1056/21.24=50,2KN/a
Note: Including reinforcement >2%, load partial coefficient=1.2
(Q)As per manufacturer, formwork weight 3921.02kg, gravity: 3921.02*9.8N/kg=38.SKN
Q2=38.5/21.24=1.81KN/m
Note: g-9.8N/kg » load partial coefficient=1.2
(3) 32a U steel 19 pieces 4.5m lay on the bailey steel
Hl total weight: 19°4,5*38.2=3266.1*9,8N/K g-32007.78N=32KN
Note: Including reinforcement >2%, load partial coefficient=1.2
(4) Bailey Steel weight
108 pieces 3.1m bailey steel will be used for each capping beam.
bailey steel weight:8"275*9.8N/Kg=21560N=21.6KN
Note: Including reinforcement >2%, load partial coefticient=1.2
(5) Weight of hoop, operating platform, adjustment block, tie bar, screws
‘As per manufacturer the hoop is 1197.5kg,opetating platform is 350.8kg,adjustment block is
45kg.tie bar 8.59kg,screws and other 12kg.
Hoop:1 197.59. 8N/kg=11735.5N=11.7KN
Opetating platform, tie bar» screws: 370.59*9.8N/KG~3631.7N=3.6KN
Adjustment block: 45*9.8N/KG=441N=0.44KN.
Note: g=9.8N/kg, load partial coefficient=1.2
(6) The impact load for pouring eonerete and vibrating
Impact load is 0.8T/m(including load from vibrating concrete) that is 8KN/m, load partial
coefficient=I.4
(7) Load of construction equipment and workers
Construction workers,material delivery,stacking load is 0.25'T/m,that is 2.5KN/m,load partial
coefficient =1.4
6.2.3. Combination of load calculation
(1) When calculating the bottom mold load stress,simple beam calculation stereotype shall apply.for
the U steel beam bears the surface load transferred from the mold,the bottom mold bears a linear
load:
That is -Q=Q1*1.2+Q2*1,.2+0.8*1.4+0.25*1.4=
50.2*1.2+1.81*1.2+0.8" 1.4+0.25*1.4=63.88KN/m
(2) When analyzing 32a U stee! beam load stress, the calculations as based on that the load is
uniformly distributing on the U steel(uniformed load distribution ranges 10.85m) load combined is:
QEL (1066+38.5132+0.36) *1.2+1.4+0,8"0.25"1.4]/4,5/10.85=27.97KN/m
(3) When calculate hoop load stress, the calculation is based on that the hoop surface and the
concrete surface friction to resist the concentrated load above the hoop.
That is + Q=[single (1066+38,5'32421.610.4443.6) *1,2+.4+0,80.25*1.4)/2698.12
6.2.4.Bailey beam calculation
6.2.4.1. Selection of the load partial coefficient
Load is a value used to indicate the uncertainty of the beating capacity associated with the structural
reliability in the design calculation .The permanent load and variable loads require different partial
coefficients
(Permanent load partial coefficient y G: In the case that the permanent load resulting unfavorable
effect on the structure, for the composition under the control of variable load effect y G=1.2while
for the composition under the control of the permanent load effect G=1.35,In the case that the
eifect is favorable, normally y G=1.0;For calculating tipping and slipping y G=0.9;For some special
cases, the value of the y G shall comply with the relevant specification.
@Variable load factors partial coefficiency G normally is 1.4
6.2.4.2. Load analysis
(Concrete weight of the capping beam:
WI=41m'*26KN/m'=1066KNNote: Including reinforcement > 2% , load partial coefficient=1.2
@Q)As per manufacturer, formwork weight 3921.02kg, gravity: W2=3921.02*9.8N/kg=38.SKN
Note: g=9.8N/kg, load partial coefficient=1.2
(3) 32a Usteel 19 pieces 4.5m lay on the bailey steel.
132a total weight:
W3=19*4.5"38.2-3266.1*9.8N/Kg=32007,78N=32KN
Note: Including reinforcement > 2% , load partial coefficient=1.2
(4) Bailey Steel weight
8 pieces 3.0m bailey stee! will be used for each capping beam. 04 pieces are allocated each single
side. bailey steel weight:
W4=8*275*9.8N/Kg- N=21.6KN
Note: Including reinforcement > 2% , load partial coefficient=1.2
(5 ) operating platform, adjustment block, tie bar, serews
‘As pet manufacturer the opetating platform is 350.8kg, adjustment block is 45kg, tie bar 8.59kg,
serews and other 12ks.
