0% found this document useful (0 votes)
103 views1 page

Programme Examples

The document contains schedules for constructing a prestressed concrete bridge and a steel composite bridge. It lists activities required for each type of bridge construction including site preparation, fabrication, substructure work, superstructure erection, and finishing work. Time estimates are provided for each activity in days, weeks, and the number of concurrent activities that can be worked on. The schedules allow planning and tracking of bridge construction progress.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
103 views1 page

Programme Examples

The document contains schedules for constructing a prestressed concrete bridge and a steel composite bridge. It lists activities required for each type of bridge construction including site preparation, fabrication, substructure work, superstructure erection, and finishing work. Time estimates are provided for each activity in days, weeks, and the number of concurrent activities that can be worked on. The schedules allow planning and tracking of bridge construction progress.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Bridge Area 100 15 1500 m2

Prestressed Concrete Bridge week


rate unit qty days wks cnc 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5 10.0 10.5 11.0 11.5 12.0 12.5 13.0 13.5 14.0 14.5 15.0 15.5 16.0 16.5 17.0 17.5 18.0 18.5 19.0

Site Prep./Mobilisa. 10 eu 1 10 2.0 2


Fabrication of
girders 45 eu 1 45 9.0 9
Substructure 39.2 7.8 10
Abut A1 and A2 8.1 1.6 2
Excavation and
backfilling 60 m3 180.0 3.0 0.6
Walls (MSE walls x5
faster) 14 m2 36.0 2.6 0.5
Footings and seat 15 m3 38.1 2.5 0.5
Pier P1 15.5 3.1 4

Drilled Shafts (30m) 0.3 eu 3.0 10.0 2.0 2


Columns 5 m3 14.1 2.8 0.6 1
Cap 8 m3 21.6 2.7 0.5 1
Pier P2 15.5 3.1 4

Drilled Shafts (30m) 0.3 eu 3.0 10.0 2.0 2


Columns 5 m3 14.1 2.8 0.6 1
Cap 8 m3 21.6 2.7 0.5 1
Superstructure 33.1 6.6 7
Girder Erection and
Setting 130 m 400.0 3.1 0.6 0.5
Slab construction 15 m3 375.0 25.0 5.0 5
Traffic barrier and
finishes 40 m 200.0 5.0 1.0 1
Misc. and
Demobilisation 5 eu 1.0 5 1.0 1
Steel Composite Bridge week
rate unit qty days wks cnc 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5 10.0 10.5 11.0 11.5 12.0 12.5 13.0 13.5 14.0 14.5 15.0 15.5 16.0 16.5 17.0 17.5 18.0 18.5 19.0

Site Prep./Mobilisa. 10 eu 1 10 2.0 2


Fabrication of
girders 120 eu 1 120 24.0 18
Substructure 41.2 8.2 10
Abut A1 and A2 8.1 1.6 2
Excavation and
backfilling 60 m3 180.0 3.0 0.6
Walls (MSE walls x5
faster) 14 m2 36.0 2.6 0.5
Seat 15 m3 38.1 2.5 0.5 overlay 200m2/day
Pier P1 16.5 3.3 3 railing 35m/day
Piles 80 m 420.0 5.3 1.1 1
Footing 12 m3 27.2 2.3 0.5 0.5
Hammerhead 6 m3 54.2 9.0 1.8 1.5
Pier P2 16.5 3.3 3
Piles 80 m 420.0 5.3 1.1 1
Footing 12 m3 27.2 2.3 0.5 0.5
Hammerhead 6 m3 54.2 9.0 1.8 1.5
Superstructure 36.7 7.3 8
Girder Erection and
Setting 60 m 400.0 6.7 1.3 1.5
Slab construction 15 m3 375.0 25.0 5.0 5
Traffic barrier and
finishes 40 m 200.0 5.0 1.0 1
Misc. and
Demobilisation 5 eu 1.0 5 1.0 1

You might also like