Opetating platform, tie bar , screws : 370.59*9.8N/KG
Adjustment block : 45¢9.8N/KG=441N=0.44KN
W5=3.6+0.44=4.04KN
Note: g=9.8N/kg, load partial coefficient=1.2
.6KN
( 6 ) The impact load! for pouring concrete and vibrating, Impact load is 0.8T/m (including load
from vibrating concrete) that is 8KN/m. Load of construction equipment and workers, Construction
workers, material delivery, stacking load is 0.25T/m, that is 2.SKN/m,
Wo=842.5-10.5K N/m
load partial coefficient =1.4
6.2.4.3. Combination of load calculation
The bailey steel structures are reinforced single rowed and single layered at one side of capping
teams during construction. As per reference books, properties for bailey steels are 1y=577434.4
em! , W,=7699.1 cm? , E=2.110°Mpao Upon analysis, the load to bear includes W1 W2 W3 W4.
W5 Wo.
This load is born at two sides of bailey steels, so the load for each single side is calculated as:
We (W1+W2+W31 W4+W5+-WO*the bailey length) /2
= ( 1066+38.5+32 121,644.04 ( 842.5 ) #12) /2
=644,07KN
Note: the total length of bailey steels: 4 pieces * 3.0m each single piece = 12m each single side, the
calculation for even los! to bear is as follows:
= W/L=644,07/12=53.67KN/m.
Based on the situation lor erections of bailey steels and hoop support at the bottom, the simple
model is detailed as follows:Calculation for bailey steel deflection:
fqL/384EI*(5-24a°/L7) :
=53.6747,0'(384*2,1*10°*577434.4)*(5-242. 5/7)
=5.37mm , less than the allowable deflection, which satisfies the sp
Calculation for bailey stce! bending moment:
M ovax=QL7/8 * ( 1-4" a2/L? )
=53.67*7.0°/8* ( 1-4*2.5°/7" )
= 161 KN.n
Mana < [MI
687.5 KN.m, which satisfies the requirements,
[M] is allowable moment for reinforced single rowed and single layered bailey steel bending,
Referring Table 11.2 tor Bailey User Manual of 321 type of year of 2007, the allowable internal
force [M]:=1687.5 KN.m.
___ ‘Table 11.2: The allowable intemal force of Bailey User Manual of 321 type
nae | Now reinforced bridges Reinforced bridges
‘Single | Doudte | Three | Double | Three | Single | Double | Three | Double [ Three
Allowable | rowed | vowed | rowed | rowed | rowed | rowed | rowed | rowed | rowed | rowed
inwml | & | & | & | & | @ | a | a@ | &@ | a | @
force | single | single | single | Double | Double | single | single | single | Double | Double
layered | layered | layered | layered | layered | layered | layered | layered | layered | layered
al 7a82 | 1576.1 | 2246 | 32654 | sess 1687.5 | 3375.0 | 4809.4 | or00 9618.8
Inaccordance with above facts, allocation of bailey steels satisfies construction requirement
and itis safe.
62.5.Hoop cals tition
Load calculation
I set of hoop will be installed on each side of the pier where the capping beam is to be constructed
cn,total two sets of hops to support the load above.As per the calculation above,the counter force
of the base is:
RI=R2=698.12KN
‘The maximum value of the vertical force the hoop needs to withstand as N,this value is the
fictional force iced tw be generated by the hoop.Hoop load force calculation
® Number of bolts
‘The vertical force the hoop needs to withstand is N=698.12KN
‘The vertical force the hoop hear is generated by the M30 high-strength bolts shear force ,Refer to
“Design Code for the Stee! Structure” for the bearing load allowed for M30 bolts:
[NL}-0.8P un
In the formula; P—- pre-stressing force of the high-strength bolt,count as 35SKN;
1 Hietion coefficient,count as 0.3;
n—the number of face the force transmission have contact with,count as 1;
0.8—ununiformed load force coefficient for the bolts.
‘Therefore:[N1]=0.8*355*0.3 -85.2KN
M=NI[N1 }-698.12/85.2=8.19=9pieces, the number of the bolts on the hoop section count as 36
pieces. Then ,the shee force yenerated by each high-strength bolt is
P=N/32=698.12/36 12.39KN< [NL] =85,.2KN
Therefore. the Loop beatin: force is satisfactory for the load force.
®Bolt axial tension ealeutivion
Provided a layer of rubber !'ctween the concrete and the bolt axial,according to which the
coefficient of ftction between the rubber and steel count as u-0.3; Then,the pressure generated by
the hoop is Pb=Nfu 98.12/0,3-2327.07KN bear by high-strength bolts
N=Pb=2327.07K
Hoop pressure geucrsted hs the stressing force of M30 high-strength bolts, That each bolt stressing
foree is
NAPD/36-2327.071.N/36. 41,1KN-<[S]35SKN.Therefore,the strength of high-strength bolts
satisfied the require
@Hoop components tensile stress caleulation
Hoop wall (cusile stress 55 "1 SN1=8*64,64=517.12KN,
14Hoop wall panel using 514mm steel plate,height 0.75m,the hoop longitudinal cross-
sectional area is
014x1.5x3.14/2=0.03297(m2)
S=N’/S=2327.07/0.03297=70581.44Kpa=70.6Mpa< {o] =140Mpa
which satisfied the requirements.
‘The shear stress of the hoop components
=RA(Q2S1)=698.12/(2*0.0297)=11752.86Kpa=1 1.75Mpa< [2] =85MPa which
satisfied the requirements.
7 Construction Quantity Control
According to the standard specifications for construction and maintenance of roads and bridges.
10,803.2 concrete.
a)Casting of concrete cubes
‘The casting of concrete cubes shall be carried out in accordance with BS 1181:part 108:83 with a
sttength requirement as specify in AASHTO T23 equivalent cylindrical specimen.
b)Testing of conerete cubes
‘The testing of concrete specimen shall be carried out AASHTO T22 (ASTM C39), equivalent test
with BS EN12390-3-2002, may be accepted according to the engineer's requirement,
¢) Slump Test
The slump test shall be carried out in accordance with ASTM test designation C143/C143M.-05* or
BS EN 12350-2-2000 or AASHTO T119-99
7.1. The control of Materials Source
* Cement: to check the surface of the cement, if can not meet the requirements, not
allowed to unloading, The strength, stability, such as setting time, standard
consistency water can be tested by bulk supply
Ultrafine mineral powder: activity index and fluidity ratio in bulk for testing,
Fly ash: to test the fineness of fy ash,
Sand: do Methylene blue test, fineness modulus, powder content, soil content,
apparent density, bulk density and crush index detection.
Rock: the approach of gravel content of silt and clay pieces first, other indicators
such as grain size distributi
n, apparent det
, bulk density and crush index, etc.
Admixture: do the cement slurry flow degree test for the admixture. The concrete
slump and the expansion degree test is req
ed when necessary, other test such as
water reducing rate, exudation rate, when the air content, slump loss, such as the
15ratio of compressive strength is also required
. Supervision for concrete at site
a) The technician must stay at the site for supervise, adjust the concrete slump, ensure the
completion of concrete pouring works.
b) The pump truck drivers and truck mixer driver act as very important rolls for the concrete
quality control
7.3. The preparing work before concrete pouring
(1) Check the formwork
Mainlly check formwork position, elevation, size, verticality degree, Formwork juncture,
embedded component place and number and its supporting,
Situation, clean the wood shavings and other waste materials in the formwork.
Further, Please refer NO.FSDI-(S01)-CATIC-1356 for form setting details at site
(I) Cheek the reinforcement
Check stee! reinforcement brand, quantity, position, joint and embedded components materials, ete
(TED) Check the materials, machinery and road
Mainly check the varieties, specifications, quantity and quality of the Materials; the number of
machines and tools, operation situation, and road Condition shall be checked also.
(IV) Check the water and electricity supply
Check the water and electricity supply, and also check the weather condition,
(V) The conerete pouring
Conerete should not drop in the form a greater distance than 1.5m ,teferd to clause
551.10.21 of project technical specifications
Layer by layer to pour the concrete, height of each layer should be determined
according to the structural characteristics, reinforcement density, and normal height is
1.25 times of vibrator function height, maximum not exceeding 500 mm, the layer
thickness for the plate vibrator is 200 mm.
‘Turn on vibrators, quick insert inside the concrete, ensure that there is no bubbles, no
16obvious sinking on the concrete surface, pan pulp and surface formation on the surface
level.Using vibrator should be insert fast & remove slowly, one area by one area
vibrating,
Conerete should be continuous until complete,
There should have one person to check whether the formwork, reinforcement, reserved
hole, embedded parts and other steel displaced/blocked or not, when pouring concrete.
1.4 The site concrete vibratory quality control
Occur when one of the following occurs, it shows that conerete vibration has been finished:
(1) Concrete surface to stop setting, or not have clear height change;
(2) Nothave significant bubbles when vibrating, or no bubbles around the vibrator;
G)The concrete surface is flat, floating pulp;
(4) The edge part of the formwork has been full filled with concrete,
1.5 Thermal control of concrete
This method does describe construction method for reinforcement, conerete or formworks in details,
but it provides details in Thermal Control and Temperature Differential Method. Measures taken are
detailedas follows:
7.8.1. Thermal Control Testing
Frior to construction of capping beam, mock up testing is done. Dimensions, temperature of the
thermal control specimen , layout of thermal control cables and detectors and testing time are
conforming to Clause 551.10.6 of the Specifications.
1.5.2. Optimize the conerete mix design
a) Select low heat portland cement approved by consultant and reduce cement quantity as
much as possible subject to satisfying strength requirements;
b) Well graded aggregates are used as coarse aggregate
©) The O~Smm quarry dust are used fine aggregates mixed with natural river sand, the silt
content and dust amount is well controlled in course and fine aggregates so as to reduce
‘cement amount in general by trial mixes subject to satisfying the design strengths
Adopt double admixing technology, i.e, adding fly ash and superplasticizer at the same time
to reduce efficiently cement usage in unit concrete and postpone emerging of the
temperature peak value.
7.53. Temperature reduction for materials,
a) A shelter is established for the aggregate store to prevent from direct sunlight and sand and
aggregates are flushed by water to reduce temperature, And the water content for batching in
the plant is adjusted according to water content in wet aggregates.
b) Water for batching will use the water approved only. If further reduction is required, ice
cube can be added to the water.
7.54. Temperature reduction in Formwork and reinforcement
7Before placement of concrete, the formwork and reinforcement is flushed by water so that the
temperature for formwork and reinforcement can be reduced on one hand and foreign matters can
be cleared and removed therein on the other hand.
7.5.5. Cooling of the Machinery
Before batching, proportioning machine and mixer are flushed by cold water. For the concrete
mixer trucks, before loading conerete and when the trucks are waiting at site for conereging, they are
parked at tree shades or sunshading places and watering is done to the conerete tank for cooling
purpose. When the trucks are loaded with conerete, their engines cannot be turn off and the conerete
tanks need rotating all the time.
7.5.6, Time for conereting.
Time for conerete placement is preferred curing period when environment temperature is low
during the day. For the batched concrete, placement should be done as soon as possible to prevent
ial set of the concrete at high temperatures,
1.5.7. Conereting from one end to another
Tor the concrete delivered to site already, temperature measured before placing into formwork
which is required to be less than 32°C,
Concrete placement is done from one end to another at thickness of 30~40cm for easy vibration to
ensure concrete quality by making full use of concrete surface for heat dissipation. But the next
hayer concreting should be completed before initial set of the previous layer to prevent cold cracks
between layers.
7.5.8. Curing of the Concrete
After concreting and final set, curing is done by specially-assigned person using gunnysacks or
geotextile to cover the surfaces and carry out watering regularly .
After removal of formwork, the lateral part is winding with gunnysacks to keep temperature and
wetness. Gunnysacks or geotextile are to be kept wet during curing period.
As for curing period, it should be done strictly as per the Specifications(7 days) and it should be
extended when necessary, and the same is applicable to the removal of formworks.
8. Construction safety guarantee
lark construction safety lines, vehicle speed below 20 km /h, set up warning signs at
18some important traffic intersection.
Set up the work way, corridor, or some simple st
Construction of electricity must be set up by a professional electrician in accordance
inside of the column,
with the requirements of operation standard.
Safety staff must take in charge of the safety management of all the construction area.
9, Civilization construction and environmental protection measures
‘The construction site and transport roads are equipped with sprinkler, use sprinkler
‘maintenance the road regularly any dust caused by the construction.
Pay attention to the construction noise at night, try to use low noise construction
equipment.
Do not use the mechanical equipment which can not meet the emissions standard.
All the waste which is harm fall to the environment, such as abandon slag, construction
waste, production waste, waste materials, etc., Can dump at a specified location for
treatment
10.Measurement.
‘The measurement shall be determined in accordance with the clause 212.11 of Technical
Specification and under pay items given below.
Item
Description Unit
pe ~ | Structure elements (tie beams, pile caps, pier, pier head, ee
abutment, approach slabs and parapat
551.009 | Wrought formwork a ‘Sqm
551.010 | Sawn formwork a Sqm
552.001 | Reinforcing steel bar oe Ke |
19